Planning, Development and Environment Committee

Similar documents
Noise Oversight Committee

Study Design Outline. Background. Overview. Desired Study Outcomes. Study Approach. Goals (preliminary) Recession History

msp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010

Noise Oversight Committee

CHAPTER 4: ALTERNATIVES

Chapter 1: Introduction Draft

Airlake Airport 2035 Long Term Comprehensive Plan (LTCP)

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i

Chapter 1: Introduction

Westover Metropolitan Airport Master Plan Update

Introduction DRAFT March 9, 2017

Noise Oversight Committee

STUDY WORK GROUP MEETING No. 4. July 12, 2017

3rd Quarter 2015 Minneapolis-St. Paul International Airport (MSP) Public Input Meeting

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

2. 1:45 to 1:50 Review and Approval of November 18, 2009 NOC Meeting Minutes

ACTION TRANSMITTAL

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D

Savannah / Hilton Head International Airport Master Plan Update

DRAFT. Airport Master Plan Update Sensitivity Analysis

AIRPORT MASTER PLAN ADVISORY COMMITTEE MEETING #2 AGENDA

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

AIRPORT MASTER PLAN FOR. charles B. WHEELER DOWNTOWN AIRPORT KANSAS CITY, MISSOURI

Welcome to the Boise Airport Master Plan Update Open House

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN

Tampa International Airport Master Plan Update. December 12, 2012

BNA Master Plan Update Community Advisory Committee Meeting No. 5

CHAPTER 1 EXECUTIVE SUMMARY

City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018

Forecast and Overview

FORECASTING FUTURE ACTIVITY

Ted Stevens Anchorage International Airport

Regular Board Meeting August 4, 2015

Ted Stevens Anchorage International Airport

Fort Wayne International Airport Master Plan Study. Executive Summary

BNA Master Plan Update Public Meeting No. 2

HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1

Master Plan Update Technical Advisory Committee Meeting

AIRPORT MASTER PLAN UPDATE

APPENDIX D MSP Airfield Simulation Analysis

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

Lake Tahoe Airport Master Plan

SAN JOSÉ INTERNATIONAL AIRPORT

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Nantucket Memorial Airport Master Plan Update

Runway Length Analysis Prescott Municipal Airport

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3

Presentation Outline. We will leave with:

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item.

General Aviation Master Plan Update

STUDY WORK GROUP MEETING No. 3. November 29, 2016

Airport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017

Chapter 1 Introduction and Project Overview

Master Plan Update Community Advisory Committee Kick-off Meeting

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

Forecast of Aviation Activity

ENVISIONING AUSTIN s Airport of the Future

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:


~ s: Memorandum

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Partnership for Quieter Skies Report

Kelly Field at Port San Antonio Airport Master Plan

The CLE Master Plan Includes:

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT

CHAPTER 1: INTRODUCTION

Table E-3 Phased Capital Improvement Program...E - 11

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

AIRPORT DEVELOPMENT PLAN. Design-Build Institute of America September 8, 2015

Nantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Partnership for Quieter Skies Report

3 Aviation Demand Forecast

Chapter 1 Introduction and Project Overview

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

Alternatives. Introduction. Range of Alternatives

EAT Master Plan Planning Advisory Committee (PAC) Meeting #2 Summary (FINAL)

Current and Forecast Demand

FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1. September 28, 2016

Norfolk International Airport

Session Six: State Aviation System Plan Overview GAA Annual Conference & Expo Jekyll Island, Ga Back to the Beach: For a Low Country Luau

FLL Master Plan Update Policy Advisory Committee (PAC) Briefing #2 July 10, 2017

Love Field Modernization Program Update: Master Planning Recommendations

Chapter 1 Introduction

Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

CHAPTER 4 DEMAND/CAPACITY ANALYSIS

FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING

Austin-Bergstrom International Airport Master Plan Update

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4

Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update. 6th Working Group Briefing 1/7/19

2 Aviation Demand Forecast

Meeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012

Transcription:

Page 1 of 7 MEMORANDUM TO: Planning, Development and Environment Committee FROM: Neil Ralston, Airport Planner Airport Development (726-8129) SUBJECT: 2035 MSP LONG TERM COMPREHENSIVE PLAN FORECAST, FACILITY REQUIREMENTS, AND STAKEHOLDER OUTREACH DATE: March 31, 2015 At the April, 2015 meeting of the Planning, Development and Environment Committee, staff will provide an overview of the Forecast, Facility Requirements, and Stakeholder Outreach elements of the 2035 Long-Term Comprehensive Plan (LTCP) for the Minneapolis St. Paul International Airport (MSP). The purpose of the LTCP is to update our view of facility needs for the next 20 years and to serve as the road map to guide our development strategy for MSP. The plan will recommend concepts for the types and locations of facility improvements needed to accommodate projected demand through the planning horizon, along with providing guidance on phasing and scheduling throughout the 20-year program. The Long-Term Comprehensive Plan is updated routinely every five years to reconcile everchanging trends in the industry. It does not authorize any construction. It is helpful however in shaping the 7-year Capital Improvement Program which is the implementation vehicle of the Commission. Attachment 1 is a glossary of key terms which may be of assistance during this discussion. Activity Forecast: The 2035 MSP LTCP forecast provides aviation activity projections through the 20- year planning horizon to serve as the basis for deriving facility needs. The elements of the forecast include passenger originations and enplanements, passenger aircraft operations, aircraft fleet mix, and design day flight schedules. Also included are projections of air cargo tonnage, and air cargo, air taxi, general aviation, and military aircraft operations. The forecast is unconstrained in nature, meaning that sufficient airfield, terminal, and landside facilities are expected to be in place to accommodate the activity levels dictated by demand. The forecast includes activity projections for milestone years 2020, 2025, 2030, and 2035. A preliminary version of the forecast for passenger-related activities through 2030 was presented to the Committee in September 2014. The projection for passenger activity has now been extended through 2035 and updated to reflect actual 2014 year-end traffic levels. There are no substantial differences between the preliminary forecast presented in September 2014 and the final draft forecast presented herein. A tabular summary of the Base Case MSP 2035 LTCP forecast follows: Revenue Passenger Total Aircraft Operations Enplanements ACTUAL 2013 16,369,938 431,573 2014 17,002,809 411,760 Historical High 17,984,311 (2005) 541,093 (2004) FORECAST 2015 17,587,794 411,036 2020 18,798,673 427,270 2025 21,137,924 449,081 2030 23,794,889 477,762 2035 26,898,904 511,315 Compound Annual Growth Rate ( 14 35) 2.2% 1.0%

Page 2 of 7 The following table compares the results of Base Case 2035 LTCP forecast with forecasts prepared for the previous LTCP in 2009 and the 2020 Improvements Environmental Assessment (EA) in 2012: Year 2030 Revenue Passenger Enplanements Year 2030 Total Aircraft Operations 2030 LTCP (2009 forecast) 28,431,850 630,837 2020 Improvements EA (2012 forecast) 26,411,706 567,396 2035 LTCP (2015 forecast) 23,794,889 477,762 When compared to these previous forecasts, the Base Case 2035 LTCP forecast is lower in terms of both revenue passenger enplanements and total aircraft operations for the planning horizon year of 2030 (the out-year for the previous projections). We have also prepared High and Low forecast scenarios so that the planning team can test the sensitivity of various development options to fluctuating demand levels. The following figures graphically show the Base Case 2035 LTCP forecast in relation to the envelope of the High and Low forecast scenario ranges. FIGURE 1 2035 LTCP PASSENGER ENPLANEMENT FORECAST RANGE 35.0 Revenue Passenger Enplanements (millions) 30.0 25.0 20.0 15.0 10.0 5.0 0.0 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2035 LTCP Forecast Scenario Envelope Historical Enplanements 2035 LTCP Base Forecast

Page 3 of 7 FIGURE 2 2035 LTCP AIRCRAFT OPERATIONS FORECAST RANGE 700.0 600.0 Aircraft Operations (Thousands) 500.0 400.0 300.0 200.0 100.0 0.0 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2035 LTCP Forecast Scenario Envelope Historical 2035 LTCP Base Forecast Facility Requirements: Upon completion of the activity forecasts, the next step is to assess the capabilities of existing facilities to accommodate projected demand levels through a Facility Requirements Analysis. An overview of the planning parameters (operational factors) and level of service standards (performance criteria) used to guide the facility requirements analysis was provided at the March Committee briefing. Identical to the previous LTCP document prepared in 2010, the Facility Requirements analysis is evaluating two distinct scenarios related to facility development: The Airlines Remain Scenario represents continuation of the existing condition where all non- Delta affiliated carriers operating at Terminal 1 remain and grow organically at Terminal 1 through the planning horizon; The Airlines Relocate Scenario represents the balanced terminal concept where all non-delta affiliated carriers (except Great Lakes) relocate to Terminal 2 within the planning horizon. As an example of the facility requirements analysis completed to date, Attachments 2 and 3 depict a level of service gap-assessment illustrating the adequacy of existing processing facilities within the terminals to accommodate demand levels projected for milestone years in the forecast. Additional details and findings from the analysis will be provided during the Committee briefing. Stakeholder Outreach: The LTCP outreach plan proposes three phases that are patterned after the engagement efforts conducted during the last LTCP effort five years ago.

Page 4 of 7 First, we will meet with stakeholders in the mid-april through June timeframe, before the draft plan is finalized, to provide information about the plan s purpose, process, preliminary findings, and timeline. This will include briefings with: Municipal planning departments in surrounding communities, and to their plan commissions and/or City Councils if requested Other agencies such as the FAA, MnDOT, and the Metropolitan Council Internal tenant groups Interested members of the public at an informational meeting The second phase will be the formal public review period after the draft plan has been completed and approved by the MAC for public distribution. We are envisioning a 30 to 45-day written comment period, with two public information meetings scheduled during this timeframe. Finally, after the public comment period closes, we will work to incorporate feedback into the plan and prepare a final draft for MAC adoption and Metropolitan Council formal review. During this time, we will continue to conduct stakeholder outreach on an as-needed basis. THIS IS AN INFORMATIONAL ITEM ONLY; NO COMMITTEE ACTION IS REQUIRED.

Page 5 of 7 Glossary of Key Terms: Aircraft Fleet Mix: The types of aircraft operating at MSP grouped into categories with similar size and performance characteristics. Aircraft Operations: Total aircraft takeoffs and landings. Airlines Relocate Scenario: An LTCP forecast scenario where all non-delta affiliated carriers (except Great Lakes) relocate to Terminal 2 within the planning horizon. Airlines Remain Scenario: An LTCP forecast scenario where all non-delta affiliated carriers operating at Terminal 1 remain and grow organically at Terminal 1 through the planning horizon. Check-in Positions: Ticket counter locations where passengers interact with airline agents or kiosk devices to obtain boarding passes and/or check baggage. Checkpoint: The passenger security screening checkpoint operated by the Transportation Security Administration (TSA). Claim Devices: Carousels in the baggage claim area where passengers retrieve checked baggage from an arriving flight. Connecting Passengers: Passengers who arrive at MSP from another airport and depart from MSP on a connecting flight. Design-Day Flight Schedule: A sample flight schedule representing the average weekday in the peak month for a particular forecast scenario. The schedule includes flight information such as origin and destination, arrival and departure time, and aircraft type. Enplaned Passengers: Total revenue passengers boarding at MSP; includes both originating and connecting passengers. Gates: Parking positions where aircraft load and unload passengers and baggage. LTCP: Long-Term Comprehensive Plan. Originating Passengers: Passengers who start their trip at MSP. Outbound Carts: Staging position for carts used by airlines to sort and transport outbound baggage from the terminal to departing aircraft. ATTACHMENT 1

Page 6 of 7 MSP 2035 LTCP Facility Requirements Analysis Level of Service Gap Analysis Summary Terminal Requirements Airlines Remain Scenario Facility Shortfall Facility Adequacy Terminal 2-Humphrey Terminal 1-Lindbergh Source: Ricondo & Associates ATTACHMENT 2

Page 7 of 7 MSP 2035 LTCP Facility Requirements Analysis Level of Service Gap Analysis Summary Terminal Requirements Airlines Relocate Scenario Terminal 1-Lindbergh Facility Shortfall Facility Adequacy Terminal 2-Humphrey Source: Ricondo & Associates ATTACHMENT 3