FEBRUARY 2019 MISSOURI STATE AIRPORT SYSTEM PLAN UPDATE. Individual Airport Report SPRINGFIELD- BRANSON NATIONAL AIRPORT

Similar documents
Recommended Airport Roles

FEBRUARY 2019 MISSOURI STATE AIRPORT SYSTEM PLAN UPDATE. Individual Airport Report CARUTHERSVILLE MEMORIAL AIRPORT

This table has been produced by

Projections of aviation demand developed for the system airports are documented in the following sections:

4. EXISTING SYSTEM EVALUATION

2. INVENTORY. 2.1 Introduction. 2.2 Data Collection Process

Current Airport Roles

Source: Chippewa Valley Regional Airport ASOS, Period of Record

Aviation Planning in Maine and Our Region. Stacie Haskell Aviation Coordinator & Study Manager Maine Department of Transportation April 27, 2011

BELFAST MUNICIPAL AIRPORT OVERVIEW

1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION

OREGON AVIATION PLAN AIRPORT SUMMARY CORVALLIS MUNICIPAL AIRPORT

AERONAUTICAL SURVEYS & INSTRUMENT FLIGHT PROCEDURES

OREGON AVIATION PLAN AIRPORT SUMMARY CRATER LAKE-KLAMATH REGIONAL AIRPORT

Agenda: SASP SAC Meeting 3

Population Estimates for Missouri Cities Report 1: Fastest Growing Cities Based on Numeric Increase,

STUDY WORK GROUP MEETING No. 3. November 29, 2016

CHAPTER 1 INTRODUCTION AND BACKGROUND

Table of Contents. Overview Objectives Key Issues Process...1-3

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

50 Ways to Improve Your Airport: Engaging Airport Management on Key Issues

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN

CHAPTER 3 ALTERNATIVES CONSIDERED

DRAFT MASTER PLAN UPDATE

CATCODE ] CATCODE

Hartford-Brainard Airport Potential Runway Closure White Paper

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

CHAPTER 5 - FACILITY REQUIREMENTS

Chapter 9 - AIRPORT SYSTEM DESIGN

chapter 5 Recommended Master Plan Concept airport master plan MASTER PLAN CONCEPT

Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES

Grants Pass Airport Master Plan & Airport Layout Plan Update

B GEORGIA INFRASTRUCTURE REPORT CARD AVIATION RECOMMENDATIONS DEFINITION OF THE ISSUE. Plan and Fund for the Future:

CHAPTER 1 EXECUTIVE SUMMARY

Population Estimates for Missouri Cities Report 1: Fastest Growing Cities Based on Numeric Increase,

3 INTRODUCTION. Chapter Three Facility Requirements. Facility Requirements PEAKING CHARACTERISTICS

CHAPTER 1 BACKGROUND AND PROPOSED ACTION

MetroAir Virtual Airlines

Chapter 2: Existing Facilities

Chapter 4.0 Facility Requirements

Population Estimates for Missouri Cities Report 1: Fastest Growing Cities Based on Numeric Increase,

Saint Petersburg-Clearwater International Airport. Airspace & Instrument Approach Analysis

approved for website qry

Approved Financial Institutions 4/24/2017

CHAPTER 1. INTRODUCTION

Chapter 8.0 Implementation Plan

TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan

AIRPORT MASTER PLAN. Newport State Airport. Draft. (Colonel Robert F. Wood Airpark) THE Louis Berger Group, INC. Prepared for: Prepared by:

Airport Master Plan. Hutchinson Municipal Airport Butler Field (HCD) Hutchinson, Minnesota. July 2015

MFA EXCHANGE 408 S BIRCH ALBANY MO ALTON FARM CENTER HWY 160 EAST ALTON MO CASS COUNTY MFA 101 WALNUT ARCHIE MO MFA

Merritt Island Airport

Navigation - Runways. Chap 2, Nolan

Runway Length Analysis Prescott Municipal Airport

Chapter 4 Airport Facility Requirements

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

JOHNSTON COUNTY AIRPORT AUTHORITY

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

APPENDIX C AIRSPACE PROCEDURES

Chippewa-Eau Claire Metropolitan Planning Area Long Range Transportation Plan

COMMERCIAL AND GENERAL AVIATION

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:

3.1 CRITICAL AIRCRAFT

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

Chapter 3 FACILITY REQUIREMENTS

Inventory of Existing Conditions.

General Aviation Master Plan Update

Pierre Regional Airport Airport Master Plan. Kickoff Meeting April 7, 2017

DATE OF AERIAL PHOTOGRAPHY:

SUMMARY OF QUANTITES NO. ITEM DESCRIPTION UNIT QUANTITY DRAWING NUMBER TITLE GENERAL ELECTRICAL

ArcadiaMunicipalAirportislocatedonthesoutheast sideofarcadia,southofstateroute70,westofstate Route31,andisaccessiblefrom AirportRoad.

FORECASTING FUTURE ACTIVITY

CHAPTER 3 AIRPORT FACILITY REQUIREMENTS

15 Precision Approach Path Indicator 33 None RSA 150 feet wide by 300 feet long 150 feet wide by 300 feet long

GLOSSARY A.1 ABBREVIATIONS/ACRONYMS

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

THE VILLAGES AVIATION CLUB. SAFETY BRIEF November 2016

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

THE VILLAGES AVIATION CLUB. November 2014 SAFETY BRIEF

Archived. Appendix - Medicaid Case Management Providers Pregnant Women and Children s Programs

4.0 FACILITY REQUIREMENTS

1 DRAFT. General Aviation Terminal Services Aircraft Hangars Aircraft Parking Aprons Airport Support Facilities

Appendix C AIRPORT LAYOUT PLANS

Airport Directory

Airport Directory

MASTER PLAN CONCEPT 1 DRAFT

MISSOURI. Airport Directory Published by the Missouri Department of Transportation Multimodal Operations Aviation Section

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

R FAA

AIRPORT MASTER PLAN UPDATE

The Future of Aviation for Central New Mexico

FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW

NEW METROPOLITAN AND MICROPOLITAN STATISTICAL AREA DELINEATIONS

Airport Master Plan Open House Front Range Airport February 23, 2017

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Appendix C. User Survey Data

Transcription:

FEBRUARY 2019 MISSOURI STATE AIRPORT SYSTEM PLAN UPDATE Individual Airport Report SPRINGFIELD- BRANSON NATIONAL AIRPORT

OVERVIEW The Aviation Section of the Missouri Department of Transportation recently completed an update to the Missouri State Airport System Plan. This report provides a summary of statewide findings and highlights study results as they pertain specifically to Springfield- Branson National Airport. This summary provides the following: System planning process Recommended state airport roles Recommended role for Springfield-Branson National Airport Outlook for general aviation demand Airport facility/service objectives Airport report card EXISTING MISSOURI AIRPORT SYSTEM In addition to this airport-specific summary report, a Technical Report, a Fact Sheet, and a statewide Executive Summary were also produced. These documents can be provided by MoDOT s Aviation Section upon request, or can be downloaded from MoDOT s website: https://www.modot.org/aviation-general-information. 29 Gould Peterson Muni Rosecrans Northwest Missouri Rgnl 29 Albany Muni Cameron 35 Butler Bethany Chillicothe Muni Grand Glaize-Osage Beach El Dorado Springs Bolivar Muni Buffalo Muni Jerry Sumners Sr Aurora Muni Branson West Muni - Emerson Field Floyd W Jones Lebanon Willow Springs Ava Bill Martin M Graham Clark Downtown Branson Cpt Ben Smith Airfield - Monroe City Cabool Gainesville Hannibal Rgnl Kansas City Intl Excelsior Springs Omar N Bradley Bowling Green Muni Carrollton Midwest National Air Center Mexico Marshall Muni St Charles Charles B Wheeler Downtown Elton Hensley County Smartt Higginsville 70 Industrial Muni Lee s Summit Muni Jesse Viertel UCM Skyhaven Hermann Muni Creve Coeur St Louis Lambert Intl 49 Sedalia Rgnl Columbia Rgnl Lawrence Smith Spirit of St Louis Jefferson City Washington Rgnl Lincoln Muni Roy Otten State Technical College Airfield 44 of Missouri Clinton Rgnl Eldon Model Airpark Nevada Muni Joplin Rgnl Stockton Muni Monett Rgnl Lamar Muni Mount Vernon Muni Neosho Hugh Robinson Cassville Muni COMMERCIAL AIRPORTS North Central Missouri Rgnl Springfield-Branson National 44 GENERAL AVIATION AIRPORTS Trenton Muni Warsaw Muni Camdenton -Lake Rgnl Mansfield Muni Unionville Muni Memphis Lee C Fine Kahoka Muni Kirksville Rgnl Lewis County Rgnl Shelby County Macon-Fower Mountain Grove Rolla National Richland Muni Waynesville- St Robert Rgnl Forney Fld Salem Houston Cuba Muni Washington County Mountain View West Plains Rgnl Bismarck Doniphan Muni Thayer Sullivan Rgnl Bonne Terre Muni Bollinger-Crass Campbell Muni Farmington Rgnl 55 Cape Girardeau Rgnl Piedmont Muni Poplar Bluff Muni Gideon Kennett Hornersville A. Paul Vance Fredericktown Rgnl Perryville Rgnl Sikeston Muni Dexter Muni Malden Rgnl County Steele Muni Mississippi County Caruthersville 1

THE SYSTEM PLANNING PROCESS The process used to update Missouri s State Airport System Plan followed the Federal Aviation Administration s (FAA s) Advisory Circular 150/5070-7 - The System Planning Process. The System Plan is important because it enables the Aviation Section to gather information on current activity, facilities, and services at the 107 airports included in the state airport system. While the state airport system includes 107 public-use airports, there are other private-use airports in Missouri. The private-use airports were not included in the System Plan. Missouri s State Airport System Plan is an important planning document; recommendations in the state study should be considered as individual airport master plans are prepared. In addition, the state study provides important information to the FAA that feeds into the National Plan of Integrated Airport Systems (NPIAS). The general process followed to conduct the update to Missouri s Airport System Plan is shown to the right. Ultimately, recommendations for Springfield-Branson National Airport, presented in this report, are a blend of projects/actions identified by the System Plan, initiatives that are included in the Airport s most current Capital Improvement Plan (CIP), and projects related to pavement maintenance and rehabilitation from Missouri s Statewide Pavement Management Plan. By considering all three, a more holistic view of the Airport s near-term development and investment needs is achieved. MISSOURI STATE AIRPORT ROLES Missouri s State Airport System Plan was last published in 2002. Since that time, the aviation industry has changed, Missouri airports have changed, and the communities that the airports serve have changed. The update provides the opportunity to set the bar for future system performance. Working with the System Plan s Project Advisory Committee (PAC), recommended roles for all 107 airports included in the Missouri system were identified. Using information on FAA airport roles, based aircraft, anticipated population and employment growth, runway lengths, operational fleet mix, and airport/community characteristics and circumstances, the PAC assigned all system airports to one of the roles shown in the table below. COMMERCIAL Commercial airports accommodate scheduled commercial airline flights and a high level of general aviation activity. Airports in this role provide access to the national and global economies. Commercial airports should have a minimum runway length of 6,000 feet. NATIONAL BUSINESS The National Business role is a new category for Missouri airports. National Business airports serve almost all business jets and connect Missouri with all domestic and some international markets. National Business airports should have a minimum runway length of 5,500 feet. REGIONAL BUSINESS Regional Business airports focus on serving business activity, including many small jet and multi-engine general aviation aircraft. Regional Business airports should have a minimum runway length of 5,000 feet. BUSINESS COMMUNITY Business Community airports focus on providing aviation access for small business, recreational, and personal flying activities throughout Missouri and contribute to supporting community economies. Business Community airports should have a minimum runway length of 4,000 feet. COMMUNITY LOCAL Community Local airports are important to the communities they serve. These airports primarily serve recreational and personal flying activities and support the local economy. The objective for airports in this role is to maintain the airport s existing runway length. 2

RECOMMENDED ROLE FOR SPRINGFIELD-BRANSON NATIONAL AIRPORT Each airport s role in the state airport system generally reflects the type of aircraft/customers the airport serves and the characteristics of the airport s service area. The recommended role for Springfield-Branson National Airport in the state airport system is Commercial. As a Commercial airport, the System Plan has identified certain facilities and services that should ideally be in place at the Airport. These objectives are considered the minimum to which the Airport should be developed. Based on local needs/ justification, it is quite possible that an airport could exceed its minimum development objectives. It is also worth noting that any recommendations for the Airport identified as part of the System Plan, need to be substantiated/supported through a local master planning effort and supporting environmental analysis, as applicable. Inclusion of a project in the System Plan does not necessarily signal MoDOT or FAA acceptance of or funding for the project. Springfield-Branson National Airport s specific objectives, as they pertain to the Airport s recommended role in the state airport system, are listed below. OBJECTIVES FOR MISSOURI COMMERCIAL AIRPORTS AIRSIDE FACILITIES: Airport Reference Code: Runway length: C-II 6,000' Runway width: 100' Taxiway: Lighting systems: Approach: NAVAIDS/Visual aids: Weather reporting: Full Parallel HIRL, MITL, and ALS Precision GENERAL AVIATION FACILITIES: Hangared aircraft storage: Apron parking/storage: Terminal/administration: Auto parking: SERVICES: Fuel: FBO: Aircraft maintenance: Rental car access: Ground transportation services: Rotating beacon, segmented circle and wind cone, VGSI (PAPI or VASI), and REILs AWOS or ASOS 70% of based aircraft fleet 30% of based aircraft fleet plus an additional 75% for daily transient aircraft 2,500 square feet minimum of public use space including restrooms, conference area, and pilots' lounge One space for each based aircraft plus an additional 50% for visitors/employees AvGas and jet fuel Yes Yes Yes Yes OUTLOOK FOR AVIATION DEMAND While most development objectives for Springfield-Branson National Airport are driven by role, rather than demand, it is still important to have a general sense of how activity (based general aviation aircraft and annual operations) at the Airport could change in the coming years. The following table shows forecasts for the Airport developed as part of the System Plan. It is worth noting that demand projections developed as part of a State Airport System Plan tend to be far more conservative than forecasts developed as part of an individual Airport Master Plan or Airport Layout Plan report. SPRINGFIELD-BRANSON NATIONAL AIRPORT FORECASTS OF AVIATION DEMAND Based Aircraft 2017 Actual 122 34,374 2022 125 36,420 2027 128 38,590 2037 134 43,330 Source: 2018 Missouri State Airport System Plan Annual General Aviation Operations The forecasts developed for the System Plan generally parallel rates of growth that the FAA anticipates for general aviation on a national basis. The graph below shows statewide projections of based aircraft and annual general aviation operations for the 107 study airports as they were developed in the update to the State Airport System Plan. STATEWIDE PROJECTIONS OF BASED AIRCRAFT & ANNUAL GENERAL AVIATION OPERATIONS 3

M I S SOU R I A I R P O R TS P R OVI DE E C ON OM I C S U P P ORT Missouri airports are important economic engines for the communities they serve. Airports support local and visiting businesses, and airports bring visitors to Missouri for vacation and leisure trips to visit friends and family. In 2012, MoDOT s Aviation Section conducted a statewide economic impact study to measure the annual benefit of each airport. Excluding the significant economic impacts associated with the major commercial airports serving Kansas City and St. Louis, all other commercial and general aviation airports included in Missouri s statewide study support an estimated 14,910 jobs; $543.7 million in annual payroll; and $1.5 billion in total annual output. The 2012 study estimated the individual annual economic impact for Springfield-Branson National Airport was $402.02 million. Since development costs for all projects at St. Louis Lambert and Kansas City International airports are not reflected in the System Plan, the annual economic impact of the two major commercial airports was not included. When this economic impact is considered, the annual total increases from $1.5 billion to $11.1 billion. The map below helps to demonstrate how the Airport supports the community s connectivity to destinations throughout the country. The FAA s National Offload Program (NOP) provides information on flights between the Airport and other US destinations. The NOP data does not reflect all destinations and originations served by the Airport, but the data does reflect a cross-section of those cities. Airports are part of the infrastructure that is needed to attract and retain economic development. S P R I NG F I E LD -B RAN S ON N AT I ON AL AI R P ORT F LI G H T M AP Arrivals & Departures Source: FAA National Offload Program (NOP) 2017 Note: Arrivals and departure shown on this map are those recorded by FAA; they represent only a percentage of the Airport s total annual operations 4

AIRPORT REPORT CARD & RECOMMENDATIONS This report provides information on facility/service objectives associated with a Commercial airport in the state airport system. The report card on the following pages shows the Airport s ability to meet its objectives. If the Airport does not meet an objective, an estimated cost to enable the Airport to meet the objective was developed. The System Plan also reviewed the Airport s current Capital Improvement Plan (CIP), as submitted to MoDOT. The Airport s CIP was compared to projects recommended by the System Plan to determine if there were any duplications; duplicate projects were removed. MoDOT also has a Pavement Management Plan for most system airports; this plan was last updated in 2018. Pavement projects that have not yet been completed are also shown in the Airport s report card. The Airport s pavement projects were compared to the projects from the System Plan and the Airport s CIP to avoid duplication. It is likely that the Airport will continue to identify development, maintenance, and rehabilitation needs not currently identified in their report card. AREAS OF FINANCIAL NEED TO MAINTAIN & IMPROVE THE MISSOURI AIRPORT SYSTEM The accompanying graph shows the various sources for the estimated financial need to maintain and improve airports in the Missouri system. When all System Plan, CIP, and pavement management projects are considered, it is estimated that statewide, a total of $702 million will be needed over the next five years to fully respond to all needs as they are known at this time. This results in an average annual statewide need of $140 million in each of the next five years. EXISTING AIRPORT FACILITIES FOR SPRINGFIELD-BRANSON NATIONAL AIRPORT COMBINED STATEWIDE 5-YEAR DEVELOPMENT COSTS (BY PLAN): $702,365,050 The System Plan has estimated that over the next five years, the Springfield-Branson National Airport could need an estimated $8.60 million to address system plan objectives, CIP projects, and pavement maintenance needs. This equates to an average annual need of $1.72 million in each of the next five years. The last statewide economic impact study, completed for Missouri airports in 2012, shows that the Airport has an average annual economic impact of $402.02 million. This benefit exceeds the Airport s estimated average yearly financial need, showing the Airport is well worth the investment! The Airport s report card from the System Plan follows. CIP costs captured in the System Plan generally do not reflect those of the Commercial airports, unless there is a potential for the CIP project to be funded through the state s Aviation Trust Fund. Commercial airports and their pavement maintenance needs are not included in the state s Pavement Management Plan; however, the graph above reflects pavement maintenance projects for some Commercial airports if these projects were part of a CIP submitted to MoDOT. 5

SPRINGFIELD-BRANSON NATIONAL AIRPORT REPORT CARD AIRPORT NAME: Springfield-Branson National CITY: Springfield AIRPORT CODE: SGF ACTIONS NEEDED TO MEET FACILITY AND SERVICE OBJECTIVES Facility Type Minimum Objective Actual Compliance Action Needed to Meet Criteria Estimated Cost ARC C-II C-IV Yes $- Runway Length (feet) 6,000 8,000 Yes $- Runway Width (feet) 100 150 Yes $- Taxiway System Full Parallel Full Parallel Yes $- NAVAIDS Rotating Beacon Yes Yes Yes $- Lighting Wind Cone Yes Lighted wind cone Yes $- Segmented Circle Yes Yes Yes $- REILS Yes (both ends) N/Y Yes $- VGSI (PAPI/VASI) Yes (both ends) P4R / P4L Yes $- Approach Precision Precision Yes $- Lighting Runway Lighting HIRL HIRL Yes $- Taxiway Lighting HITL MITL Yes $- Approach Lighting System ALS MALSR/ Yes $- Weather AWOS/ASOS ASOS HIWAS Yes $- Hangar Storage 70% of based aircraft 96 Yes $- Tie Downs 30% of based & 75% of daily transient 100 Yes $- GA Admin Building Building Area (Sq. Ft.) 2,500 5,500 Yes $- Public Restroom Yes Yes Yes $- Conference Room Yes Yes Yes $- Pilot Lounge Yes Yes Yes $- GA Auto Parking 1 space for each based & 50% for employees 700 Yes $- Ground Communications Public phone Yes Yes $- Services Jet Fuel Yes Yes Yes $- AvGas Yes Yes Yes $- FBO Yes Yes Yes $- Aircraft Maintenance Yes Yes Yes $- Rental Cars Yes Yes Yes $- Transportation Yes Yes Yes $- Estimated SASP Facility/Service Project Costs: $- Note: It is important to note that an ALS on a given runway end replaces the need for REILs on that runway end. 6

CAPITAL IMPROVEMENT PLAN (CIP) PROJECTS PLANNED Project Type Project Description Estimated Cost Taxiways Construct T-Hangar Taxilanes $3,000,000 Apron Phase II GA Development Program $950,000 Hangars Construct Taxiway to Access Hangars on the End of GA Apron $1,000,000 Acquisitions, Relocations, & Easements Land Acquisition $300,000 Safety & Security Remove Runway 32 20:1 Approach Obstruction $750,000 Apron Phase III GA Development Program $750,000 Estimated CIP Project Costs $6,750,000 MAJOR PAVEMENT MAINTENANCE PROJECTS PLANNED Project Type Project Description Estimated Cost Apron Pavement Maintenance Study $175,000 Taxiways Rehabilitate T-Hangar Taxilanes $1,400,000 Runways Runway 14 Joint Sealant and Panel Replacement $275,000 Estimated Pavement Project Costs $1,850,000 Total Estimated Project Costs $8,600,000 System plan project costs are developed to a planning, not engineering, level of detail. System plan costs are based on typical Missouri unit costs, but airport conditions may cause these costs to vary. Furthermore, bids received may be different from plan estimates. CIP projects in the report card have not been vetted, prioritized, or approved by MoDOT or FAA. A project s inclusion in the report card does not mean that either MoDOT or FAA has approved or committed funds to the project. Some projects will require additional study to justify the need/feasibility of the project, and some projects could require environmental and airspace analysis. MoDOT MULTIMODAL OPERATIONS DIVISION-AVIATION SECTION 105 West Capitol Avenue Jefferson City, Missouri 65101 573.751.2589 aviation@modot.mo.gov www.modot.org 7

GLOSSARY OF TERMS Airport Reference Code (ARC) Automated Surface Observation System (ASOS) A coding system used to relate the airport design criteria to the operational and physical characteristics of the airplanes intended to use the airport or the critical aircraft. It is a two-character code consisting of the Aircraft Approach Category and the Airplane Design Group. Similar data reporting as an AWOS, but usually owned and maintained by the National Weather Service. Automated Weather Observation System (AWOS) AVGAS An automated sensor suite which is voice synthesized to provide a weather report that can be transmitted via VHF radio, NDB, or VOR ensuring that pilots on approach have up-to-date airport weather for safe and efficient aviation operations. Most AWOS observe and record temperature and dew point in degrees Celsius, wind speed and direction in knots, visibility, cloud coverage and ceiling up to 12,000 feet, freezing rain, thunderstorm (lightning), and altimeter setting. Aviation fuel (gasoline) used for aircraft with internal-combustion engines. The most common Avgas is currently 100LL (Low Lead). Fixed Base Operation or Fixed Base Operator (FBO) A business enterprise located on the airport property that provides services to pilots including aircraft rental, training, fueling, maintenance, parking, and the sale of pilot supplies. General Aviation (GA) The segment of aviation that encompasses all aspects of civil aviation except certified air carriers and other commercial operators, such as air freight carriers. Instrument Landing System (ILS) Localizer Performance With Vertical Guidance (LPV) Medium Intensity Runway Lights (MIRL) Medium Intensity Taxiway Lights (MITL) Precision Approach Path Indicator (PAPI) A precise ground-based navigation system for aircraft that provides precision guidance to an aircraft approaching a runway. It uses a combination of radio signals and, in many cases, high-intensity lighting arrays to enable a safe landing during instrument meteorological conditions. An instrument approach procedure that uses wide area augmentation system (WAAS) and very precise GPS capabilities to attain an airplane s position. Although it does provide vertical guidance and can provide minimums consistent with an ILS, an LPV is considered to be a non-precision approach. Runway edge lights are used to outline the edges of runways during periods of darkness or restricted visibility conditions. These light systems are classified according to the intensity or brightness they are capable of producing: High Intensity, Medium Intensity, and Low Intensity. Medium Intensity Runway Lights represent the system typically utilized at most general aviation airports. Taxiway edge lights are used to outline the edges of taxiways during periods of darkness or restricted visibility conditions. These light systems are classified according to the intensity or brightness they are capable of producing: High Intensity, Medium Intensity, and Low Intensity. Medium Intensity Taxiway Lights represent the system typically utilized at most general aviation airports. A path indicator that uses a single row of lights arranged to provide precision descent guidance information during approach to a runway. Runway End Identifier Lights (REIL) Provides rapid and positive identification of the approach end of a particular runway. The system consists of a pair of synchronized flashing lights, one on each side of the runway threshold. Visual Approach Slope Indicator (VASI) A system of lights arranged to provide vertical visual approach slope guidance to aircraft during approach to landing by radiating a directional pattern of high intensity red and white focused light beams. Visual Glide Slope Indicator (VGSI) A ground device that uses lights to assist a pilot in landing an airplane at an airport. The lights define a vertical approach path during the final approach to a runway and can help the pilot determine if the airplane is too high or too low for an optimum landing. 8