1 BRIEFING FOR INCOMING SHAREHOLDING MINISTERS ŌTĀKARO LIMITED 30 OCTOBER 2017
2 1. Background of Ōtākaro Limited Briefing for Incoming Shareholding Ministers Ōtākaro Limited Ōtākaro Limited (Ōtākaro) is a Crown company listed on Schedule 4A of the Public Finance Act. While they are similar in form to a Crown Entity, some entities are set up as Schedule 4A companies to accommodate their shorter expected lifespan. As a Company, Ōtākaro is subject to the Companies Act, aspects of the Crown Entities Act, as well as some requirements of the Public Finance Act. Ōtākaro was incorporated in February 2016 and became operational in April The Company was established to take over specific functions of the Canterbury Earthquake Recovery Authority (CERA). The Company s Board of Directors includes: Ross Butler (Chair) appointed February 2016, current term expires 16 February 2018; Peter Townsend appointed February 2016, current term expires 16 February 2018; Miriam Dean appointed February 2016, current term expires 16 February 2018; and Corinne Haines appointed August 2016, current term expires 30 June A special resolution of the Shareholders of the Company was approved in May 2016 which included a clarification of the purpose of the Company, as outlined in its Constitution. The Company continues to operate effectively with a Board consisting of the four directors. The Company s Board uses governance best practices to make efficient and effective decisions with a commercial focus. One of the Board s key roles is to appoint a Chief Executive. The Board appointed Albert Brantley as the Company s Chief Executive, and Mr Brantley commenced employment on 2 May Ōtākaro s shareholders are the Minister of Finance and the Minister supporting Greater Christchurch Regeneration, with each holding 50 per cent of the share capital. The most recent letter of expectation from Shareholding Ministers was issued on 17 March A copy is attached as Appendix 1. Following submission of drafts of the Company s Statement of Intent and Statement of Performance Expectations, Shareholding Ministers agreed on 21 June 2017 that copies of these documents should be sent to the Minister supporting Greater Christchurch Regeneration for tabling in the House of Representatives. These documents are available on the Company s web site The Company also provided a draft Business Plan to Shareholding Ministers. The finalised Business Plan is a commercially sensitive document that is not otherwise disclosed, and which helps the Board guide the Company. The Company will exist until the projects it is responsible for are delivered and certain surplus Crown land in the CBD is divested. Based on current expectation, this will be a period of no longer than seven years.
3 Additional information on the current status of all projects, land divestment activities as well various governance matters is available on the Ōtākaro website at The Briefing for Incoming Ministers prepared by the Department of Prime Minister and Cabinet also provides additional information. 2. Strategic Objectives Ōtākaro s strategic objectives, acting in the interests of the Crown and the people of Christchurch, are to: Add value to Crown funded Anchor Projects by delivering the projects safely, on budget, to schedule and to the desired quality; Divest Crown land holdings in central Christchurch in a manner that balances achieving good commercial outcomes against the Crown s regeneration objectives; and Support the Crown s exit from Anchor Projects and land holdings over time on favourable terms. The overarching responsibilities of Ōtākaro include: Delivery of defined Anchor Projects by providing procurement, design management and construction management services on behalf of the Crown; Providing programme governance, including risk, cost and schedule management; Divestment of Crown owned land in central Christchurch and the RRZ (if transferred), while achieving good commercial outcomes; and Acting in a manner consistent with recovery plans and any regeneration plans. 3. Project Delivery Ōtākaro is responsible for delivery of the Crown funded Anchor Projects in Christchurch. Specifically, these projects include: Canterbury Earthquake National Memorial; Margaret Mahy Family Playground; Avon River Precinct; East Frame Public Realm and Residential Project; South Frame Public Realm; An Accessible City Phase 1 (joint delivery responsibility with Christchurch City Council); Convention Centre and Precinct; and Metro Sports Facility. While Ōtākaro is not a party to the Crown s Cost Sharing Agreement (CSA) with the Christchurch City Council (CCC), the Company is expected to support the Crown in fulfilling aspects of this agreement. In particular, the CSA deals with the transfer of public realm assets being constructed by Ōtākaro at nil value post completion, and the joint funding of the Metro Sports Facility (MSF). Ōtākaro is leading the delivery of the MSF and, as envisaged by the CSA, a draft Development Agreement has been agreed between the CCC and Ōtākaro which outlines the project s joint funding, project responsibilities and asset transfer processes. The Development Agreement records the
4 capping of the CCC s funding for the MSF at $147m, Ōtākaro and the CCC have agreed all terms in the Development Agreement. Ōtākaro inherited from CERA a long term Development Agreement with Fletcher Residential Limited (FRL) for the residential development of the East Frame. This commercial agreement outlines the expected developments, timeframes, roles of the parties and commercial terms such as milestone dates and termination clauses. Importantly, under the Development Agreement, land is transferred, s9(2)(b)(ii) to FRL at 4. Land Divestment Ōtākaro has also been tasked with divestment of certain surplus Crown-owned land in the Central Business District. While Ōtākaro is expected to undertake this divestment on commercial terms, the Company has also been given the ability to balance commercial returns against supporting the Crown s regeneration objectives. To date, this approach has been successful in divesting land for projects that have combined commercial returns with support to regeneration objectives. These projects have included, for example: the Central City Riverside Farmers Market along the Avon River; the Hoyts Entertainment Complex adjacent to the Bus Interchange; a proposed technology and educational hub at the IRD Building in the East Frame area; and, divestment of several of the heritage Duncans Buildings in High Street, with a requirement to preserve the heritage facades. Other properties have been divested to commercial parties for office and accommodation developments. 5. Monitoring of Activities The Treasury monitors the commercial and financial performance of Ōtākaro, while DPMC interfaces with the contribution of Ōtākaro to regeneration outcomes. Ōtākaro has considerable operational interfaces with the CCC in the execution of its projects, particularly with the MSF, which is jointly funded by the Crown and the CCC, as well as the Avon River Precinct and other public realm projects that will be divested to the CCC upon completion.
5 6. Other Matters Funding Arrangements Agreements between the Crown and Ōtākaro determine how the Company is funded., s9(2)(b)(ii) These funding agreements include the quarterly process by which funds are requested in advance, and the use of funds is reconciled in arrears., s9(2)(b)(ii) The quarterly funding processes continue to work effectively between Ōtākaro and The Treasury. The Company is providing the required information on time, and Treasury is ensuring that funding is available in accordance with the requests ahead of the project and operational requirements. Land Contamination/Remediation Funding and Crown Indemnity Upon establishment of Ōtākaro, a preliminary budge, s9(2) was determined to cover land (b)(ii) remediation costs for the Crown owned land transferred to Ōtākaro. This included estimated costs for removal of contamination due to the presence of asbestos, hydrocarbons or underground structures resulting from the demolition activities undertaken after the 2011 earthquakes, and covered both land for Anchor Projects as well as surplus land to be divested. At the time of setting the land remediation budget, there was significant uncertainty about the land contamination risk. To address this uncertainty, should the costs of land remediation be more extensive than considered at the Company s establishment. While some land remediation uncertainty still exists, particularly within the South Frame, the Company now has a more comprehensive view of its potential land remediation cost position and the risk spreads. The Treasury has been provided with the latest estimates and risks faced by Ōtākaro Investor Confidence Rating The Treasury has recently completed its Investor Confidence Rating (ICR) for Ōtākaro. The Company received an A rating, one of the highest ratings achieved by a Crown owned company. In light of the continued focus on improvements in internal controls, audit results for the year ending 30 June 2017 and the ICR review results, The Treasury has decided to exclude Ōtākaro from further ICR reviews. Audit New Zealand Report, s9(2)(b)(ii) As part of their audit of the financial statements of the Company, Audit New Zealand has recently confirmed their views of the Company s control environment. Their independent findings are summarised below, comparing ratings for the 2017 year with the establishment period to 30 June 2016.
6 s9(2)(g)(i) Residential Red Zones (RRZ) and the GCR Act Under section 35 of the Greater Christchurch Regeneration Act (GCR Act), Ōtākaro must provide consent before Regenerate Christchurch can submit a draft Outline, draft Regeneration Plan or an amendment to the Minister supporting Greater Christchurch Regeneration, where the draft Plan or amendment relates to an area that includes any of the Christchurch RRZ and does not relate to any area outside of the Christchurch district. Ōtākaro has been working directly with Regenerate Christchurch on consideration of options for development and how best to assist in the preparation and review of regeneration plans for the RRZ. This has been achieved through direct secondment of Ōtākaro personnel to assist Regeneration Christchurch in its technical and planning studies. Ōtākaro is also a party listed in section 29 of the GCR Act whose views are sought on draft Outlines and Regeneration Plans for Christchurch District, along with Christchurch City Council, Canterbury Regional Council, Te Rūnanga o Ngāi Tahu, Regenerate Christchurch and the Chief Executive of DPMC. Extensive discussions have taken place between Regeneration Christchurch and Ōtākaro over the past year on consideration of development strategies for the Central Business District, particularly Cathedral Square. 7. Current Status of Work Programmes and Key Priorities Convention Centre Early site works are nearly complete, with only the last sheet piles still to be removed along Colombo Street. Abstraction and reinjection bore drilling will continue through the end of October Detailed Design started on 24 July The main design focus has been on issues outstanding at the Developed Design stage, including Armagh Street activation and façade colouring. The design contract was novated to CPB Contractors Pty Ltd (CPB) during August. The Outline Plan process is complete, with the CCC advising that it would not be appealing the Plan. The CPB contract was approved as a major transaction and CPB are now mobilising and setting up site offices. Excavation for the Plenary Hall will commence in October The crane will be erected on site in November Avon River Precinct works on Oxford Terrace have been advanced to ensure that key infrastructure is in place in front of the Convention Centre works (particularly in and around the Gloucester St bridge).
7 , s9(2)(b)(ii), s9(2)(j) The Company has continued its consideration of the divestment of land on the south eastern (Cathedral Square) side of the Convention Centre site for a high quality hotel. The District Plan has a 28m height limit, so any building consent sought above this will need to be notified. No significant issues were identified in shadow and wind studies for a 50m hotel. External real estate strategic and marketing support is being engaged to assist in market positioning and potential sale of the precinct lands on the southern side of the site. Metro Sports Facility (MSF) During recent months, transfer of the project to Ōtākaro was completed (previously Ōtākaro was providing project management services to the Crown). Both Ōtākaro and The Treasury have kept Shareholding Ministers informed of the negotiation issues, s9(2)(b)(ii), s9(2)(j) In parallel to negotiations with the proposed contractor, early site works have proceeded. Stone column ground remediation testing is complete, with analysis of results now underway. This is likely to lead to a further round of tests before a design can be finalised for building consent. Site decontamination works are complete, and Detailed Design is approximately 80 percent complete. East Frame Residential Precinct Good progress is being made with delivery of the Stage 1 Super lots. Superlot 4 construction is tracking in accordance with programme, with services currently being installed, and the area is being readied for pouring of the major foundation slab. Completion of the residences are planned for mid 2018, and marketing and sales will commence in early Ōtākaro has approved the developed design stage for Superlot 7 and title for this Superlot is expected to be issued to Fletcher Residential Living (FRL) in late October Early works have also started on this Superlot in October Completion is expected by early 2019, and marketing of these residences will commence in early 2018, along with sales and marketing for Superlot 4. s9(2)(j) FRL s work with Gapfiller has commenced to achieve temporary activation of the East Frame areas not in construction.
8 East Frame Public Realm The Public Realm project is on schedule and under budget, with 90% of works complete for the linear park area, and 80% of works on adjoining streets complete. Main activities on site include paving, garden bed preparation and planting and light pole installation. During the period the public space was named Rauora Park. A variation to the existing East Frame Public Realm contract with the City Care/JFC Joint Venture (JV) has been agreed for works on the CTV site. The 90% Developed Design for the site has been received and is currently under review. The Completion of the CTV work is scheduled for February Te Papa Ōtākaro / Avon River Precinct (ARP) Works are underway under a design and build contract for the area parallel to the Avon River between Antigua Street through to the family playground end of the ARP project. Five work face areas are open at varying stages of construction. The contractor has flexibility to prioritise works across the full site. In part, this enables the contractor to manage its sub-contractor work force and to mitigate adverse impacts of any ground issues encountered. The Company has worked closely with the contractor to maintain momentum on the area in front of the Farmers Market area (Retail Precinct) and to ensure works are coordinated with the Convention Centre site to provide access as the Convention Centre contractor mobilises. Within the Victoria Square component of the project, street works are advancing on schedule with the partial completion of rain gardens and tree pits along Colombo Street. The Bowker Fountain has been returned to its newly constructed pool walls and base. The base was reinforced by the last concrete pour in late September The amphitheatre works are almost complete, hydro-seeding has been completed and lighting has been installed. Paving continues. The only remaining paving is around the Queen Victoria statue and adjacent circle, the nib walls and planter boxes. An Accessible City, s9(2)(b)(ii) This followed confirmation that additional funds to complete the works, required due to the impacts of the funding suspension, would be available. A significant feature of the renegotiated contract is the consequent delay of completion dates for each separable portion into s9(2)(j) The Company has als by taking the section of Tuam Street between Antigua Street and Hagley Avenue out of the scope of s9(2)(j) works for the Downer contract. s9(2)(j)
9 South Frame Works are proceeding in Evolution Square (eastern end of the South Frame Innovation Precinct). Works are due for completion at the end of November One of the middle sections of the South Frame is currently being reprogrammed after receiving confirmation that acquisition of the area required for the public realm at the Donnithorne s property is now complete. Work is likely to commence at the end February Activity at the Smash Palace / Hi Para Apartments site (eastern end) is on hold until compulsory land acquisition is complete. Preparation for transfer of Innovation North to the CCC is under way, as is preparation for the ECan and Mollet Street areas. It is planned to have all transfer documentation ready and executed in November The main risk to achieving this transfer is the transfer of land, some of which is still held by LINZ. Progress on the areas currently occupied by Team Hutchison Ford (THF) and Miles Toyota is delayed until the THF land is purchased by LINZ and the Miles land is made available to the Company. s9(2)(g)(i) Canterbury Earthquake National Memorial (EQM) Transfer of the EQM asset to the Ministry for Culture and Heritage (MCH) has not yet been achieved. In the interim, MCH are funding maintenance costs while Ōtākaro is managing final minor defects s9(2)(g)(i) remediation on behalf of the MCH. Bus Interchange Ōtākaro holds the completed Bus Interchange on its balance sheet, and continues to play a day to day operational role in managing the facility. Lease arrangements are in place with ECan to operate parts of the Christchurch bus network through the facility. s9(2)(g)(i) Land Divestment Work progressed in recent months with a preferred bidder for the IRD building (224 Cashel Street) and the Cashel Chambers carpark. The IRD Building was transferred to the Company with a balance s9(2)(j) sheet valu including the Pavilion Carpark and Cashel Chambers and land). A Development and Sale agreement has now been signed that will see this building developed as a technology and education hub. Settlement of the sale of land for the Farmers Market development (Retail Precinct) occurred in early October The Company also notes that the land transaction for development of a Quest Hotel in the South Frame opposite the Justice and Emergency Precinct also settled in early October Land Contamination and Remediation As part of the transfer of assets at establishment of the Company, the Shareholders provided the Company wit unding and to cover further risk for land contamination and
10 remediation. The Company monitors both spend to date and remaining risk for all land areas. The At the end of the quarter the Company had spent land remediation activity. The Company has a disciplined process for ensuring the optimal remediation approach is taken, depending on the level of contamination found, the proposed land use and the available remediation options. Ōtākaro runs a detailed quantifiable risk analysis across all remaining land areas where remediation work may be required. As at 30 September the 85 th percentile shows a possible estimate at completion of. This estimate continues to trend down from earlier quarters and is heavily influenced by broad estimates of what contamination exists in the South Frame. Work is progressing to better understand the levels of contamination existing in this land. Additional information on the current status of all projects, land divestment activities as well various governance matters is available on the Ōtākaro website at 8. People and Resourcing As at 30 September 2017, the Company had 71 employees on its payroll consistent with the Company s Business Plan. These employees are complemented by approximately 14 contractors or consultants, mainly providing additional resources to the Ōtākaro Project Support Office.
11 Ross Butler Chair Otakaro Limited Private Bag 4999 CHRISTCHURCH 8140 Dear Ross Office of Hon Gerry Brownlee MP for 11am Leader of the House Minister of Defence Minister of Civil Defence LETTER OF EXPECTATIONS FOR OTAKARO LIMITED Minister Responsible for the Earthquake Commission Minister supporting Greater Christchurch Regeneration 1 4 MAR 2017 I am writing on behalf of the shareholding Ministers of Otakaro Limited to set out our expectations for Otakaro, for the Financial Year 2017/18. We also set out our expectations of Otakaro's general long-term, specific relationship-based and monitoring requirements. Otakaro will exist until the projects it is responsible for are delivered and land is divested; based on current expectations, a period of no longer than seven years from establishment. We will review these expectations each year. Purpose and objectives of Otakaro We have established Otakaro to contribute to the regeneration of Christchurch by adding value to defined anchor projects and Crown land in a manner which balances a desire to achieve good commercial outcomes against the Crown's regeneration objectives, and by supporting the Crown's exit over time on favourable terms. As the company is funded through the Crown, this necessitates a high level of engagement between the company and Crown representatives to ensure the spending of public money delivers the outcomes sought by shareholding Ministers. Otakaro 's core functions We expect Otakaro to achieve its purpose through successful delivery of its objectives and shareholders' expectations as expressed in the Constitution, this letter and future letters of expectations. We do not expect Otakaro to take on activities that would expose the company or its shareholders to undue financial or reputational risk. Shareholding Ministers do not expect the proceeds of asset divestment to be applied to new investments, but consider that the retention of sales proceeds in excess of associated debt (including capitalised interest) provides an incentive to achieve good value for the Crown. These may be applied to meet cost pressures in the anchor project programme and operating costs in line with the funding agreement. Business cycle The timetable for Otakaro's planning documents is set out in Annex 1 to this letter. We expect the Business Plan to explain how you intend the company's work programme to be Private Bag 18041, Parliament Buildings, Wellington 6160, New Zealand. Telephone Facsimile
12
13
14
Welcome and introduction
Welcome and introduction Welcome to your role as Minister for Greater Christchurch Regeneration. On behalf of DPMC and our colleagues across regeneration-related entities, we look forward to working with
More informationTerms of Reference: Introduction
Terms of Reference: Assessment of airport-airline engagement on the appropriate scope, design and cost of new runway capacity; and Support in analysing technical responses to the Government s draft NPS
More information1. The purpose of this report is to seek the Works, Traffic and Environment Committee s recommendation for:
6. POUND ROAD ROAD STOPPING AND LAND SWAP General Manager responsible: General Manager City Environment, DDI 941-8608 Officer responsible: Authors: PURPOSE OF REPORT Asset and Network Planning Manager
More informationReport of Commissioning Director, Growth and Development. Wards Child s Hill, Golders Green and West Hendon. Summary
ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER 26 April 2016 Title Brent Cross Cricklewood Gowling Wragge Lawrence Graham (UK) LLP Report of Commissioning Director, Growth and Development Wards Child s
More informationClyde Waterfront and Renfrew Riverside Project Glasgow Airport Investment Area Project
Item 1 To: Leadership Board On: 3 June 2015 Report by: Director of Development and Housing Services Heading: City Deal Strategic Business Cases 1. Summary 1.1 This report seeks approval from the Board
More informationLocal Development Scheme
Local Development Scheme August 2014 Local Development Scheme (August 2014) / Page 2 Contents Section 1: Introduction Great Yarmouth s Development Plan 4 Section 2: Plan Making Process Public participation
More informationDEXUS Property Group (ASX: DXS) ASX release
6 May 2013 DEXUS and DWPF to acquire strategic office investment in Perth DEXUS Property Group (DEXUS or DXS) and DEXUS Wholesale Property Fund (DWPF) today announced the joint acquisition of a strategic
More informationCalderdale MBC. Wards Affected: Town. Economy and Investment Panel: 20 October Halifax Station Gateway Masterplan
Calderdale MBC Wards Affected: Town Economy and Investment Panel: 20 October 2016 Halifax Station Gateway Masterplan Report of the Acting Director, Economy and Environment 1. Purpose of the Report 1.1
More informationDevine Limited Annual General Meeting. The Marriott Hotel 515 Queen Street, Brisbane 31 October, am
Devine Limited Annual General Meeting The Marriott Hotel 515 Queen Street, Brisbane 31 October, 2008 11.00am Agenda 1. Welcome 2. Chairman s Address 3. Managing Director s Address 4. Formal Business CHAIRMAN
More informationREAUTHORISATION OF THE ALLIANCE BETWEEN AIR NEW ZEALAND AND CATHAY PACIFIC
Chair Cabinet Economic Growth and Infrastructure Committee Office of the Minister of Transport REAUTHORISATION OF THE ALLIANCE BETWEEN AIR NEW ZEALAND AND CATHAY PACIFIC Proposal 1. I propose that the
More informationGreat Portland Estates Trading Update Strong Operational Performance
Press Release 6 July 2017 Great Portland Estates Trading Update Strong Operational Performance Great Portland Estates plc ( GPE ) today publishes its trading update for the quarter to 30 June 2017. Continued
More informationSmart Cities Plan IMPLEMENTATION. Townsville City Deal. April 2017
Smart Cities Plan IMPLEMENTATION Townsville City Deal April 2017 ACKNOWLEDGEMENTS The Commonwealth Government, Queensland Government and the Townsville City Council would like to thank the Townsville community
More informationCOMMUNICATION THE RT. HON. PERRY G. CHRISTIE PRIME MINISTER AND MEMBER OF PARLIAMENT FOR CENTREVILLE
COMMUNICATION BY THE RT. HON. PERRY G. CHRISTIE PRIME MINISTER AND MEMBER OF PARLIAMENT FOR CENTREVILLE ON THE GRAND BAHAMA (PORT AREA) INVESTMENT INVENTIVES (AMENDMENT) BILL, 2016 MONDAY, 7 TH NOVEMBER
More informationThe Cobham Room, Novotel Hamilton Tainui, 7 Alma Street, Hamilton
Board Meeting Minutes Date & time Location Board Membership Apologies NZTA staff in attendance 12 August 2016, 8.00am 12.30pm Board Strategy Session 1.00pm 2.30pm The Cobham Room, Novotel Hamilton Tainui,
More informationPrecinct Properties New Zealand Annual General Meeting 7 November 2014
Precinct Properties New Zealand Annual General Meeting 7 November 2014 Craig Stobo, Chairman BOARD AND EXECUTIVE Management Scott Pritchard Chief Executive Officer George Crawford Chief Financial Officer
More informationPCT delivers strong profit result and launches One Queen Street
NZX announcement 16 August 2018 PCT delivers strong profit result and launches One Queen Street Performance summary for the 12 months ended 30 June 2018 Delivering strong results Net profit after tax increased
More informationItem 1. Leadership Board. On: 1 April Report by: Director of Development and Housing Services. Heading: Update on City Deal. 1.
Item 1 To: Leadership Board On: 1 April 2015 Report by: Director of Development and Housing Services Heading: Update on City Deal 1. Summary 1.1 This report seeks to update the Board on the work that has
More informationSTRATEGIC INVESTMENT IN MANCHESTER AIRPORT
Report To: EXECUTIVE CABINET Date: 7 February 2018 Cabinet Deputy/Reporting Officer: Subject: Report Summary: Cllr Bill Fairfoull Executive Member (Finance & Performance) Tom Wilkinson, Assistant Director
More informationAir Operator Certification
Civil Aviation Rules Part 119, Amendment 15 Docket 8/CAR/1 Contents Rule objective... 4 Extent of consultation Safety Management project... 4 Summary of submissions... 5 Extent of consultation Maintenance
More informationMessage from the Managing Director... r...
Message from the Managing Director... r... Our first full trading year has been a challenging and rewarding period for the team during the early life of the Company, a year during which we have gained
More informationMinutes of the Meeting of the Board of Scottish Canals held on 23rd August 2012 at The Kingsmills Hotel, Inverness at 9.00am.
Minutes of the Meeting of the Board of Scottish Canals held on 23rd August 2012 at The Kingsmills Hotel, Inverness at 9.00am. Present: Dr Jon Hargreaves - Chair Geoff Aitkenhead - Acting Vice Chair Tanya
More information15. BEXLEY RESERVE NORTH AVON BMX CLUB FORMALISATION OF LEASE/LICENCE
15. BEXLEY RESERVE NORTH AVON BMX CLUB FORMALISATION OF LEASE/LICENCE General Manager responsible: General Manager City Environment, DDI 941-8608 Officer responsible: Authors: PURPOSE OF REPORT Transport
More informationFrequently Asked Questions
CAA Funding Review Why has CAA s funding been reviewed? New Zealand has a well-regarded civil aviation system and a good aviation safety record. However, both the government and a range of reviews (including
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: November 18, 2013 SUBJECT: ISLINGTON STATION TEMPORARY BUS TERMINAL ACTION ITEM RECOMMENDATIONS It is recommended that the Board: 1.
More informationPrecinct Properties New Zealand Limited Annual General Meeting
NZX announcement - 9 November 2017 Precinct Properties New Zealand Limited Annual General Meeting 10:00am (New Zealand time), Thursday 9 November 2017 Pullman Auckland, Corner Princes Street and Waterloo
More informationAirlines UK 24 May 2018: Speech by Richard Moriarty
24 May 2018 Airlines UK 24 May 2018: Speech by Richard Moriarty 1. Good afternoon everyone. I d like to thank Tim and Airlines UK for organising today s event, which I hope will mark a significant milestone
More informationHotel and Hospitality Services. Capita Real Estate
Hotel and Hospitality Services Capita Real Estate About Us At GL Hearn we are seeing continuous growth in the hotel investment and development markets. We act for investors, developers and occupiers across
More informationReport of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018
Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018 Subject: M Arrangements for the establishment of a West Yorkshire Urban Traffic Management Control
More informationFor personal use only
For the period ended 30 September 2014 HIGHLIGHTS STORMONT (TASMANIA) JOINT VENTURE GOLD PROJECT MINING AND PRODUCTION COMPLETED. LORENA GOLD PROJECT CONSTRUCTION CONTINUES TO ADVANCE. COMMISSIONING EXPECTED
More informationEconomic Development Sub- Committee
Report title: Economic Development Sub- Committee Item No. Date of meeting: 24 November 2016 A47 Road Investment Strategy - update Responsible Chief Tom McCabe Executive Director, Community Officer: and
More informationFUTURE AIRSPACE CHANGE
HEATHROW EXPANSION FUTURE AIRSPACE CHANGE UPDATE SEPTEMBER 2018 On 25 June 2018, Parliament formally backed Heathrow expansion, with MPs voting in support of the Government s Airports National Policy Statement
More informationNATIONAL AIRSPACE POLICY OF NEW ZEALAND
NATIONAL AIRSPACE POLICY OF NEW ZEALAND APRIL 2012 FOREWORD TO NATIONAL AIRSPACE POLICY STATEMENT When the government issued Connecting New Zealand, its policy direction for transport in August 2011, one
More informationInvestor Update September 2017 PARTNER OF CHOICE EMPLOYER OF CHOICE INVESTMENT OF CHOICE
Investor Update September 2017 PARTNER OF CHOICE EMPLOYER OF CHOICE INVESTMENT OF CHOICE 1 Forward Looking Statements In addition to historical information, this presentation contains forward-looking statements
More informationMINUTES SPECIAL MEETING OF COUNCIL. Tuesday, 1 September 2015
MINUTES SPECIAL MEETING OF COUNCIL Tuesday, 1 September 2015 Held at the Council Conference and Reception Centre City Hall, Little Malop Street, Geelong commencing at 7.20p.m. COUNCIL: Cr. D. Lyons Mayor
More informationCommissioning Director - Environment
Finchley and Golders Green Area Committee 27 April 2017 Title Report of Wards Status Urgent Key Enclosures Summers Lane,N12 Request for Pedestrian Improvements Commissioning Director - Environment Woodhouse
More informationRyeish Green and Grays Fruit Farm Sports Hub Projects. Shinfield South and Wokingham Without. Heather Thwaites, Director of Environment
TITLE Ryeish Green and Grays Fruit Farm Sports Hub Projects FOR CONSIDERATION BY The Executive on 30 July 2015 WARD DIRECTOR LEAD MEMBER Shinfield South and Wokingham Without Heather Thwaites, Director
More informationNational Park Authority Board Meeting
Paper for decision 1. Introduction 1.1 Preparations for the introduction of four Camping Management Zones (covering less than 4% of the National Park) have progressed significantly since Scottish Ministers
More informationSKYCITY ENTERTAINMENT GROUP LIMITED (SKC) INVESTOR PRESENTATION FOR UBS INVESTOR CONFERENCE
13 November 2017 Client Market Services NZX Limited Level 1, NZX Centre 11 Cable Street WELLINGTON Copy to: ASX Market Announcements Australian Stock Exchange Exchange Centre Level 6 20 Bridge Street Sydney
More informationInvestment Opportunity
Investment Opportunity Quest Apartment Hotel Pakenham Street, Fremantle Investment Highlights 120 key Quest serviced apartment development Fremantle s CBD is undergoing renewal and Sirona Capital is a
More informationTERMS OF REFERENCE WHITSUNDAY ROC LIMITED. Adopted 17 th October These Terms of Reference are underpinned by the Constitution of the
TERMS OF REFERENCE Adopted 17 th October 2013 These Terms of Reference are underpinned by the Constitution of the WHITSUNDAY ROC LIMITED 1. COMPANY The company WHITSUNDAY ROC LIMITED is registered as a
More informationPERTH AND KINROSS COUNCIL. 22 June 2016 DEVELOPING THE CULTURAL OFFER IN PERTH AND KINROSS UPDATE AND NEXT STEPS
PERTH AND KINROSS COUNCIL 8 16/278 22 June 2016 DEVELOPING THE CULTURAL OFFER IN PERTH AND KINROSS UPDATE AND NEXT STEPS Report by Senior Depute Chief Executive (Equality, Community Planning & Public Service
More informationBusiness Case Approved. Under Construction. Business Case Approved. Under Construction
Item 6 Appendix A: LGF Project Summary for South Essex Update September Project and A127 Network Resilience (Essex) Basildon Integrated Transport Package (Essex) Range of improvements at key locations
More informationENVIRONMENT ACTION PLAN
ENVIRONMENT ACTION PLAN 2015 16 Airservices Australia 2015 This work is copyright. Apart from any use as permitted under the Copyright Act 1968, no part may be reproduced by any process without prior written
More informationA Master Plan is one of the most important documents that can be prepared by an Airport.
The Master Plan A Master Plan is one of the most important documents that can be prepared by an Airport. A Master Plan is a visionary and a strategic document detailing planning initiatives for the Airport
More information1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET
Report No. 3 of the Regional Council Meeting of March 28, 2013 1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET The recommends: 1. Receipt
More informationOpen Report on behalf of Richard Wills, Executive Director for Environment and Economy
Agenda Item 7 Executive Open Report on behalf of Richard Wills, Executive Director for Environment and Economy Report to: Executive Date: 02 September 2014 Subject: Lincoln East West Link Road Phase 1
More informationConvention Centre Proposal. Have your say before we make a final decision later this year.
Convention Centre Proposal Have your say before we make a final decision later this year. Conventions are important to cities because of the economic benefits they bring. Page 2 CONTENTS Introduction...3
More informationConsolidated Terms of Reference for Inquiry into the use of external security consultants 29 October 2018
Consolidated Terms of Reference for Inquiry into the use of external security consultants 29 October 2018 This document consolidates the Terms of Reference previously issued on 27 March 2018 and 19 June
More informationUpdate on the Thameslink programme
A picture of the National Audit Office logo Report by the Comptroller and Auditor General Department for Transport Update on the Thameslink programme HC 413 SESSION 2017 2019 23 NOVEMBER 2017 4 Key facts
More information2001/02 Financial review of the Ministry of Transport. Report of the Transport and Industrial Relations Committee
2001/02 Financial review of the Ministry of Transport Report of the Transport and Industrial Relations Committee December 2002 2 Ministry of Transport Recommendation The Transport and Industrial Relations
More informationAppendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited
Gatwick Airport Limited Response to Airports Commission Consultation Appendix 37 Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Further information
More informationISBN no Project no /13545
ISBN no. 978 1 869452 95 7 Project no. 18.08/13545 Final report to the Ministers of Commerce and Transport on how effectively information disclosure regulation is promoting the purpose of Part 4 for Auckland
More information27 December Companies Announcement Office Australian Securities Exchange Limited 20 Bridge Street Sydney NSW Dear Sir
Acting Company Secretary Cassandra Hamlin 27 December 2006 Companies Announcement Office Australian Securities Exchange Limited 20 Bridge Street Sydney NSW 2000 Dear Sir Letter from Chairman to Qantas
More informationCurriculum Vitae Brian Joseph Waddell
Curriculum Vitae Brian Joseph Waddell 18 Shelly Beach Road, Waiheke Island, Auckland 1081 Home 64 9 372 5442. Cell phone 64 21 791107 Email brian@urbanista.co.nz Professional Qualifications Bachelor of
More informationLYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN. Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS
APPENDIX 15.1-3 LYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN Purpose of the Structure Plan Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS LSP-P1 The District
More informationSTRONGER CHRISTCHURCH INFRASTRUCTURE REBUILD TEAM (SCIRT) REAAA
STRONGER CHRISTCHURCH INFRASTRUCTURE REBUILD TEAM (SCIRT) REAAA 21 st August 2012 Context Legend Areas of observed liquefaction! Port Hills area Approx Scale 1:50,000 0 500 1000 1500 2000 2500 (m) Notes:
More informationIndustry briefing NOVEMBER 2017
Industry briefing NOVEMBER 2017 SYDNEY METRO AUSTRALIA S BIGGEST PUBLIC TRANSPORT PROJECT A new stand-alone railway, this 21st century network will revolutionise the way Sydney travels. Services start
More informationResearch Briefing Flood and Coastal Erosion Risk Management in Wales
Research Briefing Flood and Coastal Erosion Risk Management in Wales Author: Wendy Dodds Date: September 2017 National Assembly for Wales Research Service The National Assembly for Wales is the democratically
More informationSCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol
The following presentation was given at: SCAF Workshop Integrated Cost and Schedule Risk Analysis Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol Released for distribution by the Author www.scaf.org.uk/library
More informationSunshine Coast Airport Master Plan September 2007
Sunshine Coast Airport Master Plan September 2007 Contents CONTENTS... I ACKNOWLEDGEMENT... II DISCLAIMER... III 1 EXECUTIVE SUMMARY...IV 1 INTRODUCTION... 1 2 AVIATION DEMAND FORECAST... 5 3 AIRCRAFT
More informationDilmunia Development Fund I L.P. Enhancing Life, Restoring Balance. January 1st 2014 to June 30th 2014
Dilmunia Development Fund I L.P. Enhancing Life, Restoring Balance January 1st 2014 to June 30th 2014 Contents Dilmunia Key Developments Project Development Key Targets Appendix The Fund Manager, Ithmaar
More informationRamsay Health Care Limited Results Briefing Half Year ended 31 December 2018
Ramsay Health Care Limited Results Briefing Half Year ended 31 December 2018 Craig McNally, Group Managing Director & Bruce Soden, Group Finance Director 28 February 2019 ramsayhealth.com Agenda Group
More informationThe Strategic Commercial and Procurement Manager
Item 3 To: Procurement Sub Committee On: 8 June 2016 Report by: The Strategic Commercial and Procurement Manager Heading: Renfrewshire Council s Community Benefit Strategy 2016 1. Summary 1.1. The purpose
More informationCrown Resorts Limited
Crown Resorts Limited 2015 Full Year Results Presentation 13 August 2015 1 Crown Resorts Limited Results Overview Crown Resorts Limited (Crown) performance: Overall, the results for Crown s portfolio of
More informationof the Resource Management Act 1991 ("RMA") PANUKU DEVELOPMENT AUCKLAND LIMITED Applicant AUCKLAND COUNCIL Consent Authority Section 274 parties
1920 IN THE ENVIRONMENT COURT AUCKLAND ENV-2018-AKL-000078 TE KŌTI TAIAO O AOTEAROA TĀMAKI MAKAURAU IN THE MATTER of the Resource Management Act 1991 ("RMA") AND IN THE MATTER of direct referral of an
More information7 June 2016 Corporate Report Format. To the Chair and Members of the Chair and Members of the Cabinet
7 June 2016 Corporate Report Format To the Chair and Members of the Chair and Members of the Cabinet Approval of the Business Case for the development of a Hotel and Apartment Complex at Doncaster Relevant
More informationPre-application submission for Committee: Phase 4 development at West Hendon
Pre-application submission for Committee: Phase 4 development at West Hendon 1. Development Details Phase 4 of the West Hendon Estate Regeneration. 2. Background The redevelopment of the West Hendon Estate
More informationSUBMISSION BY. TO THE TRANSPORT AND INFRASTRUCTURE SELECT COMMITTEE ON THE COMMERCE AMENDMENT BILL
SUBMISSION BY. TO THE TRANSPORT AND INFRASTRUCTURE SELECT COMMITTEE ON THE COMMERCE AMENDMENT BILL 15 JUNE 2018 The Commerce Amendment Bill is necessary and urgently required 1.1. Air New Zealand supports
More informationHeathrow (SP) Limited
Draft v2.0 10 Feb Heathrow (SP) Limited Results for year ended 31 December 2013 24 February 2014 Strong operational and financial performance in 2013 Passenger satisfaction at record high and over 72 million
More informationGOING PLACES MACARTHURCOOK OFFICE PROPERTY TRUST
GOING PLACES MACARTHURCOOK OFFICE PROPERTY TRUST ANNUAL REPORT 2006 1 2 3 4 1 2 181 Miller Street, North Sydney, NSW 150 170 Leichhardt Street, Spring Hill, Brisbane, QLD 3 4 38 Akuna Street, Canberra,
More informationANGLIAN WATER GREEN BOND
ANGLIAN WATER GREEN BOND DNV GL ELIGIBILITY ASSESSMENT Scope and Objectives Anglian Water Services Financing Plc is the financing subsidiary of Anglian Water Services Limited. References in this eligibility
More informationSpirit Airlines Reports First Quarter 2017 Results
Spirit Airlines Reports First Quarter 2017 Results MIRAMAR, Fla., April 28, 2017 - Spirit Airlines, Inc. (NASDAQ: SAVE) today reported first quarter 2017 financial results. GAAP net income for the first
More informationFOR CONSIDERATION BY The Executive on 30 October Angus Ross, Executive Member for Environment
ITEM NO: 69.00 TITLE Leisure Facility Options Study FOR CONSIDERATION BY The Executive on 30 October 2014 WARD DIRECTOR LEAD MEMBER None specific Heather Thwaites, Director of Environment; Stuart Rowbotham,
More informationEnhanced Engagement Terms of Reference:
Official Enhanced Engagement Terms of Reference: Assessment of how well HAL is engaging with and responding to the airline community on its plans for capacity expansion at Heathrow and whether this engagement
More informationAll reports. 1. Governance Service receive draft report Name of GSO DPR
DELEGATED POWERS REPORT NO. SUBJECT: Redevelopment at Grahame Park Estate, NW9, Phase 1B Sub-phase 1 Highways Agreement under Sections 38 and 278 of the Highways Act 1980. Control sheet All of the following
More informationCONSULTATIVE GROUP 11 DECEMBER Lori Keeve Communications Grangegorman Development Agency
CONSULTATIVE GROUP 11 DECEMBER 2014 Lori Keeve Communications Grangegorman Development Agency OVERVIEW Planning HSE Projects o Primary Care Centre o Community Nursing Unit DIT Projects o Public Realm /
More informationAustralian Securities Exchange Notice
Australian Securities Exchange Notice 30 January 2017 ILUKA BUSINESS REVIEW UPDATE AND THE IMPACT ON 2016 AND 2017 FINANCIAL RESULTS Iluka Resources Limited (Iluka) provides the following update relating
More informationGruyere Gold Project Update
ASX Announcement 30 July 2018 Gruyere Gold Project Update First gold remains scheduled for the June quarter 2019 Revised Project Final Forecast Capital cost estimate of $621 million (level of accuracy
More information2 THE MASTER PLAN 23
2 THE MASTER PLAN 23 THE MASTER PLAN 2.1 Purpose of the Master Plan A Master Plan provides the airport operator, the Commonwealth, State and Local Governments, the local community, aviation industries
More informationMetrolinx Projects: Temporary Delegation for Long- Term Road Closures
PW29.1 REPORT FOR ACTION Metrolinx Projects: Temporary Delegation for Long- Term Road Closures Date: April 24th, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation
More informationExecutive Directors Review
Financial Summary Turnover for the year ended 31 December 2011 amounted to HK$571.4 million ( 47.6 million) (2010: HK$706.8 million ( 58.7 million)). The turnover was principally attributable to the recognition
More informationPROJECTS & TECHNICAL SERVICES
PROJECTS & TECHNICAL SERVICES 1.0 2.0 3.0 4.0 5.0 JOHN NITSCHKE EGM Projects & Technical Services 6.0 7.0 8.0 9.0 OZ MINERALS NOVEMBER 2009 PAGE 40 STRATEGY SUPERIOR TOTAL SHAREHOLDER RETURNS ZERO HARM
More informationWAIMAKARIRI DISTRICT COUNCIL REPORT. Craig Sargison, Manager Community and Recreation
WAIMAKARIRI DISTRICT COUNCIL REPORT FILE NO: GOV-26-01-07, CPR-04-04-01 / 150609090834 REPORT TO: Kaiapoi Community Board DATE OF MEETING: 15 June 2015 FROM: SUBJECT: Craig Sargison, Manager Community
More informationBrisbane Metro Infrastructure Association of Queensland 14 February 2018
Brisbane Metro Infrastructure Association of Queensland 14 February 2018 Agenda Brisbane Metro project update Packaging and procurement overview Panel discussion Audience Q&A The journey so far Planning
More informationFor personal use only
ASX Announcement 16 November 2015 DESTINATION BRISBANE CONSORTIUM AND QUEENSLAND GOVERNMENT ENTER INTO AGREEMENTS FOR QUEEN S WHARF BRISBANE Echo Entertainment Group Limited (Echo) 1 today announced that
More informationAIR CANADA REPORTS 2010 THIRD QUARTER RESULTS; Operating Income improved $259 million or 381 per cent from previous year s quarter
AIR CANADA REPORTS 2010 THIRD QUARTER RESULTS; Operating Income improved $259 million or 381 per cent from previous year s quarter MONTRÉAL, November 4, 2010 Air Canada today reported operating income
More informationDisposition of Spadina Expressway Properties - Memorandum of Understanding with Infrastructure Ontario
GM22.32 REPORT FOR ACTION Disposition of Spadina Expressway Properties - Memorandum of Understanding with Infrastructure Ontario Date: September 8, 2017 To: Government Management Committee From: Chief
More informationCROWN AND NEW SOUTH WALES GOVERNMENT ENTER INTO AGREEMENTS FOR CROWN SYDNEY HOTEL RESORT
ASX / MEDIA RELEASE FOR IMMEDIATE RELEASE 11 November 2013 CROWN AND NEW SOUTH WALES GOVERNMENT ENTER INTO AGREEMENTS FOR CROWN SYDNEY HOTEL RESORT MELBOURNE: Crown Resorts Limited (ASX: CWN) announced
More informationCrown Corporation BUSINESS PLANS FOR THE FISCAL YEAR Trade Centre Limited. Table of Contents. Business Plan
Crown Corporation BUSINESS PLANS FOR THE FISCAL YEAR 2014 2015 Trade Centre Limited Business Plan 2014 2015 Table of Contents Message from the CEO and the Chair... Mission... Planning Context... Strategic
More informationPUBLIC ACCOUNTABILITY PRINCIPLES FOR CANADIAN AIRPORT AUTHORITIES
PUBLIC ACCOUNTABILITY PRINCIPLES FOR CANADIAN AIRPORT AUTHORITIES The Canadian Airport Authority ( CAA ) shall be incorporated in a manner consistent with the following principles: 1. Not-for-profit Corporation
More informationCROWN SYDNEY HOTEL RESORT - UNSOLICITED PROPOSAL
ASX / MEDIA RELEASE FOR IMMEDIATE RELEASE 25 October 2012 CROWN SYDNEY HOTEL RESORT - UNSOLICITED PROPOSAL MELBOURNE: Crown Limited (ASX: CWN) today announced that it welcomed the decision of the NSW Government
More informationRequest for quotation
Request for quotation Request: Destination NSW is seeking an itemised quotation for the provision of Event Administrator services for Vivid Sydney 2018 with an option to extend for Vivid Sydney 2019. Background
More informationDraft Western District Plan
Powered by TCPDF (www.tcpdf.org) Draft Western District Plan Submission_id: 31732 Date of Lodgment: 15 Dec 2017 Origin of Submission: Online Organisation name: APP Corporation Pty Ltd Organisation type:
More informationMayor Dave Bronconnier cc: All City of Calgary Alderman. Eastbound Extension of Airport Trail and Related Works
May 7, 2009 Mayor Dave Bronconnier cc: All City of Calgary Alderman The City of Calgary Mr. John Hubbell, GM Transportation 700 Macleod Trail SE Calgary AB T2P 2M5 Re: Eastbound Extension of Airport Trail
More informationSky City Entertainment Group Annual Meeting. Managing Director s Address
Sky City Entertainment Group 2002 Annual Meeting Managing Director s Address Thank you Jon and good morning ladies and gentlemen. 2002 has been another busy and successful year for Sky City. Jon has alluded
More informationDriving global growth
Holiday Inn, Manhattan Financial District Driving global growth Paul Edgecliffe Johnson Group CFO IHG has a consistently executed, winning strategy for high quality growth Value creation: superior shareholder
More informationPRESS RELEASE VINCI QUARTERLY INFORMATION AT 30 SEPTEMBER 2014
Rueil Malmaison, 23 October PRESS RELEASE VINCI QUARTERLY INFORMATION AT 30 SEPTEMBER Revenue at 30 September 1 : 28.4 billion (-1.5% like-for-like) Good performance in Concessions 1 : - VINCI Autoroutes
More informationStakeholder Briefing The Bays Precint Urban Transformation Program
Stakeholder Briefing The Bays Precint Urban Transformation Program November 2014 Our Lifecycle Approach 3 Our Ambition & Narrative Our Ambition Statement for UrbanGrowth NSW is - Transforming City Living
More informationHOPEWELL HOLDINGS LIMITED ANNOUNCES FY 2018/19 INTERIM RESULTS
Press Release HOPEWELL HOLDINGS LIMITED ANNOUNCES FY 2018/19 INTERIM RESULTS Highlights 1H FY19 (1 April to 30 September 2018) First financial year after the change of financial year end date from 30 June
More information4countries. We understand the fundamentals. A trusted partner. We have delivered million sqm. 1.8 million car spaces.
A trusted partner Multiplex is a trusted partner for all types of retail projects from Greenfield developments to refurbishments and vibrant mixed-use precincts, in both cities and regional locations.
More information