Queens Mirror Circle Pedestrian Safety Improvements Quail Pond Circle Complete Street/Pedestrian Connectivity Improvements Southcot Drive Bicycle/Pedestrian Improvements Public Workshop Preliminary Plans Review Projects PW 1605, 1701, & 1702 June 20, 2017
Project Background All three projects included in the Connecting Casselberry: The Casselberry Multimodal Transportation Master Plan (MTMP) adopted in 2016 Increased focus on pedestrian and bicycle improvements and complete streets Queens Mirror Circle included in current FDOT Work Program Quail Pond Circle & Southcot Dr included in current Metroplan Orlando Prioritized Project List
Queens Mirror Circle Pedestrian Safety Improvements
Queens Mirror Project Location: Queens Mirror Circle (north side of Queens Mirror Lake)
Project Area Queens Mirror Project Limits
Enhance pedestrian safety and connectivity/safe route to school Install Button activated RRFB s (rectangular rapid flashing beacon) for pedestrian crossing @ S Lost Lake Lane Install permanent speed feedback devices for traffic calming Improve accessibility and visibility of crossing at Rotary Park Queens Mirror: Project Objectives
Queens Mirror Draft Plan
Queens Mirror Draft Plan Remove old crossing signage
Queens Mirror Draft Plan Add button activated RRFB (flashing beacon operates only when pressed)
Queens Mirror Draft Plan Install permanent speed feedback devices
Queens Mirror Draft Plan
Reorient and restripe crossing with ADA compliant curb ramps Queens Mirror Draft Plan
Install new crossing signage Queens Mirror Draft Plan
Queens Mirror Preliminary Add wayfinding Additional Staff Recommendations Can be completed as separate in-house City staff project Confirm whether existing advance warning signage should remain (except New ) Confirm School crossing designation(s) Coordinate with Seminole County Public Schools and Sheriff
City Commission presentation/discussion July 24, 2017 Complete design by approx. September 30, 2017 Construction funded (by FDOT) for Fiscal Year 2020 (mid 2019-2020) Queens Mirror Anticipated Schedule
Quail Pond Circle Complete Street/Pedestrian Connectivity Improvements
Quail Pond Project Location: Quail Pond Circle (from Triplet Lake Dr to Sunset Dr)
Quail Pond Project Context
Quail Pond Project Context
Quail Pond Project Context
Project Area Quail Pond Project Limits
Quail Pond Project Objectives Enhance bike/ped safety and connectivity Add sidewalks to Quail Pond Circle Create ped connection(s) from Quail Pond Circle to Lake Concord Park (north phase) Create shared use path connection from Quail Pond Cir to Sunset Dr Install ped crossing at Sunset Dr
Quail Pond Draft Plan
Quail Pond Draft Plan
Quail Pond Draft Plan
Quail Pond Draft Plan
Construct 6 ft sidewalk starting at new parking lot driveway Quail Pond Draft Plan
Quail Pond Draft Plan
Quail Pond Draft Plan
Quail Pond Draft Plan Construct 8 ft sidewalk starting at Art House driveway Construct connection to Art House Add raised curb and pave Quail Pond Circle Construct roadside swales
Quail Pond Draft Plan
Quail Pond Draft Plan
Quail Pond Draft Plan
Quail Pond Draft Plan Construct cul-desac Construct 10 ft shared use path to Sunset Dr Add crossing at Sunset Dr
Quail Pond Preliminary Additional Staff Recommendations Add accessible ped connection (if feasible) from Triplet Lake/ Quail Pond to Public Works sidewalk Relocate oak tree a few feet to suit
Quail Pond Preliminary Additional Staff Recommendations Reorient sidewalk to shorten crossing @ driveway Make it a brick crossing
Quail Pond Preliminary Additional Staff Recommendations Add wider (8 ft) and more direct sidewalk connection to Art House/Lake Concord Park Mimic brick pattern in Lake Concord Park for connection to Art House
Quail Pond Preliminary Additional Staff Recommendations Shift sidewalk onto City properties and within right of way as needed to minimize conflicts
Quail Pond Preliminary Additional Staff Recommendations LED acorn lights Art House to cul-de-sac LED path lights for shared use path
Quail Pond Preliminary Additional Staff Recommendations Add sharrows Landscape swales with cordgrass
Quail Pond Preliminary Additional Staff Recommendations Remove invasive trees and plants and failing magnolias Plant new trees
Quail Pond Preliminary Additional Staff Recommendations No Parking from eastern edge of City property to culde-sac Remove unnecessary driveway aprons Add fence along Sunset lot line for screening from adjacent residence
Quail Pond Anticipated Schedule City Commission presentation/ discussion July 24, 2017 Complete design by approx. September 30, 2017 Construction funded (by sales tax) for Fiscal Year 2020 (late 2019-2020)
Southcot Drive Bicycle/Pedestrian Improvements
Southcot Project Location: Southcot Drive from Sunset Dr to S Triplet Lake Dr
Southcot Project Context
Southcot Project Context
Southcot Project Context
Southcot Project Context
Project Area Southcot Project Limits
Southcot Project Objectives Enhance bike/ped safety and connectivity Widen sidewalk Add midblock crossing Conduct 4-way stop analysis at Sunset Dr Integrate traffic calming
Southcot Draft Plan
Southcot Draft Plan
Southcot Draft Plan
Southcot Draft Plan Conduct 4-way stop warrant analysis for Southcot & Sunset Waiting for N Oxford to conclude and school to resume
Southcot Draft Plan
Install curb ramps & stripe crossing Southcot Draft Plan
Southcot Draft Plan Install curb ramps & stripe crossing Widen sidewalks to 8 feet Relocate electric poles
Southcot Draft Plan Add raised curb and gutter with 2-3 ft sod strip
Southcot Draft Plan
Southcot Draft Plan
Southcot Draft Plan
Southcot Draft Plan End south side sidewalk at existing location Add midblock crossing
Southcot Draft Plan
Southcot Draft Plan
Southcot Draft Plan
Widen sidewalk to 8 feet Southcot Draft Plan
Southcot Draft Plan Install raised curb on north side with 2 ft sod strip only
Southcot Preliminary Additional Staff Recommendations Evaluate installing crossing across Sunset Dr @ Southcot Consider safety concerns if 4- way stop determined to be unwarranted Make Southcot curb ramp more direct rather than angled
Southcot Preliminary Additional Staff Recommendations Only widen north side sidewalk Keep south side as-is/avoid pole relocates and landscape disruption
Southcot Preliminary Additional Staff Recommendations Install raised midblock crosswalk instead of at-grade
Southcot Preliminary Additional Staff Recommendations Integrate golf cart path better and address tie-in grading concerns adjacent to golf course
City Commission presentation/ discussion July 24, 2017 Complete design by approx. September 30, 2017 Construction funded (by sales tax) for Fiscal Year 2020 (late 2019-2020) Southcot Anticipated Schedule
Please provide comments by June 30 th 2017 to: Kelly Brock kbrock@casselberry.org (407) 262-7725 ext 1235 Project updates (and this presentation): www.casselberry.org/go