Atlantic Street Bridge Project CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro North RR Bridge Replacement Track & Station Infrastructure Improvements City of Stamford www.atlanticstreetbridge.com
Public Outreach Social Media Outlets Regular Updates: on the web: http://atlanticstreetbridge.com on Facebook: atlanticstreetbridge on Twitter: @Atlantic_Street Sign up for Email Announcements on the Website Email: info@atlanticstreetbridge.com
CONNECTICUT DOT PROJECT TEAM CTDOT District 3A Office: Domenic LaRosa, P.E. Dean Cerasoli, P.E. John Antonucci, P.E. Mohammad Masoud District Engineer Assistant District Engineer Supervising Engineer Project Engineer HAKS Engineers P.C. (Construction Engineering & Inspection): Kevin Conroy, P.E. Resident Engineer
State Project Nos.: 135 301 & 301 163 Owner: Connecticut Dept. of Transportation Inspector: HAKS Engineers Contractor: Halmar International Contract Value: $ 74,846,308 Pre Construction Started: August 28, 2017 Contract Completion Date: November 30, 2020 Contract Information
Combined Contract 135-301/301-163 EXISTING METRO NORTH BRIDGE OVER ATLANTIC STREET
Combined Contract 135-301/301-163 PROPOSED CONSTRUCTION
Combined Contract 135-301/301-163 5 3 1 2 Replace MNR Bridge Extended Platform 1 `` 3 4 Track #7 Construction Catenary Replacement 2 4 5 5 Lowering Roadway
Additional Considerations Multimodal Accommodations Provides for Future Bike Lanes Beautification Use of Concrete Form Liner Incorporation of City Streetscape Standards Salvage of Existing Brownstone for Future City Use
JUMP SPANS & TEMPORARY SUPPORTS Jump Span Installation and Abutments
PRE- DEMOLITION Bridge Roll-in: Begin June 28, 2019
PRE ROLL-IN TRACKS 2 & 4 Bridge Roll-in: June 28-July 8, 2019
TRACKS 2 & 4 RETURNED TO SERVICE Bridge Roll-in: June 28-July 8, 2019
STAGE 2 BRIDGE ROLL-IN COMPLETED Bridge Roll-in Completed: July 8, 2019
Bridge, Platform and Track #7 Complete: November 2020 PLATFORM & TRACK 7 COMPLETED
Animation
Current Schedule ACTIVITY DATE JUMP SPAN INSTALLATION FALL 2018 ATLANTIC STREET CLOSED FEBRUARY 2019 CENTER PIER CONSTRUCTION FEBRUARY JUNE 2019 NEW BRIDGE ROLL IN JUNE 28 JULY 8, 2019 LOWER ATLANTIC STREET JULY SEPTEMBER 2019 REOPEN ATLANTIC STREET SEPTEMBER 2019 PHASE 2 COMPLETE NOVEMBER 2020
Traffic Patterns During Phase 2 Temporary Lane Closures (Atlantic Street, South State Street Similar to Phase 1 Project) Temporary Detours during Bridge Demolition and Roll In Period (Atlantic St, Dock St, South State St) Approx. 6 Month Closure of Atlantic Street to Install Center Pier and Complete Roadway Lowering
Stage 1B (Center Pier Construction): February - June 2019 Road Closures: Atlantic Street (Dock St to S. State St) Detours: Washington Blvd Henry Street Dock Street Canal Street N. & S. State Streets
Stage 1B (Center Pier Construction): February - June 2019 Road Closures: Atlantic Street (Dock St to S. State St) Detours: Washington Blvd Henry Street Dock Street Canal Street N. & S. State Streets
Stages 2 & 3: June 28 th September 9 th, 2019 Road Closures: Manhattan Street (access to Atlantic) South State Street (btw Guernsey Avenue & Exit 8 NB off-ramp) Station only access from Washington Blvd. Atlantic Street (btw Dock St & N. State St) Dock Street (btw Atlantic St & John Street) Atlantic Street (btw S. State St & Dock St) Detours: Guernsey Avenue (closed to SB traffic from N. State St) Washington Blvd Washington Blvd, Henry St. to Canal St.
Road Closures: Manhattan Street (access to Atlantic) South State Street (btw Guernsey Avenue & Exit 8 NB off-ramp) Station only access from Washington Blvd. Atlantic Street (btw Dock St & N. State St) Dock Street (btw Atlantic St & John Street) Atlantic Street (btw S. State St & Dock St) Detours: Guernsey Avenue (closed to SB traffic from N. State St) Washington Blvd Washington Blvd, Henry St. to Canal St. Stages 2 & 3: June 28 th September 9 th, 2019
Pedestrian Detour of Atlantic Street: June - September 2019 Sidewalk Closures: Atlantic Street (btw N. or S. State St & Dock St) Detours: Guernsey Avenue Xing over Tracks via Station Station Place Access to S. State Street until Stage 2 (June 2019)
Pedestrian Detour of Atlantic Street: June - September 2019 Sidewalk Closures: Atlantic Street (btw N. or S. State St & Dock St) Detours: Guernsey Avenue Xing over Tracks via Station Station Place Access to S. State Street until Stage 2 (June 2019)
THANK YOU!!! Regular Updates: on the web: http://atlanticstreetbridge.com on Facebook: atlanticstreetbridge on Twitter: @Atlantic_Street Sign up for Email Announcements on the Website Email: info@atlanticstreetbridge.com Project Signage in Station and Downtown Regular Public Meetings Flyers and Bulletins
Atlantic Street Bridge Project CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro North RR Bridge Replacement Track & Station Infrastructure Improvements City of Stamford www.atlanticstreetbridge.com