For personal use only

Similar documents
Mine Production and Shipping

December 2018 Quarterly Production Report

Atlas Lifts Production Guidance and Lowers Cost Forecast After Record September Quarter

Focus Begins Accelerated Development of the Mount into New Stand Alone Mining Operation

Overview. Mining projects map

Australian Securities Exchange Notice

Development Projects. Turner River Hub Project. centralised processing facility drawing feed from nearby satellite mines.

P esent n atio i n o n f or o H alf l Y e Y ar E n E d n e d d d 31 D ecemb m e b r 2 008

For personal use only

Matilda Zircon Limited (ASX: MZI) (formerly Olympia Resources Ltd) Quarterly Activities Report for Period Ended. 30 June 2009

For personal use only

BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES. July 2002 September 2002

US Operations Overview. Shane Tilka General Manager US Operations May 2014

MOUNT GIBSON IRON LIMITED QUARTERLY REPORT FOR THE PERIOD ENDED 31 MARCH April 2018

For personal use only

CATALYST SECURES $1.5 MILLION PLACEMENT WITH ST BARBARA LIMITED

For personal use only

JUPITER MINES LIMITED Q4 FY2019 QUARTERLY ACTIVITIES REPORT

Department of Infrastructure, Planning and Logistics

ERA overview. Dan Janney General Manager, Operations

First Thunderbox gold now anticipated in June Quarter 2016

BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES. September 2002 December 2002

Curragh Operational Tour

PROJECTS & TECHNICAL SERVICES

BHP Billiton Iron Ore Western Australia. Iron Ore. Mining Operations. Phil Price Vice President Integrated Planning

Iron Ore Update. Ian Ashby President Iron Ore 6 May 2009

For personal use only

Our local knowledge teamed with our global expertise provides our customer base with the complete heavylift and transportation solution across

RAILWAY LANDS SUB-COMMITTEE

BRIEFING PAPER APRIL 2002 MINING AREA C DEVELOPMENT PORT HEDLAND PORT & CAPACITY EXPANSION

JUNE 2017 QUARTERLY ACTIVITIES REPORT

BOOMING LABRADOR NEIA October 28, 2011

Gruyere Gold Project Development Update

Quarterly Activities Report For The Period Ending 31 March 2018

Outlook: FY13 EBITDA guidance $28M - $29M. Pursuing contracted 300MW in 2013 growth strategy. FY13 maiden franked dividend payment expected

ON TIME AND ON BUDGET: PROCESSING PLANT OVER 90% COMPLETE AND FIRST PRODUCTION SET FOR MARCH

Gruyere Gold Project Update

Gruyere Project Development Update

QUARTERLY ACTIVITIES REPORT. For three months ended 31 March Highlights. 2. Operating Summary

For personal use only

Euroz Rottnest Investor Briefing

QUARTERLY ACTIVITIES REPORT SEPTEMBER 2018

Recent Exploration of the Olympic Dam

HISTORY OF THE CENTRAL EYRE IRON PROJECT (CEIP)

Chapleau Mining Readiness and Growth Strategy Addendum Number 1 February 27 th, 2017

NEWS RELEASE 8 NOVEMBER Gladstone LNG Project Arrow-AGL Joint Venture Acquires Enertrade s Gas and Pipeline Business

Gold Mining an Industry in Transition. Melbourne Mining Club 7 June Ian Smith Managing Director and CEO Newcrest Mining Limited NEWCREST 1

Australian Site Tour Mt Keith Operation. Jaco Harwig General Manager

Browns Range Heavy Rare Earths Project - Update

Morgan Stanley 2011 Emerging Companies Conference 9 June 2011

For personal use only

Gruyere Gold Project Development Update

Candelaria and Ojos del Salado Chile

THE CONSTRUCTION INDUSTRY OUTLOOK

For personal use only

For personal use only

Australian Site Tour Ravensthorpe Nickel Operation. Isak Buitendag General Manager

REPORT ON ACTIVITIES FOR THE QUARTER ENDED 30 JUNE 2016

South Fremantle Solar Farm Agenda 1 March 2018

Mt Arthur Coal. Investor/Analyst Presentation September 2003

sdrftsdfsdfsdfsdw Comment on the draft WA State Aviation Strategy

INTERIM REVIEW OF AUSTRALIAN CONSTRUCTION MARKET CONDITIONS JULY 2015

Bumper Quarter for Atlas as Production Hits 10Mtpa

For personal use only

December Quarterly Report 17 February 2014

For personal use only

HARMONY GOLD AND NEWCREST FORM PAPUA NEW GUINEA GOLD JOINT VENTURE

PROJECT UPDATE BETTER TIMES AHEAD ON CLEM7 CLEM JONES TUNNEL. Fast facts AUGUST 2008

For personal use only

ASX Announcement. Company Update

EL LIMON MINE: EMPLOYEES & CONTRACTORS 133

Orocobre Limited. The next low cost lithium producer

SEPTEMBER 2018 QUARTERLY ACTIVITIES REPORT

Quarterly Activities Report For The Period Ending 30 June 2018

For personal use only

Ramelius Resources Limited ASX:RMS

Lorena Gold Project Malachite AGM 29 November 2017

MOUNT GIBSON IRON LIMITED QUARTERLY REPORT FOR THE PERIOD ENDED 30 SEPTEMBER October 2017

GOLD RESOURCE CORPORATION REPORTS 2017 ALTA GRACIA EXPLORATION DRILL RESULTS, INCLUDING 1.29 METERS GRADING 4.33 G/T GOLD AND 1,710 G/T SILVER

Kinross Production Continues on Plan

QANTAS DELIVERS STRONG FIRST HALF RESULT DESPITE HIGHER FUEL BILL

Watpac advises that the Scheme Resolution was not passed by the requisite majorities of Watpac shareholders, with:

Quarterly Activities Report Period Ended 31 March 2018

LAS OPEÑAS DRILLING COMMENCED

GENERAL CONCEPT. Contents

The Lufthansa Group in Panama A Successful Launch of Operations a six month retrospective

For personal use only

Correction to Quarterly Report for quarter ending June 2016

20 November Company Announcements Australian Securities Exchange Limited Level 4, 20 Bridge Street SYDNEY NSW 2000 AUSTRALIA.

QUARTERLY ACTIVITIES REPORT 31 JANUARY 2019

Mungana Signs Agreement with Newcrest to unlock Porphyry Gold-Copper Potential at Chillagoe

FOUR EAGLES JV FORMALISED SEISMIC AND DRILLING PROGRAMME COMMENCES

For personal use only

For personal use only

For personal use only

HALF YEAR REPORT February Leighton Holdings Limited

ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery 9 July 2015

BHP Billiton Iron Ore. Asset Development Projects

Partnership Prospectus

WORKING THE CRUISE MARKET IN THE NT

Transcription:

22 March 2016 MINING ACTIVITIES COMMENCE AT BAOBAB PHOSPHATE PROJECT, SENEGAL PROJECT ON TRACK FOR 2016 PRODUCTION Highlights Site and pit access roads complete, mining workshop concrete works complete, civil works and construction underway Mining equipment delivery to site is almost complete Mining operations have started and are ramping up to optimise mining fleet Processing plant fabrication underway in Johannesburg First production remains on target for the second half of CY2016 Avenira Limited ('Avenira' or the 'Company') is pleased to announce continued steady progress has been made on all key critical path items at the Baobab Phosphate Project ( Project ) including mining, processing, infrastructure and water supply. The progress reflects Avenira's accelerated strategy to break into the buoyant nutrient and fertiliser sector. The Company's strategy to develop the Project is based on an initial Stage 1 operation producing 500,000 tonnes per annum of phosphate concentrate. Total capital expenditure to production is $US15 million and the Project is fully funded. The operation has been designed to enable multiple stages of expansion across the Project. Avenira s Managing Director and CEO Cliff Lawrenson commented: It is very pleasing to see the Baobab Phosphate Project development advancing rapidly. The project team is making solid progress in all key areas and the Project remains on budget and on schedule for first production in the second half of calendar 2016. The Project is fully funded to production, while separately Avenira retains cash reserves allowing the Company to proceed with development beyond Stage 1 of the project."

Project Status Development of the Project is well advanced with mining activities now commenced and production of first phosphate rock on schedule for early in the second half of 2016. Mine and Process Plant access roads are complete with the open pit ramp being established. Mining operations have now commenced. Figure 1: Stage 1 Open pit access ramp establishment in progress. Site Infrastructure is being established with office and accommodation units on site and main access roads complete. Figure 2: Project access road construction 2

Figure 3: Project mine site facilities and offices being installed German company BAUER Resources Senegal has been contracted to drill and install 2 water bores for the Project, principally for processing the phosphate ore. This drilling is well underway with the first of two 500m-deep water bores drilled and airlifting water. Once complete the drill rig will start the second process water bore. Figure 4: BAUER Resources Senegal drilling rig operating at the Project 3

Mining contractor Agromines has completed top soil clearing of the first stage of the open pit and the main mining fleet has commenced overburden removal and is ramping up to be fully operational by the end of March. Figure 5: Ore haulage fleet on start line. South African-based specialist engineering group Consulmet is progressing with the fixedprice design and construction of the Project modular wet screening plant. The plant is being fabricated in Johannesburg and will be transported to site for final erection and installation. The preferred tenderer for road transport of product to the Port of Dakar has been selected and draft contracts are currently being reviewed. Avenira has signed MOUs for approximately double the initial annual production target of the Project and is currently working with buyers to convert the MOUs into offtake contracts. Further updates will be provided throughout the construction process. Cliff Lawrenson Managing Director 4

Baobab Mining and Chemicals Corporation SA Gadde Bissik Mine Site Visit 18 March 2016

Gadde Bissik Mine Location

Gadde Bissik Mine Layout

Mine Site Offices

Manar Ba BMCC GM

Completion of the first process water bore by Bauer

Water bore gravel samples from the aquifer zone

Process water bore showing good initial water flow

Completing road access to the initial mine pit

Site of the inital mine pit, cleared of topsoil Start of pit ramp

Paul Richardson - Project Director with mining contractor Agromines

Agromines excavator ready to start stripping overburden

Mansour Gaye BMCC Moustapha Sy Agromines President

Agromines dumptruck fleet at the site

Macoumba Gaye BMCC President Ibrahima Diop Agromines GM Manar Ba BMCC GM

Agromines maintenance shop under construction

Completing the water bore for the local community Russell Fulton Avenira Geological Manager

Dirt road from the minesite to Bambey going through the village of Darou Khoudoss

An excavator en route to the mine site on the paved national road from Bambey to Dakar

Avenira Limited ABN 48 116 296 541 www.avenira.com Ground Floor, 20 Kings Park Road West Perth, WA 6005 AUSTRALIA PO Box 1704 West Perth WA 6872 AUSTRALIA +61 8 9264 7000 info@avenira.com 2016 Avenira Limited