SR 429/WEKIVA PARKWAY FTBA CONFERENCE March 20-21, 2012 Presented By Suzanne Phillips, P.E., FDOT District 5
Project Description The Wekiva Parkway project constructs 25 centerline miles of new toll expressway. Total project cost $1.7 billion which includes $500 million of non toll road improvements including Construction of 7 miles of 4 and 6-laning of SR 46 in Lake and Seminole Counties Reconstruction of the US 441/SR 46 interchange in Mount Dora Relocation of CR 46A to provide improved wildlife connectivity and additional local road system benefits Provides connectivity to SR 417 and I-4 corridors 2
Wekiva Parkway Seminole County Lake County Orange County 9.4 Miles Expressway Arterial < x > Number of Lanes Both Directions 3
Tolled/Non-Tolled Segments US 441/SR 46 Interchange Redesign CR 46A Realignment Service Road Seminole County SR 46 Six-Laning SR 46 Six-Laning Lake County Orange County Frontage Roads 4
Funding Partners Florida Department of Transportation District 5 Florida s Turnpike Enterprise Orlando Orange County Expressway Authority 5
Project Construction Sections D R A F T 6
FDOT/OOCEA Agreement in Principle For each agency s respective section they will: Perform Final Design Construct Finance Operate Maintain Collect Tolls Keep all toll revenue 7
Project Status - Environmental FONSI Finding of No Significant Impactapproval anticipated soon FHWA has given the go ahead to advertise Sections 4A & 4B for Design Build Procurement 8
Project Status 15 %Design 15% preliminary engineering currently being performed by D5 FDOT. HNTB - Sections 1-5 Atkins Sections 6-8 Identifying Right of Way Requirements Value Engineering Risk Assessment Determining logical terminii for final design/segments 9
Project Status Final Design FDOT Final Design procurement for Sections 3A, 3B, 5, 6, 7A Begin this summer Last contract executed early winter 2013 Each design segment will last approximately 2 years. OOCEA Sections 1A, 1B, 2A, 2B, 2C Begin this summer 10
Project Status - Construction Section 4A & 4B - Fall 2012 Section 1 2015 Section 2-2016 Section 3A & 3B - 2016 Section 5 & 6-2016 Section 7B - 2016 Section 7A 2017 Section 8-2018 11
OOCEA Section 1 Orange Co. N. of Kelly Park Rd. N. Of US 441
Kelly Park Interchange
OOCEA Section 1A & 1B Orange Co. Section 1A - From 0.25 Mi. N, of US 441 to 0.129 mi. N. of Ponkan Road Section 1B - From 0.129 Mi. N. of Ponkan Rd to 0.485 mi. N. of Kelly Park Rd Final Design - Design consultants have been selected. Construction Begin January 2015 Complete Summer 2016 Estimated Costs 1A - $65,000,000 1B - $76,000,000
OOCEA Section 2 Orange & Lake Co. Systems Interchange
OOCEA Section 2A, 2B, & 2C Orange & Lake Co. SR 429/SR 46 Systems Interchange Final Design Currently in Procurement Section 2A Systems Interchange In advertisement Section 2B & 2C Systems Interchange connections to SR 429 in Orange Co. and SR 46 in Lake Co. Advertised after 2A selected Construction Begin Spring 2015 Complete Summer 2017 Total Estimated Costs - $124,000,000
Section 3A Lake Co. East of Round Lake Rd. East of Pond Rd.
Section 3A Lake Co. FP 238275-3-52-01 SR 46 From 0.038 mi. East of Pond Road to 0.313 mi. East of Round Lake Road Widen Existing SR 46 to 6-lanes Urban Section Final Design - Fall 2012 Construction Begin Spring 2016 Complete Summer 2019 Estimated Costs $11,000,000
Section 3B Lake Co. E of Pond Road. W of US 441
Section 3B Lake Co. FP 238275-2-52-01 US441/SR 46 Interchange - from 0.2 mi. W of US 441 to 0.038 Mi. East of Pond Rd 6 lane US 441 6 lane SR 46 SB to WB flyover ramp Final Design Summer 2012 Construction Begin Summer 2016 Complete Summer 2019 Estimated Costs $32,000,000
Section 4A & 4B Lake & Orange Co. W. Of Old McDonald Rd. Mt. Plymouth/CR 435
Section 4A & 4B
Section 4A & 4B Lake & Orange Co. FP 431163-5-52-01 & 238275-6-52-01 From CR 435/Mt. Plymouth to 0.358 mi. W. of Old McDonald Rd NO New Construction 4 lane rural section Construction CONTACT Design Build Advertised March 16, 2012 3 Week Advertisement 2 Phase Adjusted Score Design Build Procurement Commitment to turn dirt Fall 2012 Estimated Costs $34,000,000 See Advertisement for direction on how to obtain additional information on the project
Section 5 Lake Co. N. of Arundel Way SR 46
Section 5 Lake Co. FP 238275-8-52-01 Realignment of CR 46A from SR 46 to 0.04 mi. N of Arundel Way Removal of portions of Existing 46A Final Design Fall 2012 Construction Begin July 2016 Complete July 2020 Estimated Costs - $10,000,000
Section 6 Lake Co. E of Wekiva River Rd W. of Old McDonald Rd
Section 6 Lake Co. FP 238275-7-52-01 From 0.358 Mi. W. of Old McDonald Rd to 0.5 mi. East of Wekiva River Rd Includes approximately 8000 of wildlife bridging Extensive Environmental considerations Replacement of existing Wekiva River Bridge Wekiva River National Wild & Scenic River State Wild & Scenic River Florida Aquatic Preserve OFW Outstanding Florida Waterway
Section 6 Lake Co. FP 238275-7-52-01 SR 429 Typical Section - 4-lanes expandable to 6-lanes Non-tolled frontage roads Final Design Fall 2012 Construction Begin July 2016 Complete July 2020 Estimated Cost - $198,000,000
Section 7A Seminole Co. East of Wekiva River Rd. Orange Blvd.
Section 7A Seminole Co. FP 240200-2-52-01 SR 429 from 0.5 mi. East of Wekiva River Rd. to Orange Blvd Non-tolled frontage roads Significant Utility effort Final Design Fall 2012 Construction Begin - Summer 2017 Complete Summer 2020 Estimated Costs - $108,000,000
Section 7B Seminole Co. W. of Center Rd. W. Of I-4
Section 7B Seminole Co. FP 240200-3-52-01 SR 46 from 0.057 mi. West of Center Rd to Interstate 4 Widen existing SR 46 from 4 to 6 lanes Final Design Concept Complete Draft RFP Complete Construction Design Build Begin Summer 2016 Complete Winter 2017 Estimated Costs - $17,000,000
Section 8 Seminole Co. I-4 Interchange
Section 8 Seminole Co. FP 240200-4-52-01 I-4 Interchange Currently performing Design Initial Line & Grade Line & Grade complete Fall 2012 Construction Design Build Begin - July 2018 Complete - December 2021 Estimated Costs - $260,000,000
QUESTIONS? FDOT - Suzanne Phillips Suzanne.Phillips@dot.myflorida.com OOCEA - Glenn Pressimone - PressimoneG@oocea.com