NORTHEAST OHIO AREAWIDE COORDINATING AGENCY MEMORANDUM TO: FROM: NOACA Board of Directors Grace Gallucci, Executive Director DATE: October 3, 2014 RE: Resolution No. 2014-044 Project Planning Reviews 1 st Quarter State Fiscal Year (SFY) 2015 ACTION REQUESTED The Board of Directors is asked to approve Resolution No. 2014-044, which acknowledges that the projects included in the resolution have successfully completed project planning review (PPR). The Planning and Programming Committee recommends this action. BACKGROUND/JUSTIFICATION FOR CURRENT ACTION Attached is a list of the proposed projects that were presented to the NOACA Transportation Subcommittee (TS) at its July 18, 2014 meeting, the NOACA Planning and Programming Committee at its August 8, 2014 meeting and to the NOACA Executive Committee at its September 12, 2014 meeting in accordance with the PPR process. All three committees have recommended their approval. NOACA s Regional Transportation Investment Policy (Resolution 2012-023) requires that all proposed federal-aid transportation projects be processed through PPR in order to meet NOACA s adopted goals and federal requirements. PPR consists of four components: staff review, committee review, intergovernmental review and consultation (IGRC), and public involvement. The end product of PPR is a Board resolution that certifies that the project has had thorough review, allowing the project to proceed to the programming stages of the planning process. As part of the PPR process, a detailed summary of the proposed improvement and staff and committee assessment of the project are posted on NOACA s website, www.noaca.org. A link to the PPRs is included on the home page by clicking the Comment of Projects button. Staff adds comments obtained from the public, governmental organizations and NOACA committees as they are received. Proposed projects are posted on the website for three months, allowing adequate time for review and comment. 5-131
FINANCIAL IMPACT The estimated total cost of the proposed projects is approximately $151.8 million, which includes approximately $17.7 million in NOACA-controlled funds. Funding for these projects is being provided from a variety of federal, state, and local sources. Federal funding is provided by the Federal Highway Administration and Federal Transit Administration and is administered through NOACA and the Ohio Department of Transportation. CONCLUSION/NEXT STEPS Project sponsors will be notified that their project has completed PPR. NOACA staff will work with project sponsors to address any planning issues identified during PPR. GG/em/2793b Attachments: Project Summaries 5-132
Resolution No. 2014-044 SFY 2015 1st Quarter Project Planning Review Projects 10/3/2014 Primary Work Category PID No. County Sponsor Project Name Project Description Total Cost SFY Bridge 94577 ODOT 12 CUY US-6-21.27 Upgrade of the stone arch drainage structure carrying Dugaway Brook under Euclid Avenue (US-6), located just east of Superior Avenue, in East Cleveland. $500,000 PLAN Bridge 90202 ODOT 12 CUY SR-14-2.19 PAINT Painting bridge on Broadway Avenue (SR-14), over IR-490, in Cleveland. $3,140,000 PLAN Bridge 81552 ODOT 12 CUY IR-71-17.95L Replace the deck of the SR-176 southbound bridge, over IR-71 southbound, in Cleveland. $1,755,000 PLAN Bridge 88348 ODOT 12 CUY IR-90-24.10/24.63 Replace decks of the mainline IR-90 bridges, over East 140th Street and East 152nd Street, in Cleveland. $12,998,000 PLAN Cleveland- Intermodal/ CUY CLEVE/CUY CO PORT Construction of two cranes for unloading general cargo at the Port of Cleveland to County Freight AUTHORITY CRANES support its liner cargo service between Cleveland and Europe. Port Authority $7,000,000 PLAN Interchange Modifications and improvements to the interchange at IR-90 and SR-252, in Westlake CUY IR-90/SR-252 INTERCHANGE Modification Westlake. $7,709,000 PLAN Maintenance 97311, Guardrail upgrade and repair on various routes and sections in, Geauga ODOT 12 CUY D12 GR FY2016 Geauga, Lake and Lake Counties. $1,442,000 2016 Maintenance 97291, Geauga, Lake ODOT 12 CUY D12 PM FY2016CUY D12 PM FY2016 94721 ODOT 12 CUY SR-17-12.16 Pavement marking on various routes and sections in, Geauga and Lake Counties. Resurface SR-17 (Granger Road), from the Brooklyn Heights WCL to Tuxedo Avenue, in Brooklyn Heights. $1,843,980 2016 $342,000 2015 85529 ODOT 12 CUY IR-71-10.48 Preventive maintenance on IR-71, from IR-480 to the Brooklyn WCL, in Cleveland. $8,263,500 PLAN 90900 ODOT 12 CUY IR-271-9.73 85601 Geauga ODOT 12 GEA SR-87-00.00 90908 Geauga ODOT 12 GEA SR-528-1.29 85605 Geauga ODOT 12 GEA SR-700-00.00 85532 Lake ODOT 12 LAK SR-44-4.14 Preventive maintenance on IR-271, from Fairmount Boulevard to Wilson Mills Road, in Beachwood, Lyndhurst, Mayfield Heights and Mayfield. Resurface SR-87 (Kinsman Road), from the County Line to the Chillicothe Road (SR-306), in Russell Township. Resurfacing SR-528 (Madison Road), from Nash Road (SR-88) to Kinsman Road (SR-87), in Parkman Township, Middlefield Township and the Village of Middlefield. Resurfacing SR-700 (Claridon-Troy Road), from the Portage County Line to US- 422, in Troy Township. Resurfacing SR-44, from SR-84 (Johnnycake Ridge Road) to Headlands Park, in Painesville Township, Painesville and Grand River; and on SR-2, from SR-44 to the Painesville west corporation line (WCL), in Painesville Township. $4,635,000 PLAN $1,030,000 PLAN $1,957,000 PLAN $1,030,000 PLAN $6,180,000 PLAN Safety 97676 ODOT 12 CUY IR-271-10.87 Modifications to the interchange at IR-271 and Brainard Road, in Lyndhurst. $2,552,000 2016 Safety 89168 Geauga Geauga County CUY IR-480-22.41EB Addition of an auxiliary lane on IR-480 eastbound, from Lee Road to Northfield Road, in Maple Heights, Cleveland and Warrensville Heights. $13,841,993 2017 Signals Brecksville CUY BRECKSVILLE RD SIGNALS Upgrading traffic signals along Brecksville Road, from Snowville Road to Wallings Road, in Brecksville. $1,380,000 PLAN Signals Rocky River Upgrading traffic signals along Center Ridge Road, from Spencer Road to Wooster CUY CENTER RIDGE RD SIGNALS Road, in Rocky River. $2,310,000 PLAN Signals Cleveland CUY CLARK AVE SIGNALS Upgrading traffic signals along Clark Avenue, from Lorain Avenue to West 14th Street, in Cleveland. $4,139,500 PLAN Signals Lake Willoughby LAK SR-84 SIGNALS Installation of traffic signals along SR-84 (Ridge Road) at the intersections of Robinhood Drive, Shankland Road and Willoughcroft Road, in Willoughby $315,944 PLAN Signals Lorain Avon LOR AVON SIGNALS Upgrading traffic signals at intersections along Center Road (SR-83), Nagel Road, Detroit Road (SR-254), Lorain Avon Road (SR-611) and Chester Road, in Avon. $5,896,000 PLAN 5-1 139
Resolution No. 2014-044 SFY 2015 1st Quarter Project Planning Review Projects 10/3/2014 Primary Work Category PID No. County Sponsor Project Name Project Description Total Cost SFY Signals Lorain Lorain LOR LORAIN SIGNALS Shared use Cleveland Shared use Shared use Cleveland Metroparks Cleveland Metroparks Transit GCRTA Transit Lake Laketran Lorain Elyria LOR SR-57 Lake CUY JOHNSTON MILL RUN TRAIL PHASE I CUY RED LINE GREENWAY PHASES I & II CUY VALLEY PARKWAY CONNECTOR PHASE II CUY GCRTA HAYDEN GARAGE CNG FACILITY LAKETRAN VEHICLE REPLACEMENT PROGRAM Willoughby and LAK SR-91 Willoughby Hills Parma, Parma Hts., Middleburg Hts. and CUY US-42 Cleveland Maple Hts., Bedford, and CUY SR-8 Bedford Hts. Cleveland, Parma, CUY RIDGE RD and Brooklyn Mayfield Heights CUY US-322 Strongsville CUY US-42 Brook Park, Parma, Parma Hts., and Middleburg Hts. CUY W 130TH ST Brook Park CUY SNOW RD Parma CUY PLEASANT VALLEY RD Lorain Avon and Avon Lake LOR SR-83 Shaker Heights CUY WARRENSVILLE CTR RD Euclid CUY SR-175 Lake Mentor LAK SR-306 Lake Willoughby LAK ERIE ST Replacement of traffic signals at intersections along Broadway and 28th Street, in Lorain. Construction of a off-road shared-use path facility, north of Broadway, from Miles Avenue to Lee Road and Kerruish Park, in Cleveland. Construction of a multi-purpose trail from W 53rd Street, north of I-90, along the GCRTA Red Line Rapid Transit corridor, to the intersection of Columbus Road and Franklin Avenue, in Cleveland. Construction of an all purpose trail, from Ridge Road to Broadview Road, in North Royalton and Broadview Heights Installation of a compressed natural gas (CNG) fueling system at GCRTA s Hayden Bus Garage, in Cleveland. Purchase of replacement vans and buses in calendar years 2015 through 2020 for paratransit service and commuter service. Pavement repairs along SR-57 (Lorain Boulevard), from SR-113 to the Ohio Turnpike off ramp, in Elyria Pavement repairs along SR-91 (SOM Center Road), from the Lake/ County Line to US-20, in Willoughby and Willoughby Hills. Pavement repairs along US-42 (Pearl Road), from Sprague Road to Wetzel Avenue, in Parma, Parma Heights, Middleburg Heights and Cleveland. Pavement repairs along SR-8 (Northfield Road), from the Maple Heights, Bedford, and Bedford Heights corporation limits to the North Randall south corporation line, in Maple Heights, Bedford Heights and Warrensville Heights. Pavement repairs along Ridge Road, from Pearl Road to Fowerdale Avenue, in Cleveland, Parma and Brooklyn. Pavement repairs along US-322 (Mayfield Road), from Eastwood Avenue to Lander Road in Mayfield Hts. Pavement repairs along US-42 (Pearl Road), from Shurmer Road south of the Ohio Turnpike access road in Strongsville. Pavement repairs along West 130th Street, from Pleasant Valley Road to Snow Road in Brook Park, Parma, Parma Hts. and Middleburg Hts. Pavement repairs along Snow Road, from SR-237 to Van Wert Avenue, in Brook Park. Pavement repairs along Pleasant Valley Road, from State Road to Broadview Road, in Parma. Pavement repairs along SR-83 (Center Road), from Detroit Road to Walker Road, in Avon and Avon Lake. Pavement repairs along Warrensville Center Road, from Farnsleigh Road to Fairmount Boulevard, in Shaker Heights. Pavement repairs along SR-175 (East 260th Street), from Euclid Avenue to IR-90, in Euclid. Pavement repairs along SR-306 (Reynolds Road), from Johnnycake Ridge Road to the Lakeshore Boulevard, in Mentor. Reconstruction of Erie Street, from US-20 (Mentor Avenue) to Stevens Boulevard, in Willoughby. $4,980,000 PLAN $3,993,801 PLAN $5,956,135 PLAN $1,586,000 PLAN $4,000,000 PLAN $18,118,280 PLAN $716,580 PLAN $1,482,823 PLAN $4,130,765 PLAN $1,734,474 PLAN $437,516 PLAN $205,751 PLAN $853,681 PLAN $966,739 PLAN $1,008,257 PLAN $570,478 PLAN $1,620,402 PLAN $573,894 PLAN $523,000 PLAN $3,757,717 PLAN $4,312,000 PLAN TOTAL $151,789,210 5-2 140