Pre-Construction Public Meeting July 2017

Similar documents
Commonwealth Avenue Bridge Deck Replacement Project. Legislative and Stakeholder Briefing. April 13, 2017

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

November 21, 2012 Barbara Kelleher, (954)

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

Guide to. Road Construction Projects

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

Route 29 Solutions Projects

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

Hospital Link Project Project Update September 2015

Frequently Asked Questions on the Route 29 Solutions Improvements Projects

FDOT Treasure Coast Traffic Report through

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015

Whittier Bridge Project

Organization Date. Sound Regional Council Regional Project Evaluation Committee. Brian Nielsen, Program Administrator

MEMORANDUM. for HOV Monitoring on I-93 North and the Southeast Expressway, Boston Region MPO, November, 2011.

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road

DALLAS HORSESHOE PROJECT. Project Update including the Margaret McDermott Bridge Transportation and Trinity River Project Committee February 22, 2016

I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required.

Day and night work: Hills M2 Motorway tunnel portals and Coral Tree Drive electrical substation

AGENDA ITEM I-6 Public Works

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

5.1 Traffic and Transportation

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

Palm Beach County Traffic Report July 13 through July 20, 2012

Arlington County Board Meeting Project Briefing. October 20, 2015

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

Strategies to keep people and goods moving in and through Seattle. SR 99 Closure and the Seattle Squeeze

PRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction

PennDOT Interstate Work next week March 30-April 3:

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30

McLean Citizens Association Transportation Committee Project Briefing

Important Lane Closures, April 3 9, 2011

TORONTO TRANSIT COMMISSION REPORT NO.

State Route 8 Corridor. Northern Summit County s Path to Success

25 th Avenue Grade Separation. September 13, 2017

Milestone: Bridge to Nowhere scheduled for demolition Aug 14

FDOT Treasure Coast Traffic Impact Report

Atlantic Street Bridge Project CTDOT Project Nos & (Phase 2)

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District

A VISION FOR I-95. January 12, Delaware Department of Transportation

Capital Beltway HOT Lanes Project

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District

Long water shutdown scheduled for Tuesday, September 18

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County

October Business Owner Task Force. Matt Sanman Public Information Coordinator

SR 934 Project Development And Environment (PD&E) Study

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

State Project Reconstruction I-84

I-270 Bridge Renovation at New Florissant Road

Georgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour

Transform66 Transportation Management Plan: Transit & TDM Strategies

I-10 will close overnight Sunday through Thursday next week. Crews continue to make progress on Sunland s new bridges and ramps.

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT

I-95/395 HOV/Bus/HOT Lanes Project Overview

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015

Route 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release.

Project Overview. Hunter Mill Road Over Colvin Run Bridge Replacement Fairfax County. Get Involved. Public Information Meeting. Contact Information

2 Construction Program

Pardon Our Dust Public Information Meeting

Astoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019

Our ref: FRC/REC/Nov Steve Farrell Clerk to the Rural Economy and Connectivity Committee The Scottish Parliament.

Road Construction Ahead January-April 2015 NORTHWEST REGION

Damen Elston Fullerton Reconstruction, Intersection Improvements CDOT Project B-1-501

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

Monthly Traffic Update

CITY OF BEVERLY HILLS TRAFFIC & PARKING COMMISSION TO: FROM: SUBJECT: ATTACHMENTS: June 1,2017. Aaron Kunz, Deputy Director

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District

BRIEFING Subject: 2017 Visitation Initiatives

All closures this week happen at night, including full closures of Mesa and I-10

Atlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2)

Appendix 4.1 J. May 17, 2010 Memorandum from CTPS to the Inter Agency Coordinating Group

Metro ExpressLanes April 5, 2011 Community Meeting re: Adams Blvd Improvements

Public Information Meetings. October 5, 6, 7, and 15, 2015

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

Palm Beach County Traffic Report August 24 through August 31, 2012

Ohio Department of Transportation Construction Update

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

McCORMICK QUARRY BRIDGE EAST SHORE EXPRESSWAY BRIDGE WITOLD H. KLOCZKOWSKI, P.E. PROJECT MANAGER COMMONWEALTH ENGINEERS & CONSULTANTS, INC.

ACCELERATED CONSTRUCTION LANE RENTAL FEES & A+B BIDDING DALLAS DISTRICT. June 7, 2018 Transportation Planning Conference June 7, 2018

PRIORITIES COMMITTEE MEETING

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

Arlington County Board Work Session Eastbound Widening January 17, Amanda Baxter, VDOT Special Projects Development Manager

Construction Staging Area Blue Jays Way (357 King Street West)

Astoria Boulevard ADA and Station Renewal Track Improvements. January 30, 2019

Neighbourhood Committee NDG - Westmount. September 12, 2016

Work in 2015 and Annual Mobility- Management Plan

FOR IMMEDIATE RELEASE February 22, 2019 CONTACT: Jen K. Ward, SALEM 69

October 31, 2014 Chuck McGinness, (954)

Boston Redevelopment Authority 2/26/ Chestnut Hill Avenue Boston/Brookline, MA

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

Transportation Management Program Office Newsletter J A N U A R Y

September 1, 2017 I-10 night closures scheduled for September hour full closure of I-10 West happens Sunday, Sept. 10

Transcription:

Pre-Construction Public Meeting July 2017

Agenda Introduction to Project Team Project Description Schedule Impacts Communication/Public Outreach 2

Contractor Walsh Construction Design Team HDR Lead City Point Partners, LLC Fort Hill Infrastructure Services, LLC Kleinfelder, Inc. KM Chng Environmental, Inc. LTK Engineering Services McMahon Associates Inc. Nitsch Engineering, Inc. Regina Villa Associates, Inc. RM Engineering, Inc. Project Team MassDOT Highway Division District 6 Construction Traffic/Safety MBTA Subway, Bus, and Railroad Operations Power Department Track Department Safety Department Police Capital Delivery Keolis 3

4 Project Location

Need for Replacement The bridge was originally constructed in 1965 and is structurally deficient The concrete deck has deteriorated and the steel beams are corroded The substructure was rehabilitated from 2014-2016 as a precursor to this project Conventional construction would take an estimated 4-5 years with substantial lane closures/reductions on I-90 and on Commonwealth Avenue 5

Background The project will use Accelerated Bridge Construction (ABC) to replace the superstructure over two intensive construction windows: Summer 2017 (eastbound portion of the bridge) Summer 2018 (westbound portion of the bridge) During Summer 2017, there will be an 18 ½ day intensive closure window which will have significant impacts to local/regional vehicular traffic and Green Line/Commuter Rail travelers The Summer 2017 construction window will occur from July 26 August 14 This window was a carefully selected timeframe to minimize traffic impacts based on traffic volumes, MBTA ridership, Boston University summer break, and special events in the area 6

Keeping Massachusetts Moving Strategy will be to minimize traffic volume in the area Reduce Seasonal reduction (Colleges/Universities/Schools on summer break) Public outreach to make informed decisions Reroute Alternate routes / avoid the area, if possible Re-mode Shift to walking and biking Encourage commuter rail ridership during weekdays vs. I-90 travel 7

Sequence of Work 1. July 26 at 9:00 PM: De-energize Green Line catenary and remove cables and existing track 2. July 27 at 7:00 PM: Comm Ave Bridge is closed to private vehicular traffic 3. July 28 at 9:00 PM: Implement I-90 crossover into westbound barrel (All traffic on the westbound side of I-90) 4. July 29 (approx.): Demolition of existing spans over Commuter Rail and I-90 eastbound 5. July 30 (approx.): Install new spans over Commuter Rail and I-90 eastbound 8

Sequence of Work (cont.) 6. Traffic is channelized into the eastbound barrel (All traffic on the eastbound side of I-90) 7. August 2 (approx.): Demolition of existing span over I-90 westbound 8. August 3 (approx.): Install new spans over I-90 westbound 9. August 7 through 5:00 AM on August 14: Sidewalks and Paving 9

Finished Condition Cycle track/bike accommodations Refinements in accessibility/pedestrian accommodations Inclusion of floating bus island/sidewalk improvements Refined landscaping and lighting elements 10

2017 Project Schedule July 26 August 14 Facility Traffic Impact Notes MBTA Green B Line (Blandford St to Babcock St) MBTA Bus Routes CT2 and 47 Commonwealth Avenue (Packard s Corner to Kenmore Sq) Boston University (BU) Bridge I-90 (Mass Turnpike) (between Allston Interchange and Beacon Street Overpass) MBTA Commuter Rail Framingham/Worcester Line Amtrak Lake Shore Limited Line 11 Closed from Blandford St to Babcock St for 18½ days Detoured from normal routes for 17 ½ days Closed to private vehicular traffic for 17½ days Closed to private vehicular traffic for 17½ days Traffic shift and intermittent ramp closures for 9 ½ days Closed from Boston Landing to South Station for 2 weekends Closed for 2 weekends Shuttle bus service between Blandford St and Babcock St Detour maps are posted on the project website Bridge open to buses, emergency vehicles, peds/bikes Bridge open to buses, emergency vehicles, peds/bikes 2 lanes in each direction during peak period; The I-90 Eastbound on-ramp from Cambridge Street/Soldiers Field Road will be closed during this entire period. The I-90 Westbound Exit 20 off-ramp to Brighton/Cambridge will also be closed intermittently. Shuttle bus service from Boston Landing to Reservoir Station (Yawkey Way during Sox games) Shuttle bus service from Albany, NY to Boston

2017 Project Schedule * = Red Sox Home Games 12

13 MBTA Service Impacts

Green Line B Line Service Beginning Wednesday, July 26 at 9:00 PM for 18.5 days Light Rail Service terminates at Babcock Street Station and Blandford Street Station Replacement shuttle bus service Police details and Customer Service personnel at stations Route 57 bus will make the same stops Regular light rail service commences at 5:00 AM on Monday, August 14 - BACK ON TRACK Goal: Provide the best possible transportation options during the construction period

MBTA Commuter Rail Framingham/Worcester Line Service impacts for two weekends: July 29-30 and August 5-6 Normal weekday operations (maximum capacity) under flag operations Shuttle buses between Boston Landing and Reservoir Station (Green Line C&D Branch) Shuttle from Boston Landing to Yawkey Way for the weekend Red Sox games Amtrak Lakeshore Line: No service disruptions on weekdays. Two weekends: July 29-30 and August 5-6. Shuttle bus service will run between South Station and Albany, NY. Parking lots at stations near full capacity. Plan ahead, car pool, seek alternate routes, etc.

Added Green Line Resources During the Commuter Rail weekend suspensions and Red Sox games/fenway Park events, extra Green Line service will be added to: C Branch (Cleveland Circle) D Branch (Reservoir) Customer service personnel will be located at Babcock Street, Blandford Street, Boston Landing and Reservoir Stations Police details along the route to progress bus traffic 16

Bus Routes Beginning Thursday, July 27 at 7:00 PM: MBTA Bus Routes CT2 and 47 will be detoured from normal route Route 57 bus will continue to run and make most of regular stops

Commonwealth Avenue/ BU Bridge Impacts 19

Commonwealth Ave Restricted access from Packard s Corner to Kenmore Square Maintain access in two-directions for buses/emergency vehicles Maintain access for pedestrians, bicycles, abutters, local business Commonwealth Ave Eastbound Closure 20

21 Work Zone : Babcock St to Comm Ave Bridge

22 Work Zone : Comm Ave Bridge

23 Work Zone : Comm Ave Bridge to Blandford St

Encouraging Walking/Biking MassDOT/MBTA plans to utilize pedestrian and bicycle wayfinding signage to encourage active transportation, especially for short trips This will help optimize shuttle bus operations by shortening bus wait times and headways The Project Team is also partnering with Hubway to provide additional bike service along Comm Ave 24

25 I-90 Impacts

I-90 Crossover 26 Limits of the crossover are Allston/Brighton Toll Plaza and Beacon Street Overpass (~6600 feet)

Similar to the HOV Zipper Lane on I-93 Use of Movable Barrier 27

I-90 Dry Run (Weekend of June 3) I-90 was restricted from 4 lanes to 2 lanes in each direction beginning 11:00 PM Friday The I-90 Eastbound on-ramp from Cambridge Street/Soldiers Field Road was closed during this entire period The I-90 Westbound Exit 20 off-ramp to Brighton/Cambridge was closed intermittently Learned valuable lessons on Friday night closure that enabled Saturday night to proceed smoothly (reopened Sunday morning 20 hours ahead of schedule) 28

I-90 Impacts Pre-Shutdown I-90 was reduced from 4 to 3 lanes in each direction on July 7 (between the Allston Interchange and the Beacon Street Overpass in Boston) This is in order to construct a crane in the median of I-90, essential to demolition/construction operations during the shutdown 29 I-90 Eastbound Crossover This will be the same lane configuration travelers saw during the substructure repairs that took place from August 2014 to June 2016

I-90 Impacts During Shutdown I-90 will be reduced to 2 lanes in both directions from 9:00 PM on July 28 to 5:00 AM on August 7 (with additional lane closures during off-peak hours, see next slide for more details) The I-90 Eastbound on-ramp from Cambridge Street/Soldiers Field Road will be closed during this entire period and the I-90 Westbound Exit 20 off-ramp to Brighton/Cambridge will also be closed intermittently during this timeframe The eastbound lane reductions will begin in advance of the Allston Interchange Westbound lane reductions will begin at the onramp from Mass Ave 30 State troopers escorting contraflow traffic during Dry Run

I-90 Off-Peak Lane Reductions The I-90 lane reductions allow room for demolition and for the crane to safely install precast concrete panels Weekdays During I-90 EB Shift (Jul. 28 Aug. 1): 7:00 PM to 5:00 AM 1 eastbound lane open 2 westbound lanes open During I-90 WB Shift (Aug. 2 Aug. 7): 8:00 PM to 6:00 AM 1 westbound lane open 2 eastbound lanes open I-90 EB I-90 WB Demolition of deck above I-90 Westbound (all traffic is shifted to the I-90 Eastbound lanes) Weekends 9:00 PM (Friday) to 5:00 AM (Monday) 1 eastbound and 2 westbound lanes open OR 2 eastbound and 1 westbound lane open 31

I-90 Ramp Closures Detour In effect from 9:00 PM on July 28 to 5:00 AM on August 7 32

I-90 Ramp Closures Detour I-90 Eastbound On-Ramp from Cambridge Street Closure: Use the I-90 westbound on-ramp to continue onto I-90 westbound. Take Exit 16 (Route 16 West Newton/Wellesley) and follow signs to access I-90 eastbound. I-90 Westbound Exit 20 Closure: From I-90 westbound, continue to Exit 16 (Route 16 West Newton/Wellesley) and follow signs to access I-90 eastbound. Continue on I-90 eastbound to Exit 18 (Brighton/Cambridge) and use the eastbound off-ramp to exit onto Cambridge Street. 33

I-90 Eastbound Traffic Volume Results: Three-Lane Pattern Implemented on July 7 If drivers continue normal patterns, this scenario (eastbound) is estimated to: Increase AM peak travel times from 24 to 35 minutes (a 47% increase) Increase PM peak travel times from 20 to 43 minutes (a 110% increase) *travel times are estimated from I-95 in Weston to I-93 in Boston

I-90 Westbound Traffic Volume Results: Three-Lane Pattern Implemented on July 7 If drivers continue normal patterns, this scenario (westbound) is estimated to: Increase AM peak travel times from 15 to 22 minutes (a 46% increase) Extend the duration of PM peak congestion far longer into the evening *travel times are estimated from I-93 in Boston to I-95 in Weston

Memorial Drive Memorial Drive will be OPEN to Vehicles on Sunday, July 30 and Sunday, August 6 36

I-90 Impacts Post-Shutdown At 5:00 AM on August 7, I-90 will open from 2 to 3 lanes in both directions On August 28, I-90 will fully reopen to 4 lanes in both directions 37

Real-Time Traffic Information Real Time Traffic Management System active during both shutdowns Dial 511 before heading out onto the roadways and select a route to hear realtime conditions Visit www.mass511.com, a website which provides real-time traffic and incident advisory information, access to traffic cameras, and allows users to subscribe to text and email alerts for traffic conditions Follow MassDOT on Twitter @MassDOT to receive regular updates on road and traffic conditions Download MassDOT s GoTime mobile app and view real-time traffic conditions before setting out on the road 38

39 Public Outreach and Communication

Project Website www.mass.gov/massdot/commavebridge Sign up for email construction updates and traffic alerts View a detailed project schedule, including temporary traffic impacts Download maps of detour routes Learn more about traffic options in your area View project documents and presentations Find out about upcoming meetings 40

Project Website Pre-Closure Outreach Public meetings and briefings for stakeholders Printed materials (brochures, flyers) available in multiple languages Door to Door Business Outreach Project Website Email to E-ZPass / Letters to Pay By Plate Email Red Sox season ticket holders During Closure Outreach Email alerts Real Time Traffic Monitoring System active during shutdown Dedicated Project Email Address 24/7 Hotline for abutters (noise issues) 41

Work Zone Safety Message Be Patient Minimize Distractions Give your full attention to navigating through the work zone This is not the time to talk on a cellphone, text, or change the radio station 42

Contact Us Sign up for email alerts! www.mass.gov/massdot/commavebridge For noise complaints during the shutdown (July 26- August 14), please call the 24/7 abutters hotline: (617) 350-4004 Questions? Email us at CommAveBridge@dot.state.ma.us 43