Work in 2015 and Annual Mobility- Management Plan KPH-Turcot July 14, 2015
2 Presentation Outline Division into sectors Work in 2015 without disruptions West sector Center sector East sector South sector Work in 2015 with Disruptions West sector Center sector East sector South sector
3 Turcot Project Division into Sectors East sector West sector Center sector South sector
4 West Sector: Work without Disruptions Excess of materials with a view to shifting the railroad tracks Excavation and displacement of materials Installation job-site offices in the Turcot Yards Construction of the Highway 20 lanes (east and west) Construction of a service road for Highway 20
5 Center Sector: Work without Disruptions Excavation and displacement of materials Construction of structures over the future railroad tracks Highway 20 Highway 15 Dismantling of 780 St- Rémi Street
6 Center Sector: Dismantling of 780 St-Rémi Street Schedule: late July to early October 2015 No disruptions Work hours: Monday to Friday, 7:00 a.m. to 7:00 p.m.
7 East Sector: Work without Disruptions Dismantling of a building on De Richelieu Street Construction of a retaining wall between De Courcelle and Lenoir streets
8 South Sector: Work without Disruptions Construction of northbound Highway 15 Between Hadley and Eadie streets Between Saint-Rémi and Angers streets
9 KPH-Turcot Work in 2015 with Disruptions Objectives: o Perform work associated with compressible soils. o Perform work related to moving the railroad tracks. Work performed primarily outside current highway lanes Involves few lane closures Requires the use of three deviations Coordination with partners
10 Planning for Disruptions Started in February 2015 Dynamic design Coordination of disruptions with partners Adjustment of designs and disruptions; the final scenarios will be presented again. Preliminary schedules will be firmed up over time. Proactive communication with partners and the public
11 Center Sector: Area Affected Construction of highway structures over Saint-Rémi St. Coordination of disruptions and reworking of the detour resulting from MTQ work Yellow: detour road Orange: approximate work area
12 Center Sector: Dismantling of the Saint-Jacques Ramp Scenario under study Work carried out over a weekend Work hours: 7:00 a.m. to 7:00 p.m. Closure of Saint-Rémi and De Courcelle streets simultaneously during the weekend Closure of the Highway 15 North ramp to Highway 720 East Closure of the Highway 20 East to Highway 720 East Yellow: detour road Orange: approximate work area Construction of wall and backfill on Selby St. Demolition of Greene St. ramp Reconstruction of Greene St. Dismantling of the remaining portion of the Saint-Jacques St. ramp onto Highway 720 East
13 Center Sector: Preliminary Schedule Work Temporary redevelopment for the construction of the structure over Saint-Rémi Street Dismantling of the Saint-Jacques Street ramp onto Highway 720 East Construction of the structure over Saint- Rémi Street Dates September 11-12, 2015 September 11, 12, and 13, 2015 September 23, 2015 to October 2016
14 South Sector: Areas Affected Construction of the foundation for the Lachine Canal bridge Construction for structures of Highway 15 North between Hadley and Eadie streets and between Saint-Rémi and Angers streets Orange: approximate work areas
15 South Sector: Disruptions One lane open in each direction on Saint Patrick Street Dedicated left-turn-only lane onto De l Église Avenue removed South-side sidewalk preserved Saint-Patrick St. Yellow: detour road Orange: approximate work area
16 South Sector: Preliminary Schedule Work Dates Deviation of Saint-Patrick Street November 15, 2015 Deviation of the bikepath To be determined with Parks Canada
17 East Sector: Area Affected Construction of the new Route 136 Work area: Selby St. and Greene Avenue ramp Selby St. Orange: approximate work area
18 East Sector: Dismantling of the Greene Ave. Ramp 1. Complete closure of Greene Avenue for reconstruction and removal of a Gaz métro line (5 days) Definitive closure of the Greene Avenue ramp to Highway 720 East and Selby Street 2. Reconstruction of Greene Avenue to create north south movement; partial closure; one northbound lane kept open for 2 weeks 3. Reopening of Greene Avenue in both directions (north south) 4. Dismantling of the Greene Avenue ramp to Highway 720 East
19 East Sector: Disruptions Definitive closure of Selby St. and Greene Avenue ramp During the dismantling of the Greene Avenue ramp: Work carried out over a weekend Work hours: 7:00 a.m. to 7:00 p.m. Closure of Atwater Avenue and the Guy Street ramp Closure of an eastbound lane of Highway 720 Selby St. Red: closures
20 East Sector: Detour for the Greene Avenue Ramp Red: closures Yellow: detour road
21 East Sector: Preliminary Schedule Work Closure of the Greene Ave. ramp to Highway 720 East Dates August 20, 2015 Closure of Selby St. August 20, 2015 Complete closure of Greene Ave. for removal of the Gaz métro line Closure of southbound traffic on Greene Avenue for reconstruction Reopening of Greene Avenue (north and south) Dismantling of the Greene Avenue ramp to Highway 720 East - Closure of Atwater Avenue - Closure of exit 3, Guy Street, Montréal (downtown) - Closure of the right-hand lane on Highway 720 East August 20, 2015 (for 5 days) August 21 to September 3, 2015 September 4, 2015 Weekend of September 4, 2015
22 West Sector: Areas Affected Temporary road set up via Notre-Dame Street West Construction of a service lane for Highway 20 Realignment of Pullman Boulevard Sainte-Anne-de- Bellevue Blvd. Route 138 Saint-Pierre Ave. Ramp Notre-Dame St. West Angrignon Blvd.
23 West Sector: Subsequent Steps 1. Dismantling of the CN tunnel (in orange) 2. Dismantling of the Sainte-Anne-de-Bellevue Blvd. ramp (in purple) 3. Construction of CN bypass tracks (in red) 3 2 1
24 West Sector: Work Details 1. Realignment of Pullman Blvd. (temporary lane) partial and occasional disruptions 2. Construction of a service lane for Highway 20 no disruptions 3. Construction of a temporary deviation to connect Angrignon Blvd. and the service road: complete closure 1 2 Angrignon Blvd. 3
25 West Sector: Work Details Relocation of exit 64 for Saint-Jacques Street and Angrignon Blvd. Notre-Dame St. West Angrignon Blvd. Green: current exit Purple: relocated exit Orange: intersection with temporary traffic lights
26 West Sector: Disruptions 1. Closure of Brock Avenue South 2. Closure of the Saint-Pierre Avenue ramp to Highway 20 East 3. Notre-Dame St. West Narrowing of lanes Temporary reduction of an eastbound lane 4. Complete closure of Angrignon Blvd. between the Highway 20 East ramp and Sainte-Anne-de-Bellevue Blvd. 5. Contraflow lane reversal on Sainte-Anne-de-Bellevue Blvd. 4 Angrignon Blvd. 3. Notre-Dame St. West Red: closures Orange: approximate work areas
27 West Sector: Detour Roads Closure of the Saint-Pierre Ave ramp.; detour road for access to Highway 20 East Closure of Montréal Toronto Blvd. between Saint-Joseph Blvd. and Saint- Pierre Ave. X X X X Angrignon Blvd. Notre-Dame St. West Red: closures Yellow: detour road
28 West Sector: Detour Roads Temporary closure of Angrignon Blvd.; westbound detour road from Saint-Anne-de-Bellevue Blvd. Notre-Dame St. West Angrignon Blvd. Red: closures Yellow: detour road
29 West Sector: Detour Roads Temporary closure of Angrignon Blvd.; eastbound detour road from Highway 20 East towards Angrignon Blvd. South Notre-Dame St. West Angrignon Blvd. Red: closures Yellow: detour road
30 West Sector: Detour Roads Temporary closure of Angrignon Blvd.; detour road from Brock Avenue South Richmond St. Notre-Dame St. West Angrignon Blvd. Red: closures Yellow: detour road
31 West Sector: Detour Roads Relocation of exit 64 for Saint-Jacques St. / Angrignon Blvd. with a temporary exit on Notre-Dame St. West Notre-Dame St. West Angrignon Blvd. Purple: relocated exit / temporary route Yellow: detour road Red: closure Orange: intersection with temporary traffic lights
32 West Sector: Preliminary Schedule Work Realignment of Pullman Blvd. Closure of the Saint-Pierre Avenue ramp Dates Early August 2015 to September/October 2015 Mid-December 2015 to November 2019 Disruptions on Notre-Dame St. West Early November 2015 to December 2015 Complete closure of the north part of Angrignon Blvd. Contraflow lane reversal on Sainte-Anne-de- Bellevue Blvd. Detour implemented via a temporary passage on Notre-Dame St. West Mid-November 2015 for 4 weeks Mid-October 2015 to mid-december 2015 Mid-December 2015 to November 2019
33 Question Period