GALVESTON DISTRICT Dredging Schedules Christopher Frabotta Chief, Navigation Branch Southwestern Division - Galveston District November 2, 2016 Galveston District Dredging Meeting Custodians of the Texas Coast US Army Corps of Engineers
GALVESTON DISTRICT FACTS ü Texas #2 in Nation in Maritime Commerce ü Texas Ports moved 538M+ tons at $320B in 2014 ü Galveston District Ports National Rank ü Houston (2) ü Beaumont (4) ü Corpus Christi (6) ü Texas City (15) ü Port Arthur (20) ü Freeport (32) ü Matagorda (48) ü Galveston (52) ü Brownsville (67) Galveston District Dredging Meeting ü Victoria (70) Custodians of the Texas Coast ü Gulf Intracoastal Waterway (3) ü GIWW-TX 73M+ tons at $43B in 2014 ü 21.8% Nation s Import/Export/Domestic Tonnage üus 23.9% of Nation s Total Export tonnage Army Corps of Engineers übuilding 29.6% of Nation s Total Import tonnage STRONG 50,000 square miles
GALVESTON VIGATION OM FUNDING FY-16 Execution President s Budget $110,404,000 FY-16 Allocation $151,869,000 Carry-in $ 21,837,000 Available to Obligate $173,706,000 Obligated ~$161,000,000 Percent Execution ~93% FY-17 Funding Outlook President s Budget $107,815,000 Carry-in $ 13,727,000 Total Anticipated $121,542,000
GALVESTON DISTRICT INITIATIVES Continue Hydrographic Survey Webpage All six (6) Deep Draft Navigation Complexes now online Gulf Intracoastal Waterway & Tributaries also online Implement of Vertical Datum Conversion Sabine-Neches Waterway Set-Back Policy Restore TCOON Functionality to 30 Stations Bring new Sentinel Stations online Re-Space & Deploy new GIWW Mooring Buoys
Galveston District Hydrographic Survey Website http://www.swg.usace.army.mil/missions/navigation.aspx 5
Galveston District Hydrographic Survey Website 6
Galveston District Hydrographic Survey Website 7
GALVESTON DISTRICT INITIATIVES Continue Hydrographic Survey Webpage All six (6) Deep Draft Navigation Complexes now online Gulf Intracoastal Waterway & Tributaries also online Implement of Vertical Datum Conversion Sabine-Neches Waterway Set-Back Policy Restore TCOON Functionality to 30 Stations Bring new Sentinel Stations online Re-Space & Deploy new GIWW Mooring Buoys
Galveston District Vertical Datum Conversion 9
GALVESTON DISTRICT INITIATIVES Continue Hydrographic Survey Webpage All six (6) Deep Draft Navigation Complexes online Gulf Intracoastal Waterway & Tributaries online Implement Vertical Datum Conversion Sabine-Neches Waterway Set-Back Policy Restore TCOON Functionality to 30 Stations Bring new Sentinel Stations online Re-Space & Deploy new GIWW Mooring Buoys
TEXAS COASTAL OCEAN OBSERVATION NETWORK
TEXAS COASTAL OCEAN OBSERVATION NETWORK
FY17 CONTRACT SCHEDULES SABINE-NECHES WATERWAY
SABINE-NECHES WATERWAY PORT ARTHUR CAL,TURNING BASIN, JUNCTION AREA AND TAYLORS BAYOU Port Arthur Turning Basins 9 Port Arthur Junction Area 8 Dredging Depth: Sabine-Neches Waterway Port Arthur Canal, Turning Basin, Junction Area and Taylors Bayou 42 ft. Required Depth 400-1200 ft. Varies 1,387,000 cubic yards Silt/Clay Placement Area: PA 8 and PA 9 Distance to Place Area: Type of Equipment: Contractor: 1.5-2 Miles Avg. Pipeline RLB & Mike Hooks Contract Amount: $5,782,500 Est. Start Date October 2016 Est. Completion Date February 2017
SABINE-NECHES WATERWAY OUTER BAR AND BANK CHANNEL 4 3 2 1 Dredging Depth: Placement Area: Distance to Placement Area: Type of Equipment: Contractor: Sabine Neches Waterway Outer Bar and Bank Channel 44 ft. Required Depth 800 ft. Varies 3,153,000 cubic yards Silt/Clay Offshore 3 Mile Avg. Hopper Manson Construction Contract Amount: $5,189,300 Est. Start Date October 2016 Est. Completion Date December 2016
SABINE-NECHES WATERWAY NECHES RIVER Sabine-Neches Waterway Neches River Dredging Depth: Placement Area: Distance to Placement Area: Type of Equipment: Env. Window: Reason for Window: 42 ft. Required Depth ~200 ft Varies 500,000 cubic yards Silt Various Upland PAs 1-2 Miles Pipeline Est. Start Date: April 2017 Est. Completion Date: August 2017
FY17 CONTRACT SCHEDULES GALVESTON-TEXAS CITY-HOUSTON
GALVESTON HARBOR Galveston Inner Harbor Dredging Depth: 41-46 ft. Required Depth 1000 ft. Varies Pelican Island PA San Jacinto PA Placement Area: 3,443,000 cubic yards Silt Offshore Distance to Place Area: 8 Miles Avg. Type of Equipment: Hopper Dredge Contractor: Dutra Group Contract Amount: $13,739,100 Est. Start Date September 2016 Est. Completion Date January 2017
HOUSTON SHIP CHANNEL MORGAN S POINT TO EXXON & BARBOURS TERMIL Houston Ship Channel Morgan s Point to Exxon & Barbours Terminal Dredging Depth: 49 ft Required Depth Varies Varies 2,498,000 cubic yards Silt Placement Area: Alexander Distance to Place Area: 1 Mile Avg. Type of Equipment: Pipeline Contractor RLB Contracting Contract Amount: $6,543,800 Est. Start Date: August 2016 Est. Completion Date: May 2017
HOUSTON SHIP CHANNEL BAYPORT FLARE AND RED FISH REEF TO MORGAN Dredging Depth: Placement Area: Dist. to Place Area: Type of Equipment: Contractor: Houston Ship Channel Bayport Flare and Redfish Reef to Morgan Point (include Bayport Bend E.) 47 ft. Required Depth 530 ft. Varies 2,382,000 cubic yards Sand/Silt Mid-Bay PA 1-4 miles Pipeline Weeks Marine Contract Amount $15,692,500 Est. Start Date: November 2016 Est. Completion Date: April 2017
HOUSTON SHIP CHANNEL BAYPORT SWEEP & BAYPORT FLARE BEND EASING La Porte Spilman Is. Atkinson Is. 16 15 14 Dredging Depth: Houston Ship Channel Bayport Flare 47 ft. Required Depth Varies Varies cubic yards Silt / Clay Placement Area: PA14, M7-10 Distance to Place Area: Type of Equipment: Contractor: 1-5 Mile Avg. Pipeline Dredge WEEKS Marine Contract Amount: $32,147,330 Est. Start Date: April 2016 Est. Completion Date: April 2017
HOUSTON SHIP CHANNEL SPILMAN ISLAND PA DEWATERING Lost Lake Peggy Lake Goat Island Type of Work: Placement Area: Houston Ship Channel Spilman Island PA Dewatering Dewatering Silt/Clay Spilman Island Spilman Island PA Dewatering Alexander Island Spilman Island Distance to Place Area: Type of Equipment: Contractor: Marsh Buggy/ Excavation Equipment Affolter Contracting Contract Amount: $2,374,082 Est. Start Date: October 2016 Est. Completion Date: April 2017
Filter-Bed Glendale House-Stimson Tracts HOUSTON SHIP CHANNEL ROSA ALLEN CONTAINMENT DIKE RAISE Type of Work: Placement Area: Houston Ship Channel Rosa Allen Containment Dike Raise Levee Raising Silt/Clay Rosa Allen PA Rosa Allen Containment Dike Raise Contractor: Type of Equipment: Contractor: Dragline/Earthmoving equipment Affolter Contract Amount: $2,593,045 Est. Start Date November 2016 Est. Completion Date September 2017
HOUSTON SHIP CHANNEL SIMS BAYOU TO TURNING BASIN Dredging Depth: Placement Area: Distance to Place Area: Type of Equipment: Env. Window: Reason for Window: Houston Ship Channel Sims Bayou to Turning Basin 39.5 ft. and 42 ft. Required Depth 300-250 ft. Varies TBD cubic yards Silt House Tract; West Clinton 3 Miles Average Pipeline Dredge Est. Start Date: February 2017 Est. Completion Date: November 2017
TEXAS CITY CHANNEL MAIN CHANNEL AND TURNING BASIN Dredging Depth: Texas City Channel Main Channel and Turning Basin 48 ft. Required Depth 400-1200 ft. Varies 1,400,000 cubic yards Silt/Sand Placement Areas: SPPA 3, 4, 5 Distance to Place Area: 1 Mile Avg. Type of Equipment: Pipeline Env. Window: Reason for Window: Est. Start Date: March 2017 Est. Completion Date: July 2017
GALVESTON ENTRANCE CHANNEL AND HSC - BOLIVAR ROADS TO REDFISH Morgan s Point Galveston Harbor - Galveston Entrance Channel and Houston Ship Channel - Bolivar Roads to Redfish Dredging Depth: Placement Area: 48-50 ft. Required Depth 800-1000 ft. Varies 2,500,000 cubic yards Varies Offshore Distance to Place Area: 1-8 Mile Avg. Type of Equipment: Hopper Env. Window: Reason for Window: Est. Start Date: March 2017 Est. Completion Date: September 2017
HOUSTON SHIP CHANNEL LOST LAKE PA DEWATERING Lost Lake Dewatering Green s Bayou PA Lost Lake Type of Work: Placement Area: Houston Ship Channel Lost Lake PA Dewatering Dewatering Silt/Clay Goat Island Distance to Place Area: West & East Jones Peggy Lake Alexander Island PA Type of Equipment: Env. Window: Reason for Window: Marsh Buggy/ Excavation Equipment Est Start Date: April 2017 Est. Completion Date: April 2018
HOUSTON SHIP CHANNEL PEGGY LAKE PA DEWATERING Houston Ship Channel Peggy Lake PA Dewatering Type of Work: Dewatering Lost Lake Green s Bayou PA Placement Area: Silt/Clay Goat Island Distance to Place Area: Peggy Lake Dewatering Peggy Lake Type of Equipment: Marsh Buggy/ Excavation Equipment West & East Jones Alexander Island PA Env. Window: Reason for Window: Est. Start Date: June 2017 Est. Completion Date: October 2017
HOUSTON SHIP CHANNEL ALEXANDER ISLAND PA DEWATERING Houston Ship Channel Alexander Island Dewatering Peggy Lake Alexander Island Type of Work: Dewatering Alexander Island PA Dewatering La Porte Spilman Island Atkinson Is. 16 Placement Area: Distance to Place Area: Type of Equipment: Silt/Clay Alexander Island PA Marsh Buggy/ Excavation Equipment 15 Env. Window: Reason for Window: 14 Est. Start: November 2017 Est. Completion: November 2018
HOUSTON SHIP CHANNEL SPILMAN ISLAND PA CONTAINMENT DIKE RAISE Lost Lake Peggy Lake Goat Island Type of Work: Placement Area: Houston Ship Channel Spilman Island PA Containment Dike Raise Levee Raising Silt/Clay Spilman Island Alexander Island Spilman Island Distance to Place Area: Type of Equipment: Env. Window: Reason for Window: Dragline/Earthmoving equipment Est. Start Date: September 2017 Est. Completion Date: September 2018
HOUSTON SHIP CHANNEL HOUSE TRACT AND CLINTON PA CONTAINMENT DIKE RAISE Filter-Bed Glendale House-Stimson Tracts Type of Work: Placement Area: Distance to Place Area: Houston Ship Channel House Tract & Clinton Containment Dike Raise Levee Raising Silt/Clay House Tract & Clinton Type of Equipment: Env. Window: Reason for Window: Dragline/Earthmoving Equipment Estimated Start Date: October 2017 Est. Completion Date: October 2018
FY17 CONTRACT SCHEDULES FREEPORT HARBOR
FREEPORT HARBOR ENTRANCE CHANNEL Brazos Harbor Turning Basin and Channel Stauffer Channel Upper (De-Authorized) Brazosport Turning Basin Turning Basin Surfside Freeport Harbor Entrance Channel 1 Quintana 7 85 Dredging Depth: Placement Area: Distance to Place Area: 47-49 ft. Required Depth 600 ft. Varies 2,517,000 cubic yards Sand/Silt Offshore 2.5 Mile Avg. 88 1-A Type of Equipment: Contractor: Hopper Manson Construction Contract Amount: $7,629,200 Buffer Zone Start Date: September 2016 Limits of Discharge Completion Date: October 2016
FREEPORT HARBOR ENTRANCE CHANNEL Brazos Harbor Turning Basin and Channel Stauffer Channel Upper (De-Authorized) Brazosport Turning Basin Turning Basin Surfside Freeport Harbor Entrance Channel 1 Quintana 7 85 Dredging Depth: Placement Area: Distance to Place Area: 47-49 ft. Required Depth 600 ft. Varies 2,600,000 cubic yards Sand/Silt Offshore 2.5 Mile Avg. 88 1-A Type of Equipment: Env. Window: Hopper Reason for Window: Buffer Zone Est. Start Date: July 2017 Limits of Discharge Est. Completion Date: September 2017
GALVESTON DISTRICT VIGATION Questions/Comments? http://www.swg.usace.army.mil/missions/navigation.aspx