Airports Program Western-Pacific Region Presented to: ACA By: Robin Hunt & David Cushing Date: September 14, 2012
FY11 Program Highlights AIP Performance Metric FAA Modernization and Reform Act of 2012 Are You Ready for FY13? Safety/Compliance Initiatives 2
$180 FY11 AIP Projects Funded (Western-Pacific Region) $160 $140 $120 $100 Total: $461M $80 $60 $40 $20 $0 Land Acquisition $8M Navaids / Equipment $10 Environmental / Planning $14M Other $36M Building/Terminal $41M Noise $45M Taxiway $71M Apron $74M Runway $162M 3
AIP Funding for FY10 & FY11 4
FY11 AIP Program (by State in millions) Fund Types AZ CA NV HI Pacific Total State Apportionment $7 $21 $5 $1 $2 $36 Entitlement $24 $77 $14 $23 $9 $147 Discretionary $55 $140 $36 $9 $38 $278 Total: $86 $238 $55 $33 $49 $461 5
AIP Performance Metric Office of Management and Budget (OMB) outlay rates: By end of year in which appropriated, disburse 18% By end of 1st year after appropriation, disburse 60% By end of 2nd year after appropriation, disburse 81% By end of 3rd year after appropriation, disburse 91% By end of 4th year after appropriation, disburse 96% After the 4th year, all funds should be fully disbursed and the grant closed. 6
Current Grant Performance Target 40% (FY11 Grant balance) 19% (FY10 Grant balance) 9% (FY09 Grant balance) 4% (FY08 Grant balance) Arizona 54% 15% 7% 1% California 59% 16% 7% 5% Nevada 50% 16% 6% 3% Hawaii 75% 26% 10% 12% Pacific 77% 28% 11% 1% 7
Financial Report SF-425 SF-272 is obsolete SF-425 replaced SF-272 Submit SF-425 to FAA within 30 days after the end of each fiscal year 8
FAA Modernization and Reform Act of 2012 The President signed the FAA Modernization & Reform Act of 2012 on February 14, 2012 4-year FAA reauthorization bill Authorizes $3.35 billion for AIP (FY12 15) $165 million less than previous years ($3.5 billion) Still subject to annual appropriation bill 9
New Federal Share for AIP Grants The federal share for development projects reverts back from 95% to the following rate: o Arizona 91.06% (except PHX 75%) o Nevada 93.75% (except LAS 75%) o Hawaii 90% o Pacific Islands 90% o California 90.06% (except BUR, ONT, OAK, SMF, SAN, SJC, SNA - 80.59%, SFO & LAX 75%) 10
Essential Air Service Airports in Economically Distressed Areas US DOT determined the following airports to remain eligible at a 95% federal share: Kingman (AZ) Prescott (AZ) Show Low (AZ) Crescent City (CA) El Centro (CA) Merced (CA) Visalia (CA) 11
Miscellaneous Provision Construction projects with discretionary funds may begin before execution of grant agreements, due to climatic condition Changes made to residential through-the-fence (TTF) and disposal of noise land requirements TTF adds language enabling a GA airport to enter into an agreement with a person to access airport with property adjacent to or near the airport Disposal of noise land allows designation of noise land as buffer land. Airports can lease without treating land as disposal. 12
New Electronic Grant Payments Delphi einvoicing is in operation. Call DOT Help desk if you have any registration issues. 1 (866) 641-3500, Option 4, Option 3 1 (405) 954-3000, Option 4, Option 3 Delphi einvoicing manual payment will begin on November 1 st. 13
Are You Ready for FY13? Ready means that by 12/31/12 you have: Planning complete Project on an approved ALP FAA environmental complete (FONSI, ROD, or submission of extraordinary circumstance form) Airspace review and approval complete Design complete and project ready for bid 14
FY13 Environmental Deadline Environmental documents should be completed by December 31, 2012 Finding of No Significant Impact (FONSI) for Environmental Assessment (EA) Record of Decision (ROD) for Environmental Impact Statement (EIS) Submission of extraordinary circumstance form to support categorical exclusions 15
FY 2013 Grants Applications Get your application is early Ensure calculation adds up and are supported Administrative cost and support services need to have back-up for all numbers Force Account work must be approved by FAA Bids should not include contingency even by another name 16
Important Dates for FY13 (AIP Grants) Events Due Dates Environmental (FONSI, ROD, or CAT EX) December 2012 Application December 2012 Open Bids March 31 Carryover May 1 Grant Offers (approximate) July 30 Grant Execution August 15 Grant Payments Periodically- at least every 6 months Financial Report (SF-425) With 30 days of the end of each FY Grant Closing < 4 Years (within 30 days of final inspection) 17
Vehicle Pedestrian Deviations In FY11, there were 44 Vehicle/Pedestrian Deviation related Runway Incursions (VPD-RIs) in AWP. This is by far the highest number of all Regions. To date in FY12, there have been 18 VPD Runway Incursions in AWP. By this time last year, AWP had experienced 22 so we are doing better, but We need your vigilance as we move into spring and summer which are our peak times for V/PD RIs. Nevada Airports are doing well. NV Airports had 4 VPD-Ris in FY11. There have been 3 VPD-RI this fiscal year to date at Nevada Airports. 2 at LAS and 1 at VGT. ASDE-X snapshot of HNL VPD Runway Incursion on 2/22/12. Aircraft overflew HNL Ops Vehicle by approximately 150 feet. 18
Wildlife Hazard Management To date in FY12, A total of 123 wildlife strikes have been reported at or near AWP Airports. Of those, 116 occurred at Part 139 certificated airports. The remaining occurred at General Aviation (GA) airports. We strongly recommend all Part 139 certificated airports and busy GA Airports conduct a Wildlife Hazard Assessment and develop a Wildlife Hazard Management Plan even if they have not experienced a triggering event. All wildlife strikes should be reported to FAA at http://wildlife.faa.gov. 19
Runway Safety Area Program All practicable improvements to RSAs at Part 139 airports, including NavAids related actions, must be completed by December 30, 2015. GOOD NEWS: Based on the information we have, all Part 139 Certificated Runways in Nevada meet current RSA Standards. Not So Good News: We have 30 RSA projects to be completed by the deadline. AWP program is faced with timing & funding challenges in meeting the 2015 deadline. Our ACIP, includes over $400 million in AIP funding for RSA projects. This means that other, lower priority, projects must be deferred. 20
Safety Management System (SMS) Airports implementation of SMS is limited to Large Hub Airport projects only until further notice. FAA-Air Traffic Organization (ATO) implementation of SMS may include any project with potential to impact operation of the National Airspace System. AWP has identified the following large hub airport projects that require further screening under the SMS process in 2012: McCarran (LAS) Two Taxiway Rehabilitations (CSPP). Honolulu (HNL) Rehabilitate Taxiway Z (design only). San Francisco (SFO) Runway 10L-28R and 10R-28L Runway Safety Areas. Los Angeles (LAX) Construct two aprons at Bradley Terminal and Taxiway T. Phoenix (PHX) Rehab Taxiway B8. Other SRMPs may be initiated by FAA-ATO. 21
Design Standards Update FAA is working on update to Advisory Circular 150/5300-13, Airport Design. FAA s goal is to publish AC 150/5300-13A by the end of Fiscal Year 12. Principal Changes are in the areas of: Chapter 3, Runway Design Chapter 4, Taxiway and Taxilane Design Declared Distances and RSA Application Runway Protection Zone (RPZ) Taxiway Design Group (TDG) Concept for Fillet Design Runway Design Code (RDC), Runway Reference Code (RRC) and Taxiway Design Group (TDG) designation Minimum separation between non-intersecting runways Runway incursion prevention geometry for new construction Consolidation of numerous runway design tables to one design requirements matrix Table 3-5 FAA is also working on updates to the Heliport Design AC and new standards for Parachute Landing Areas on airports. 22
National ADO Initiatives Geographic Balancing (Geo-balancing) National redistribution of resources to better serve our customers New Phoenix ADO to serve AZ and NV Phoenix office will initially report to LAX ADO LAX and SFO ADOs will exclusively serve California National SOPs under development to create consistency among ADOs 23
Summary Talk to us. Talk early. Plan ahead. Stay abreast of current regulation and guidance. Please talk to us before an issue becomes a problem! 24
Contact Information Mark McClardy, Division Manager Western-Pacific Region (310) 725-3600 Debbie Roth, Deputy Manager Western-Pacific Region (310) 725-3654 Mia Ratcliff, Manager Planning and Programming Branch (310) 725-3610 Brian Armstrong, Manager Safety and Standards Branch (310) 725-3620 David Cushing, Manager Los Angeles Airports District Office (310) 725-3644 Robin Hunt, Manager San Francisco Airports District Office (650) 827-7601 Ron Simpson, Manager Honolulu Airports District Office (808) 541-1232 25