2018 Project Presentation Delaware County Engineer 2018 ASHE LUNCHEON JANUARY 30, 2018
What s New at DCEO? New County Logos and Website Redesign GIS Upgrades Drone Program Planning for the Future ROADS, ROADS, ROADS!!!
New County Logos! Website redesign coming this spring!
GIS Upgrades Collecting GIS inventory and inspection data for roads, culverts, guardrail, storm sewers, Information will be available soon through DCEO webmap
Drone Program Two FAA Part 109 certified commercial remote pilots on staff Drone equipment has become very affordable Dozens of different applications
Construction Photos
Construction Photos
Construction Videos
Bridge Inspection
Traffic Studies
Roads, Roads, Roads!!! DCEO 5-year Capital Improvement Plan includes $120 million investment of County funds over next 5 years, leveraging another $125 million in federal, state and other local revenues
2017 Construction Summary 8 road and bridge construction contracts East Powell Road, Phase 1 (final 35%) - $0.8M of $2M Lewis Center and Bale Kenyon Intersection - $2.2M Bale Kenyon Road, Phase 1 - $2.4M Worthington and Big Walnut Intersection - $2.5M Klondike Road Bridge - $0.8M 2017 Design-Build Bridges (2 rural bridges) - $0.6M South Old State Road (30% complete) - $5M of $15M 2018 Road Improvement Program (resurfacing) - $8.2M $22.5 million of work completed
2018 Construction Program 11 construction projects scheduled Worthington & Highland Lakes Traffic Signal - $0.2M Liberty Road and Jewett Road Intersection - $1.3M Home Road at SR 315 (50% in 2018) - $3M of $6M South Old 3C Improvements (40% in 2018) - $2.5M of $6M Piatt Road Extension (30% in 2018) $1M of $3.2M Bainbridge Mills Drive Relocation - $0.4M S.R. 3 and Galena Road Intersection - $1.2M Home Road & Scioto Chase Traffic Signal - $0.2M Lewis Center & North Road Improvements 20% - $0.7M of $3.2M South Old State Road (completion) - $10M 2018 Road Improvement Program - $7.2M $28 million estimated work to be completed
North-South Corridor Projects South Old State Road Polaris Pkwy to Orange Road $15 million project, completion scheduled for fall 2018
North-South Corridor Projects Piatt Road Extension Cheshire to Berlin Station Rd. $3.2 million project, completion scheduled summer 2019
East-West Corridor Projects Home Road at S.R. 315 Construction summer 2018 to Fall 2019 $6M estimate
East-West Corridor Projects Lewis Center & North Road $3.2 million construction Fall 2018 to Summer 2019
36 Delaware 36 37 131 Sunbury 71 37 42 DELAWARE 124 Home Rd. DELAWARE 106 Lewis Center Rd. 124 DELAWARE 109 DELAWARE 25 Big Walnut Rd. Center Village Rd. 33 121 Polaris Pkwy. 270 119 I-71/I-270
140 121 131 2 interchanges serving nearly 200,000 residents 119
Big Walnut Interchange Phase 1 (Interchange and Nearby Local Roads) = $36.34 M Schedule: Preliminary Engineering: 2016-19 Right of Way & Utilities: 2019-21 Construction: 2022 Costs: TRAC: $15 million (FY 2022) ODOT: $3.58 million (FY 2016-19) Local: $17.76 million
Big Walnut Interchange Current Status: Received TRAC approval for Tier II Status in January 2018 Completion of feasibility study scheduled for spring 2018 Interchange Justification Study and final design planned for 2018 to 2020 Construction of Phase 1 planned 2022+
Upcoming Design Contracts Consultant selection two times per year Announcements and scope of services advertised last week of January and July each year http://www.co.delaware.oh.us/engineer/design/consultantinfo.htm
January 2018 Currently advertised Letters of Interest due February 19 1. Liberty Road and Salisbury Drive Intersection $1.8M construction estimate 2. 2018-1 General Engineering Services $200,000 two-year task-order agreement
Liberty Road and Salisbury Drive single lane roundabout
July 2018 Scheduled for advertisement July 25, 2018 1. Cheshire Road over CSX Railroad Grade Separation $12M construction estimate Currently studying conceptual alternatives 2. Berlin Station Road Improvements, Phase 1 and 2 Currently studying conceptual alternatives
January 2019 Scheduled for advertisement January 28, 2019 1. Africa Road Improvements, Phase 1 Widening from Worthington Road to Big Walnut Road 2. CR 54 over Big Walnut Creek 135-foot span bridge replacement plus approach realignment 3. General Engineering Services $200,000 two-year task-order agreement
2018-21 Consultant Program $3,500,000 $3,000,000 $2,500,000 $2,000,000 $1,500,000 $1,000,000 $500,000 $0 2018 2019 2020 2021 County Funds Federal Funds
2018-21 Construction Work $35,000,000 $30,000,000 $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 $0 2018 2019 2020 2021 County Funds Other Funds
2018-21 Capital Summary Mostly roadway and intersection projects focused on major corridors $24 million average annual construction program $2.7 million average annual consultant design program
Don t Do This
Questions? Robert Riley, PE, PS Chief Deputy Engineer Delaware County Engineer s Office 740-833-2400 delcoeng@co.delaware.oh.us