PRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction

Similar documents
Hospital Link Project Project Update September 2015

Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program,

25 th Avenue Grade Separation. September 13, 2017

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017

Carlisle Connectivity Projects Communication Plan and Project Status

Atlantic Street Bridge Project CTDOT Project Nos & (Phase 2)

Exposition Light Rail Transit Project

Route 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016

9 CONSTRUCTION OF BATHURST STREET FROM GREEN LANE WEST TO SOUTH OF HIGHWAY 11, TOWN OF EAST GWILLIMBURY AND TOWNSHIP OF KING

90 I-90 Snoqualmie Pass East September Annual Mega-Project Report. Project Benefits

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization

Commonwealth Avenue Bridge Deck Replacement Project. Legislative and Stakeholder Briefing. April 13, 2017

Project Overview. Hunter Mill Road Over Colvin Run Bridge Replacement Fairfax County. Get Involved. Public Information Meeting. Contact Information

Damen Elston Fullerton Reconstruction, Intersection Improvements CDOT Project B-1-501

Community Advisory Panel Meeting #

Regional Connector Transit Project Community Leadership Council. 2 nd Hope Station & Flower St Committees January 17, 2017

PROGRESS REPORT WATERFRONT PROGRAM. Q (January - March) Highlights from Q1 2018

Mason Street Bike/Pedestrian Trail Project

Pre-Construction Public Meeting July 2017

Atlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2)

Chicago St. Louis High-Speed Rail. Braidwood Construction. Local Officials Briefing August 7, 2014

Hospital Link Project Project Update Winter 2018

Crystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S.

25 th Avenue Grade Separation. December 13, 2017

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET

Construction Update. Local Officials Briefing March 2016

KING STREET PILOT STUDY PUBLIC MEETING

Construction Staging Adelaide Street West

Second Street Improvements Project Project Update Archive

I-35 Reconstruction Project

N. Central St. & W. Jackson Ave. Streetscape Projects

San Pedro Waterfront Development Efforts Presentation for Trade, Commerce & Technology Committee

Planning & Development Group

Figure 1: Little Dry Creek Trail Crossing

Long water shutdown scheduled for Tuesday, September 18

Trail # NW Tuesday, June DESIGN. Provide an Review the Provide an. Project Goals: System system. wayfinding

EAST DON TRAIL ENVIRONMENTAL ASSESSMENT. Community Liaison Committee Meeting #3 July 15, :30 to 8:30 pm Flemingdon Park Library

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018

Grade Crossings in High Speed Rail Corridors

Palm Beach County Traffic Report July 13 through July 20, 2012

First rail. August 2011

Engagement Summary Report. Trans-Canada Highway 1 RW Bruhn Bridge Replacement Project. Community Engagement November 15, 2016 to January 15, 2017

AGENDA ITEM 5 D WAKULLA ENVIRONMENTAL INSTITUTE (WEI) TRAIL FEASIBILITY STUDY

Miami Orlando Passenger Rail Project Overview

Blackburn Road Blackburn Level Crossing Removal. Frequently Asked Questions August 2014 GENERAL

Third Parties/Crossing

Chapter 6: POLICY AND PROCEDURE RECOMMENDATIONS

Route 29 Solutions Projects

ONONDAGA CREEKWALK PHASE II. Public Information Meeting Series 1

Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017

P3 & Design-Build. 101 st Annual THE Conference February 25 th, Speaker: Andrew Gensch, P.E.

Monday, September 18, 2017 Sunday, October 1, 2017

City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting

IRONTON-RUSSELL BRIDGE REPLACEMENT

Chicago St. Louis High-Speed Rail. Enos Park Neighborhood Association May 13, 2014

November 21, 2012 Barbara Kelleher, (954)

Construction Staging Area Blue Jays Way (357 King Street West)

Public Information Center August 12, 2010

25 th Avenue Grade Separation. Community Meeting November 13, 2018

Industry briefing NOVEMBER 2017

US 380 FEASIBILITY STUDY

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30

RESORT AREA STRATEGIC ACTION PLAN (RASAP) STEERING COMMITTEE MEETING - APRIL 3, 2019

New 55-Dogpatch Outreach Findings & Route Development

Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018

Palm Beach County Traffic Report August 24 through August 31, 2012

Citrus Heights Creek Corridor Trail Project Trail Advisory Group Field Trip #2 September 11, :00 11:00 am Trellis Hall, Citrus Heights

C. APPROACH FOR IDENTIFYING THE BEST ROUTES FOR THE NEEDED TRANSMISSION SYSTEM IMPROVEMENTS

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

Public Informational Meeting

Miami Orlando Passenger Rail Project Overview

General Issues Committee Item Transit Operating Budget Ten Year Local Transit Strategy

Main Street Station Upgrades

Having trouble reading this ? View it in your browser. Welcome

Dawlish & South West rail

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017

Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT

CITY OF BEVERLY HILLS TRAFFIC & PARKING COMMISSION TO: FROM: SUBJECT: ATTACHMENTS: June 1,2017. Aaron Kunz, Deputy Director

CHAPTER 16 STREETS, SIDEWALKS AND OTHER PUBLIC PLACES*

WATERFRONT PROGRAM PROGRESS REPORT

2016 Regional Transportation Alternatives Program (TAP) Grant Application

South Bay Metro Light Rail Extension. Summer/Fall 2017 Project Briefings

October 31, 2014 Chuck McGinness, (954)

New Jersey Department of Transportation

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.

APPENDIX F List of Commitments

Rails with Trails Finding the mobility, safety, and liability sweet spot 5/10/2017

Update on the Thameslink programme

G Street Undercrossing. City Council Meeting Date: November 3, 2008

E-Newsletter Keeping Our Community Informed Volume 1, Issue 4

CREATING CONNECTIONS IN THE CITY OF ST. CATHARINES

Railway-Highway Crossing at Grade Regulations: Guidelines for British Columbia s Provincial Heritage Railways

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

State Route 8 Corridor. Northern Summit County s Path to Success

Provincial Railway Technical Standards

PROGRESS REPORT. OCTOBER and NOVEMBER 2013

South Bay Light Rail Extension Summer/Fall 2017 Project Briefing

The Baker/Carver Regional Trail is intended to

Transcription:

PRESENTED TO Town of Middlebury, VT PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction

Meeting with you today Brian Carpenter, Middlebury Selectboard Chair Jim Gish, Middlebury Community Liaison Wayne Symonds, PE, Structures Program Manager, VTrans Aaron Guyette, PE, Design Project Manager, VHB Mark Alexander, Senior Construction Manager, Kubricky Construction Jill Barrett, Public Outreach Coordinator, Fitzgerald & Halliday, Inc. (FHI)

Community Project Goals Protect the safety of the community: people, property, environment Minimize the project impact on the vitality of the downtown community: businesses, residents, institutions Maintain traffic flow and pedestrian access to the greatest extent possible Develop and maintain a credible schedule Engage with the local community and facilitate clear communication with all stakeholders

Purpose and Need Replace bridges on Main Street and Merchants Row Reconstruct rail through the project area Address existing drainage concerns of the rail line General map of project area

Bridge Replacement Main Street and Merchants Row bridges at the end service life Structurally deficient, but currently safe Complete replacement of both bridges is necessary VTrans quarterly bridge inspection If bridges become unsafe, temporary bridges will be installed in 7 days

Rail Reconstruction/Drainage Improvement Address poor rail alignment through the project Replace track and ties at the end of service life Provide drainage of the rail corridor Increase vertical clearance from approx. 18' to 21' Improve safety and reliability for rail operation Plan for future freight opportunities and passenger service

Vertical Clearance Measured from the top of the rail to low point on bridge Increase from existing 18'-0" clearance to 21' -0" Legislation in 2016 authorizes reduction from 23'-0" to 21'-0" VTrans, Vermont Railway, and Middlebury sign agreement for 21'-0" Supports future increase height for freight cars New bridges have 100 year life

Accelerated Bridge Construction (ABC) New project approach Short road closure and train detour 10-week road closure with detour vs. 2 years of conventional construction New bridge uses precast concrete pieces to rapidly replace the bridges Project designed to be built quickly

Accelerated Bridge Construction (ABC) VTrans has been successful in delivering ABC projects We understand 10 weeks is a lot for the Community Strive to communicate and provide valid schedules for stakeholders to plan Strive to provide mobility and pedestrian access during the closure

ABC Middlebury Sand Hill Bridge (6 week closure)

Customer Survey Results How satisfied were you with ABC? 397 Responses from 9 projects 0% Very Dissatisfied Somewhat Dissatisfied Neither Satisfied nor Dissatisfied Somewhat Satisfied How satisfied are you with the information you received about the bridge project? 223 Responses from 9 projects 9% 5% 1% Very Satisfied 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 85% Very Satisfied Somewhat Satisfied Neither Satisfied nor Dissatisfied Somewhat Dissatisfied Very Dissatisfied 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% Overall, how satisfied were you with how VTrans delivered this project? 0% 382 Responses from 9 projects Very Satisfied Somewhat Satisfied Neither Satisfied nor Dissatisfied Somewhat Dissatisfied Very Dissatisfied

Big question: Why not just replace the bridges with a 19' 0" RR clearance? Wouldn t that be easier and reduce the project impact on Middlebury?

New Bridge Design

Project Overview Project length 3,550 Tunnel length 360 Number of tunnel pieces - 100

2016 2017 2018 2019 2020

2016 2017 2018 2019 2020

2016 2017 2018 2019 2020 2016 Construction Activity Tree cutting Bat impact avoidance Utilities

2016 2017 2018 2019 2020 Winter 2016 Tree cutting

2016 2017 2018 2019 2020

2016 2017 2018 2019 2020 2017 Construction Activity Temporary access road Drainage system Maintenance road and outfall Underground utility infrastructure

2016 2017 2018 2019 2020 Summer 2017 Temporary access road

2016 2017 2018 2019 2020 2017 Drainage system installation Drainage outfall/ receiving shaft 1 Drive 1 Drive 2 Drive 3 Receiving shaft 2 Launch shaft Receiving shaft 3

2016 2017 2018 2019 2020 2017 Utility infrastructure Buried communications conduits Buried electrical conduits Buried utility crossing railroads

2016 2017 2018 2019 2020 2017 Maintenance access road/outfall Park area undisturbed during construction

2016 2017 2018 2019 2020 2017 Traffic, pedestrian, and parking impacts

2016 2017 2018 2019 2020 2017 Project Impacts Traffic, parking, and pedestrian impacts Main Street and Triangle Park area Printer s Alley Short term lane closures Working hours Anticipated weekday 7:00am 5:00pm Isolated extended working hours

2016 2017 2018 2019 2020

2016 2017 2018 2019 2020 2018 Construction Activity Utility construction Support of excavation installation along railroad Initial excavation along railroad

2016 2017 2018 2019 2020 Support of Excavation (SOE) What is Support of Excavation? Temporary structure to support roads, buildings, and slopes Why is it needed? To minimize impacts to existing infrastructure Preparation for accelerated construction in 2019 What are the extents? Along the railroad corridor

2016 2017 2018 2019 2020 2018 Support of Excavation extents Total length of SOE 3,000

2016 2017 2018 2019 2020 2018 Triangle Park

2016 2017 2018 2019 2020 2018 Traffic and pedestrian impacts

2016 2017 2018 2019 2020 2018 Project Impacts Traffic, parking, and pedestrian impacts Main Street and Merchants Row/Triangle Park area Printer s Alley Short term lane closures Working hours Anticipated weekday 7:00am 5:00pm Isolated extended working hours

2016 2017 2018 2019 2020

2016 2017 2018 2019 2020 2019 Construction Activity Pre-closure (April and May) Closure (June, July, August) Main Street and Merchants Row closures Railroad detour Post-closure (September, October, November, December)

2016 2017 2018 2019 2020 2019 Closure Activity (10 Weeks) Track removal/existing bridge demolition Earth and rock excavation Precast tunnel placement Return traffic to Main Street and Merchants Row

2016 2017 2018 2019 2020 2019 Closure Main Street and Merchants Row closed Bridge demolition Track removed

2016 2017 2018 2019 2020 2019 Closure Earth excavation

2016 2017 2018 2019 2020 2019 Closure U-walls set Earth excavation Rock excavation

2016 2017 2018 2019 2020 2019 Closure Precast tunnel placement Railroad approach excavation

2016 2017 2018 2019 2020 2019 Closure Tunnel backfill Continued excavation and tunnel construction at Main Street Final U-walls

2016 2017 2018 2019 2020 2019 Closure Tunnel complete Main Street and Merchants Row open to vehicle and pedestrian use Continued railroad approach work

2016 2017 2018 2019 2020 2019 Road closures

2016 2017 2018 2019 2020 2019 Vehicle detour North

2016 2017 2018 2019 2020 2019 Vehicle detour South

2016 2017 2018 2019 2020 2019 Pedestrian mobility and access routes

2016 2017 2018 2019 2020 2019 Parking impacts

2016 2017 2018 2019 2020 2019 Closure Project Impacts (10 weeks) Traffic, parking, and pedestrian impacts Main Street and Merchants Row closed at bridge crossings Printer s Alley closed Working hours 24 hours per day, 7 days per week

2016 2017 2018 2019 2020 2019 Post-Closure Activity U-wall installation Curbs and sidewalks Bridge railing Grading

2016 2017 2018 2019 2020 2019 Post-closure, tunnel complete and roads open

2016 2017 2018 2019 2020 2019 Post-Closure Project Impacts Traffic, parking, and pedestrian impacts Phased lane and sidewalk closures Working hours Extended 20-hour work windows for track work Daily 7:00am 5:00pm roadway work

2016 2017 2018 2019 2020

2016 2017 2018 2019 2020 2020 Construction Activity Final railroad track construction Final paving, line striping, and signs Crosswalks Landscaping and parks

2016 2017 2018 2019 2020 2020 Project completion Printer s Alley reconstruction Improved vehicular and pedestrian access

2016 2017 2018 2019 2020 2020 Project Impacts Traffic, parking, and pedestrian impacts Phased lane and sidewalk closures Working hours Anticipated 7:00am 5:00pm

Big question: Given the structurally deficient condition of the bridges, why are you waiting until 2019 to actually replace them?

Big question: Ten weeks is a long time to close Main Street and Merchants Row. Is there anything that you can do to shorten the duration? What are the considerations for businesses?

Recap of Community Project Goals Protect the safety of the community: people, property, environment Quarterly bridge safety inspections Construction fencing and barricades Due diligence with contaminants, structural integrity of buildings, and traffic control

Recap of Community Project Goals Maintain traffic flow and pedestrian access to the greatest extent possible Minor traffic and pedestrian impacts during 2017, 2018, and 2020 allowing to plan for major impacts Major traffic and pedestrian impacts for 10 weeks in 2019

Recap of Community Project Goals Minimize the project impact on the vitality of the downtown community: businesses, residents, institutions Accelerated construction to reduce impacts to 10 weeks in 2019 Clearly defined vehicular and pedestrian detours Downtown pedestrian shuttle bus

Recap of Community Project Goals Develop and maintain a credible project schedule Reset design and construction critical path schedules Track potential schedule risks Transparent communication regarding schedule and status of risks

Recap of Community Project Goals Engage with the local community and facilitate clear communication with all stakeholders Community engagement through public meetings Public facing website and social media updates Individual project stakeholder meetings Transparent communication and updates

Our Approach to Public Outreach Open and continuous communication Project phone number (802) 272-1248 E-alerts/project updates Meetings large and small Project website Identify opportunities to collaborate Scheduling Site tours/education programs

vtrans.vermont.gov/projects/middlebury

Why we love Middlebury!