U.S. Progress in ADS-B Systems Development and Implementation

Similar documents
Place image here (10 x 3.5 ) FAA NEXTGEN DATA COMM TOWER SERVICE: CPDLC DCL NEW OPERATOR INTRODUCTION HARRIS.COM #HARRISCORP

The Anatomy of Delays:

Data Communications Program

Surveillance and. Overview. Federal Aviation Administration Broadcast Services. Presented to: ADS-B Technology Forum. By: Andy Leone, FAA, SBS Program

Passengers Boarded At The Top 50 U. S. Airports ( Updated April 2

World Class Airport For A World Class City

World Class Airport For A World Class City

World Class Airport For A World Class City

3.3 Specific Developments in Air Navigation CNS AUTOMATIC DEPENDENT SURVEILLANCE BROADCAST (ADS-B) (Presented by the United States of America) SUMMARY

World Class Airport For A World Class City

Place image here (10 x 3.5 ) FAA NEXTGEN DATA COMM TOWER SERVICE: CPDLC DCL NEW OPERATOR INTRODUCTION HARRIS.COM #HARRISCORP

SEPTEMBER 2014 BOARD INFORMATION PACKAGE

Industry Voluntary Pollution Reduction Program (VPRP) for Aircraft Deicing Fluids

The O Hare Effect on the System

2016 Air Service Updates

2016 Air Service Updates

79006 AIR TRAVEL SERVICES 2001 AWARD

TravelWise Travel wisely. Travel safely.

En Route Merging and Spacing Preparation

FLIGHT TEST & SAFETY CONSULTANTS, LLC FLIGHT READINESS REVIEW (FRR)

ATO Program Management Organization. ADS-B Program Status. Federal Aviation Administration. ICAO NAM/CAR/SAM ADS-B Implementation Meeting & Workshop

2016 Air Service Updates

Surveillance and. Program Status. Federal Aviation Administration Broadcast Services. To: By:

2016 Air Service Updates

October Air Traffic Statistics. Prepared by the Office of Corporate Risk and Strategy

November Air Traffic Statistics. Prepared by the Office of Corporate Risk and Strategy

Surveillance and Broadcast Services

2012 Airfares CA Out-of-State City Pairs -

PITTSBURGH INTERNATIONAL AIRPORT ANALYSIS OF SCHEDULED AIRLINE TRAFFIC. October 2016

Have Descents Really Become More Efficient? Presented by: Dan Howell and Rob Dean Date: 6/29/2017

Associates 2009 Rental Car Satisfaction Study SM (Page 1 of 2)

September Air Traffic Statistics. Prepared by the Office of Corporate Risk and Strategy

Airport Surface Detection. ASDE-X and Data Distribution System Overview. Presented to the Tarmac. Federal Aviation Administration

DEPARTMENT OF HOMELAND SECURITY U.S. CUSTOMS AND BORDER PROTECTION. CBP Dec. No EXPANSION OF GLOBAL ENTRY TO NINE ADDITIONAL AIRPORTS

MANGO MARKET DEVELOPMENT INDEX REPORT

Trusted Traveler Program Overview and Best Practices. February 2017

Aviation Gridlock: Airport Capacity Infrastructure How Do We Expand Airfields?

AGENCY: U.S. Customs and Border Protection; Department of Homeland Security.

United States Aircraft Certification Standards and Guidance on ADS-B

Escape the Conventional. Air Access Report January 2014 to March 2014

Lower Income Journey to Work Market Share From American Community Survey

Trends Shaping Houston Airports

Distance to Jacksonville from Select Cities

ENRI International Workshop on ATM/CNS

Mango Market Development Index

Kansas City Aviation Department. Update to Airport Committee January 26, 2017

Beyond Measure jdpower.com North America Airport Satisfaction Study

TERMS OF REFERENCE Special Committee (SC) 186 Automatic Dependent Surveillance Broadcast (ADS-B) Revision 22

June Air Traffic Statistics. Prepared by the Office of Corporate Risk and Strategy

August Air Traffic Statistics. Prepared by the Office of Corporate Risk and Strategy

Benefits Analysis of a Runway Balancing Decision-Support Tool

air traffic statistics

October 2018 October 2017 Change

July air traffic statistics. Prepared by the Office of Corporate Risk and Strategy

8th USA/Europe. Paper #141: Lateral Intent Error s Impact on Aircraft Prediction. Federal Aviation Administration ATM R&D Seminar

September Air Traffic Statistics. Prepared by the Office of Marketing & Consumer Strategy

Avionics Session. Monday, March 21, :30 p.m. 4:45 p.m. Moderated BY: Carey Miller

Enhancing Air Service Through Community Partnerships ACI NA Marketing & Communications Partnering with Carriers

Capacity Constraints and the Dynamics of Transition in the US Air Transportation

August air traffic statistics. Prepared by the Office of Corporate Risk and Strategy

Uncertainty in Airport Planning Prof. Richard de Neufville

Harvest Donation Program

air traffic statistics

Westshore Development Forum April 11, Hillsborough County Aviation Authority

Performance Metrics for Oceanic Air Traffic Management. Moving Metrics Conference Pacific Grove, California January 29, 2004 Oceanic Metrics Team

PFC Collection Analysis

Managing And Understand The Impact Of Of The Air Air Traffic System: United Airline s Perspective

January Air Traffic Statistics. Prepared by the Office of Marketing & Consumer Strategy

J.D. Power and Associates Reports: Customer Satisfaction with Airports Declines Sharply Amid an Industry Fraught with Flight Delays

JANUARY 2014 BOARD INFORMATION PACKAGE

TSA Pre. July 18, 2016

Fort Lauderdale August 8, 2017

February Air Traffic Statistics. Prepared by the Office of Corporate Risk and Strategy

August Air Traffic Statistics. Prepared by the Office of Marketing & Consumer Strategy

December Air Traffic Statistics. Prepared by the Office of Marketing & Consumer Strategy

ADS-B Seminar. National Institutes of Aviation Management and Research (NIAMAR) Rangpuri, Maharuli, New Delhi

Rank Place State Native Hawaiian and Pacific Islander population (alone or in combination

Future ATM Concepts & Technology

Free Flight En Route Metrics. Mike Bennett The CNA Corporation

ADS-B. Not just a mandate! Forrest Colliver Becker Avionics GmbH Becker Avionics GmbH All rights reserved -

air traffic statistics

May Air Traffic Statistics. Prepared by the Office of Corporate Risk and Strategy

FAA Progress on Wake Avoidance Solutions for Closely Spaced Parallel Runways (CSPR)

TERMS OF REFERENCE Special Committee (SC) 186 Automatic Dependent Surveillance Broadcast (ADS-B) Revision 18

Hector International Airport Fargo, North Dakota

National Airspace System Infrastructure Management Conference

STRATEGY/ACTION PLAN FOR IMPLEMENTATION OF REDUCED VERTICAL SEPARATION MINIMA IN THE AFRICA-INDIAN OCEAN REGION 22 NOVEMBER 2003

(Presented by the United States)

Puget Sound Trends. Executive Board January 24, 2019

Airline Dispatchers Federation Leading the Way By Strategic Collaboration. Orlando, FL October 11, 2012

Kansas City Aviation Department. Update to Airport Committee October 20, 2016

CANSO Workshop on Operational Performance. LATCAR, 2016 John Gulding Manager, ATO Performance Analysis Federal Aviation Administration

NextGen and GA 2014 Welcome Outline Safety Seminars Safety Seminars

2012 Airport Ground Transportation

2011 AIRPORT UPDATE. March 25, 2011

Optimized Profile Descents A.K.A. CDA A New Concept RTCA Airspace Working Group

South Florida Customer Advisory Group: Quarterly Meeting. Federal Aviation Administration

February Air Traffic Statistics. Prepared by the Office of Marketing & Consumer Strategy

Hector International Airport Fargo, North Dakota

ADS-B/IMP IP/05 21/04/15 Automatic dependent surveillance broadcast (ADS-B) Implementation Meeting (ADS-B/IMP) Mexico City, Mexico, April 2015

Transcription:

U.S. Progress in ADS-B Systems Development and Implementation 3rd ENRI International Workshop on ATM/CNS February 20, 2013 Presenter: Mark Reeves Author: Doug Arbuckle

ADS-B Service Architecture ADS-B UAT 1090ES ADS-R UAT 1090ES Non-Equipped Non-Equipped Radio Station Radio Station FIS-B Provider Control Station FAA FIS-B Provider Control Station FAA Surveillance of ADS-B equipped aircraft for Air Traffic Control and Aircraft Situational Awareness Cross-Linking of ADS-B data for Aircraft Situational Awareness TIS-B UAT 1090ES FIS-B UAT 1090ES Non-Equipped Non-Equipped Radio Station Radio Station FIS-B Provider Control Station FAA FIS-B Provider Control Station FAA Uplink of Surveillance Data of Non-ADSB equipped aircraft for Aircraft Situational Awareness Copyright 2007, ITT Corp., and used by permission Uplink of Weather and other Flight Information for UAT Equipped Aircraft

Implementation Status February 4, 2013 http://www.faa.gov/nextgen/flashmap/ 445 Operational Radio Stations 4

FY13 En Route Sites (12 ERAM sites) Site SBS Infrastructure Pilot Advisory Services Automation Ready ADS-B IOC 1 Chicago (ZAU) February 2013 2 New York (ZNY) March 2013 3 Boston (ZBW) March 2013 4 Cleveland (ZOB) May 2013 5 Washington (ZDC) February 2013 May 2013 6 Indianapolis (ZID) March 2013 June 2013 7 Miami (ZMA) August 2013 August 2013 8 Kansas City (ZKC) April 2013 August 2013 August 2013 9 Memphis (ZME) April 2013 August 2013 March 2013 August 2013 10 Ft. Worth (ZFW) April 2013 June 2013 August 2013 11 Oakland (ZOA) September 2013 12 Los Angeles (ZLA) September 2013 13 Atlanta (ZTL) June 2013 FY2014 14 Jacksonville (ZJX) September 2013 FY2014 15 Salt Lake City (ZLC) October 2013 February 2014 FY2014 As of 1/23/2013 5

FY13 Terminal Sites: 31 sites (3 CARTS, 28 STARS) CARTS STARS Site SBS Infrastructure Pilot Advisory Services Automation Ready ADS-B IOC ATC Separation Services Operational 1 Atlanta (ATL) February 2013 June 2013 2 Potomac (PCT) March 2013 May 2013 3 Chicago (C90) March 2013 March 2013 1 Orlando (MCO) 2 Cleveland-Hopkins (CLE) 3 Jacksonville (JAX) 4 Pensacola (P31) 5 Charlotte (CLT) 6 Tucson (U90) 7 Norfolk (ORF) 8 Raleigh-Durham (RDU) 9 Pittsburgh (PIT) February 2013 10 Phoenix (P50) 11 Santa Barbara (SBA) February 2013 12 Albany (ALB) March 2013 March 2013 March 2013 13 Milwaukee (MKE) March 2013 February 2013 March 2013 March 2013 As of 1/23/2013 6

STARS FY13 Terminal Sites: 31 sites (3 CARTS, 28 STARS) Site SBS Infrastructure Pilot Advisory Services Automation Ready ADS-B IOC ATC Separation Services Operational 14 Bradley-Windsor (Y90) February 2013 March 2013 March 2013 15 Syracuse (SYR) March 2013 April 2013 16 Columbus (CMH) February 2013 February 2013 March 2013 April 2013 17 Indianapolis (IND) March 2013 March 2013 April 2013 18 Detroit (D21) March 2013 February 2014* 19 Nashville (BNA) March 2013 March 2013 April 2013 April 2013 20 Tampa (TPA) February 2013 April 2013 May 2013 21 Memphis (M03) March 2013 April 2013 April 2013 May 2013 22 Lubbock (LBB) April 2013 May 2013 May 2013 June 2013 23 Little Rock (LIT) May 2013 May 2013 June 2013 June 2013 24 Birmingham (BHM) April 2013 April 2013 June 2013 July 2013 25 Covington-Cincinnati (CVG) May 2013 May 2013 June 2013 July 2013 26 Omaha (R90) March 2013 July 2013 June 2013 July 2013 July 2013 27 Rochester (ROC) February 2013 July 2013 July 2013 28 Boston (A90) April 2013 July 2013 July 2013 August 2013 September 2013 29 Providence (PVD) April 2013 July 2013 July 2013 FY2014 FY2014 *Due to PRM-A integration As of 1/23/2013 7

FY13 Surface Advisory Sites (15 Sites) Site SBS Infrastructure Pilot Advisory Services ASDE-X Upgrade ATC Services Operational 1 Houston Intercontinental (IAH) January 2013* January 2013* 2 Atlanta (ATL) February 2013 February 2013 3 Milwaukee (MKE) February 2013 February 2013 February 2013 4 Denver (DEN) February 2013 March 2013 5 Baltimore-Washington (BWI) April 2013 April 2013 6 Detroit Wayne County (DTW) April 2013 April 2013 March 2013 April 2013 7 Chicago Midway (MDW) April 2013 April 2013 April 2013 June 2013 8 Los Angeles (LAX) June 2013 July 2013 9 John F Kennedy (JFK) May 2013 June 2013 June 2013 July 2013 10 Providence (PVD) February 2013 August 2013 May 2013 August 2013 11 Bradley International (BDL) February 2013 August 2013 June 2013 August 2013 12 Memphis (MEM) June 2013 May 2013 August 2013 13 Chicago O Hare (ORD) May 2013 July 2013 June 2013 August 2013 14 Washington Dulles (IAD) June 2013 July 2013 July 2013 August 2013 15 Minneapolis St. Paul (MSP) June 2013 September 2013 June 2013 September 2013 *will be missed 8

FAA Funded Avionics Upgrades ADS-B Out Aircraft: 35 A320 STC approved July 2012 All 35 modifications complete ADS-B Out Aircraft: 143 13 747 39 767 53 A300 38 MD11 STC for 767 and 747/767 AML approved (December 2011 and January 2012, respectively) 39 installs complete; Upgrades complete by June 2014 ADS-B Out and In Aircraft: 12 747 STC approved June 2011 12 ADS-B In equipped; Upgrades to DO-260B in 2014 ADS-B Out Aircraft: 110 737NG Boeing Service Bulletin expected Apr 2014 Upgrades to DO- 260B complete by December 2017 ADS-B Out Aircraft: 54 helicopters (9 Chevron and 45 PHI) STC for Chevron approved June 2012; Approval expected February 2013 for PHI Upgrades to complete by 2015 ADS-B Out and In Aircraft: 20 A330-300/200 STC for ADS-B Out approved August 2012; STC for Merging & Spacing approved January 2013 7 ADS-B Out installs complete Upgrades complete by October 2013 ADS-B Out Aircraft: Up to 400 legacy Capstone aircraft Request for Offer released September 2012 and contract award in spring 2013 Upgrades targeted for completion by December 2014 9

Vehicle ADS-B Summary June 2011 Development of MOA partnership with Massport November 2011 First article Vehicle ADS-B unit delivered to FAA for performance testing at WJHTC May 2012 Production unit FAA testing completed September 2012 AC updated with approved unit September 2012 $1.2M in AIP grants for Chicago, Denver, and San Francisco for Vehicle ADS-B units December 2012 Completion of 37 total installations at BOS February 2013 (planned) Testing of mod to continue transmission with loss of GPS at Boston Sites Pending St. Louis and Milwaukee 10

Ground-Based Interval Management - Spacing Purpose: Minimize vectoring during arrival sequence and maximize the opportunities for OPDs and FIM-S operations Goal: Achieve optimal spacing intervals between arriving aircraft using an ATC based spacing/metering tool Objective: Ensure NAS implementation of GIM-S functionality to begin benefits accrual (GIM-S IOC) Partners: TBFM, ERAM, ATO-T Safety and Operations and ATO-E Safety and Operations In Progress Not Yet Started * Activity Target Key Site Approval Key Site Outreach to Facility GIM-S Test Plan* End-End Test at WJHTC End-End Test at Key Site GIM-S IOC* Jan 2013 Apr 2013 Aug 2013 Jan 2014 Aug 2014 Sep 2014 12

Flight-deck-based Interval Management (FIM) Purpose: Reduce fuel burn, noise and emissions, while maintaining high throughput and efficient flight operations throughout the NAS Goals: Develop and validate flight deck technology to enable FIM-S Operations Objective: Produce a FIM MOPS Partners AIR, AFS, RTCA, EUROCAE In Progress Not Yet Started Unfunded *Activity Target 2017+ IM CONOPS* Scope Agreement for MOPS Preliminary OPA* Detailed OSA* TFID Final Report FIM-S MOPS* Feb 2013 Mar 2013 Jun 2013 Aug 2013 Jan 2014 May 2014 13

In-Trail Procedures Purpose: Goal: Provide operational benefits in non-surveillance airspace by enabling in-trail climbs/descents at reduced separation distances Employ ITP in oceanic air carrier operations (revenue service) Objectives: Validate operational performance and economic benefits of ITP Develop and validate ADS-B ITP MOPS material Partners: United Airlines, Honeywell, Goodrich, Airservices Australia, Airways Corp NZ Desired Altitude Standard Separation ITP Separation Standard FL360 FL350 FL340 In Progress Not Yet Started ITP OpEval Results Year 1 d Begin 2 nd Year ITP OpEval ITP OpEval Results Year 1.5 2 nd Year ITP OpEval ATOP ITP Modifications d ATOP ITP Modifications Implemented August 2012 Sept 2012 March 2013 August 2013 TBD 2015 TBD 2016 14

ITP Operational Evaluation Metrics January 2013 Application Validation Metric Southern Pacific Expected Measurement Actual Measurement Northern Pacific Expected Measurement Actual Measurement Number of trained and approved pilots (747 subfleet) 598 (Expected) /171 (Actual) 171 Number of ITP capable flights (ITP aircraft, pilot and airspace) 60 18 120 23 168 Number of ITP requests 2 0 30 2 19 Number of ITP maneuvers performed 1 0 3 1 9 Number of "standard" flight level changes resulting from an ITP request 1 0 24 0 7 Totals 8/12-1/13 * Any CDPs are included in standard climbs Safety measurements Parameter to be Monitored Expected Avg. Actual Measurements Measurements (8/12-1/13) Measurement Min Mean Max Min Mean Max ITP Initiation Distance 20 nm 49.1 49.1 49.1 19.1 34.2 59.1 ITP Distance at Co-altitude 18 nm 48.8 48.8 48.8 20.2 34.4 59.7 Time From ITP Initiation to Level Off at New 7 min 4 4 4 2.0 3.9 6.0 Percentage of ITP maneuvers where a wake encounter occurred and a wake turbulence incident 2% * Wake Turbulence Incident Severity (5-1)** 5 ** 5 is minimal, 1 is catastrophic 15

Traffic Situation Awareness with Alerts (TSAA) Purpose: Enhance safety in the National Airspace System by providing alerts to General Aviation pilots of conflicting airborne traffic Goals: Reduce the risk of airborne aircraft-to-aircraft encounters Expand ADS-B benefits for General Aviation Objective: MOPS, TSO Partners: MIT/Avidyne Stakeholders: AOPA, GAMA, HAI, ALPA ConOps and Stakeholder Buy-in Mature OSED Simulations OPA Airport Analysis Flight Tests MOPS Approved In Progress Not Yet Started May 2011 Oct 2011 Sept 2012 March 2013 May 2013 Sept 2013 16

ADS-B-In Aviation Rulemaking Committee First meeting held July 1, 2010 Member Affiliation Requested Deliverables: Task 1: Endorsement (or not) of continued work on 3 ADS-B-In application standards development projects by October 2010 Task 2: Final ARC ADS-B-In Strategy Recommendations by September 2011 Released to Public on 9-Nov-2011 Task 3: all follow on work by June 2012 17

U.S. Public Law 112-95, section 211(b) (February 14, 2012) Requirement: Directs Administrator to initiate rulemaking proceeding within 1 year after enactment to issue guidelines & regulations relating to ADS-B In Rulemaking scope: by 2020, all aircraft operating in one of below to be equipped with ADS-B In technology in capacity constrained airspace at capacity constrained airports or in any other airspace deemed appropriate Before issuing a final rule, Chief NextGen Officer must verify necessary ground infrastructure is functioning properly certification standards are approved appropriate operational platforms interface safely and efficiently 18

Modified Approach Revised ADS-B-In ARC Tasking (May 2012) By October 31, 2012, submit recommendations on how to frame an ADS-B In equipage mandate such that benefits exceed costs before 2035 ARC asked to identify: In what airspace, and/or At what airports, and/or Other criteria FAA could apply to frame an ADS-B-In mandate (examples including by operator class or aircraft class) ARC requested to provide feedback on 2020 compliance date FAA Strategy to Initiate Rulemaking Application for Rulemaking Submitted to the Rulemaking Management Council (RMC) on August 14, 2012 Approved by RMC on September 11, 2012 Rulemaking Action Plan (RAP) Draft prepared and under FAA management review 19

Status: ADS-B-In Aviation Rulemaking Committee Member Affiliation Requested Deliverables: Task 1: Endorsement (or not) of continued work on 3 ADS-B-In application standards development projects by October 2010 Task 2: Final ARC ADS-B-In Strategy Recommendations by September 2011 Task 3: Recommendations on how to frame an ADS-B In equipage mandate by October 2012 Task 4: all follow on work by November 2012 20