Kilkenny Mobility Management age e Plan The plan sets out a series of mobility management proposals together with an implementation pro

Similar documents
IRISH PARKING ASSOCIATION. The use of Pay and Display in Traffic Management in Kilkenny City

Guildford Borough Transport Strategy 2017, Topic Paper: Transport, June 2017 (accompanying Local Plan 2017) Local Plan Transport Strategy 2017

PART VIII APPLICATION FOR REVISED SOUTH SIDE TRAFFIC MANAGEMENT WORKS TO FACILITATE LUAS BXD PLANNING REPORT ROADS & TRAFFIC DEPARTMENT

Presentation by John Brennan, Car Parks Manager, Dublin Airport

Borders Railway - Scottish Borders Work Plan

DRAFT MINUTES OF THE ADAMSTOWN SDZ STEERING GROUP MEETING

IAT Annual Conference 'Driving Forward

Land Use Planning & Transportation Land Use Planning & Transportation Land Use Planning & Transportation

Cycling as part of the NZ transport system

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street

Kilkenny Borough Council. Heavy Commercial Vehicles Route Management April 2014

WELCOME WELCOME TO OUR PUBLIC EXHIBITION FOR THE BOND STREET PUBLIC REALM PROJECT.

The Point Roundabout Improvement Scheme

Haworth Tr T avel Plan r 10th February 2006

Integrated Area Plan. Kilkenny

Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT

Map showing location of public transport projects in vicinity of railway station

BILLY BISHOP TORONTO CITY AIRPORT 2018 MASTER PLAN UPDATE

CHELMSFORD CITY LOCAL HIGHWAYS PANEL MINUTES 14 MARCH 2017 at 13:00 at the Civic Centre, Chelmsford

Calderdale MBC. Wards Affected: Town. Economy and Investment Panel: 20 October Halifax Station Gateway Masterplan

St. Dunstan s Regeneration Steering Group 7 th August to 1300 Marion Attwood Room, Canterbury City Council Offices

Miontuairiscí / Meeting Minutes. Trim Municipal District. Ordinary Meeting

College Green Traffic Management Measures Consultation Submission On behalf of Parliament Street Businesses and Residents

Appendix C Stage 1 Road Safety Audit

Cammachmore. Community Action Plan Prepared by Newtonhill, Muchalls & Cammachmore Community Council

2.3 On 27 November, the Department for Transport issued guidance on the use of the powers contained in the Act.

MINUTES OF PROCEEDINGS AT MEETING OF THE COBH MUNICIPAL DISTRICT, HELD IN CARRIG HOUSE, COBH ON TUESDAY, 13 TH JUNE, 2017.

CITY OF EDINBURGH COUNCIL WRITTEN SUBMISSION

Presentation to the British Irish Airport s EXPO John Heffernan Chief Development Officer, Dublin Airport

Smarter Travel Sutton

Commissioning Director - Environment. Officer Contact Details Jane Shipman;

Board meeting

Item 3.1 Attachment 1

Port Macquarie-Hastings Pedestrian Access and Mobility Plan. Working Paper COMMUNITY ENGAGEMENT

Report to: Greater Cambridge Partnership Joint Assembly 18 January A10 Foxton level crossing bypass and travel hub

Multi-storey station car park opens in New Year

Seek the Board s approval for the Donald Place kerb and channel renewal to progress to final design, tender and construction; and

Miontuairiscí / Meeting Minutes. Trim Municipal District. Ordinary Meeting

Parking Amendments - Bay Street, between Harbour Street and Queens Quay West (York Street, Bay Street, and Yonge Street Ramp Removal)

Congestion. Addressing urban congestion in SEQ. How do you define congestion? South East Queensland is growing. Sustained growth in motorised travel

Strategic Transport Forum

Major Scheme Business Case Summary Report for Programme Entry

Visitor information: An Bord Pleanála

Review of Highcliffe Shopping Centre

2.0 POLICY AND DEVELOPMENT FRAMEWORK. Introduction. Transport21. Celbridge Development Plan 2002

Sharing the Way with Sustainable Transport Options

Riverside Heights, Norwich. Travel Plan

Draft City Centre Transport Proposals

Whether travelling on two wheels or two feet, we help communities stay active and sustainable.

BUSINESS ZONE - OPTION 400 (Western footpath) Have your say. Love the Bay Delivering on the Cycleway

NEWRY, MOURNE & DOWN DISTRICT COUNCIL

LLANBEDR ACCESS IMPROVEMENTS

Coca-Cola Zero Belfast Bikes.

Glasgow Street Traffic Review

N11 Arklow / Rathnew & N7 Newlands Cross PPP Contract. Kieran Kelly

Next Generation Cycleway Design. Improving connectivity and cycling behaviours through design

Gold Coast. Rapid Transit. Chapter twelve Social impact. Chapter content

Emmet Square BIRR PUBLIC REALM

Submission to NSW Koala Strategy Consultation Process. March 2017

Miontuairiscí / Meeting Minutes. Trim Municipal District. Ordinary Meeting

Open Report on behalf of Richard Wills, Executive Director for Environment and Economy

Guidance for Blue Badge holders on parking in Weymouth and Portland

MINUTES OF PROCEEDINGS AT ANNUAL AND JULY MEETING OF THE COBH MUNICIPAL DISTRICT, HELD AT CARRIG HOUSE, COBH, ON TUESDAY, 11TH JULY, 2017

Moving Brisbane is the Newman Liberal team s blueprint for a modern and efficient transport system.

Member-led Review of Cycling Infrastructure

The National Transport Authority

Norfolk Parking Partnership Joint Committee

AUCKLAND $1.2 BILLION $1.9 BILLION $149 MILLION 15% SPEND $5.7 BILLION

Member-led Review of Cycling Infrastructure

St. Patrick s Street Development Brief

Cheshire West and Chester Parking Strategy

Leicester Square Action Plan Summary

COCONUT GROVE WATERFRONT MASTER PLAN. ERA / Curtis Rogers / ConsulTech / Paul George Ph.D.

Environment Committee 24 September 2015

Planning application for minor changes to extension, internal modifications and 1 off-street disabled parking space to Dublin City Council

ROADS POLICING TRAFFIC MANAGEMENT PLAN

Monaghan County Council Jobs Initiative Smarter Travel Projects 2011 Evaluation

Leave No No Trace Ireland

SINGAPORE AIRSHOW 2018 TRAFFIC ARRANGEMENTS AND TRANSPORTATION ADVISORY

Committee. Presentation Outline

DATE: 23 March, 2011 TO: Communities FROM: BlazeSports America. RE: Accessible Trails Checklist 1

A63 Castle Street, Hull HullBID Network Lunch 24 August 2017

Pre-application submission for Committee: Phase 4 development at West Hendon

Table 1 overleaf summarises the changes in planned growth between the 2016 and 2017 iterations of the plan.

Uniclass L534+L212. August home zones. paving PRECAST CONCRETE PAVING SOLUTIONS FOR TODAY S RESIDENTIAL STREET ENVIRONMENTS.

DUBLIN 15 COMMUNITY COUNCIL

Macleod Trail Corridor Study. Welcome. Macleod Trail Corridor Study Open House. Presentation of Proposed Design Concepts

An Bord Pleanála STRATEGIC INFRASTRUCTURE DEVELOPMENT PLANNING AND DEVELOPMENT ACTS 2000 TO An Bord Pleanála Reference Number: 29N.

Treasurer s House (York) Access Statement

4 YORK REGION TRANSIT DON MILLS SUBWAY STATION ACCESS AGREEMENT

Roads, Transportation and Safety

Railfuture East Anglia Whittlesford Parkway station audit

Reports on Traffic Studies in Ranelagh, Terenure & Donnybrook. Order: Noted. Proposed deletions from the Record of Protected Structures

Airport Surface Access Strategy December 2011

4 VIVA PHASE 2 YONGE STREET - Y2, AND HIGHWAY 7 - H3 CORRIDORS PRELIMINARY ENGINEERING UPDATE

Bridge School, Longmoor Campus, Coppice View Road, Sutton Coldfield, Birmingham, B73 6UE

Active Travel Strategy for Perth and Kinross

Member-led Review of Cycling Infrastructure

London and Crossrail 2. Chris Moores Transport for London

Scottish Storytelling Centre Access Statement

Transcription:

Kilkenny City and Environs Mobility Management Plan 2009 to 2014. Report and Presentation to Kilkenny Borough Council on 21st September, 2009

Kilkenny Mobility Management age e Plan 2009-2014 2014 The plan sets out a series of mobility management proposals together with an implementation programme over a period of five years commencing in 2009. The draft plan was discussed at the Feb 09 monthly meeting of Kilkenny Borough Council at which members agreed that the plan should proceed to public consultation. Agreement under Section 85 of Local Government Act, 2001, in Feb 2009 by which Kilkenny Co Council assigned responsibility to Kilkenny Borough Council in relation to planning and implementation of proposed development.

Kilkenny Mobility Management Plan 2009-20142014 The measures contained in the plan are summarized as follows: 1) The provision of approx 50 km of cycleway lanes in the city and environs street network. 2) The introduction of a one way street system on John Street Lower, Rose Inn Street, High Street, Michael Street t and Back Lane. A smaller one way system is also proposed for Upper Patrick Street/Jacob Street. 3) The reallocation of road space in favour of increased pedestrianization (wider footpaths) on High Street, Rose Inn Street and John Street Lower.

Kilkenny Mobility Management age e Plan 2009-2014 4) An option for full pedestrianization of High Street from its junction with Friary Street to its junction with James Street during busy shopping periods or during festival/cultural occasions. 5) The introduction of special speed limits of 30 km/hr in the core city centre area i.e. John Street, The Parade, part of Patrick Street, Rose Inn Street, High Street, Friary Street and James Street. 6) The provision of new signage capable of proving real time information to motorists regarding parking availability etc.

Kilkenny Mobility Management age e Plan 2009-2014 7) The consideration of a shuttle bus service for the inner city and two bus routes serving the city environs. 8) The improvement of accessibility in the built environment and streetscape. 9) The promotion and coordination of workplace transport plans, walking buses, other soft options and awareness campaigns. 10) The implementation of on street parking tarriffs aimed at rationalizing parking in the city centre area.

Kilkenny Mobility Management age e Plan 2009-2014 2014 Consultation Proposed plan advertized in local press 27/03/2009. Closing date for submission on 12/05/2009. Open evening at local hotel on April 2nd. Attended by 40 members of the public. Discussions on an individual basis with some school committees. Discussion with persons with disability and presentation at IWA national conference on May 23 rd. Discussions with bus operators and taxi service providers. Submissions carried from Notices of Motion from Kilkenny Borough Council. Awareness through free electric bike draw.

Kilkenny Mobility Management Plan 2009-20142014 Some points on Accessibility The introduction of the 2005 Disability Act places requirements on all local l authorities to put in place measures to actively support participation of people with disabilities in Irish society. The overall objective is to promote universal access to all public spaces, buildings and services owned and operated by Local Authorities at the earliest possible date. It is intended that the objective will be reached by 2015. DoEHLG sectoral plan. Kilkenny Local Authorities through its Barcelona team set about implementing its requirements and undertook comprehensive audit of Kilkenny streets. Councils to adopt disability proofing in their decision making.

Kilkenny Mobility Management Plan 2009-2014 IWA/Disability Issues The Medieval Citie. Great for visitors, great shopping, culture and social life, an international award winning city, but how easy is it to get around if you need a wheelchair? Challenges Fitting modern improvements into the fabric of the city. Agreement towards a common goal of accessibility... an accessible city Car domination viz a viz pedestrian and wheelchair priority.

High Street / James Street Junction Narrow footpaths unsuitable for wheelchairs and buggies.

Rose Inn Street Very Narrow footpaths

John Street Lower difficult for wheelchairs John Street Lower difficult for wheelchairs and some pedestrians

An example of good practise aimed at improving accessibility

Ramping, handrails, grip zone, colour contrast.

Kilkenny Mobility Management Plan 2009-2014 Key related developments since April, 2009. An Bord Pleanala decision on the Central Access Scheme for Kilkenny City support in principle i for the bridge crossing. EIS to be amended. smarter travel >>> A New Transport Policy for Ireland 2009 to 2020. This sets out the Government s vision for sustainability in transport in five key areas. 50 million competition launched by the DoT in July 15 th. National Cycle Policy Framework launched in April, 2009. Draft design guidelines for cycle lanes published by Dublin Transportation Office in August, 2009.

Kilkenny Mobility Management age e Plan 2009-2014 Report on submissions in accordance with Section 179 (3) of Planning and Development Act 2000 and Part 8 of Planning Regulations, 2001. Road Traffic Regulations 1961 to 2004. Kieran Fitzgerald, Senior City Engineer.

Kilkenny Mobility Management age e Plan 2009-2014 Estimate of Cost Pedestrian improvements on John Street, Rose Inn St, High Street estimated at 2.5 million Completion of Kieran Street. 0.2million Patrick Street, Jacob St... 0.2million Signage Scheme... 0.35m from 2009-20132013 City Centre Shuttle bus service.. 0.5m 05 (annual running costs not included)

Kilkenny Mobility Management age e Plan 2009-2014 Programme and Timeline for Implementation. 2009 Continuation of implementation of cycle path network in city and environs Provision of bicycle parking facilities at various locations. Provision of car parking and cycle information signage. Implementation of on street parking charges Accessibility improvements Capacity improvements on Ring Road Establish Smart Travel Office

Kilkenny Mobility Management Plan 2009-2014 Programme and Timeline for Implementation. 2010 Implementation of City Centre one way street system commencing February on trial basis. (Michael St, Jacob St, Uppr New St, Fr Hayden Road to operate oneway from same date in Feb) Completion of Kieran Street pavements. Implementation of city centre 30kph zone. Completion of cycle way network and cycle parking. Provision of real time information signs for parking. Provision of bus set down areas and taxi rank accommodation. Detailed design of High st and John St improvements. Carry out works on Michael Street and Back Lane Continue programme of accessibility improvements. Data compilation and modal shift education programme.

Kilkenny Mobility Management age e Plan 2009-2014 Programme and Timeline for Implementation. 2011 Commence streetscape improvements on John Street, Rose Inn St and High Street Completion of works on Jacob St, Uppr New Street. Complete public lighting Patrick St, Bateman Quay Continue to provide bicycle stands and facilities. Continuous accessibility improvements. Data compilation and education and awareness on modal shift.

Kilkenny Mobility Management age e Plan 2009-2014 Programme and Timeline for Implementation. 2012, 2013 Complete streetscape improvements on John Street, Rose Inn St and High Street Commence work on public transport service tendering subject to available resources. Continuous accessibility improvements. Data compilation and education, awareness and review of progress on modal shift.

Kilkenny Mobility Management age e Plan 2009-2014 In accordance with Section 179 (4) of the Planning and Development Act,2001 members are requested to consider the proposed developments, approve the plan subject to the amendments listed in the Co Manager s report, and approve the implementation of the development works as resources permit. Approval of Council is sought towards the preparation of a bid under the smarter travel area scheme in respect of funding assistance for proposals in Kilkenny City and Environs.

Críoch

Street Peak Hour Volume 2006 Peak HourVolume post one way system Johns Bridge 1135 484 High St 398 296 Parliament St 330 362 Irishtown 485 449 Dean St 689 763 Greens Bridge 1362 1621 Wolfe Tone 114 92 Michael St 143 354 Dominic St 714 941