Aviation Summit 2017 Design and Construction Services
Agenda: Terminal 3 Modernization PHX Sky Train Stage 2 Terminal 4 S1 Concourse & Apron Other Capital Program Projects
Terminal 3 Modernization
Processor Phase 1 Complete 3 1 2 Component 1 Terminal Processor Phase 1 Complete Phase 2 in Construction Component 2 South Concourse In Construction Component 3 North Concourse In Design Construction Early 2019 Terminal 3 Modernization Overall Plan
Terminal 3 Modernization Construction Schedule 2014 2015 2016 2017 2018 2019 2020 Terminal Processor Phase I Phase II Phase III South Concourse I North Concourse February 2017 South Concourse II
Design and Construction Services Terminal 3 Processor Phase 1 Complete
Terminal 3 - South Concourse Demo Started
Terminal 3 Modernization South Concourse
Terminal 3 - North Concourse in Design
Design and Construction Services Terminal 3 Modernization North Concourse
PHX Sky Train Stage 2 Transparency Policy in Effect
At Grade Section Depressed Section Future Terminal Station West GTC Station Rental Car Station PHX Sky Train Stage 2
Terminal 4 S1 Concourse & Apron
S1 Terminal 4 S1 Concourse & Apron: New Building (220,000 SF) & Apron Budget $250 Million
Planning Environmental Design Construction Testing Opening 2016 2017 2018 2019 2020 2021 2022 Terminal 4 S-1 Concourse & Apron Schedule
Terminal 4 S1 Concourse & Apron
Terminal 4 S1 Concourse & Apron
Terminal 4 S1 Concourse & Apron
Terminal 4 S1 Concourse & Apron
Terminal 4 S1 Concourse & Apron
Other Capital Program Projects PHX
PHX: T3 Southeast Transition Apron/Taxiway D Segment Subcontracting Opportunities
PHX: T4 North Apron Reconstruction Subcontracting Opportunities
PHX: Reconstruct T3 Norh Apron, (outer portion of apron) Design: Early 2018, pending FAA funding
PHX: Airfield Utility Access Upgrades Design: Mid-2021, pending ADOT funding; subcontracting opportunities
PHX: Reconstruct T2 Apron & Demo T2 Concourse Design: Spring 2019, pending FAA funding
PHX: West Air Cargo Apron Reconstruction (design complete, awaiting grant funding for construction, summer 2021)
PHX: F 8 Connector Design: Early 2021, pending FAA funding
PHX: Taxiway V Design: Mid-2021, pending FAA funding
Other Capital Program Projects DVT
DVT: Reconstruct B3 Connector Bidding: Summer 2017, pending ADOT funding
DVT: Construct New Taxiway D Design: Early 2018, pending FAA funding
DVT: Relocate Taxiway B Design: Early 2019, pending FAA funding
DVT: Upgrade PAPI System Design: Early 2019, pending ADOT funding
DVT: Construct Taxiway Connectors B6 & B9 Design: Early 2020, pending FAA funding DVT: Install Blast Pads Design: Early 2020, pending ADOT funding
DVT: Rehabilitate Runway 7R-25L Design: Early 2021, pending FAA funding
Other Capital Program Projects GYR
GYR: Airfield Drainage Improvements Bidding: Summer 2018, pending ADOT funding
GYR: Reconstruct South T-Hangar Apron Bidding: Spring/Summer 2017, pending FAA funding
GYR: Reconstruct North T-Hangar Apron Design: Early 2018, pending FAA funding* * Masterplan update may effect.
GYR: Apron Rehabilitation Phase I (PCCP) Design: Early 2018, pending FAA funding* GYR: Rehabilitation, Taxiway A Design: Early 2019, pending FAA funding* * Masterplan update may effect.
GYR: Apron Rehabilitation Phase II (PCCP) Design: Early 2019, pending FAA funding* GYR: Apron Rehabilitation Phase III (PCCP) Design: Early 2020, pending FAA funding* * Masterplan update may effect.
GYR: Infield Paving Design: Early 2019, pending ADOT funding* GYR: Public Access Road Design: Early 2019, pending ADOT funding* * Masterplan update may effect.