ASYNCHRONOUS START OF LARGE UNIT IN PUMPED STORAGE HPP "ČAPLJINA" IN PRESENT POWER SYSTEM OF BOSNIA AND HERZEGOVINA

Similar documents
Pumped storage hydroelectric power plants: Issues and applications BIH Case Study

IEEJ: June 2010 JICA JFY 2010 Energy Policy (B) NO. J / ID Country Report: Bosnia and Herzegovina March 2010 Prepared by JICA trainee

VAR-501-WECC-3 Power System Stabilizer. A. Introduction

Northfield to Ingle Farm #2 66 kv Sub transmission line

A. Introduction Title: Power System Stabilizer (PSS) 2. Number: VAR 501 WECC

Attachment F1 Technical Justification - Applicability WECC-0107 Power System Stabilizer VAR-501-WECC-3

SIMULATION OF BOSNIA AND HERZEGOVINA AIRSPACE

Southeast Europe Transmission Network Under Future Market Conditions

SECI Regional Projects Update

A Practical Power System Stabilizer Tuning Method and its Verification in Field Test

Reforms in Kosovo s power System

UC Berkeley Working Papers

Power System Stabilizer(PSS) Design Using ANFIS Algorithm and Comparing the Results with conventional and fuzzy PSS

Interconnections of Greek islands The Regulatory Approach

MATL Reference. MATL Path 83 Transfer Capability with Seasonal SOL Effects. Document. 1. Purpose

M A T L Reference. MATL Path 83 Transfer Capability with Seasonal SOL Affects. Document. 1. Purpose

PRAJWAL KHADGI Department of Industrial and Systems Engineering Northern Illinois University DeKalb, Illinois, USA

Estimating the Risk of a New Launch Vehicle Using Historical Design Element Data

A. Introduction Title: Power System Stabilizer (PSS)

Elektroprivreda BiH. 6th South East Europe Energy Dialogue (6th SEEED) Redefining SE Europe s Energy Map

ARRIVAL CHARACTERISTICS OF PASSENGERS INTENDING TO USE PUBLIC TRANSPORT

Load-following capabilities of Nuclear Power Plants. Erik Nonbøl

Breakthrough of the Tunnel with the Biggest Overburden in Croatia

New FPL 2012 Planning and Implementation Bosnia and Herzegovina

EPCG is seated at the address no 2 Vuka Karadžića St. in Nikšić

Gain-Scheduled Control of Blade Loads in a Wind Turbine-Generator System by Individual Blade Pitch Manipulation

HYDRAULIC STUDY OF THE NERETVA RIVER (FROM MOSTAR TO THE BORDER WITH THE REPUBLIC OF CROATIA)

FORECASTING OF INDUSTRIAL ROUNDWOOD PRODUCTION FOR THE PART OF SOUTH-EAST EUROPE. Maja Moro, Darko Motik, Denis Jelačić, Marek Drimal

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

HOW TO IMPROVE HIGH-FREQUENCY BUS SERVICE RELIABILITY THROUGH SCHEDULING

Feasibility of Battery Backup for Flight Recorders

The Electric Power System

CASM electric cylinders The modular electric cylinder system

SOME NSW SYSTEM PLANNING ISSUES. Dr Col Parker Manager/System Planning & Analysis

Measuring Productivity for Car Booking Solutions

OPTIMAL PUSHBACK TIME WITH EXISTING UNCERTAINTIES AT BUSY AIRPORT

CAPAN Methodology Sector Capacity Assessment

DGAC Costa Rica. MCAR OPS 1-Subpart Q LIMITATIONS OF FLIGHT TIME AND TIME OF SERVICE AND REST REQUIREMENTS. 30-June-2009

Part 171. Aeronautical Telecommunication Services - Operation and Certification. CAA Consolidation. 10 March 2017

Advanced Flight Control System Failure States Airworthiness Requirements and Verification

A Study on Berth Maneuvering Using Ship Handling Simulator

Future Automation Scenarios

Landsnet. Five years of synchrophasor use in the control center. NASPI Work Group Meeting February 2013, Huntington Beach, CA

Ticket reservation posts on train platforms: an assessment using the microscopic pedestrian simulation tool Nomad

Load-following capabilities of nuclear power plants

An Analysis of Dynamic Actions on the Big Long River

Black Start Ancillary Service Schedule

SATELLITE CAPACITY DIMENSIONING FOR IN-FLIGHT INTERNET SERVICES IN THE NORTH ATLANTIC REGION

Project Data Sheet BASIC PROJECT DATA. Rehabilitation and Development of Transport and Navigation on the Sava River Waterway. Full project title:

Figure 1.1 St. John s Location. 2.0 Overview/Structure

AIRBUS FlyByWire How it really works

INNOVATIVE TECHNIQUES USED IN TRAFFIC IMPACT ASSESSMENTS OF DEVELOPMENTS IN CONGESTED NETWORKS

INVESTMENT PROJECT Preparation and management for professional automatic greenhouses

HEAD-UP DISPLAY (HUD), EQUIVALENT DISPLAYS AND VISION SYSTEMS

Hydrological study for the operation of Aposelemis reservoir Extended abstract

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:

East European Trio 6N/7D

Analyzing Risk at the FAA Flight Systems Laboratory

PERFORMANCE MEASURE INFORMATION SHEET #16

HONDURAS AGENCY of CIVIL AERONAUTICS (AHAC) RAC-OPS-1 SUBPART Q FLIGHT / DUTY TIME LIMITATIONS AND REST REQUIREMENTS. 01-Jun-2012

1. TITLE OF THE PROJECT HYDROPOWER SYSTEM UPPER HORIZONS. 2. SECTOR Energy

GRAVITY ROLLER COASTER LAUNCH COASTER

Depeaking Optimization of Air Traffic Systems

The role of Serbia in the security of supply in Europe

IONIAN ADRIATIC PIPELINE IAP

1. Purpose and scope. a) the necessity to limit flight duty periods with the aim of preventing both kinds of fatigue;

SIMULATION MODELING AND ANALYSIS OF A NEW INTERNATIONAL TERMINAL

Abstract. Introduction

Transfer Scheduling and Control to Reduce Passenger Waiting Time

Wind Energy in South-east Europe: Seminar III: WIND ENERGY PROJECT DEVELOPMENT. Mostar,

Bird Strike Damage Rates for Selected Commercial Jet Aircraft Todd Curtis, The AirSafe.com Foundation

Wind Power Plant Podveležje

Comparison on the Ways of Airworthiness Management of Civil Aircraft Design Organization

Today: using MATLAB to model LTI systems

ATTEND Analytical Tools To Evaluate Negotiation Difficulty

OPEN SEASON Phase 2 Rules. Project on the development and expansion of Bulgartransgaz EAD gas transmission system (GTS)

WakeNet3-Europe Concepts Workshop

FACTORY CONSTRUCTION FOR THE PRODUCTION OF FERROSILICIUM IN GORNJI VAKUF - USKOPLJE MINISTRY OF ECONOMY, CENTRAL BOSNIAN CANTON

All-Weather Operations Training Programme

Time-Space Analysis Airport Runway Capacity. Dr. Antonio A. Trani. Fall 2017

American Airlines Next Top Model

OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs)

Fuel Conservation Reserve Fuel Optimization

Project of E-763 Motorway Construction, Section: Belgrade Ostružnica - Požega Boljare/ Border of Montenegro

Case No COMP/M GENERAL ELECTRIC / THOMSON CSF / JV. REGULATION (EEC) No 4064/89 MERGER PROCEDURE

Cuadrilla Elswick Ltd

Restructuring of advanced instruction and training programs in order to increase the number of flight hours for military pilots.

Controlled Cooking Test (CCT)

Air Carrier E-surance (ACE) Design of Insurance for Airline EC-261 Claims

Workshop on WATER-FOOD-ENERGY-ECOSYSTEMS NEXUS ASSESSMENT IN THE SAVA RIVER BASIN. Sectoral goals in the Sava River Basin

The Potential of Renewable Energy Sources in Bosnia and Herzegovina

EXTENDED-RANGE TWIN-ENGINE OPERATIONS

A RECURSION EVENT-DRIVEN MODEL TO SOLVE THE SINGLE AIRPORT GROUND-HOLDING PROBLEM

NATIONAL REPORT of CROATIA

Schedule Compression by Fair Allocation Methods

THE DISINTEGRATION OF SETTLEMENTS IN BOSNIA AND HERZEGOVINA THE EXAMPLE OF SARAJEVO/EAST SARAJEVO

Estimating passenger mobility by tourism statistics

National Association of Rocketry Level 3 High Power Certification Requirements

CAAV VAR 15 DFR Jan-2011 Version 1.0

Official Journal of the European Union L 7/3

Transcription:

ASYNCHRONOUS START OF LARGE UNIT IN PUMPED STORAGE HPP "ČAPLJINA" IN PRESENT POWER SYSTEM OF BOSNIA AND RZEGOVINA Nikola Rusanov*, JP EP BiH Sarajevo, Bosnia and Herzegovina Srećko Vučina Elektroprivreda HZ HB, Mostar, Bosnia and Herzegovina Milan Stojsavljević, Darko Nemec Energy Institute Ltd. Zagreb, Croatia tel. +387 33 657-138; fax:+387 33 650 908 n.rusanov@elektroprivreda.ba* ABSTRACT: According to the European Community plan POWER III, the rehabilitation of the power system of Bosnia and Hercegovina (BiH) and its reconnection with Croatian power system should be completed by the end of 2005. Use of available resources under constraints imposed by actual and prospective states of the power systems of BiH and Croatia (particularly Adriatic lines) leads to operational problems: violation of (n-1) criteria, high voltages, voltage instability, thermal power plants (TPPs) operating below minimum, etc. Having outstanding capabilities, pumped storage HPP Čapljina (2x240 MVA) could contribute to mitigating some of those problems while fully exploiting its advantages on the open electricity market. Two system services should be provided for HPP Čapljina: asynchronous start (with and/or without phase reactors at the generator starpoint) and transmission capacity for pumping. To find out if these services are available before rehabilitation of the power system a study was done and results are outlined in this paper. Regarding voltage / reactive power dynamics, asynchronous start of units at HPP Čapljina with phase reactors is possible, but reactive capability of nearby generators is fully used. With the other machine at HPP Čapljina operating as generator voltage/reactive power conditions in this part of the system are significantly improved. Two variants of supplying power for pumping were considered, from TPPs in BiH and from UCTE. In the latter case the constraint is violation of the (n-1) criterion for Adriatic lines in the Croatian power system. Key words: pumped-storage hydro power plant, asynchronous start, pumping, system services, dynamic simulation I. INTRODUCTION Power system of Bosnia and Herzegovina (BiH) has been severely damaged during the war 1992-1995. Pre-war BiH transmission network and the actual state is shown scematically in fig.1. Rehabilitation and reconnection of BiH power system with power system of Croatia is planned to be completed by the end of 2005 (European Community POWER III plan). In the meantime, reduced availability of transmission network (400 and 220 kv) causes many operational problems and prevents full use of some plants' capabilities. One of such plants is pumped-storage hydro power plant (PS HPP) Čapljina (2x240 MVA, commissioned in 1979), situated in the southern part of BiH power system. It is connected via two 220 kv transmission lines (37.4 km, 2x360mm 2 AlFe) to 220 kv bus Mostar 4 which was connected in the pre-war system by two 400 MVA transformers to the 400 kv network (so called "Adriatic Line"). The plant was designed for night pumping/daily peak operation (typically 225 days/year), and for generator operation (typically 140 days/year, 12-14 hours/day in favourable hydrological conditions) and also as synchronous compensator (±150 Mvar). In the pre-war power system (1990) all foreseen regimes were possible with no limitations, including asynchronous start of the units into motor operation with or without phase reactors at the starpoint. Since beginning of the war HPP Čapljina, although not damaged itself, has been operating with significant restrictions. Pumping has not even been attempted because of the belief that the damaged system would be too weak to support asynchronous start of the units. On the other hand, the importance of this plant to the system can be illustrated by the following figures: in 1991 its total electricity production was 481.925 MWh, with 110 starts into motor operation and 6 starts into compensator regime. Total number of starts since 1979 was 1621, and in 1990 there was the highest annual number of starts (258). In the period 1982-1991 total energy for pumping amounted to 1,774 206 MWh, resulting in the production of 1,312 912 MWh from pumping with the very high ratio equal to 0.74. To fully exploit its outstanding capabilities it was decided to investigate possibilities and necessary conditions for asynchronous start and pumping of HPP Čapljina units in the present power system of Bosnia and Herzegovina and neighbouring power system of Croatia (particularly with respect to its southern part and "Adriatic Line"). To that purpose a study was performed to provide the necessary answers from the system point of view. The study comprised: (i) steady state analysis with particular observation of voltage profile/reactive power support, (ii) short circuit calculation in order to determine system short circuit capacity (i.e. system "stiffness"), and (iii) dynamic simulation of chosen scenarios of asynchronous starts.

A Obersielach KAINACHTAL MARIBOR Cirkovce VIZ HU I REDIPUGLIA Padricano HPP TPP OKROGLO Kle~e Diva~a DIVA^A Pehlin Rijeka Plom in KR[KO BERI^EVO SLO MELINA PO DLO G Brinje Senj line out of service in present configuration TUM BRI 400 kv line existing in 1990 and present network 400 kv line in present network not existing in 1990 400 kv line existing in 1990 but not in present network 220 kv line existing in 1990 and present network 220 kv line in present network not existing in 1990 220 kv line existing in 1990 but not in present network Mraclin Biha} Sisak HR BiH Me uri} Prijedor PS HPP VELEBIT BANJA LUKA Jajce \akovo Grada~ac Zenica ERNESTINOVO Kakanj SARAJEVO Ram a Jablanica KONJSKO BUK BIJELA Bilice Grabovica Orlovac Salakovac M OSTAR GACKO Piva Zaku~ac Mostar4 Dubrovnik UGLJEVIK TU ZLA TREBINJE MLADOST VI[EGRAD YU PO DG O RICA Figure 1 Power system of BiH and neighbouring power systems pre-war state (1990) and actual configuration A II. STEADY STATE ANALYSIS Load flow analysis Having in mind actual power system condition in the region of Herzegovina (BiH) and Dalmatia (Croatia), special attention has been payed to system security issues. According to UCTE recommendations each member should take care of minimizing risk of unwanted influence of disturbances in its own system to neigbouring systems. This is of special importance in case of major power plants such as HPP Čapljina connected to relatively weak transmission network. Currently, power system of BiH is connected through Croatian power system to UCTE (I. synchronous zone) via interconnection lines Mostar 4 Konjsko (400 kv, operating under 220 kv), Mostar 4 Zakučac (220 kv) and Tuzla Đakovo (220 kv). It should be noted that HPP Čapljina is radially connected to 220 kv bus Mostar 4. Power system model for steady state analysis comprised power system models the part of the BiH system being in the I. UCTE synchronous zone (400, 220 and 110 kv levels), and power systems of Croatia and Slovenia.(400 and 220 kv levels), with slack bus in Divača. All generating units were modelled with unit transformers and it was assumed that voltage regulators would keep nominal voltage at generator terminals within actual capability chart limits. Steady state analysis was performed for assumed actual network configuration, light load condition (night period) and several variants of generator scheduling. The following system state(s) have been considered: (i) immediately before asynchronous start, (ii) during the start (one quasi-steady state), (iii) after synchronization of the unit at HPP Čapljina to the system, and (iv) during pumping. On basis of this analysis minimum requirements to the power system have been established. According to operation experience and previous field test results (1979), the system should provide approximately 20 MW and 200 Mvar during asynchronous start of one unit at HPP Čapljina with phase reactors at the starpoint and with no water in turbine. Obviously, this is primarily voltage/reactive power problem. Basic requirement for succesful asyncronous start is that the power system must be "stiff" enough (sufficient short circuit capacity at the connection point) and should have sufficient reactive power reserve in order to prevent excessive voltage sags in the network during the start.

In case of HPP Čapljina both power systems of BiH and Croatia would play key role in providing system service of supporting asynchronous start. Two of several considered network configuration/generator scheduling cases were found acceptable: BC-1 - with one generator at HPP Rama and one generator at HPP Dubrovnik, and BC-2 - with one generator scheduled at each of the HPPs near Mostar 4 (Rama, Salakovac, Grabovica) but without HPP Dubrovnik. In both cases one generator at HPP Zakučac in Dalmatia was assumed to be in operation. In given conditions all generators had sufficient reactive power reserve for supporting asynchronous start. Analysis results are briefly summarized in figs. 2 and 3. Reactive power outputs of selected generators (for states immediately before and during asynchronous start in both above described cases) are shown in bar-graph form in fig. 2 along with generator reactive capabilities. Voltage profiles in the representative 220 kv nodes before and during start are shown in fig. 3. Bus voltages were initially rather high (night period of daily load diagram) and in both cases remained above nominal values during the start (fig 3). In both cases reactive capability of nearby generators was fully used, i.e. without any safety margin. To provide additional reactive power support during the start it was decided to operate the other unit at HPP Čapljina in generatorcompensator regime with rated voltage at the generator terminals. B. Short circuit calculation results As already mentioned, short circuit currents and powers at connection point are important indices of system capability to support asynchronous start. Short circuit capacity at the connection point should be greater than certain minimum value ((i.e. equivalent system impedance should be less than certain maximum value). This critical value can be determined on a single machine inifinite bus model by applying criteria that the machine current, bus voltage drop and duration of start are kept below acceptable limits. In the case of HPP Čapljina this value is about 3600 MVA at 220 kv bus Mostar 4. This value is very convenient for practical purposes because it could be verified in the real system by measuring the equivalent reactance of the system seen from 220 kv bus at HPP Čapljina once the desired system state is established. Since HPP Čapljina is connected radially to the system in the 220 kv node Mostar 4, short circuit calculations have been done for that node. It was assumed that the power system is in the state immediately before asynchronous start. Given the initial short circuit current I k " the initial (subtransient) threephase short circuit power S k " is calculated according to: Sk = c 3 U n I k (1) where c=1 for minimum short circuit [1]. Short circuit results are summarized in table 1. Short circuit levels for cases with 400 kv network partially restored and with transmission network fully restored according to the POWER III project are given here for comparison. Q (MVAr) Q (MVAr) 160 140 120 100 80 60 40 20 0 160 140 120 100 80 60 40 20 0 Qgmax A2 - during start A1 - before start Qgmax A4 - during start A3 - before start RAMA GRABOVICA SALAKOVAC TE KAKANJ 7 TE TUZLA 6 DUBROVNIK ZAKUČAC Figure 2. Generator reactive powers before and during the start, cases BC-1 and BC-2 U (kv) U (kv) 250 245 240 235 230 225 220 215 210 250 245 240 235 230 225 220 215 210 RAMA RAMA A1 - before start A2 - during start GRABOVICA A3 - before start A4 - during start GRABOVICA SALAKOVAC SALAKOVAC TE KAKANJ 7 TE TUZLA 6 DUBROVNIK TE KAKANJ 7 TE TUZLA 6 DUBROVNIK BC-1 BC-2 ZAKUČAC MOSTAR 4 KONJSKO 220 ZAKUČAC MOSTAR 4 KONJSKO 220 Figure 3. Bus voltages (220 kv) before and during the start, cases BC-1 and BC-2 Table 1 Short circuit calculation results for Mostar 4 BC-1 BC-2

CASE BC-1 (with HPP Dubrovnik 220 kv) BC-2 (with HPP Salakovac and HPP Grabovica) Base case(bc-1) + TL 400kV Sarajevo 10-Mostar 4 Konjsko and transformation at Mostar4-2x400MVA Peak load 2005 (after completion of the 'POWER III' project) U Mostar 4 (pre-fault) (kv) I 3 F (ka) S 3 F (MVA) 236.5 8.184 3348 237.7 8.925 3671 244.5 9.513 4040 241 18.167 7574 The base case with HPP Dubrovnik has the lowest short circuit level which is near/slightly under the estimated critical value (3600 MVA) and the base case variant with HPP Salakovac and Grabovica has only marginally higher short circuit level. In both cases it was obviously necessary to check system behaviour by performing dynamic simulations of the start. With 400 kv network partially restored the situation becomes favourable while in the last case with fully restored network the short circuit level exceeds the value of 7000 MVA in which case even direct asynchronous start (without the phase reactors) would be possible. III. DYNAMIC SIMULATION RESULTS Simulations of system dynamics during asynchronous start of one unit at HPP Čapljina with phase reactors in its starpoint were performed on the multimachine model of the BiH power system and relevant parts of the neighbouring Croatian system (the same extent as in steady state analysis). Excitation systems with automatic voltage regulators and maximum field current limiters as well as turbine governors were modelled for all generators represented with subtransient models. Model parameters were determined on basis of available equipment data. The motor/generator at HPP Čapljina was represented with the equivalent double-cage induction machine. Its parameters were determined by fitting the model response against the time responses of the actual machine during start, recorded in 1979. The main purpose of the dynamic simulation was to confirm the preliminary conclusion based on steady state analysis that the asynchronous start could be succesfully performed in given system conditions. It should also make planning and performing of field tests easier by providing deeper insight into system dynamic behaviour during the process. Two cases were simulated: providing entire reactive power support (200 Mvar) as a system service AS-2) asynchronous start of one motor/generator at HPP Čapljina with the other machine operating in generator/compensator regime at rated voltage, in which case the system service is reduced by approximately 50% Thirty-two quantities (motor/generator speed, bus voltages, generator active and reactive powers, active and reactive power flows in transmission lines, generator angles,...) were monitored during the simulation. Simulation results for both cases are illustrated simultaneously in Fig. 5 by time diagrams of representative variables. Values of bus voltages at four characteristic moments are compared in fig. 4 for both cases (AS-1 and AS-2). Duration of the start up to reaching the synchronous speed is 126 seconds. The system response is stable and machine oscillations are well damped. Bus voltages remain above the limits all the time during the start. As expected from steady state analysis, in case AS-1 generators at HPP Zakučac, HPP Rama and HPP Dubrovnik reached their maximum reactive power in the overexcited region. Naturally, in case AS-2 bus voltage deviations are even smaller and none of the generators reached its reactive power limit due to support of the other machine at HPP Čapljina. Duration of the start was 115 seconds. In either case there was no operation of overexcitation limiters. voltage (pu) 1.3 1.2 1.1 1 0.9 0.8 0.7 0.6 0.5 before start 0.4 s after beginning during start at synchronous speed pump (motor) Čapljina 220 Mostar 4 220 voltage (pu) 1.3 1.2 1.1 1 0.9 0.8 0.7 0.6 0.5 before start 0.4 s after beginning during start at synchronous speed pump (motor) Čapljina 220 Mostar 4 220 AS-1 AS-2 Fig. 4 Representative bus voltages at characteristic moments during asynchronous start This dynamic simulation results confirmed that it would be possible to perform asynchronous start in given "minimum" conditions. These results proved also very useful in the process of planning actual field tests. AS-1) asynchronous start of one motor/generator without support of the other machine at HPP Čapljina in which case the power system is responsible for

AS-2 Start with support from the other HPP Čapljina machine as generator-compensator motor/generator slip AS-1 Start without support from the other HPP Čapljina machine U Mostar 4 reactive power in TL Mostar 4 - Čapljina Figure 5. Results of asynchronous start dynamic simulations, cases AS-1 and AS-2 time diagrams of representative variables IV. TRANSMISSION CAPACITY NECESSARY FOR PUMPING In two characteristic cases electric power and energy required for pumping can be secured: PC-1) from UCTE interconnection, in which case the Croatian power system must provide transmission capacity for that service PC-2) from power plants within power system of BiH. In the first case (PC1) practically the entire power for pumping is transported over transmission network in Dalmatia (southern Croatia). Security criterion (n-1) is not satisfied since the outage of the 400 kv line Melina Velebit results in overloading and outage of the 220 kv line Brinje Konjsko followed by the outage of the 220 kv line Tuzla Đakovo, leading eventually to separation of power systems of Dalmatia, Bosnia and Herzegovina from UCTE, probably ending with voltage and frequency collapse, i.e. total blackout in the so formed island. This scenario obviously requires careful operational planning and precisely defined procedures in order to prevent spreading of disturbances. The second case (PC-2) is more favourable because in that scenario there are no (n-1) security limitations (also thermal generating unit outage??). Besides, available (coal-fired) thermal power plants in the BiH, which sometimes were operating at or even below their technical minimum (using oil), can be more economically used. At the same time transmission costs for pumping could be significantly reduced compared to case PC-1. V. CONCLUSION Steady-state analysis results indicated that security of BiH power system and neighbouring power systems would not be endangered during asynchronous start of one unit at HPP Čapljina with phase reactors at the starpoint and with no water in tne turbine. Short circuit capacity at Mostar 4 node depends much on the actual system configuration and generator scheduling. Before the 400 kv network is restored it is about the critical level. Reactive power support from nearby generators is of utmost importance so that their actual reactive power capabilities, at this stage determined from capability charts, must be revised taking into account effects of automatic voltage regulators and associated limiting devices. This was done, on basis of available data, in dynamic simulations. Results of dynamic simulations confirmed the preliminary conclusion and gave valuable insight into system dynamic behaviour. All system quantities are within acceptable limits but nearby generators are pushed to their reactive power limits. If the other machine at HPP Čapljina operates as generator/compensator prior to and during the asynchronous start, requirements from the system are significantly decreased. Since that means safer start and reduced risk to the system, this variant is to be preferred and should become regular operating scenario, at least until the transmission system is fully restored. Finally, actual system behaviour should be tested by performing corresponding field tests. These tests should be carefully planned and should cover system-wide monitoring of relevant plants. Study results should be extensively used in preparing the tests, i.e. for checking settings of protection

devices, defining requirements to recording devices, investigate scenarios in case of unsuccesful start and so on. VI REFERENCES [1] IEC 909 Standard [2] N. Rusanov: The possibility of the asynchronous start [3] motor/generator PHPP Capljina (2x240 MVA) into consideration on the limitations power network, Study report, ZEKC, Sarajevo, October 2001. [4] N.Rusanov, H. Ferizovic: The Dynamic Performance of Power System B&H, Study report, JP EP BiH, Sarajevo, 2000. [5] M.S. Čalović: Regulacija elektroenergetskih sistema Tom 1 i Tom 2: Beograd 1997. [6] Excitacion System Models for Power System Stability Studies, IEEE Transactions on Power Apparatus and Systems, Vol. Pas-100, No 2. pp. 494-509 1981. (Committe Report). [7] PSS/E Program Application Guide & Program Operation Manual VII BIOGRAPHIES N.Rusanov was born in 1946. at Karlovac, Croatia. He received his degree in 1971 at the Elctrotehnical faculty. At the same university, in 1983. he finished M. Sc. degree and made final dissertation about voltage regulation of generators and transmission networks. Same year when he received diploma, he was employed by the Enterprise for production, transmission and distribution electrical energy Elektroprivreda Bosnia & Herzegovina. Immediately he started with scientific investigation. In this time, his firm formed dynamic model of electrical power system (micro network), and he made some projects and constructed specific equipment for this laboratory. Since 1985. till beginning war he was head of this laboratory. His professional orientation are load flow analysis, voltage and reactive power regulation in transmission networks and dynamic stability in power systems. Hi is the author a lot of essays about these problems end results were applied in Power system BiH. Before 1991. he was a member of some expert groups of JUGEL (ex Yugoslavia) and he published more then 30 professional essays in journals and consultations. Since 1987. he was a secretary of JUKO CIGRE (former Yugoslavia) Study Committee 38. After established BiH Committee CIGRE, he is the Chairman of Study Committee 38. In this moment, he is elected to observer member of the International Committee CIGRE, SC 38. author a lot of papers on the field HPP and the systems of uninterruptible power supply. He is an outstanding specialist in field of power sources of wind, water and trash. M. Stojsavljević was born in 1946 at Velika Popina, Croatia. He received his B.S. and M.S. degrees from Faculty of Electrical Engineering, University of Zagreb, in 1969 and 1980 respectively. In 1969 he was employed by Electrotechnical Institute "Rade Končar", first as a field test engineer, then in development and testing of control systems. He participated in numerous projects in the field of power system stability and control, e.g. dynamic stability enhancement of power system of former Yugoslavia in parallel operation with UCPTE (1973). From 1984 to 1991, he was the manager of Power plants and systems division in "Končar" Institute. Since 1991 he is with Energy Institute Zagreb. Currently, he is head of the Department for analysis of electric power plants and systems. He was a member of the CIGRE Task Forse 38.01.09: Requirement and Performance of Excitation Systems. From 2000 he is chairman of the Study Committee 38 of Croatian CIGRE. D. Nemec was born in 1961 in Zagreb, Croatia. He received his B.S. and M.S. degrees from Faculty of Electrical Engineering, University of Zagreb, in 1983 and 2000 respectively. From 1983 to 1991, he was employed in Končar Electrotechnical Institute where he was working in the field of power system modelling, analysis and testing. Since 1991 he is with Energy Institute Zagreb. His main area of interest is modelling and analysis of power system dynamics and control. From 2000 he is secretary of the Study Committee 38 of Croatian CIGRE. S. Vucina was born at Mostar, Bosnia and Herzegovina. He received his B.S. degrees from Faculty of Electrical Engineering, University of Sarajevo in 1975. Since 1978 he was working as leading engineer for equipment for HPP Grabovica (2x57 MW). Since 1984 he was working in numerous search and development hydro projects, and special interconnection projects of HPP with Power system. Hi is the