Greater Bristol Bus Network (GBBN)

Size: px
Start display at page:

Download "Greater Bristol Bus Network (GBBN)"

Transcription

1 West of England Partnership Joint Transport Executive Committee 21 January 2011 Agenda item 9 Greater Bristol Bus Network (GBBN) Purpose 1. To provide an update on the successful progress in delivering the Greater Bristol Bus Network and the end of financial year projection. 2. To inform members of change requests approved at Programme Board level and to seek approval for a number of new change requests recommended by the Board. Background 3. Since funding was approved in May 2008 all four authorities and First have been working to deliver GBBN. The scheme comprises 10 corridors with bus priority measures and improvements involving over 70 million investment. For more information on the background of GBBN including a map of the 10 corridors see Appendix At the meeting of the Joint Transport Executive Committee (JTEC) on 24 April 2009 members approved a modification to the GBBN project management arrangements whereby decisions under 100,000 could be agreed by the Programme Board subject to the cost being within the overall GBBN scheme budget, the decision not substantially changing the scheme elements and periodic reports being provided to the Committee. Changes to the scheme with a value over 100,000 continue to require the approval of the Committee. 5. Updates on progress with delivery of the programme were provided on 1 October 2009 and 18 March The first meeting approved the delegation to the Programme Board of authority to agree changes to the bus lane length of up to 20% subject to these decisions being reported to this Committee. 6. This report provides the requested six monthly update on scheme delivery, the changes approved by the Programme Board, and requests approval for changes to the scheme with a value over 100,000. Progress to Date 7. To enable monitoring of the programme the GBBN project has been divided into a number of discreet task orders. To date 33 infrastructure task orders have been completed and a further 21 are in progress. This equates to 85% of all the grantfunded infrastructure task orders being completed or in progress, reflecting the significant steps that have again been made towards delivering the programme 1

2 to date. Appendix 2 shows the infrastructure task orders to be completed by the end of January 2011 and those that are in progress. 8. Save for the installation of the Real Time Information (RTI) equipment, the A367 corridor is now substantially complete, as are all of the Bath and North East Somerset (B&NES) infrastructure task orders. Completion of all the North Somerset Council (NSC) infrastructure task orders is expected during early Summer 2011, followed closely by all of the South Gloucestershire Council (SGC) grant funded infrastructure task orders during late Summer The Bristol City Council (BCC) infrastructure task orders (which includes the RTI equipment) are then expected to be complete during early Spring Available Funds, Approved Budgets and Current Estimates 9. The majority of task orders are being delivered on or under budget due to cost savings and good risk management and these savings are being returned to the change budget. However there remains a risk of cost increases on a number of schemes, particularly those proceeding through consultation and those just starting on site. A reasonable contingency is therefore still being held in reserve in order to ensure that any additional costs arising can be contained within the overall budget. Overall therefore the GBBN project is expected to be within the total approved budget. 10. The budget is regularly reviewed to ensure that spending is on track to meet DfT targets. The current predicted grant spend this financial year is million compared with million reported to DfT in Q4 2009/10. The current spend is 3.95 million lower since the figure reported includes a change budget allowance of some 2.30 million. In addition there has been some deferment of spend, particularly in relation to the 2.30 million A4 Callington Road to Stockwood Road scheme due to protracted land acquisition negotiations, the 1.90 million A432 Staple Hill to Lodge Causeway scheme due to protracted consultation, the 1.26m Lysander Road (Pegasus Road to Retail Park) scheme due to a need to re-design the scheme to take on board DfT comments and the 6.10 million A4174 Coldharbour Lane to M32 scheme (and associated 1.30 million Coldharbour Lane Bus Lanes scheme) due to protracted contract negotiations and enabling works. Change Requests 11. Change requests are the process whereby amendments are made to task orders from the initial programme. These require approval at different levels as per the Programme Handbook. The change requests for which approval is now sought are all shown in Appendix 3, these requests concern Real Time Information, bus stops (route 73 and on the A432), further changes to Lysander Road (Pegasus Road to Retail Park) and the signalisation of the Abbeywood Roundabout. Update on Quality Partnership Schemes (QPSs) 12. The first QPS scheduled is due to be made for Corridor 10 (the A367 corridor from Midsomer Norton to Bath) by Bath and North East Somerset Council. First 2

3 have maintained a strong concern over the inclusion of limits on fares and fare increases and the details and timescales of the fare review mechanism have been modified in the light of these concerns. Discussions are also underway regarding alternative frameworks, which are currently being evaluated by officers and may be further developed and considered for future corridors. 13. The single-member decision to make the first QPS in Bath & North East Somerset is scheduled for January 2011 with the implementation of the first QPS to follow in May Real Time Passenger Information 14. The RTI contract was finalised in October Work is well underway on the initial two corridors, corridor 8 and corridor 10 with RTI ready for mid March Following the award of the contract for RTI and a review of the scope of the project the RTI supplier has offered to upgrade the 346 new at stop displays. This includes the upgrade of the communication technology from analogue radio to digital (GPRS) which offers more reliable communications, better messaging to the displays and an upgrade to text-to-speech audio announcements to the nation RNIB React 3 standard. The existing audible RTI relies on recorded voice files which can be expensive to keep up to date. All this is being offered at no additional cost to the project due to the benefits it also offers ACIS in terms of reduced maintenance costs. 16. In order to be consistent in having one type of audio system and messaging, ACIS have also offered to upgrade the existing 156 RTI displays in Bristol and South Gloucestershire to this level at a reduced cost. This upgrade then allows for existing red LED displays to be upgraded to make them more accessible for people with visual impairments. The upgrading of these facilities and the RNIB React 3 keyfobs results in a requirement of an additional 304,020 ( 96,801 for equipment on GBBN routes and 207,199 for non-gbbn routes) and as such will require JTEC and DfT approval. Marketing and Communications update Newsletter 17. On 5 November a GBBN newsletter was issued as a wrap (the two outside pages) on the Metro newsletter which is distributed in city centres and on public transport across the South West. Please see appendix 4 for a copy of the newsletter. 18. This was chosen as the most appropriate method to update the public on the progress of GBBN as it is widely distributed to thousands of readers, it covered a key segment of public transport users, and because it is also distributed on-street it will have been seen by commuters another key segment. Positive feedback was received from this newsletter and as a result it will be used as part of the corridor launches. 3

4 Weston-super-Mare to Bristol (corridor 8 launch) 19. Corridor 8 is due to complete early next year. The proposal is to officially launch the corridor on 15 March Members, partners in the project and the press will be invited to a special launch event which will start in Weston-super-Mare and then come along the corridor on a First bus with commentary on the improvements along the corridor and arrive in Bristol. 20. Following this a promotional campaign will be implemented with the aim of increasing patronage along the corridor. Activities will include targeted door drop to residents along the route, advertising on parking tickets, and road shows to key destinations and employers along the route. Launch timetable 21. Please see appendix 5 for the proposed promotional timetable for the corridor launches. At the September 2010 JTEC a proposed corridor completion, Quality Bus Partnership and Promotional timetable was included. The promotional implementation plan in appendix 5 varies slightly from this original timetable as follows: Corridor 8 Weston-super-Mare to Bristol brought forward to March at the request of North Somerset Corridor 3 Bath to Bristol delayed by one month this is to enable a slow drip, drip effect of corridors being launched one after the other in each authority area on the lead up to the big bang launch Corridor 9 Portishead to Bristol delayed from October 2011 to March 2012 this will result in every area having a corridor launched as part of the Big Bang promotional activity at the end of the programme completion. Branding of GBBN bus stops 22. All local authority officers are currently working together to agree a common standard for branding the GBBN bus stops, this includes how the information is displayed and where the Travel+ branding is applied. Please see appendix 6 for a couple of example pages from the draft branding guidelines. Environmental Impact Assessment 23 The promotion of modal shift from car to bus will be facilitated through GBBN, improving air quality and reducing carbon emissions. Risk 24 The measures outlined in this report are either intended to reduce revenue risk to the authorities or be revenue neutral. 4

5 Resources (financial and personnel) 25 Funding for initiatives summarised in this report is provided through award settlements from the Department for Transport, and there are no specific implications arising from the recommendations in this report. Equalities Implications 26 There are no specific implications arising from this report. Recommendation That the Joint Executive Committee: (a) Notes the progress made to date (b) Approves or ratifies the change requests set out in Appendix 3 Author: Chris Sane, South Gloucestershire Council chris.sane@southglos.gov.uk Appendices Appendix 1 Background Appendix 2 Progress to Date Appendix 3 Change Requests Appendix 4 GBBN Newsletter (Metro newspaper wrap) Appendix 5 Proposed Promotional Plan Timeline Appendix 6 Bus Stop Examples 5

6 Appendix 1 Background The 78.8 million investment in the Greater Bristol Bus Network comprises 42.3m of grant funding from DfT, an increased contribution of 22.5m from First, and, subject to JTEC approval, an increased developer contribution of 5.9 million and an increased local authority contribution of 8.1 million. The programme introduces the ten showcase bus corridors shown in Figure 1, these to provide new bus priority measures, improved bus shelters, real-time information (which tells you when the bus is due) and new buses. Figure 1 The 10 GBBN Corridors 6

7 Appendix 2 Progress to date Table 1 Infrastructure task orders to be complete by end January 2011 Corridor Corridor Name Task Name 1 M32 M32 Junction 2 to Houlton Street 2 A4018 A4018/Lysander Road Roundabout 3 A4 Bus Stops - A4 B&NES 3 A4 A4 Hicks Gate 3 A4 A4 Twerton Fork 3 A4 Bus Stops - A4 Hicks Gate to Callington Road 3 A4 Bus Stops - A4 Callington Road to City Centre 4 Route 73 Bus Stops - Route 73 Filton Avenue 4 Route 73 Filton Avenue/Lockleaze Road 4 Route 73 Aztec West Roundabout 4 Route 73 New Road Bus Link 4 Route 73 Great Stoke Way Southbound Bus Lane 4 Route 73 Filton Avenue Northbound Bus Lane 4 Route 73 Northfield NF8/NF3 Junctions 4 Route 73 Northfield East-West Link 6 A37 Bus Stops - A37 B&NES 6 A37 A37 Staunton Lane Signals 6 A37 A37 Haverstock Road to Three Lamps 7 A4174 A4174 Westbound to B4058 Frenchay 7 A4174 A4174/M32 Junction 1 Roundabout Works 7 A4174 Abbey Wood Roundabout Signalisation 7 A4174 A4174 Abbey Wood Eastbound Bus Gate 8 A370 A370 Plimsoll Bridge 8 A370 B3440 Locking Road/New Bristol Road 8 A370 M5 J21 Westbound Approach 8 A370 A370 Congresbury Bus Lane 9 A369 A369 Beggar Bush Lane HOV Lane 9 A369 A369 Bridge Road Signals 10 A367 Bus Stops - A367 B&NES 10 A367 A367 Odd Down 10 A367 A367 Midford Road to Red Lion 10 A367 A367 Bear Flat Table 2 Infrastructure task orders in progress at end January 2011 Corridor Corridor Name Task Name 2 A4018 Bus Stops - A4018 Henbury to Whiteladies Road 2 A4018 Bus Stops - The Mall 2 A4018 Bus Stops - A4018 South Gloucestershire 2 A4018 Lysander Road (Retail Park to Merlin Road) 3 A4 Callington Lane to Stockwood Road 3 A4 Totterdown Bridge to Three Lamps 4 Route 73 Bus Stops Route 73 South Gloucestershire 5 A432 Bus Stops - A432 Staple Hill to Royate Hill 5 A432 Bus Stops A432 Muller Road to City Centre 5 A432 A432 Staple Hill to Lodge Causeway 7

8 Corridor Corridor Name Task Name 5 A432 A432 Coombe Road to Robertson Road 5 A432 Bus Stops - A432 South Gloucestershire 6 A37 Bus Stops - A37 Airport Road to City Centre 7 A4174 A4174 Coldharbour Lane to M32 7 A4174 Coldharbour Lane Bus Lanes 8 A370 Bus Stops - A370 North Somerset 9 A369 Bus Stops - A369 Bower Ashton to City Centre 9 A369 Bus Stops - A369 North Somerset 9 A369 St Georges Hill/Portbury High Street HOV Lane 10 A367 A367 Wellsway Lower All - Real Time Passenger Information 8

9 Appendix 3 Change requests for approval Since the last report the Board have approved all of the changes set out in the tables below. Approval is now being sought from JTEC for the change requests set out in Tables 1 and 2. The change requests set out in Table 3 have all been approved by the Board in accordance with the Programme Handbook and are for information only. Table 1 Changes to Grant-Funded Task Orders PN- CRN Partner Task Name Cost Impact (Value) Time Impact (Months) Change Budget (Value) Local Contribution Change (Value) BCC Real Time Passenger Information 304, , Abbey Wood Roundabout SGC Signalisation 54, , Bus Stops Route 73 South SGC Gloucestershire 240, , SGC Lysander Road (Pegasus Road to Retail Park) - 626, , Bus Stops A432 South SGC Gloucestershire 360, , Developer Contribution Change (Value) CRN relates to the upgrading of the existing RTI units to the higher standards of the 346 new RTI displays for the GBBN in terms of reliability, messaging and upgrading the audio facility. This improved audible RTI will be to the national RNIB 'React 3' standard, and also to upgrade the older red LEDs to amber LEDs, which are more accessible for people with visual impairments such as colour blindness. Change requests and relate to the need to provide electrical supplies to bus shelters on Corridors 4 and 5 in South Gloucestershire that will have Real Time Information equipment supplied by ACIS, and to replace some existing parish shelters that are unable to accept RTI equipment in their present form. Since the MSBC was submitted in 2007, quotations for electrical supplies at some location have been found to be substantially more expensive than originally estimated for. Change Request relates to Lysander Road (Pegasus Road to Retail Park). In a report to the Committee on 21st July 2010, a major change in bus length was reported and a substantial saving of 740,000 in the cost of the scheme was demonstrated. Due to the scale of the change required, DfT support for this change was required. Early engagement with the DfT and a review of benefits confirmed that the suggested alteration to the length of bus lane would not deliver the benefits as per the previous scheme. Engagement with Cribbs Causeway landowners and management has resulted in agreement on a further amended scheme which delivers these benefits. This amended scheme continues to show a reduced but substantial cost saving of 626,800. Subject to further consultation and land transfer, it is recommended that this latter scheme, which is no longer a major change due to the restoration of the bus lane length within tolerance, is now taken forward. CRN includes for additional support work required to enable bus priority to be established at the Abbey Wood roundabout junction. Taking account of 9

10 previous change requests for this task, the total value of change requests for TN4025 stands at 381,823. Table 2 Changes Approved by the Programme Board PN- CRN Partner Task Name Cost Impact (Value) Time Impact (Months) Change Budget (Value) Local Contribution Change (Value) B&NES A4 Twerton Fork 31, , BCC Real Time Passenger Information 81, , NSC B3440 Locking Road/New Bristol Road 11, , NSC A370 Congresbury Bus Lane 52, , Filton Avenue A4174 Junction SGC Works 42, , A4174 Westbound to B SGC Frenchay 34, , SGC Aztec West Roundabout 1, , SGC Coldharbour Lane Bus Lanes 9, , Developer Contribution Change (Value) For information only, the change requests listed in Table 3 above have been approved by the Board since the last report. 10

11 Appendix 4 Travel + Metro Wrap (November 2010) 11

12 12

13 13

14 14

15 Appendix 5 Proposed Promotional Plan Timeline 15

16 16

17 Appendix 6 Bus Stop Examples 17

Joint Local Transport Plan 3 Update

Joint Local Transport Plan 3 Update West of England Partnership Joint Transport Executive Committee 1 July 2011 Agenda item 10 Joint Local Transport Plan 3 Update Purpose 1. To update Members on Joint Local Transport Plan 3 (JLTP3) issues

More information

SOUTH GLOS COUNCIL UPDATE FOR SUSCOM - JANUARY 2016

SOUTH GLOS COUNCIL UPDATE FOR SUSCOM - JANUARY 2016 SOUTH GLOS COUNCIL UPDATE FOR SUSCOM - JANUARY 2016 Go Ultra Low City Bid Success Announced on Monday 25 January, the Department for Transport (DfT) allocated 7M to the four West of England authorities

More information

1. To inform members of the views of the West of England Joint Scrutiny Committee (JSC) following a meeting held on Wednesday 5 th March 2014

1. To inform members of the views of the West of England Joint Scrutiny Committee (JSC) following a meeting held on Wednesday 5 th March 2014 West of England Joint Transport Executive Committee 13 th March 2014 Agenda Item 5 Views of Joint Scrutiny Committee Purpose 1. To inform members of the views of the West of England Joint Scrutiny Committee

More information

The West of England Partnership is the sub-regional partnership formed by the four councils working together with partners

The West of England Partnership is the sub-regional partnership formed by the four councils working together with partners Great Western Route Utilisation Strategy Evidence Submission June 2008 Wilder House Wilder Street Bristol BS2 8PH 0117 903 6868 www.westofengland.org 1 The West of England Partnership is the sub-regional

More information

Joint Transport Executive Committee

Joint Transport Executive Committee Agenda item 6 Draft minutes of meeting of the Joint Transport Executive Committee Friday 21 January 2011, 10.30am 13.00pm, BAWA, Filton Present Cllr Charles Gerrish Cllr Gary Hopkins Cllr Elfan Ap Rees

More information

Member & Public Forum

Member & Public Forum Agenda item 3 West of England Planning, Housing and Communities Board 18 December 2014 Member & Public Forum Notice has been given for the following representations: Statements Items 1: Item 3: David Redgewell

More information

Henbury rail loop and the sale of the former goods yard

Henbury rail loop and the sale of the former goods yard West of England Partnership Joint Scrutiny Committee 12 December 2008 Agenda item 9 Henbury rail loop and the sale of the former goods yard 1. Purpose of Report To review the recent sale of the former

More information

Investing in our local rail network June 2014

Investing in our local rail network June 2014 Investing in our local rail network June 2014 Bath & North East Somerset, Bristol, North Somerset and South Gloucestershire councils working together to improve your local transport MetroWest: Investing

More information

Smarter Travel Sutton

Smarter Travel Sutton Smarter Travel Sutton Lee Parker 15 th September 2010 Project Scope Three-year pilot social marketing project. Launched in Sept 2006, delivery commenced in April 2007. Delivered in partnership and funded

More information

Transport Delivery Committee

Transport Delivery Committee Agenda Item No. 11 Transport Delivery Committee Date 6 th March 2016 Report title Accountable Director Accountable Employee Virgin Trains Partnership Agreement Update Pete Bond, Director of Transport Services

More information

3. Coach Supporting Statement

3. Coach Supporting Statement 3. Coach Supporting Statement Content 1. Setting the Scene 2. Vision 3. Coaches and the Shared Priorities 4. Issues 5. Delivery Programme in the first Plan Period 2001/02 2005/06 6. Good Practice 7. Strategy

More information

PERTH AND KINROSS COUNCIL. Housing and Health Committee. 25 May Perth and Kinross Local Housing Strategy

PERTH AND KINROSS COUNCIL. Housing and Health Committee. 25 May Perth and Kinross Local Housing Strategy PERTH AND KINROSS COUNCIL 7 16/234 Housing and Health Committee 25 May 2016 Perth and Kinross Local Housing Strategy 2016-2021 Report by Director (Housing and Social Work) PURPOSE OF REPORT This report

More information

Economic Development Sub- Committee

Economic Development Sub- Committee Report title: Economic Development Sub- Committee Item No. Date of meeting: 24 November 2016 A47 Road Investment Strategy - update Responsible Chief Tom McCabe Executive Director, Community Officer: and

More information

A Quality Partnership Scheme is a statutory agreement between parties to provide improved bus infrastructure and services.

A Quality Partnership Scheme is a statutory agreement between parties to provide improved bus infrastructure and services. BRIEFING NOTE FOR BUS OPERATORS Inverclyde statutory Quality Partnership Scheme - 2015 What is an sqps? A Quality Partnership Scheme is a statutory agreement between parties to provide improved bus infrastructure

More information

North Bristol SusCom meeting

North Bristol SusCom meeting North Bristol SusCom meeting 19 th January 2017 Southmead Hospital Get ahead. Travel smarter. Agenda 10:00 Welcome, Introduction and apologies - Chair 10:05 WORKSHOP Car Share 11:15 Break Networking 11:30

More information

Investing in Greater Manchester transport 2017/2018

Investing in Greater Manchester transport 2017/2018 TRAFFIC Investing in Greater Manchester transport 2017/2018 INFORMATION www.greatermanchester-ca.gov.uk Transport is an important part of life for residents and businesses in Greater Manchester. It connects

More information

TRANSPORT FOR GREATER MANCHESTER COMMITTEE REPORT FOR RESOLUTION

TRANSPORT FOR GREATER MANCHESTER COMMITTEE REPORT FOR RESOLUTION TRANSPORT FOR GREATER MANCHESTER COMMITTEE REPORT FOR RESOLUTION DATE: 11 November 2011 SUBJECT: REPORT OF: Proposed making of a Quality Partnership Scheme for the A6 corridor between Manchester and Hazel

More information

West of England. Priority Places Requiring Public Investment

West of England. Priority Places Requiring Public Investment West of England Priority Places Requiring Public Investment Development Urban Regeneration & Suburban Intensification Bristol Central Area Bristol Central Area; Stokes Croft, Temple Meads & St Philips

More information

Wolverhampton City Council

Wolverhampton City Council Agenda Item: 7G Wolverhampton City Council OPEN EXECUTIVE DECISION ITEM Cabinet / Cabinet Team CABINET Date 24 MARCH 2010 Portfolio(s) Originating Service Group(s) COUNCILLOR MRS BRADLEY (REGENERATION

More information

Open Report on behalf of Richard Wills, Executive Director for Environment and Economy

Open Report on behalf of Richard Wills, Executive Director for Environment and Economy Agenda Item 7 Executive Open Report on behalf of Richard Wills, Executive Director for Environment and Economy Report to: Executive Date: 02 September 2014 Subject: Lincoln East West Link Road Phase 1

More information

2.3 On 27 November, the Department for Transport issued guidance on the use of the powers contained in the Act.

2.3 On 27 November, the Department for Transport issued guidance on the use of the powers contained in the Act. Director: Dave Pearson, Director of Transport Services Report to: Bradford District Consultation Sub-Committee Date: 22 January 2018 Subject: Information Report 1 Purpose 1.1 Matters of information relating

More information

South of England north-south connectivity

South of England north-south connectivity South of England north-south connectivity An outline economic case for the inclusion of north-south connectivity improvements to form part of the government s road investment strategy (RIS2) Weston-super-Mare

More information

Commissioning Director - Environment

Commissioning Director - Environment Finchley and Golders Green Area Committee 27 April 2017 Title Report of Wards Status Urgent Key Enclosures Summers Lane,N12 Request for Pedestrian Improvements Commissioning Director - Environment Woodhouse

More information

Rail Update, Decentralisation and Fares consultations

Rail Update, Decentralisation and Fares consultations Agenda item 12 West of England Joint Transport Executive Committee 19 June 2012 Rail Update, Decentralisation and Fares consultations Purpose 1. To provide Members with a response to the Department for

More information

First West of England Service Status Update

First West of England Service Status Update First West of England Status Update Bath City s Bristol City s North Somerset s West of England s First West of England: Bath City Bus s Status Update Normal Route Roads/Areas not being operated Alternative

More information

PORTFOLIO: TRANSPORT, PLANNING AND SUSTAINABILITY (COUNCILLOR RAMESH PATEL)

PORTFOLIO: TRANSPORT, PLANNING AND SUSTAINABILITY (COUNCILLOR RAMESH PATEL) CYNGOR DINAS CAERDYDD CITY OF CARDIFF COUNCIL CABINET: 15 DECEMBER 2016 CARDIFF WEST TRANSPORT INTERCHANGE REPORT OF DIRECTOR CITY OPERATIONS AGENDA ITEM: 9 PORTFOLIO: TRANSPORT, PLANNING AND SUSTAINABILITY

More information

Major Scheme Business Case Summary Report for Programme Entry

Major Scheme Business Case Summary Report for Programme Entry Paper A Heart of South West Local Transport Board Major Scheme Business Case Summary Report for Programme Entry M5 Junction 25, Taunton July 2016 1 SCHEME SUMMARY Scheme Name M5 Junction 25, Taunton Date

More information

Report to: Greater Cambridge Partnership Joint Assembly 18 January A10 Foxton level crossing bypass and travel hub

Report to: Greater Cambridge Partnership Joint Assembly 18 January A10 Foxton level crossing bypass and travel hub Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018 Lead officer: Chris Tunstall GCP Director of Transport A10 Foxton level crossing bypass and travel hub 1. Purpose 1.1 The list of

More information

Glasgow Street Traffic Review

Glasgow Street Traffic Review Glasgow Street Traffic Review Recommendation That the Standing Policy Committee on Transportation recommend to City Council: 1. That the Administration proceed with removing the pinch points installed

More information

Roundhouse Way Transport Interchange (Part of NATS City Centre Package)

Roundhouse Way Transport Interchange (Part of NATS City Centre Package) Roundhouse Way Transport Interchange (Part of NATS City Centre Package) 15/16 16/17 17/18 18/19 19/20 Total TOTAL COST Roundhouse Way Transport Interchange 0.5m 0.5m FUNDING CIL 0.05m 0.05m Growth Deal

More information

Calderdale MBC. Wards Affected: Town. Economy and Investment Panel: 20 October Halifax Station Gateway Masterplan

Calderdale MBC. Wards Affected: Town. Economy and Investment Panel: 20 October Halifax Station Gateway Masterplan Calderdale MBC Wards Affected: Town Economy and Investment Panel: 20 October 2016 Halifax Station Gateway Masterplan Report of the Acting Director, Economy and Environment 1. Purpose of the Report 1.1

More information

West of England One Front Door Programme Schemes

West of England One Front Door Programme Schemes West of England One Front Door Programme Schemes Note: Funding Streams include Local Growth Fund (), Economic Development Fund (EDF) and Revolving Infrastructure Fund (RIF) Schemes fully approved Schemes

More information

Bus Priority Package. Presentation to Leigh Business Forum. 11 December 2015

Bus Priority Package. Presentation to Leigh Business Forum. 11 December 2015 Bus Priority Package Presentation to Leigh Business Forum 11 December 2015 Over 25 miles of bus routes improved What is the bus priority package? Key Strategic Benefits Shorter journey times, more punctual

More information

Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018

Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018 Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018 Subject: M Arrangements for the establishment of a West Yorkshire Urban Traffic Management Control

More information

What s happening with Transport in Bristol?

What s happening with Transport in Bristol? What s happening with Transport in Bristol? Bristol Local Transport Plan Update Autumn 2002 getting Bristol to work Bristol s five-year Local Transport Plan was published in July 2000 after extensive public

More information

Toronto 2015 Pan Am/Parapan Am Games Temporary Traffic By-law Amendments for High Occupancy Vehicle Lanes (Supplementary Report)

Toronto 2015 Pan Am/Parapan Am Games Temporary Traffic By-law Amendments for High Occupancy Vehicle Lanes (Supplementary Report) STAFF REPORT ACTION REQUIRED Toronto 2015 Pan Am/Parapan Am Games Temporary Traffic By-law Amendments for High Occupancy Vehicle Lanes (Supplementary Report) Date: March 25, 2015 To: From: Wards: Reference

More information

West of England One Front Door Programme Schemes

West of England One Front Door Programme Schemes West of England One Front Door Programme Schemes Note: Funding Streams include Local Growth Fund (), Economic Development Fund (EDF) and Revolving Infrastructure Fund (RIF) Schemes fully approved Schemes

More information

Joint Local Transport Plan Public Realm. Box 9a : Pier Square, Weston-super-Mare

Joint Local Transport Plan Public Realm. Box 9a : Pier Square, Weston-super-Mare 9.1.3 Transport it should be remembered is not an end in itself. Getting somewhere is our goal for work, shopping, meeting friends and accessing services. We use a range of modes to get there although

More information

Rail Delivery Group. Consultation on the future of the East Midlands rail franchise

Rail Delivery Group. Consultation on the future of the East Midlands rail franchise Rail Delivery Group Response to: Department for Transport Consultation on the future of the East Midlands rail franchise Date: 11 October 2017 Rail Delivery Group Limited Registered Office, 2nd Floor,

More information

Proposed Lidl Food store West Hendford, Yeovil

Proposed Lidl Food store West Hendford, Yeovil Proposed Lidl Food store West Hendford, Yeovil Lidl Travel Plan October 2015 CONTENTS Page 1.0 INTRODUCTION 1 1.1 Background 1 1.2 Aim of Travel Plan 1 1.3 Contents 2 2.0 TRANSPORT CONTEXT 3 2.1 Site Location

More information

THE NORTH SOMERSET COUNCIL (SOUTH BRISTOL LINK CLASSIFIED ROAD) SIDE ROADS ORDER 2013

THE NORTH SOMERSET COUNCIL (SOUTH BRISTOL LINK CLASSIFIED ROAD) SIDE ROADS ORDER 2013 NSC/1/1 THE NORTH SOMERSET COUNCIL (SOUTH BRISTOL LINK CLASSIFIED ROAD) SIDE ROADS ORDER 2013 THE NORTH SOMERSET COUNCIL (SOUTH BRISTOL LINK) COMPULSORY PURCHASE ORDER 2013 THE NORTH SOMERSET COUNCIL (SOUTH

More information

Clyde Waterfront and Renfrew Riverside Project Glasgow Airport Investment Area Project

Clyde Waterfront and Renfrew Riverside Project Glasgow Airport Investment Area Project Item 1 To: Leadership Board On: 3 June 2015 Report by: Director of Development and Housing Services Heading: City Deal Strategic Business Cases 1. Summary 1.1 This report seeks approval from the Board

More information

Open Report on behalf of Executive Director for Environment & Economy. Highways and Transport Scrutiny Committee

Open Report on behalf of Executive Director for Environment & Economy. Highways and Transport Scrutiny Committee Agenda Item 9 Policy and Scrutiny Open Report on behalf of Executive Director for Environment & Economy Report to: Date: 13 June 2016 Subject: Summary: Highways and Transport Scrutiny Committee Rail Update

More information

Update on the development of the Regional Real Time Passenger Information (RTPI) System

Update on the development of the Regional Real Time Passenger Information (RTPI) System Agenda Item 11 Update on the development of the Regional Real Time Passenger Information (RTPI) System Committee Strategy and Programmes Date of meeting 23 November 2018 Date of report 30 October 2018

More information

Presentation to BRT UK Technical Visit to Leigh to Ellenbrook Guided Busway

Presentation to BRT UK Technical Visit to Leigh to Ellenbrook Guided Busway Presentation to BRT UK Technical Visit to Leigh to Ellenbrook Guided Busway Welcome Introductions: Anthony Murden Project Sponsor Adam Price Project Manager Martin Shier - Bus Partnerships Delivery Manager

More information

This report is PUBLIC [NOT PROTECTIVELY MARKED] Board Meeting. Councillor Roger Lawrence Transport

This report is PUBLIC [NOT PROTECTIVELY MARKED] Board Meeting. Councillor Roger Lawrence Transport Agenda Item No. 5.4 Board Meeting Date 17 February 2017 Report title Cabinet Member Portfolio Lead Accountable Managing Director Accountable Employee Report has been considered by West Midlands Bus Alliance

More information

Monaghan County Council Jobs Initiative Smarter Travel Projects 2011 Evaluation

Monaghan County Council Jobs Initiative Smarter Travel Projects 2011 Evaluation Monaghan County Council Jobs Initiative Smarter Travel Projects 2011 Evaluation Background Monaghan County Council received funding from the Dept of Transport, Tourism and Sport for three projects during

More information

8 CROSS-BOUNDARY AGREEMENT WITH BRAMPTON TRANSIT

8 CROSS-BOUNDARY AGREEMENT WITH BRAMPTON TRANSIT 8 CROSS-BOUNDARY AGREEMENT WITH BRAMPTON TRANSIT The Transportation Services Committee recommends the adoption of the recommendations contained in the following report dated May 27, 2010, from the Commissioner

More information

Report Author: Jo Turton, Executive Director for the Environment, Lancashire County Council

Report Author: Jo Turton, Executive Director for the Environment, Lancashire County Council Transport for Lancashire Committee 1 st July 2013 Local Major Transport Scheme Investment Programme Report Author: Jo Turton, Executive Director for the Environment, Lancashire County Council Executive

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Executive Director / Senior Planning Policy Officer

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Executive Director / Senior Planning Policy Officer SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Leader and Cabinet 8 May 2008 AUTHOR/S: Executive Director / Senior Planning Policy Officer SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL S RESPONSE TO UTTLESFORD

More information

Arrangements for the delivery of minor highway maintenance services by Town and Parish Councils

Arrangements for the delivery of minor highway maintenance services by Town and Parish Councils Arrangements for the delivery of minor highway maintenance services by Town and Parish Councils Cabinet Date of Meeting 8 March 2017 Officer Cllr Peter Finney, Cabinet Member for Environment, Infrastructure

More information

PERTH AND KINROSS COUNCIL. 5 October 2016 COMMUNITY PLANNING PARTNERSHIP UPDATE

PERTH AND KINROSS COUNCIL. 5 October 2016 COMMUNITY PLANNING PARTNERSHIP UPDATE PERTH AND KINROSS COUNCIL 6(ii) 16/437 5 October 2016 COMMUNITY PLANNING PARTNERSHIP UPDATE Report by Senior Depute Chief Executive (Equality, Community Planning and Public Service Reform) PURPOSE OF REPORT

More information

West Sussex Local Authority Parking Enforcement Agreement

West Sussex Local Authority Parking Enforcement Agreement Report to Cabinet 24 th March 2016 By the Cabinet Member for Local Economy DECISION REQUIRED Not Exempt West Sussex Local Authority Parking Enforcement Agreement Executive Summary The existing Agency Agreement

More information

Agenda Item 5: Rail East Midlands Rail Franchise Consultation

Agenda Item 5: Rail East Midlands Rail Franchise Consultation Strategic Transport Forum 15 th September 2017 Agenda Item 5: Rail East Midlands Rail Franchise Consultation Recommendation: It is recommended that the Forum agree (subject to any amendments agreed by

More information

Local Development Scheme

Local Development Scheme Local Development Scheme August 2014 Local Development Scheme (August 2014) / Page 2 Contents Section 1: Introduction Great Yarmouth s Development Plan 4 Section 2: Plan Making Process Public participation

More information

Consultation on Draft Airports National Policy Statement: new runway capacity and infrastructure at airports in the South East of England

Consultation on Draft Airports National Policy Statement: new runway capacity and infrastructure at airports in the South East of England Tony Kershaw Honorary Secretary County Hall Chichester West Sussex PO19 1RQ Telephone 033022 22543 Website: www.gatcom.org.uk If calling ask for Mrs. Paula Street e-mail: secretary@gatcom.org.uk 22 May

More information

Outline Business Case for the Henbury Loop

Outline Business Case for the Henbury Loop Outline Business Case for the Henbury Loop What is the Henbury Loop? The Henbury loop line is a piece of railway line, from Filton North Station through to Chittening Station, (see map) which connects

More information

STAFF REPORT INFORMATION ONLY

STAFF REPORT INFORMATION ONLY Insert TTC logo here STAFF REPORT INFORMATION ONLY Outstanding Board Items Date: February 25, 2016 To: From: TTC Board Chief Executive Officer Summary A status update on outstanding items is submitted

More information

Enhancing customer service Offering the right services Improving integrated journeys Facilitating local

Enhancing customer service Offering the right services Improving integrated journeys Facilitating local London City Airport London City Airport: Background London City Airport (LCY) is the only airport so close to the centre of London. It is also London s fastest growing airport, having grown twice as fast

More information

M621. Junctions 1 to 7 Improvement scheme. Share your views

M621. Junctions 1 to 7 Improvement scheme. Share your views M621 Junctions 1 to 7 Improvement scheme Share your views Investing in your roads Every road user wants less congested roads to enable swift, safe, comfortable and informed travel. On behalf of the government,

More information

Decisions To authorise revised costings of the existing Design Services Agreement between the Council and Network Rail, from 921,100 to 1,340,642.

Decisions To authorise revised costings of the existing Design Services Agreement between the Council and Network Rail, from 921,100 to 1,340,642. ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER In consultation with the Chairman of the Assets Regeneration Committee Title Report of 13 October2015 Brent Cross Cricklewood Regeneration: Thameslink Station

More information

Finchley and Golders Green Area Committee 27 April 2017

Finchley and Golders Green Area Committee 27 April 2017 Finchley and Golders Green Area Committee 27 April 2017 Title Report of Wards Status Urgent Key Enclosures Officer Contact Details Junction of Regents Park Road / Tillingbourne Gardens, N3 Commissioning

More information

SUMMARY PROOF OF EVIDENCE. Gerald Kells Transport Policy and Campaigns Advisor

SUMMARY PROOF OF EVIDENCE. Gerald Kells Transport Policy and Campaigns Advisor Highways Inquiry Procedure Rules 1994 Doc Ref: OBJ/0125 2 For a local inquiry into: SUMMARY PROOF OF EVIDENCE Gerald Kells Transport Policy and Campaigns Advisor For Friends of the Earth Cymru / Cyfeillion

More information

Item 1. Leadership Board. On: 1 April Report by: Director of Development and Housing Services. Heading: Update on City Deal. 1.

Item 1. Leadership Board. On: 1 April Report by: Director of Development and Housing Services. Heading: Update on City Deal. 1. Item 1 To: Leadership Board On: 1 April 2015 Report by: Director of Development and Housing Services Heading: Update on City Deal 1. Summary 1.1 This report seeks to update the Board on the work that has

More information

1.1. The purpose of this report is to seek approval for the adoption and publication of the Sports Pitches Strategy for East Dunbartonshire.

1.1. The purpose of this report is to seek approval for the adoption and publication of the Sports Pitches Strategy for East Dunbartonshire. REPORT FOR EDLC BOARD Report Title: EDC Pitches Strategy Update Contact Officer: Mark Grant (0141 777 3146) Date: 30 th March 2016 Agenda Item No: 5 Report No: EDLCT/52/15/MG 1.0 PURPOSE 1.1. The purpose

More information

Agenda item no 7. Strathclyde Bus Alliance - Proposal. Committee. Strategy and Programmes. Date of meeting 20 May 2016 Date of report 25 April 2016

Agenda item no 7. Strathclyde Bus Alliance - Proposal. Committee. Strategy and Programmes. Date of meeting 20 May 2016 Date of report 25 April 2016 Agenda item no 7 Strathclyde Bus Alliance - Proposal Committee Strategy and Programmes Date of meeting 20 May 2016 Date of report 25 April 2016 Report by Assistant Chief Executive (Operations) 1. Object

More information

PERTH AND KINROSS COUNCIL. Enterprise and Infrastructure Committee 4 November 2009

PERTH AND KINROSS COUNCIL. Enterprise and Infrastructure Committee 4 November 2009 PERTH AND KINROSS COUNCIL 4 09/494 Enterprise and Infrastructure Committee 4 November 2009 STRATEGIC PRIORITIES FOR TOURISM AND AREA TOURISM PARTNERSHIP ARRANGEMENTS Report by Depute Director (Environment)

More information

Written evidence submitted by National Express West Midlands (BSB 15)

Written evidence submitted by National Express West Midlands (BSB 15) Written evidence submitted by National Express West Midlands (BSB 15) National Express West Midlands 1. National Express West Midlands (West Midlands Travel Ltd) is the major bus operator in the West Midlands.

More information

PERTH AND KINROSS COUNCIL. 22 June 2016 DEVELOPING THE CULTURAL OFFER IN PERTH AND KINROSS UPDATE AND NEXT STEPS

PERTH AND KINROSS COUNCIL. 22 June 2016 DEVELOPING THE CULTURAL OFFER IN PERTH AND KINROSS UPDATE AND NEXT STEPS PERTH AND KINROSS COUNCIL 8 16/278 22 June 2016 DEVELOPING THE CULTURAL OFFER IN PERTH AND KINROSS UPDATE AND NEXT STEPS Report by Senior Depute Chief Executive (Equality, Community Planning & Public Service

More information

INVITATION FOR EXPRESSION OF INTEREST

INVITATION FOR EXPRESSION OF INTEREST 1. Introduction INVITATION FOR EXPRESSION OF INTEREST Indah Water Konsortium Sdn Bhd (Company No. 211763-P) ( IWK ) is seeking for Expression of Interest (EOI) from consultants registered with the Ministry

More information

Business Case Approved. Under Construction. Business Case Approved. Under Construction

Business Case Approved. Under Construction. Business Case Approved. Under Construction Item 6 Appendix A: LGF Project Summary for South Essex Update September Project and A127 Network Resilience (Essex) Basildon Integrated Transport Package (Essex) Range of improvements at key locations

More information

Community Engagement Policy

Community Engagement Policy Bishop s Cleeve Parish Council Community Engagement Policy Bishop s Cleeve Parish Council Parish Office Church Road Bishop s Cleeve Cheltenham GL52 8LR Telephone 01242 674440 Email clerk@bishopscleevepc.org

More information

A303. Sparkford to Ilchester Dualling Scheme Preferred Route Announcement

A303. Sparkford to Ilchester Dualling Scheme Preferred Route Announcement A303 Sparkford to Ilchester Dualling Scheme Preferred Route Announcement About this booklet This booklet presents the preferred route for the A303 Sparkford to Ilchester dualling scheme and a summary of

More information

Your Transport Levy Your Transport Future. Sunshine Coast Council Transport Levy Annual Report

Your Transport Levy Your Transport Future. Sunshine Coast Council Transport Levy Annual Report Your Transport Levy Your Transport Future Sunshine Coast Council Transport Levy Annual Report 2016-2017 www.sunshinecoast.qld.gov.au T 07 5475 7272 F 07 5475 7277 Locked Bag 72 Sunshine Coast Mail Centre

More information

A303. Sparkford to Ilchester Dualling Scheme. Public consultation. Welcome. Highways England -- creative MCR18_0016

A303. Sparkford to Ilchester Dualling Scheme. Public consultation. Welcome. Highways England -- creative MCR18_0016 Sparkford to Ilchester Dualling Scheme Public consultation Welcome Background The /A358 corridor provides vital east-west connectivity between the south west and London and the south east for people, communities

More information

Team London Bridge Response to the Department for Transport Consultation on the combined Thameslink, Southern and Great Northern franchise

Team London Bridge Response to the Department for Transport Consultation on the combined Thameslink, Southern and Great Northern franchise Team London Bridge Response to the Department for Transport Consultation on the combined Thameslink, Southern and Great Northern franchise 23 August 2012 Table of Contents 1. Executive Summary 2. Introduction

More information

Report of Commissioning Director, Growth and Development. Wards Child s Hill, Golders Green and West Hendon. Summary

Report of Commissioning Director, Growth and Development. Wards Child s Hill, Golders Green and West Hendon. Summary ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER 26 April 2016 Title Brent Cross Cricklewood Gowling Wragge Lawrence Graham (UK) LLP Report of Commissioning Director, Growth and Development Wards Child s

More information

Terms of Reference: Introduction

Terms of Reference: Introduction Terms of Reference: Assessment of airport-airline engagement on the appropriate scope, design and cost of new runway capacity; and Support in analysing technical responses to the Government s draft NPS

More information

Airways New Zealand Queenstown lights proposal Public submissions document

Airways New Zealand Queenstown lights proposal Public submissions document Airways New Zealand Queenstown lights proposal 2014 Public submissions document Version 1.0 12 December, 2014 Contents 1 Introduction... 3 2 Purpose... 3 3 Air New Zealand Limited... 4 3.1 Proposed changes

More information

M56. New Junction 11a Summary of the consultation report

M56. New Junction 11a Summary of the consultation report M56 New Junction 11a Summary of the consultation report August 2017 M56 New Junction 11a Summary of the public consultation The scheme The M56 New Junction 11a scheme is part of our continued programme

More information

BARROW GURNEY PARISH COUNCIL

BARROW GURNEY PARISH COUNCIL BARROW GURNEY PARISH COUNCIL Minutes of the Annual Parish Meeting of the Parish Council held in the village hall, Barrow Gurney, on 11 May 2015. Present: Eric Gates (Chairman), Phil Carnell, Andy Robbins,

More information

VISITSCOTLAND ICENTRE UPDATE EXECUTIVE COMMITTEE. 5 December Report by Executive Director

VISITSCOTLAND ICENTRE UPDATE EXECUTIVE COMMITTEE. 5 December Report by Executive Director VISITSCOTLAND ICENTRE UPDATE Report by Executive Director EXECUTIVE COMMITTEE 5 December 2017 1 PURPOSE AND SUMMARY 1.1 This report provides an update to members on how VisitScotland is responding to changes

More information

Ashton Vale Industrial Estate alternative access report on second micro-consultation. MetroWest Phase 1

Ashton Vale Industrial Estate alternative access report on second micro-consultation. MetroWest Phase 1 Ashton Vale Industrial Estate alternative access report on second micro-consultation MetroWest Phase 1 January 2017 THIS REPORT REMAINS IN DRAFT FORM AS THE WORKSTREAM ENDED AND IS MADE AVAILABLE FOR INFORMATION

More information

New free City connector bus service

New free City connector bus service The Adelaide City Council invites engagement from the community about New free City connector bus service 99C City Loop and Adelaide Connector free bus services to merge: Project Summary Adelaide City

More information

NOISE MANAGEMENT BOARD - GATWICK AIRPORT. Review of NMB/ th April 2018

NOISE MANAGEMENT BOARD - GATWICK AIRPORT. Review of NMB/ th April 2018 NOISE MANAGEMENT BOARD - GATWICK AIRPORT Review of NMB/10 11 th April 2018 Synopsis This paper provides a brief review of the issues discussed at the NMB/10 meeting, which was held on 11 th April. Introduction

More information

Regulatory Committee

Regulatory Committee Page 1 - Proposed Turning Movement Bans at South Gate Junction, Dorchester Regulatory Committee Date of Meeting 16 March 2017 Officer Subject of Report Executive Summary Andrew Martin Service Director

More information

The Strategic Commercial and Procurement Manager

The Strategic Commercial and Procurement Manager Item 3 To: Procurement Sub Committee On: 8 June 2016 Report by: The Strategic Commercial and Procurement Manager Heading: Renfrewshire Council s Community Benefit Strategy 2016 1. Summary 1.1. The purpose

More information

NORTH BRISTOL TRANSPORT PLAN including a Housing and Development Update. from DARREN JONES MP

NORTH BRISTOL TRANSPORT PLAN including a Housing and Development Update. from DARREN JONES MP NORTH BRISTOL TRANSPORT PLAN including a Housing and Development Update from DARREN JONES MP THREE NEW TRANSPORT HUBS bringing together rail, bus, car parking, EV charging, cycle hire and lock-up on one

More information

Strategic Transport Forum

Strategic Transport Forum Strategic Transport Forum Friday 16 th March 2018 www.englandseconomicheartland.com Item 3: Innovation www.englandseconomicheartland.com Innovation work stream - EEH 1. Policy modelling 2. MaaS 3. EEH

More information

LINCOLNSHIRE PARKING POLICY DRAFT

LINCOLNSHIRE PARKING POLICY DRAFT LINCOLNSHIRE PARKING POLICY DRAFT Draft 23/05/11 1 of 7 1. Introduction This document sets out and explains the County Councils Parking Policy. The County Council is planning to apply for powers to take

More information

First West of England Service Status Update

First West of England Service Status Update First West of England Service Status Update Bath City Services Bristol City Services North Somerset Services West of England Services First West of England: Bath City Bus Services Service Status Update

More information

VisitEngland Business Support Update. Vicky Parr, VisitEngland Business Support Manager Tuesday 2 nd April 2019

VisitEngland Business Support Update. Vicky Parr, VisitEngland Business Support Manager Tuesday 2 nd April 2019 VisitEngland Business Support Update Vicky Parr, VisitEngland Business Support Manager Tuesday 2 nd April 2019 1 Our Aims As the National Tourism Agency: VisitBritain: Market the nations and regions of

More information

5.1 Traffic and Transportation

5.1 Traffic and Transportation 5.1 When it opens in 2009, the Bellevue Nickel Improvement Project will increase the number of vehicles able to travel through the study area, improve travel speeds, and improve safety by reducing the

More information

Committee. Presentation Outline

Committee. Presentation Outline CW-33-15 11/9/2015 Community and Corporate Services Committee November 10, 2015 1 Presentation Outline Background Vision and Objectives Study Process and Timeline Public and Stakeholder Engagement Organization

More information

May 2011 to April 2012.

May 2011 to April 2012. Annual Performance 2011-2012 KEY FACTS 2011/12 11 million passenger journeys were made on Stagecoach Bluebird services 12.9 million miles operated throughout Aberdeen City and Shire, Moray and Buchan 537

More information

Ridership Growth Strategy (RGS) Status Update

Ridership Growth Strategy (RGS) Status Update For Information Ridership Growth Strategy (RGS) Status Update Date: July 10, 2018 To: TTC Board From: Deputy Chief Executive Officer Summary The TTC s Ridership Growth Strategy (RGS), with all its components,

More information

SOUTHPORT MARKETING MARKETING SUPPORT FOR TOURISM BUSINESSES. #SouthportTime

SOUTHPORT MARKETING MARKETING SUPPORT FOR TOURISM BUSINESSES.   #SouthportTime MARKETING SOUTHPORT MARKETING SUPPORT FOR TOURISM BUSINESSES Every effort has been made to ensure the accuracy of all information within this brochure. Marketing Southport cannot be held responsible for

More information

Map showing location of public transport projects in vicinity of railway station

Map showing location of public transport projects in vicinity of railway station Map showing location of public transport projects in vicinity of railway station Market Town Transport Strategy 2013 39 ID PT1a Specific Location Approach at Detail of Project Develop Area Master plan

More information

APPENDIX 1 Background to the Bower Ashton Residents' Parking Scheme proposals The RPS proposals meet the objectives of the Council's overall transport

APPENDIX 1 Background to the Bower Ashton Residents' Parking Scheme proposals The RPS proposals meet the objectives of the Council's overall transport APPENDIX 1 Background to the Bower Ashton Residents' Parking Scheme proposals The RPS proposals meet the objectives of the Council's overall transport strategy as set out in the Joint Local Transport Plan

More information

Blackburn Road Blackburn Level Crossing Removal. Frequently Asked Questions August 2014 GENERAL

Blackburn Road Blackburn Level Crossing Removal. Frequently Asked Questions August 2014 GENERAL Frequently Asked Questions August 2014 Blackburn Road Blackburn Level Crossing Removal GENERAL What is the project? The Victorian Government has committed to eliminating a number of the busiest level crossings

More information