1 MOUNT CAIN SKI AREA 2010 Master Plan Update

2 Table of Contents EXECUTIVE SUMMARY... 4 INTRODUCTION... 4 PROJECT VISION... 4 GENERAL OVERVIEW OF BUSINESS... 4 SECTION 1: DESCRIPTION OF EXISTING OPERATION DESCRIPTION OF EXPERIENCE/ACTIVITIES BEING OFFERED BASE OPERATION AND EXISTING IMPROVEMENTS MOUNTAIN OPERATION AND IMPROVEMENTS EXISTING TENURES ACCESS SERVICING SKI AREA CAPACITY AND SKIER VISITS... 9 SECTION 2: OVERVIEW OF PROPOSED EXPANSION NEW OPERATING AGREEMENT AND FUTURE EXPANSION AREA BASE IMPROVEMENTS MOUNTAIN IMPROVEMENTS PROPOSED TENURE REVISIONS ACCESS UPGRADES SERVICING PROJECTED CAPACITY AND SKIER VISITS MOUNT CAIN ALPINE PARK SOCIETY S FIVE YEAR DEVELOPMENT PLAN ECONOMIC BENEFITS OPPORTUNITIES AND CONSTRAINTS SECTION 3: ENVIRONMENTAL & CULTURAL VALUES FISH VALUES WILDLIFE VALUES WATER VALUES ENVIRONMENTAL VALUES FIRST NATIONS SECTION 4: OVERLAP WITH EXISTING USE MINERAL TENURE TIMBER TENURE & FOREST USE LAND USE PLANNING, LOCAL OR REGIONAL ZONING REQUIREMENTS COMMERCIAL RECREATION TENURE & GUIDE OUTFITTER TERRITORIES PUBLIC RECREATIONAL USE APPENDIX A MAPPING FIGURE 1 LOCATION MAP P a g e

3 FIGURE 2 LAND ACT INTERESTS MAP FIGURE 3 FORESTRY AND MINERAL INTERESTS MAP FIGURE 4 - WILDLIFE INTERESTS MAP FIGURE 5 PROPOSED LAND ACT TENURE REVISIONS MAP APPENDIX B - SAFETY MANAGEMENT PLAN APPENDIX C - MT. CAIN ALPINE PARK LODGE DRINKING WATER SYSTEM EMERGENCY RESPONSE PLAN APPENDIX D REGIONAL DISTRICT OF MOUNT WADDINGTON ZONING REQUIREMENTS APPENDIX E SUMMARY OF COMMITMENTS AND ASSURANCES P a g e

4 Executive Summary Introduction The Resort Development Branch has worked collaboratively with the Mt Cain Alpine Park Society (MCAPS, ski area operator) and the Regional District of Mt. Waddington (RDMW, Operating Agreement holder) to prepare the Mt. Cain 2010 Ski Area Master Plan Document. This update identifies existing developments on the land, proposes further improvements to the ski hill to support its continued sustainability and will permit RDB to review MCAPS s request for greater land tenure security for 52 recreational cabin owners at Mt. Cain. This summary document identifies the key improvements and associated tenure revisions contained within the Mount Cain Alpine Recreation Area Development Master Plan Update and the Mt. Cain Alpine Park Society Five Year Ski Hill Development Plan documents for the purpose of agency, First Nation and stakeholder referral and consultation. Referral and consultation with interested parties has been undertaken in order to identify specific interests, potential negative impacts and issues of concern. The Resort Development Branch has worked with engaged parties throughout the master plan review process to identify further changes and mitigation strategies to address potential negative impacts from the proposed changes in the Master Plan Update and to incorporate others parties interests to the extent possible. Resulting commitments and assurances have been incorporated into Appendix E, Summary of Commitments and Assurances and the Draft Mt. Cain Operating Agreement. Project Vision The Mt. Cain Ski Area has operated under the management of MCAPS, a non-profit, volunteer driven society, for over thirty years (since 1977) with the focus of providing affordable, family-oriented alpine skiing opportunities in northern Vancouver Island. MCAPS and RDMW wish to continue to operate the Mt. Cain Ski Area for the enjoyment and benefit of the communities of the North Island while addressing operational, environmental and infrastructure issues and constraints to increased skier visitation. The RDMW and MCAPS also wish to expand recreational opportunities in adjacent areas, including the area north to Mt. Hapush and the West Bowl. The creation of a regional four-season recreation area would offer a broader range of recreation activities including skiing, snowshoeing and Nordic skiing in the winter months and hiking and climbing during spring, summer and fall. It would also create a year round presence at the ski hill which would then offer improved security and management of the ski area improvements and surrounding sensitive alpine ecosystems. RDB has advised that for the purpose of this master plan review, RDB will limit its review to improvements and revisions specific to the lift-based ski area and that an application for the proposed park establishment in the adjacent areas would be separate and under the jurisdiction of the Integrated Land Management Bureau. General Overview of Business Mount Cain Ski Area is managed and operated by the Mount Cain Alpine Park Society (MCAPS), a registered non-profit society, which operates largely on volunteer labour and donated resources. The ski area is operational on weekends and holidays from December through to early April depending on snow accumulations. Situated on the north end of Vancouver Island, Mount Cain offers a unique experience to skiers, snowboarders and backcountry explorers. Mt Cain primarily draws clientele from communities in northern and central Vancouver Island. It is Vancouver Island's only community owned and operated ski-hill and offers the following winter recreation opportunities: 18 ski runs from novice to expert; food and beverages available on the main floor of the day lodge; hostel style accommodations on the upper levels of the day lodge; two rental cabins and a group accommodations building; ski/board/snowshoe equipment rentals, sales and service offered at the ski shop; 4 P a g e

5 a ski school offering skiing and snowboarding lessons and packages with equipment rental for beginners; and, although it is not encouraged due to avalanche and terrain hazards, access to backcountry skiing and boarding opportunities outside of the patrolled Controlled Recreation Area are very popular. The proposed improvements and tenure revisions described within this document and the attached documents are required to further ensure the sustainability of the Mt. Cain Ski Area operation for the benefit of the communities of northern Vancouver Island. 5 P a g e

6 Section 1: Description of Existing Operation 1.1 Description of Experience/Activities Being Offered The Mount Cain Ski Area is managed and operated by the Mount Cain Alpine Park Society, a registered nonprofit society, which operates largely on volunteer labour and donated resources through an agreement with the Regional District of Mount Waddington. The ski area is operational on weekends and holidays from December through to early April depending on snow accumulations. Situated on the north end of Vancouver Island, Mount Cain offers a unique experience to skiers, snowboarders and backcountry explorers. Mt. Cain offers visitors a rustic, community focused ski experience set in the stunning viewscapes of Vancouver Island. The ski area primarily draws clientele from communities in northern and central Vancouver Island although it is becoming more widely known with ski enthusiasts for the unique ski experience it offers. It is Vancouver Island's only community owned and operated ski-hill and offers the following winter recreation opportunities: 18 patrolled ski runs from novice to expert; food and beverages available on the main floor of the day lodge; hostel style accommodations on the upper levels of the day lodge; two rental cabins and a group accommodations building ski/board/snowshoe equipment rentals, sales and service offered at the ski shop; ski school offers skiing and snowboarding lessons and packages with equipment rental for beginners; and, although it is not encouraged due to avalanche and terrain hazards, access to backcountry skiing and boarding opportunities outside of the patrolled Controlled Recreation Area are very popular. 1.2 Base Operation and Existing Improvements Existing improvements in the ski hill s base area include: a 3-storey lodge housing a ski shop, restaurant and hostel style accommodation for up to 18 people ( Base Area Lease); 52 developed cabins managed by MCAPS ( License of Occupation); 2 rental cabins (located immediately outside of the Base Area Lease); original works shop ( Base Area Lease); new maintenance shop (located partially outside of the Base Area Lease); new works shop (located partially outside of the Base Area Lease); day visitor parking lot ( Base Area Lease); RV/overnight parking lot (located partially outside of the Base Area Lease); lift ticket office ( Base Area Lease); a new staff, hostel-style accommodations building ( Base Area Lease); and a washrooms building ( Base Area Lease). Some existing improvements have been located on, or immediately outside of, the base lease tenure area boundary as noted in the summary above. Those include the two existing rental lodges, the overnight/rv parking and the new maintenance building. This was identified during a preliminary mapping review `1done by RDB and was in part why RDB has required a more comprehensive Master Plan Update process to address a number of tenure irregularities. The cabin colony at Mount Cain was developed in order to establish on-site accommodation to support the visitation, operation, security and management of the ski area facilities. Due to the remote location of the ski area and the travel time required to access it from communities in the North Island, on-site recreation residential accommodation was needed. 52 privately owned ski-in/ski-out cabins currently exist at Mt. Cain and are classified as recreational residential or season residence. The cabins are on a shared License of Occupation tenure. The cabins are accessed by two branch roads which commence from the main ski hill access road, downhill from the day-visitor parking. The cabins are privately owned and managed by an 6 P a g e

7 agreement between MCAPS and the cabin owners. MCAPS also administers license fee payments and compliance and enforcement of the Sewage Treatment Services Agreement. MCAPS has recently finished the construction of a new staff, hostel style accommodation building and ticket/administration building within the base lease tenure area. These new buildings replace several old buildings which were becoming difficult to maintain and unsuitable for accommodation. A new machine maintenance building with a concrete floor was also constructed to support ski area operations and to provide improved catchment for heavy duty maintenance activities. Further base area improvements include the removal of several derelict buildings and abandoned personal property from the overnight parking area. A sewage holding tank has been installed for the collection of waste from overnight visitors staying in the RV parking area. RDB has advised MCAPS and RDMW that the base area lease tenure would need to be expanded to incorporate these recreational infrastructure improvements and that boundary locations will need to be confirmed prior to construction of new base area facilities. 1.3 Mountain Operation and Improvements Existing improvements in the ski hill s Mountain Area include: 18 runs/trails ( Trails License of Occupation); 2 T-Bar lift systems and a Beginner's Handle Tow ( Lifts Statutory Right-of-Way) Nordic skiing/snowshoe trails (untenured and outside of CRA) Preliminary mapping of ski area tenures and existing improvements done by RDB in 2007 identified a discrepancy between the western portion of the Statutory Right-of-Way and the actual T-bar/lift location. RDB has advised MCAPS and RDMW that the location of SRW will need to be reconciled with the actual location of the lift. 1.4 Existing Tenures Table 1 Tenure Summary File No. Tenure Type Purpose Area (ha) Tenure Holder License Cabin Sites MCAPS Statutory Right of Way Ski lifts RDMW License Ski trails RDMW Lease Day lodge, parking lift & equipment maintenance 2.18 RDMW Operating Agreement Framework for all tenures within Controlled Recreation Area (CRA), includes license of occupation RDMW * See Figure 2: Land Act Interests Map in Appendix A. 1.5 Access Mt. Cain is located in Northern Vancouver Island, approximately 75 km north-west of Sayward and half-way between Campbell River and Port McNeill. Mt. Cain is accessed from Highway 19 via Western Forest Products (WFP) Road Permit R MCAPS currently holds a road use agreement with WFP to allow for public access and maintenance of the ski hill access. The initial segment of road access from the junction of Highway 19 is also shared access with Schoen Lake Park. The Namgis First Nation currently participates in the operation and maintenance of the park. Beyond the gravel road junction to Schoen Lake, the forest road access to Mt. Cain is maintained by the mountain's maintenance department and assisted by WFP which holds Tree Farm License 37, situated immediately adjacent to the Mt. Cain Controlled Recreation Area. While WFP is supportive of the ski area and 7 P a g e

8 provides ski area access through a road use and maintenance agreement with MCAPS, it is limited in its ability to maintain the road in an operational state outside of active forestry operations windows. WFP has committed to work with MCAPS and the RDMW to ensure that public access to Mt. Cain is maintained. MCAPS has advised RDB that Mt. Cain is the only community ski area in the province which does not receive assistance from Provincial or Local Government to maintain its road access. A significant amount of the ski area s operational budget is dedicated to maintain road access, primarily snow clearing, during winter months. MCAPS and RDMW would like to pursue some form of assistance from The Province or Local Government to maintain its road access. RDB has had preliminary discussions with the MOTI about the possibility of assisting the ski area with road access maintenance. Several issues prevent MOTI from providing road maintenance assistance including: The Mt. Cain road access is a forest road permit under WFP Tree Farm License and not a public road. The Mt. Cain road access is of a forest road standard which does not comply with public road standards. MOTI s road service contractor is not insured to operate on TFL roads. MOTI does not currently have the resources to undertake additional road maintenance for the ski area. RDB preliminary mapping identified an unclassified/non-status section of the Mt. Cain access road between the point of termination of WFP s road permit and the CRA boundary. The section of road is approximately 900m long, is located within WFP s TFL and is maintained consistent with the terms and conditions of the road use agreement. In October 2009, MCAPS facilitated the grading of the initial 3.5 kilometers of the Western Forest Products forest road permit which was heavily pot-holed and posed an immediate hazard to road traffic. Continued road improvements and maintenance are anticipated and expected to represent a substantial portion of MCAPS s annual operating budget. 1.6 Servicing Water: The Mt. Cain Day Lodge Restaurant and base area facilities are currently supplied by Ultra Violet treated water which is derived from a water reservoir located adjacent to the bunny hill. The reservoir is supplied by overland sheet flow from the ski area catchment and does not require a water license, as confirmed with the Ministry of Environment, Water Stewardship Division. While the existing system has met day lodge demand, it is recognized that additional water supply will be required to facilitate the proposed facility improvements in the base area. The Drinking Water System Emergency Response Plan has been developed to ensure that the base area water supply meets the applicable water standards as administered by Vancouver Island Health Authority. See Appendix C for the Mt. Cain Alpine Park Lodge Drinking Water System Emergency Response Plan. Water for the cabins is brought in by the cabin occupants or it is attained from an existing standpipe located on the hill. The water supplied by the standpipe is not treated and intended for washing purposes only. This is indicated by signage posted at the standpipe location. Sewer: Until recently, pit privies were the only means of dealing with septic waste at the ski area. Several years ago, Vancouver Island Health Authority (VIHA) requested that pit privies be phased out. Since then, composting toilets were installed in a new public washroom building by the day lodge and holding tanks were installed by the cabin owners and for the overnight parking area. While the composting system is adequate for the day lodge and current skier visitation, it is recognized that upgrades will be necessary if the ski area facility is expanded and skier visits grow. VIHA has issued an order requiring cabin owners to install 4500-litre holding tanks for each cabin. MCAPS has confirmed that all of the cabins have complied with the VIHA order. All private cabins owners are now required to be a party to the Cabin Area Sewage Treatment Services Agreement, completed by MCAPS subsequent to the VIHA holding tank order. The Sewage Treatment Services Agreement requires all cabin 8 P a g e

9 owners to ensure that their tanks are pumped out yearly and the waste hauled away. Under the agreement, a local sewage hauler disposes of the waste at the RDMW Hyde Creek Treatment Facility. MCAPS indicates a new agreement needs to be signed with the hauler and that the existing outhouses need to be decommissioned. Electrical: Electricity is currently produced by a large diesel generator located in the maintenance shop in the base area. It is backed up by another generator in case of failure. Electricity has been routed to the lower lift and will be routed to the upper lift in the future. No electrical power is supplied to the recreational residential cabins and there are no plans to connect Mt. Cain to hydro due to the projected cost of constructing a transmission line. 1.7 Ski Area Capacity and Skier Visits Mt. Cain draws skiers and boarders primarily from northern Vancouver Island including the communities of Port McNeil, Port Hardy, Woss, Zeballos, Tahsis, Sayward, Campbell River and Courtenay. Mount Cain has maintained a steady visitation of approximately 7,000 to 8,000 annual skier visits for the last 9 seasons. In , however, insufficient snow accumulations prevented the ski area from operating which caused significant financial pressure on MCAPS. While visitation has remained flat, Mt. Cain is increasingly becoming known for its unique ski opportunities and family oriented experience. It is expected that skier visits will grow due to the market niche Mt. Cain occupies and as more accommodation becomes available. Existing Capacity Estimation: The two existing T-bar lifts and handle tow at Mount Cain have a combined skier/boarder carrying capacity of approximately 1500 skiers per hour. The ski terrain and lifts combined have a comfortable carrying capacity of approximately 700 skiers per day. While lifts and terrain could accommodate up to 20,000 visits per year, base area facilities, including parking and day lodge, are currently at capacity and will constrain significant future skier visit growth. Skier Visits: YEAR CALCULATED VISITS* , , , , (Ski area did not open due to insufficient snow) , , , , ,000 *Calculated visits based upon ticket sales plus season-pass visit formula These numbers are also reflective of the number of operating days per year. For example there were 50 operating days while there were only 38. Nordic Ski/Snowshoe trail visitation and capacity have not been included within these visitation figures above because the trails are untenured, unmanaged and for the most part, outside of the Controlled Recreation Area. 9 P a g e

10 Section 2: Overview of Proposed Expansion 2.1 New Operating Agreement and Future Expansion Area The updated Master Plan serves to outline the short and long term goals of the resort, and if approved will allow the ski hill to move towards a new Operating Agreement with the Province. A new Operating Agreement (OA) will provide for the following: 30 year tenure term, which was previously 20 years The ability for the resort to conduct recreation activities year round on the land, rather than being restricted to the winter ski season Provide the resort operator with the ability to directly authorize other commercial recreation uses consistent with the objectives of the Resort Master Plan, which were previously tenured independently. Updated language and improved clarity of rights, limitations, conditions, etc. conveyed through the agreement. While no significant expansion of mountain, base or residential areas are being contemplated, MCAPS and RDMW would like to allow for the modest expansion of recreational and residential improvements to further ensure the sustainability of the Mt. Cain Ski Area. Small area expansions are required for base area improvements (RV parking area, new maintenance shop, and rental lodges), recreational infrastructure (Nordic Ski Trails) and to reconcile the Controlled Recreation Area with the area deleted from the Provincial Forest in See Appendix A, Figure 2 - Land Act Interests Map. The Mt. Cain Alpine Park Society Five Year Ski Hill Development Plan and the Mount Cain Alpine Recreation Area Development Master Plan (May 23, 2008) identify proposed improvements and changes for Mt. Cain for the five year period from 2009 to 2013 and for longer term changes which include an expanded, all-season regional park concept. See those documents for detailed information related to the proposed five year improvements and the long term vision of Mt Cain. MCAPS has advised that the proposed five year improvements are contingent on funding opportunities, available resources, further detailed planning and the successful completion of the master plan update process and associated tenure revisions. Due to the uncertainty of the timing and funding of improvements, RDB recognizes that MCAPS s and RDMW s prioritization of improvements will be based on: Address safety issues; Address immediate environmental priorities; Compliance with law, regulation, and agreements; Address operational requirements; Provide additional skier capacity and accommodation. Existing and Proposed Controlled Recreation Area (CRA): The existing Controlled Recreation Area (CRA) is ha and is located within a Provincial Forest Deletion Area of approximately 168 ha. The CRA was established with the finalization of the existing Operating Agreement in 1989 and is not consistent with the Provincial Forest Deletion Area, established previously by Order in Council in RDB would like to expand the CRA by approximately 40ha within the Provincial Forest Deletion Area in order to allow for the inclusion of the existing and proposed improvements, including existing Nordic ski trails, the cabin development area, Mistaken Lake and other base area facilities. The proposed CRA expansion will also allow for future base area expansion if required. See Appendix A, Figure 5 Proposed Land Act Tenure Revisions Map. 2.2 Base Improvements A number of base area improvements are being proposed for the ski area to facilitate improved skier experience, increased visitation and improved maintenance and operating facilities. Additional parking, 10 P a g e

11 maintenance/operations areas, staff and rental accommodation and skier day services will be required. Water, sewer and further electrical upgrades will also be necessary to support increased visitation. Ski Shop and Day Lodge: MCAPS has advised that they intend to prepare a plan to relocate and upgrade the ski shop and day lodge in 2011 with construction targeted for 2012/2013. The relocation of the ski shop and day lodge will be within the base area lease tenure. RV Park: MCAPS has advised that they intend to develop and implement an RV Park Management Plan in 2010 to ensure the overnight/rv parking area is maintained and improved in a manner which further supports the growth of visitation at the ski area and ensures that health, safety and environmental requirements are satisfied. The base area lease will be expanded to include the entire overnight parking area. Day Visitor Parking: Current day visitor parking capacity is estimated to be approximately 100 vehicles and occupies an area of approximately 0.8ha within the base area lease tenure. It has been noted that parking does fill up at times and the RV/overnight parking area is utilized as overflow for day visitors. MCAPS has identified the need to increase parking capacity for both day use and overnight visitors to address peak periods when they are over capacity. MCAPS will undertake a parking upgrade and road realignment plan in 2010 and will commence upgrades/plan implementation in 2011/2012. Day use parking improvements may be located west of the existing day use parking lot along the Mt. Cain access road as identified within the D.R. Matthews Mt. Cain Ski Area Conceptual Master Plan (2000). Final parking improvements will be proposed once the plan is completed. RDB notes that parking relocation and upgrades may necessitate further expansion of the RDMW base area lease tenure. Cabin Colony: MCAPS has requested the approval of additional cabin sites in the existing cabin area and has confirmed with Vancouver Island Health Authority that they are agreeable to having additional cabins under the Sewage Treatment Services Agreement. Due to the remote location of Mt. Cain, it is recognized that the availability of on-mountain accommodation supports skier visits, revenue generation and increases MCAPS volunteer resources which support ski area operations. RDB has advised MCAPS and RDMW that it will consider a detailed MCAPS/RDMW proposal for an additional 5 cabins within the cabin area after a Master Plan and Operating Agreement decision has been made. Namgis Area of Interest RDB has entered into a Memorandum of Understanding with the Namgis First Nation which will allow for a Namgis Community Use Nominal Rent Tenure (NRT) of approximately 1.74 ha. This tenure is recognizes Namgis interests including recreation, tourism and land development at Mt. Cain and will facilitate the Namgis development of up to five community use cabins on the NRT. 2.3 Mountain Improvements Several mountain improvements are planned for Mt. Cain which will improve the skiing experience and safety of the ski area. The proposed Mountain Improvements include: bunny hill upgrade and relocation; cross country ski trails; Lift L3 bottom terminal and traverse trail relocation. Bunny Hill Upgrade and Relocation: The bunny hill upgrade and relocation is required to improve the skiing experience and safety of the bunny hill for beginner and novice skiers and boarders. MCAPS will undertake an engineering report and relocation plan in 2011 to facilitate the relocation. The implementation of this plan is targeted for P a g e

12 Nordic Trails: MCAPS wishes to undertake a cross-country (Nordic) ski trail plan for Mt. Cain to improve the Nordic experience and increase recreational opportunities available at the ski area. Trails currently exist in the Mistaken Lake area, uphill of the cabin colony and in the adjacent West Bowl however these trails are not actively managed or maintained by MCAPS due to limited resources and their untenured status. The trails have existed for approximately thirty years and are heavily used by Nordic skiers, backcountry enthusiasts and snowshoers. The Nordic trails within the Mistaken Lake area have been identified to be included within the expanded Controlled Recreation Area. MCAPS has targeted 2011 for the completion of the Nordic plan and will commence implementation afterwards depending on available resources and the improvements identified within the plan. Lift L3 and Traverse Trail Relocation: MCAPS has identified the need to lower the bottom terminal of Lift L3, the uphill/eastern T-bar, to improve skier/boarder access. The bottom terminal of Lift L3 is currently located too high in elevation which does not allow for a sufficiently steep grade to move skiers and boarders into the loading area. The downhill relocation of the bottom lift terminal will facilitate the relocation and steepening of the traverse trail to improve skier and boarder movement into the lift loading area. 2.4 Proposed Tenure Revisions Listed in order of priority of execution, the proposed tenure revisions include: Replacement of the existing Operating Agreement (OA) for an extended 30 year term; o Includes the issuance of a blanket Licence of Occupation for recreational infrastructure within Controlled Recreation Area (CRA) as included within the new OA template; o Other house-keeping tenure boundary revisions required to adjust the CRA boundary to incorporate existing improvements and to be consistent with the Provincial Forest deletion area. Conversion of an existing License of Occupation for recreational cabin purposes to 52 individual recreational cabin Leases. Issuance of a Nominal Rent Tenure within the Namgis Parcel of Interest to the Namgis First Nation for Community Use and cabin development. Expansion of the Base Area Lease for recreational infrastructure improvements including maintenance facility, RV parking and sani-dump facility, day visitor parking, day lodge improvements; Consideration of up to 5 additional cabin sites (Lease lots). Modification of existing Statutory Right-of-Way to lengthen upper lift area to accommodate proposed extension. Establishment of a Section 16 Map Reserve over Namgis First Nation Area of Interest. See Appendix A, Figure 5 Proposed Land Act Tenure Revisions Map. Table 1 Summary of Proposed Tenure Revisions (See Figure 5 Proposed Land Act Tenure Revisions Map) File No. Tenure Type Area (ha) Estimated Revised or New Area Proposed Revision to Tenure Operating Agreement (ha) Conversion of existing OA to new OA template. Includes blanket licence for ski area infrastructure/access, 30 year term and year round authority P a g e Licence to Lease Controlled Recreation Area to be expanded within Provincial Forest Deletion Area to include existing improvements (ie. Cabins, Nordic ski/snowshoe trails) and Mistaken Lake Conversion to individual Lease tenures;

13 TBD Conversion Nominal Rent License Proposed house-keeping boundary revision NA 1.74 For the purpose of Namgis First Nation Community Use and development of up to 5 community use cabins Lease Modification TBD Section 16 Map Reserve Expansion to include existing rental cabins by lake, new maintenance shop, parking and road access improvements, day lodge improvements, water, sewer and electrical upgrades. NA 9.47 Map Reserve will be placed over Controlled Recreation Area expansion area south of main access road and west of Mistaken Lake, consistent with Namgis Area of Interest. Map Reserve will be for the purpose of Ski Area Planning and recognition of First Nation interests. 2.5 Access Upgrades Improvement of road access to Mt. Cain will further support the sustainability of Mt. Cain as a community ski area by enhancing the safety and ease of access for the visiting public and MCAPS members. Access upgrades will need to done in cooperation with Western Forest Products, the current road permit holder, and other stakeholders including RDMW, the Ministry of Transportation and Infrastructure (MOTI), BC Parks and the Namgis First Nation. RDB preliminary mapping identified an unclassified/non-status section of the Mt. Cain access road between the point of termination of WFP s road permit and the CRA boundary. The section of road is approximately 900m long, is located within WFP s TFL and is maintained consistent with the terms and conditions of the road use agreement. A new tenure may be required to legalize this section however, it is outside the jurisdiction of RDB and may require application to MNRO, West Coast Region. WFP wishes to maintain its road permit to ensure access to future harvest opportunities and silviculture sites. WFP s maintenance and upgrade of the Mt. Cain access road will be dependent on the frequency and nature of their operations. WFP currently supports the Mt. Cain Ski Area by providing access and maintenance privileges through a Road Use Agreement. WFP benefits by having MCAPS members monitor and maintain the road access within their Tree Farm License. MCAPS has recently undertaken the grading of initial sections of the road access which had become seriously deteriorated (potholed) in recent years in advance of the fall and winter weather. Winter and snow clearing maintenance operations, which represents a significant portion of the MCAPS operating budget, will commence shortly. MCAPS has advised that they will continue to seek financial and resource assistance from public agencies to alleviate the financial impact of their road maintenance operation. Winter access is currently considered sufficient based on the current winter maintenance program. While it is likely there will not be any significant programmed road improvements other than current road maintenance completed in the near future. It is nonetheless, with or without improved or expanded facilities, a priority. Upgrades will be essential to the proposed expansion of Mt. Cain as a four-season recreational area. While winter road access and maintenance can be readily and efficiently achieved with a compacted snow base, spring rains and snow melt hamper maintenance efforts in the spring, summer and fall. This could be exacerbated by increased road traffic due to increased visitation. To support future growth in visitation, a summer road maintenance program and winter road design will be undertaken by MCAPS. As a future initial step MCAPS and the RDMW should cost-share in the preparation of a road and traffic analysis that identifies road conditions, priorities for immediate, short and long term improvements and costs to meet current use needs for Mt. Cain. Subsequent to completion of the road and traffic analysis, MCAPS and the RDMW should establish their priorities and seek and obtain funding to implement the priorities of the study. 13 P a g e

14 Construction of road improvements should take advantage of local experience and provide employment to area residents. MCAPS will explore possible synergies to improve road access to recreation areas with the Namgis First Nation given the shared access with Schoen Lake Park and Mt. Cain. 2.6 Servicing Water, Sewer and Electrical: MCAPS has identified the need for the improvement of water and sewer system upgrades for the Day Lodge and other base area improvements in order to ensure it meets Health Standards as advised by the Vancouver Island Health Authority (VIHA) and the Ministry of Environment. MCAPS undertook Water and Sewer Upgrade planning in 2010 and will commence upgrades in 2011 in conjunction with other base area improvements, with completion targeted for Recent and planned electrical upgrades completed in the base area will facilitate future water and sewer system and other operational improvements. 2.7 Projected Capacity and Skier Visits While visitation has remained relatively unchanged over the past decade, approximately 7000 to skier visits per year, RDB expects increased visitation in the future. Mt. Cain is increasingly becoming known for its unique ski opportunities and rustic, family-oriented experience which is an alternative to larger, resort-style ski areas. It is expected that Mt. Cain will increase annual skier visits within this market niche and the provision of increased accommodation availability and utility infrastructure will support its continued growth. The Master Plan Update includes infrastructure improvements which will facilitate increased recreational opportunities, improved skier experience and moderate growth in ski area visits, utilizing existing mountain carrying capacity. 14 P a g e

15 2.8 MCAPS Five Year Development Plan Focus Accommodation, Public Develop plan for rental cabins Build new rental cabins Accommodation, Staff Include in new lodge plans Bunny Hill Engineering report for bunny hill upgrade/relocation Begin bunny hill relocation and upgrade Cross Country Ski Develop a cross Trails Electrical Station Human Resources Management Lifts Lodge L3 Lift Station Maintenance Building Park Boundaries Continue with overhaul of the electrical station and power generator Continue Capital upgrade T-bars, rope tow, sheaves assembly & spring boxes. Replace shack at L4 Seek CRA boundary extension to include Mistaken Lake & West Bowl Continue with overhaul of the electrical station and power generator Create a plan for human resources management and acknowledgement Develop plan for lodge update/replacement Engineering report done for lowering L3 country trail plan Complete overhaul of the electrical station and power generator Engineering done in order to increase lift capacity Implement lowering of L3 Increase lift capacity and add Ts Develop lodge replacement plan Construct new lodge

16 Parking Lot Plan parking lot upgrade Upgrade of parking lot completed. Road Develop plan for road upgrade Begin road upgrade Continue with road upgrade Complete road upgrade Road Grader/14G Grader upgrade Grader upgrade Grader upgrade New Grader Grader upgrade Groomers Maintenance Maintenance Maintenance Maintenance New Groomer RV Park Develop and implement RV park management plan Sewage System Develop Sewage System upgrade plan and start upgrade Continue with sewage system upgrade Continue with sewage system upgrade Complete sewage system upgrade Ski Shop Ticket Booth Water System Master Development Plan Equipment Purchases Ski Patrol Update DRAFT Master Development Plan Plan for First Aid Upgrades include in sewer and water plans Plan ski shop relocation/upgrade Lodge plan/separate building Plan for water system upgrade Review and replace Plan Purchase new Purchase new snowmobiles snowmobiles Upgrades to ski patrol Upgrades to ski patrol Upgrades to ski patrol Upgrades to ski patrol

17 2.9 Economic Benefits Mount Cain currently employs approximately seasonal staff and will require additional staff as skier and winter recreation visits grow. Two full time and four extended term seasonal jobs were also involved in the recent construction of staff accommodations. Other economic benefits related to the operation of Mt. Cain include: construction & trades jobs; benefits to local tourism operators, B&Bs, restaurants, sporting goods retail, rental and supply, gas stations, motels, etc; potential alignment with Namgis First Nation Tourism Strategy Objectives Opportunities and Constraints The physical aspects of Mount Cain offer many opportunities for recreational development and expansion. A four-season, regional resort concept has been developed by D.R. Matthews in two conceptual master plans completed in 1990 and 2000, based on the Commercial Alpine Ski Policy. While these master plans identified the site s substantial capacity as a regional resort, neither was formally adopted by the RDMW and Mt. Cain continues to operate based on a community, family-oriented ski area concept within the same historical ski area. Both the Regional District of Mount Waddington and the Mt. Cain Alpine Park Society wish to expand recreational opportunities in and around the ski area while maintaining the community/family orientation of the ski area. Expansion of the regional park designation area north to Mt. Hapush and the West Bowl would create a regional four-season recreation area that would to include skiing, snowshoeing and other winter activities and hiking and climbing during spring, summer and fall. It would also create a year round presence at the ski hill which will offer improved security and the ability to improve the management and protection of sensitive alpine ecosystems. The proposed expansion would help accommodate interest in wilderness recreation, a growing component of the tourism sector on the north Island. The potential will be created to include First Nations opportunities on Mt. Cain, improved access, increased number of recreational opportunities and overall improved management of a larger recreational area. POTENTIAL EXPANDED WINTER OPERATIONS: Nordic skiing Expanded skiing terrain in adjacent bowls Expanded snowshoeing terrain Skiing/Boarding Terrain Park POTENTIAL SUMMER OPERATIONS: Hiking Rock climbing Cabin rentals Mount Cain s short-term skier visit growth is currently limited by operational resources, available utility services and ski area infrastructure. MCAPS is making utility infrastructure improvements opportunistically as funding is available to allow for future growth and development at the ski hill. The ski area has an annual mountain/skier capacity in excess of 20,000 skier visits based on 500 skier visits per day over a 40 day operating season. It is recognized that the existing parking and day lodge facilities in the base area is at capacity at the current average visitation rate of approximately 200 skiers/boarders per day. As Mt. Cain is operated largely on a volunteer basis by MCAPS, the operational capacity of the ski area is limited to MCAPS resources. At this time, MCAPS does not have sufficient resources to expand alpine ski terrain and the Controlled Recreation Area into adjacent bowls. The Master Plan Update does however include base area tenure expansion which will consider future recreational infrastructure expansion. 17 P a g e

18 RDB has advised that for the purpose of this master plan review, RDB will limit its review to improvements and revisions specific to the lift-based ski area. Further expansion of lift based skiing will require a more detailed and comprehensive expansion master plan. An application for the proposed park establishment in the adjacent areas would be separate from ski area tenure revisions and under the jurisdiction of the Integrated Land Management Bureau. RDB commits to participating in a review of a Park Expansion Plan if and when one is prepared to ensure that the management and administration of ski area tenures is considered. 18 P a g e

19 3.1 Fish Values Section 3: Environmental & Cultural Values No fishery values have been identified within or adjacent to the Mt. Cain Controlled Recreation Area due to the presence of terrain and gradient barriers to fish migration. 3.2 Wildlife Values In response to the Master Plan referral, RDB received information and feedback related to existing wildlife values and/or management issues for the Mt. Cain Ski Area from the Ministry of Environment, Fish and Wildlife Branch. MOE provided specific feedback related to access, wildlife species, fish, and water values/issues which will provide guidance and inform operational activities for ski area managers and staff. 3.3 Water Values MCAPS will work with the Ministry of Environment, RDB and the Vancouver Island Health Authority to address water stewardship and health standards requirements in the development of their Water Supply Upgrade Plan. RDB notes that the Mt. Cain Ski Area does not conflict with any designated community watersheds, points of diversion, water licensed works, water reserves or registered well sites. MOE, Department of Fisheries and Oceans staff and the Namgis First Nation provided detailed feedback related to environmental values. For detailed information, see the Mt. Cain Master Plan Issues Tracking Sheet. 3.4 Environmental Values RDB has noted the following environmental values within the Mt. Cain Controlled Recreation Area and surrounding areas. Mistaken Lake Headwaters/catchment area Alpine ecosystem By way of the Master Plan referral, RDB requests information from the Ministry of Environment which identifies specific environmental and wildlife values and management issues which may need to be addressed within the ongoing management of the ski area. MOE, Department of Fisheries and Oceans staff and the Namgis First Nation provided detailed feedback related to environmental values. For detailed information, see the Mt. Cain Master Plan Issues Tracking Sheet. 3.5 First Nations RDB is aware that First Nations communities on northern Vancouver Island contribute significantly to skier visits at Mt. Cain and benefit from the recreational activities offered at the ski hill. RDB is supportive of increased participation of First Nations in the development, operation and recreation opportunities available at Mt. Cain. Namgis First Nation: Mt. Cain is located in the Namgis First Nation Traditional Territory which includes the Nimpkish River System in northern Vancouver Island. The Namgis First Nation belongs to a broader cultural-linguistic group called the Kwakwaka wakw who occupied islands and inland areas proximal to Port McNeill, BC at the time of European contact. The Mt. Cain Controlled Recreation Area is located in the southern, inland portion of the Namgis Traditional Territory. 19 P a g e

20 RDB engaged the Namgis First Nation in consultation discussions to determine the scope and nature of their interests in Mt. Cain Ski Area. RDB learned that the Namgis have strong interests in enhanced participation in recreational, tourism and land development opportunities at Mt. Cain. In July 2010, RDB and the Namgis First Nation entered into a Memorandum of Understanding which will support the enhanced participation of the Namgis in recreational, development and tourism opportunities at Mt. Cain. The MOU is an over-arching agreement regarding a 9.47 hectare parcel of land located adjacent to the existing base lease area which has been identified as a parcel of interest in on-going Treaty negotiations. The MOU will provide for the following: Inclusion of the parcel in the Controlled Recreation Area; Recognition of Namgis interests in the parcel area; Development of the parcel will be done by the Namgis in accordance with a Resort Development Branch-led Master Planning process which will include collaboration with MCAPS, the ski area operator, and the RDMW, the Operating Agreement holder; The issuance of a Nominal Rent Tenure within a sub-area of the Namgis Parcel of Interest which will allow for the development of up to five community use cabins and related infrastructure; The establishment of a Section 16 Map Reserve over the remaining Namgis Parcel of Interest for the purpose of Ski Area Planning and First Nations Interests. Nanwakols Council/Tlowitsis Tribe: The Tlowitsis Tribe s consultative area is located on the opposite side of the mountain from the Mt. Cain Ski Area and encompasses the adjacent watershed to the east and portions of the West Bowl. While there is a very small overlap of the uppermost elevations of the ski area (near the height of land) and the Tlowitsis consultative area, the majority of the Mt. Cain Controlled Recreation Area and the entirety of the base area are outside of the consultative area. RDB engaged the Tlowitsis Tribe/Nanwakols Council in preliminary consultation discussions in Master Plan Update information was provided to Kathy Campbell, Referrals Office Project Manager for their review and comment. Nanwakolas primary concern is the protection of archaeological information. RDB will ensure that further archaeological survey/assessment work is done prior to any new development to ensure that archaeological values are protected. While the focus of the Mt. Cain Master Plan Update Review is specific to the proposed changes and improvements within the ski area, RDB recognizes that the broader regional district park concept discussed in this Mt. Cain Master Plan Update represents a substantial overlap with the Tlowitsis Consultative Area and will necessitate consultation with the Tlowitsis Tribe. Kwakiutl Indian Band: Mount Cain is situated within the Kwakiutal Indian Band s Traditional Use Study Area. No specific sites have been identified within the ski area. The closest site was noted to be 4.8 km away from the Mt. Cain Ski Area. RDB has confirmed that the Mt. Cain Ski Area is outside of the Kwatiutl Band s consultative area and that their interests will not be affected by the proposed changes in the Mt. Cain Master Plan Update. 20 P a g e

21 4.1 Mineral Tenure Section 4: Overlap With Existing Use There are no existing mineral tenures which overlap the Mt. Cain Ski Area. A Conditional Staking Reserve ( ) was established to ensure that the ski area is not impacted by future and mineral extraction activities. Figure 3: Forestry and Mineral Interests Map in Appendix A. 4.2 Timber Tenure & Forest Use The Mount Cain Controlled Recreation Area (CRA) was deleted from the Tsitika Provincial Forest in The CRA was designated under the Resort Timber Administration Act (RTAA) in 2008, which transferred the authority to administer timber within the Mt. Cain CRA to the Ministry of Tourism, Culture and the Arts (RDB). See Figure 3: Forestry and Mineral Interests Map in Appendix A. The intent of transferring the timber administration to RDB from the Ministry of Forest and Range was to provide a one window approach for ski area developments within CRAs, in order to streamline and integrate provincial review and application processes. Also, the transfer recognized that any land use decision that may be made in relation to the CRA is consistent with the ski area development purpose. Mt. Cain is situated within the Mountain Hemlock Biogeoclimatic Zone. Timber species include Mountain Hemlock, Yellow Cedar, and Balsam Fir and are estimated to be at least 100 to 200 years old. No forest health issues were noted on site. No significant expansion of the Mount Cain Ski Area is being proposed at this time. Should timber harvesting be required Mt Cain will apply for a License to Cut through the Resort Development Branch Timber Section of RDB. Any tree removal will be done in accordance with the Resort Timber Administration Act, Forest Act, Forest and Range Practices Act and regulations as well as with all land and forest tenure requirements. Tree Farm License 37, held by Western Forest Products, is located immediately adjacent to the Mt. Cain Ski Area and the ski hill s road access is via WFP s TFL road permit. MCAPS commits to maintain regular communications with WFP regarding ski area and TFL operations, planned road maintenance and future upgrades to ensure that there are no logistical conflicts and safety for both the public and workers is maintained. There are no existing range tenures that overlap the CRA. 4.3 Land Use Planning, Local or Regional Zoning Requirements Mount Cain is within the Upper Nimpkish Land Unit area that is covered by the Vancouver Island Land Use Plan (VISLUP) The VILUP was completed in 1994, and followed by a number of Sustainable Resource Management Plans (SRMPs) and the Vancouver Island Summary Land Use Plan, intended to address VILUP strategies and targets on an areaspecific basis, and provide detailed objectives and strategies for the management of the Vancouver Island s resources and the maintenance of environmental values. The Mt. Cain Ski Area is located in both the Woss- Vernon General Management Area, RMZ #13 and to a lesser extent, the Tsitika General Management Area, RMZ # P a g e

22 Mt. Cain is located within Rural Zone A-1. Refer to Appendix D for Regional District of Mount Waddington zoning requirements. 4.4 Commercial Recreation Tenure, Trapline Holder & Guide Outfitter Territories There are no known commercial recreation tenures in the Mount Cain Ski Area. The CRA is overlapped with two guide outfitter area: Guide Certificate # registered to Glen Venus Guide Certificate # registered to David Fyfe The CRA is overlapped by Trapline holder TR0110T609 area: See Figure 4: Wildlife Interests Map in Appendix A. 4.5 Public Recreational Use The Mt. Cain CRA is used for public recreation including hiking, berry picking and rock climbing in summer months and alpine lift-based skiing, backcountry skiing, Nordic skiing and snowshoeing in the winter months. Although it is not encouraged due to avalanche danger, backcountry enthusiasts, including skiers, snowboarders and snowshoers, access backcountry opportunities in winter months from Mt. Cain. Motorized recreation is actively discouraged at Mt. Cain due to the inherent conflicts between non-motorized and motorized recreation. Public access and recreation may need to be controlled by signage, information booth and education programs in the future to ensure that worker and visitor safety is maintained. 22 P a g e

23 23 P a g e Appendix A Mapping

24 Figure 1 Location Map

25 Figure 2 Land Act Interests Map

26 Figure 3 Forestry and Mineral Interests Map

27 Figure 4 - Wildlife Interests Map

28 Figure 5 Proposed Land Act Tenure Revisions Map

29 Appendix B - Safety Management Plan MOUNT CAIN SKI AREA SAFETY MANAGEMENT PLAN SCOPE OF RESPONSIBILITY Lifts Applicable: Handle Tow Lower T-Bar Upper T-Bar Structure and Responsibilities of the Lift Maintenance Department A. Operations Director - Lifts o Overall responsibility for lift maintenance o Directs lift maintenance staff in their duties B. Lift Maintenance Staff o Performs routine lift maintenance tasks SAFETY POLICY Mount Cain is cognizant of the need to promote and instill safe work practices throughout its operation. Operations Director - Lifts interacts on a regular basis with lift manufacturer, BC Safety Authority, local CSPS, CWSAA and our insurance provider. Z Passenger Ropeways The Z-98 code book is issued to Lift Maintenance and supervisors. (Work chair guidelines follow standards as outlined in the Z-98) Mountain Operations Manual Is issued to all personnel working in or around lifts and includes details of lift evacuation procedures, lift operating procedures, rigging procedures and emergency protocols. TRAINING & SUPERVISION Required Training: Operations Director Lifts and Lift Supervisor are the only persons responsible for supervision and/or training of any lift maintenance personnel. Lift Supervisor has completed regulations and standards training acceptable to the Provincial Safety Manager for Surface Lift and Fixed-Grip passenger ropeways through Selkirk College. Any person supervising and training lift operators have been certified through Selkirk College s Train the Trainer program. Training records for each employee are maintained by our Administration office. 29 P a g e

30 All personnel supervising employees have a copy of the Z98 and are issued updates as applicable. They also have input into the design and content of the Mountain Operations manual which is issued to all employees involved in working with or around lifts. Lift Supervisor has overall responsibility for training lift maintenance personnel and may demonstrate routine tasks to lift personnel. EXTERNAL CONTRACTORS AND AUTHORITIES Contractors and sub-contractors working on lifts at Mount Cain are organized through lift manufacturer or are restricted to well-known industry affiliations (Inter-Mountain Testing Ltd for NDT testing, etc). Any others (e.g.: lift mechanics from other ski areas, etc.) are asked for proof of certification to be placed on file. SCHEDULED MAINTENANCE, TESTING AND INSPECTION Mount Cain follows lift manufacturers recommendations as outlined in the Operating and Instruction manuals, as well as the Z Passenger Ropeways standards. MAINTENANCE RECORDS Record keeping is conducted in accordance with Z Passenger Ropeways, Section 11 (specifically Section 11 Clauses 12, 16, 18 and 24). Maintenance Records for each lift are maintained by the Lift Supervisor and are retained at mountain office. These detail any required work done on the lifts, and would also include details of any worked performed by external contractors. A daily log for each lift is maintained by lift maintenance and lift operations personnel and is retained at individual drive stations (during off-season - moved to mountain office). COMPLIANCE Mount Cain is aware that lift maintenance and operations must conform to standards and acts issued by the BC Safety Authority, and WCB. We are also responsible for complying with directives received from our insurance provider as well as lift manufacturer s recommendations. I certify that I have prepared Hazards and Safety Plan which meets or exceeds Workers Compensation Board and approved industry standards and that my operation will meet the requirements of this plan. Signed Date 30 P a g e

31 Appendix C - Mt. Cain Alpine Park Lodge Drinking Water System Emergency Response Plan Certified Operator: Rick Adams Operations director: Jeff Gaetz Kitchen manager: Sharon Schraud Medical Health Officer: Charmaine Enns fax Environmental Health Officer: Joseph Baratta fax Emergency Situations Sample analysis indicates e-coli Loss of power from generator Frozen pipes Response 1. Call system operator, operations director and kitchen operator and advise them a boil water advisory is in effect. 2. Signs to be posted immediately. Ongoing All 4 outlets (2 washrooms, kitchen and water room) to have permanent signs advising a power loss means no UV treatment is being applied and boil water advisory is in effect. Emergency supply of bottled water to be kept in lodge. (80 liters) Emergency Response Plan reviewed by Rick Adams on April 28, PREAMBLE This system is gravity fed and originates from a reservoir located approximately 100 meters uphill from the lift motor on the beginners slope known as the Bunny Hill. It services the maintenance staff quarters ( Andy s Shack ), the main ski lodge building and the composting toilet s building. The reservoir is a partly rubber lined excavation approximately 20 feet in diameter which is fed from an existing mountain run-off stream. The working depth appears to be about 4 5 feet and there are provisions to handle overflow. It is surrounded by a 10 ft metal fence to exclude wildlife. 2 inch poly piping runs downhill to a point behind the maintenance staff quarters where it tee s into two 1 ABS lines, one going to the lodge and one to the staff quarters. 1. The line into the maintenance staff quarters provides raw unfiltered water to the shower, toilet and kitchen sink. They are signed with boil water advisory. This line must be left partially running through the building during midweek downtime to keep it from freezing. 2. The line to the main lodge is partially restricted in the water control room and the resulting back pressure is used to charge the lines to the kitchen sink on the first floor, the public water room line, and the two sinks present in the composting toilet building outside. There is a standard particulate canister filter assembly with a 1 micron element ahead of a Sterilight Model S12Q UV filter and the system allows for either filtering or bypassing. Current certified Small Water Systems Operator: Rick Adams, 156 Rockland Road, Campbell River, BC. V9W 1N info@mountcain.com 31 P a g e

32 OPERATION START UP Usually the maintenance person will start up the system when he arrives on Thursday or Friday. He will already have the generator on so the UV filter will be operative. 1. Replace particulate filter element (ensure proper fitting) and hand tighten canister to seal on o-ring. (New elements are stored overhead) 2. Close filter by-pass valve #3 3. Open filter inlet valve #4 4. Open filter outlet valve #5 5. Open hot water heater inlet valve #6 6. Slowly open filter system inlet valve #2 and check for leaks at filter canister. 7. Close system drain valve #1. 8. Ensure UV filter is plugged in and light is present at end of tube. 9. Check for water present at water room, kitchen and toilets SHUTDOWN AND DRAIN The system must be shut down and drained to prevent lines from freezing over the week and this operation is normally done by the maintenance person. 1. Turn off gas for water heater, (blue valve above heater) and unplug UV filter. 2. Open system drain valve #1 3. Close system inlet valve #2 4. Open filter bypass valve #3 5. Go to storage room under washrooms and open and drain line from lodge. (use small rubber hose attached to tap and drain into bucket) Stay with it until water stops and then CLOSE THIS TAP. 6. Return to water control room and open small hot water drain line at bottom of the heater. When drained, close the valve. Remove particulate filter canister, discard used element and leave disassembled. 32 P a g e

33 MAINTENANCE 1. Replace UV bulb (if necessary, 1000hr life) and wipe clean the inner tube assembly annually prior to ski season start-up. 2. Visually inspect reservoir for contaminants annually prior to ski season start-up. 3. Cleanse system downstream of filter system with bleach annually prior to ski season start-up. (Put 6 oz of bleach into empty filter canister, install and then charge system. Open and run all taps until bleach smell is strong. Close taps and let water/bleach mixture remain in lines overnight. Flush system after 24 hrs by opening all taps with system charged and UV filter operative.) 4. Test water samples from lodge kitchen annually for trace minerals, monthly for micro-biology. 5. Replace particulate filter element weekly. 6. Document all procedures in water system records and particulate filter element changes in log on water control room wall. EQUIPMENT 1. Sterilight Model S12Q UV filter assembly using #S36L Tube 2. Big Blue particulate filter canister using #CP1 US Filter 1 micron element 33 P a g e

Mount Cain Alpine Park Society Board of Directors Meeting Saturday, June 12, Minutes

Mount Cain Alpine Park Society Board of Directors Meeting Saturday, June 12, Minutes Mount Cain Alpine Park Society Board of Directors Meeting Saturday, June 12, 2010 Minutes Directors: Tony Madsen Jennifer Lash Don Mancell Darren Rowsell Trevor Hatelt Dean Davidson Peter Knott Devin Miller

More information

Policy PL Date Issued February 10, 2014

Policy PL Date Issued February 10, 2014 Subject RENEWABLE ENERGY ON CROWN LAND Compiled by Renewable Energy Program, Biodiversity Branch Replaces Policy Directives Waterpower Site Release Crown Land Onshore Windpower Development - Crown Land

More information

Preferred Recreation Recommendations Stemilt-Squilchuck Recreation Plan March 2018

Preferred Recreation Recommendations Stemilt-Squilchuck Recreation Plan March 2018 Preferred Recreation Recommendations Stemilt-Squilchuck Recreation Plan March 2018 Below are the recommended recreation ideas and strategies that package together the various recreation concepts compiled

More information

Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan

Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan New Plan Acheson Industrial Area Structure Plan Amendment Parkland County Municipal Development Plan Board Reference

More information

TELEMARK NORDIC 5 YEAR PLAN OCTOBER, 2014

TELEMARK NORDIC 5 YEAR PLAN OCTOBER, 2014 Page 1 of 6 TELEMARK NORDIC 5 YEAR PLAN OCTOBER, 2014 VISION At Telemark all individuals will be able to follow their passion of cross country skiing, biathlon and snowshoeing in a first class, stimulating

More information

MANAGEMENT DIRECTION STATEMENT June, 1999

MANAGEMENT DIRECTION STATEMENT June, 1999 Thompson River District MANAGEMENT DIRECTION STATEMENT June, 1999 for Roche Lake Provincial Park Ministry of Environment Lands and Parks BC Parks Division Table of Contents I. Introduction A. Setting

More information

As outlined in the Tatshenshini-Alsek Park Management Agreement, park management will:

As outlined in the Tatshenshini-Alsek Park Management Agreement, park management will: Management Strategy General Strategy The priority management focus for the park is to ensure that its internationally significant natural, cultural heritage and recreational values are protected and that

More information

A Master Plan is one of the most important documents that can be prepared by an Airport.

A Master Plan is one of the most important documents that can be prepared by an Airport. The Master Plan A Master Plan is one of the most important documents that can be prepared by an Airport. A Master Plan is a visionary and a strategic document detailing planning initiatives for the Airport

More information

Proposal to Redevelop Lower Kananaskis River-Barrier Lake. Bow Valley Provincial Park. Frequently Asked Questions

Proposal to Redevelop Lower Kananaskis River-Barrier Lake. Bow Valley Provincial Park. Frequently Asked Questions Proposal to Redevelop Lower Kananaskis River-Barrier Lake Bow Valley Provincial Park Frequently Asked Questions What is being proposed? What are the details of the proposal? Where is the project area located?

More information

APPENDIX. Alberta Land Stewardship Act AMENDMENTS TO THE SOUTH SASKATCHEWAN REGIONAL PLAN

APPENDIX. Alberta Land Stewardship Act AMENDMENTS TO THE SOUTH SASKATCHEWAN REGIONAL PLAN APPENDIX Alberta Land Stewardship Act AMENDMENTS TO THE SOUTH SASKATCHEWAN REGIONAL PLAN 1 All references to Alberta Environment and Sustainable Resource Development, Environment and Sustainable Resource

More information

Disclosure Document for Castle Mountain Resort Future Development

Disclosure Document for Castle Mountain Resort Future Development Disclosure Document for Castle Mountain Resort Future Development September 2018 1._ Introduction Castle Mountain Resort Inc. (CMR) has completed a Master Development Plan that proposes to expand the existing

More information

BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM

BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM Backcountry Trail Flood Rehabilitation A June 2013 Flood Recovery Program Summary In June 2013, parts of Southern Alberta were devastated from significant

More information

PROUDLY BRINGING YOU CANADA AT ITS BEST. Management Planning Program NEWSLETTER #1 OCTOBER, 2000

PROUDLY BRINGING YOU CANADA AT ITS BEST. Management Planning Program NEWSLETTER #1 OCTOBER, 2000 PROUDLY BRINGING YOU CANADA AT ITS BEST VUNTUT NATIONAL PARK Management Planning Program NEWSLETTER #1 OCTOBER, 2000 INTRODUCTION This newsletter launches the development of the first management plan for

More information

Restore and implement protected status that is equivalent, or better than what was lost during the mid-1990 s

Restore and implement protected status that is equivalent, or better than what was lost during the mid-1990 s THE ROSSLAND RANGE, OLD GLORY AREA. Executive summary. The Friends of the Rossland Range Society, on behalf of the local outdoor community, seeks to accomplish the following with respect to the Old Glory

More information

FILE: /PERM EFFECTIVE DATE: May 16, 2014 AMENDMENT:

FILE: /PERM EFFECTIVE DATE: May 16, 2014 AMENDMENT: APPROVED AMENDMENTS: Effective Date Briefing Note /Approval Summary of Changes: FILE: 11000-00/PERM EFFECTIVE DATE: May 16, 2014 AMENDMENT: Table of Contents 1. POLICY APPLICATION... 1 2. PRINCIPLES AND

More information

Proposed Action. Payette National Forest Over-Snow Grooming in Valley, Adams and Idaho Counties. United States Department of Agriculture

Proposed Action. Payette National Forest Over-Snow Grooming in Valley, Adams and Idaho Counties. United States Department of Agriculture United States Department of Agriculture Forest Service January 2012 Proposed Action Payette National Forest Over-Snow Grooming in Valley, Adams and Idaho Counties Payette National Forest Valley, Adams

More information

communication tower means a tower or structure built to support equipment used to transmit communication signals;

communication tower means a tower or structure built to support equipment used to transmit communication signals; Ontario Ministry of Natural Resources Subject Communication Tower Sites on Crown Land Compiled by - Branch Lands & Waters Section Land Management Policy PL 4.10.02 Replaces Directive Title Communication

More information

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012 1. Introduction The Federal Aviation Administration (FAA) recommends that airport master plans be updated every 5 years or as necessary to keep them current. The Master Plan for Joslin Field, Magic Valley

More information

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the

More information

Marble Mountain Development Corporation. Annual Report

Marble Mountain Development Corporation. Annual Report Marble Mountain Development Corporation Annual Report 2016-17 Chairpersons Message As Transitional Chair of the Marble Mountain Development Corporation (MMDC), I am pleased to submit the Annual Report

More information

Alternative Highest & Best Use Analysis Boutique Hotel

Alternative Highest & Best Use Analysis Boutique Hotel Alternative Highest & Best Use Analysis In response to numerous comments received from the public, as well as issues raised by the CCC in the Appeal Staff Report Substantial Issue Determination, the following

More information

Proposal to Redevelop Lower Kananaskis River-Barrier Lake. Bow Valley Provincial Park

Proposal to Redevelop Lower Kananaskis River-Barrier Lake. Bow Valley Provincial Park Frequently Asked Questions Proposal to Redevelop Lower Kananaskis River-Barrier Lake Bow Valley Provincial Park Frequently Asked Questions What has been decided? What are the details of the plan? What

More information

5.0 OUTDOOR RECREATION OPPORTUNITIES AND MANAGEMENT

5.0 OUTDOOR RECREATION OPPORTUNITIES AND MANAGEMENT 5.0 OUTDOOR RECREATION OPPORTUNITIES AND MANAGEMENT 5.1 Introduction This section describes the range of recreational activities that currently take place in Marble Range and Edge Hills Parks, as well

More information

Safety Regulatory Oversight of Commercial Operations Conducted Offshore

Safety Regulatory Oversight of Commercial Operations Conducted Offshore Page 1 of 15 Safety Regulatory Oversight of Commercial Operations Conducted Offshore 1. Purpose and Scope 2. Authority... 2 3. References... 2 4. Records... 2 5. Policy... 2 5.3 What are the regulatory

More information

Mt. Hood National Forest

Mt. Hood National Forest United States Department of Agriculture Forest Service Mt. Hood National Forest Zigzag Ranger District 70220 E. Highway 26 Zigzag, OR 97049 503-622-3191 Fax: 503-622-5622 File Code: 1950-1 Date: June 29,

More information

GOLDEN BACKCOUNTRY RECREATION ADVISORY COMMITTEE (GBRAC)

GOLDEN BACKCOUNTRY RECREATION ADVISORY COMMITTEE (GBRAC) GOLDEN BACKCOUNTRY RECREATION ADVISORY COMMITTEE (GBRAC) MINUTES from November 1, 2006 Meeting Attending: Sector / Stakeholder GBRAC Commercial Aerial Motorized Sector GBRAC Habitat Protection; Sport Fishing

More information

A GUIDE TO MANITOBA PROTECTED AREAS & LANDS PROTECTION

A GUIDE TO MANITOBA PROTECTED AREAS & LANDS PROTECTION A GUIDE TO MANITOBA PROTECTED AREAS & LANDS PROTECTION Manitoba Wildands December 2008 Discussions about the establishment of protected lands need to be clear about the definition of protection. We will

More information

REGIONAL BOARD REPORT

REGIONAL BOARD REPORT REGIONAL BOARD REPORT Administrator s Office For the Board August 21, 2008 DATE: August 14, 2008 FILE NOS.: A-07-06377/8/9.000 FROM: RE: Chief Administrative Officer OCP and Zoning Amendment Application

More information

ROBERTS CREEK PROVINCIAL PARK MASTER PLAN. November, 1981

ROBERTS CREEK PROVINCIAL PARK MASTER PLAN. November, 1981 Ministry of Lands, Parks and Housing Parks and Outdoor Recreation Division Park Operations Branch North Vancouver, B. C. ROBERTS CREEK PROVINCIAL PARK MASTER PLAN November, 1981 Mr. G. Trachuk Director

More information

Adventure Tourism Management Plan. Adventure Tourism Intensive Use Sites MANAGEMENT PLAN

Adventure Tourism Management Plan. Adventure Tourism Intensive Use Sites MANAGEMENT PLAN Adventure Tourism Intensive Use Sites MANAGEMENT PLAN ACCEPTED BY: FILES #: 1413906 1413905 LICENSES #: 112857 112905 DATE: April 25, 2018 SIGNED on behalf of HER MAJESTRY THE QUEEN IN THE RIGHT OF THE

More information

8 CROSS-BOUNDARY AGREEMENT WITH BRAMPTON TRANSIT

8 CROSS-BOUNDARY AGREEMENT WITH BRAMPTON TRANSIT 8 CROSS-BOUNDARY AGREEMENT WITH BRAMPTON TRANSIT The Transportation Services Committee recommends the adoption of the recommendations contained in the following report dated May 27, 2010, from the Commissioner

More information

Policy. Huts, Cabins and Lodges in BC Provincial Parks

Policy. Huts, Cabins and Lodges in BC Provincial Parks Policy Huts, Cabins and Lodges in BC Provincial Parks Federation of Mountain Clubs of BC Version 1.3 Published August 2, 2015 INTRODUCTION The Federation of Mountain Clubs of BC (FMCBC) promotes self-propelled

More information

Steps in the Management Planning Process

Steps in the Management Planning Process Steps in the Management Planning Process Developing a management plan for Kalamalka Lake Park will follow a multi-stage process. The planning process for this park is currently in the Draft Management

More information

Bloor Street West Rezoning Application for a Temporary Use By-law Final Report

Bloor Street West Rezoning Application for a Temporary Use By-law Final Report STAFF REPORT ACTION REQUIRED 3741 3751 Bloor Street West Rezoning Application for a Temporary Use By-law Final Report Date: June 12, 2007 To: From: Wards: Reference Number: Etobicoke York Community Council

More information

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES Over the term of the Master Amendment to the Airline Use and Lease Agreement, the Kansas City Aviation Department

More information

CHAPTER 5. Chapter 5 Recreation Element

CHAPTER 5. Chapter 5 Recreation Element CHAPTER 5 Recreation Element Chapter 5 Recreation Element The Recreation Element of the Meyers Area Plan is a supplement to the Recreation Element of the TRPA Regional Plan and the El Dorado County General

More information

Draft Executive Summary

Draft Executive Summary Draft Executive Summary The Juneau Tourism Plan development process was undertaken by Egret Communications and ARA Consulting in April 2001, under contract with the City and Borough of Juneau, Alaska.

More information

Loveland Valley Lodge Expansion Environmental Assessment Recreation Resource Report

Loveland Valley Lodge Expansion Environmental Assessment Recreation Resource Report United States Department of Agriculture Forest Service Loveland Valley Lodge Expansion Environmental Assessment Recreation Resource Report Clear Creek Ranger District, Arapaho National Forest, Clear Creek

More information

The Strategic Commercial and Procurement Manager

The Strategic Commercial and Procurement Manager Item 3 To: Procurement Sub Committee On: 8 June 2016 Report by: The Strategic Commercial and Procurement Manager Heading: Renfrewshire Council s Community Benefit Strategy 2016 1. Summary 1.1. The purpose

More information

Watchorn Provincial Park. Management Plan

Watchorn Provincial Park. Management Plan Watchorn Provincial Park Management Plan 2 Watchorn Provincial Park Table of Contents 1. Introduction... 3 2. Park History... 3 3. Park Attributes... 3 3.1 Natural... 4 3.2 Recreational... 4 3.3 Additional

More information

Marchand Provincial Park. Management Plan

Marchand Provincial Park. Management Plan Marchand Provincial Park Management Plan 2 Marchand Provincial Park Table of Contents 1. Introduction... 3 2. Park History... 3 3. Park Attributes... 4 3.1 Natural... 4 3.2 Recreational... 4 3.3 Additional

More information

Sunshine Coast Airport Master Plan September 2007

Sunshine Coast Airport Master Plan September 2007 Sunshine Coast Airport Master Plan September 2007 Contents CONTENTS... I ACKNOWLEDGEMENT... II DISCLAIMER... III 1 EXECUTIVE SUMMARY...IV 1 INTRODUCTION... 1 2 AVIATION DEMAND FORECAST... 5 3 AIRCRAFT

More information

Little Limestone Lake Provincial Park. Draft Management Plan

Little Limestone Lake Provincial Park. Draft Management Plan Little Limestone Lake Provincial Park Draft Management Plan Little Limestone Lake Provincial Park Draft Management Plan Table of Contents 1. Introduction... 3 2. Background... 3 3. Planning context...

More information

Decision Memo Broken Wheel Ranch Equestrian Outfitter Special-Use Permit Proposed Action

Decision Memo Broken Wheel Ranch Equestrian Outfitter Special-Use Permit Proposed Action Decision Memo Broken Wheel Ranch Equestrian Outfitter Special-Use Permit USDA Forest Service Mississippi Bluffs Ranger District, Shawnee National Forest Jackson and Union Counties, Illinois Proposed Action

More information

Sport Capital Improvement Plan. Paul Borci Manager, Campus Planning Property & Campus Services

Sport Capital Improvement Plan. Paul Borci Manager, Campus Planning Property & Campus Services Sport Capital Improvement Plan Paul Borci Manager, Campus Planning Property & Campus Services What is SCIP? Property and Campus Services (PCS) in collaboration with Melbourne University Sport (MU Sport)

More information

Pillar Park. Management Plan

Pillar Park. Management Plan Pillar Park Management Plan January 2014 Pillar Park Management Plan Approved by: Jeff Leahy Regional Director Thompson Cariboo Region BC Parks January 9, 2014 Date Brian Bawtinheimer Executive Director

More information

D IRECTION S TATEMENT

D IRECTION S TATEMENT Vancouver Island Region M ANAGEMENT D IRECTION S TATEMENT September 2003 for Lower Nimpkish Provincial Park Ministry of Water, Land and Air Protection Environmental Stewardship Lower Nimpkish Provincial

More information

Logo Department Name Agency Organization Organization Address Information 5700 North Sabino Canyon Road

Logo Department Name Agency Organization Organization Address Information 5700 North Sabino Canyon Road Logo Department Name Agency Organization Organization Address Information United States Forest Coronado National Forest 5700 North Sabino Canyon Road Department of Service Santa Catalina Ranger District

More information

Tahoe National Forest Over-Snow Vehicle Use Designation

Tahoe National Forest Over-Snow Vehicle Use Designation Tahoe National Forest Over-Snow Vehicle Use Designation USDA Forest Service Tahoe National Forest February 20, 2015 Introduction The Forest Service, U.S. Department of Agriculture will prepare an Environmental

More information

Final Environmental Impact Statement for the Merced Wild and Scenic River. Comprehensive Management Plan, Yosemite National Park, Madera and Mariposa

Final Environmental Impact Statement for the Merced Wild and Scenic River. Comprehensive Management Plan, Yosemite National Park, Madera and Mariposa This document is scheduled to be published in the Federal Register on 02/26/2014 and available online at http://federalregister.gov/a/2014-04061, and on FDsys.gov DEPARTMENT OF THE INTERIOR 4312-FF NATIONAL

More information

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington Vista Field Airport February, 2006 Prepared for: Port of Kennewick One Clover Island Kennewick, Washington 99336 Prepared by: J-U-B ENGINEERS, Inc. 2810 W. Clearwater Avenue, Suite 201 Kennewick, Washington

More information

13.1 REGIONAL TOURISM ISSUES AND SUMMARY OF FINDINGS

13.1 REGIONAL TOURISM ISSUES AND SUMMARY OF FINDINGS 13 REGIONAL TOURISM T he County of Mariposa s recreation needs and facilities fall within two categories: regional tourism and local recreation. This Element focuses on regional tourism issues related

More information

China Creek North Park Upgrades and Glen Pump Station. Park Board Committee Meeting Monday, July 10, 2017

China Creek North Park Upgrades and Glen Pump Station. Park Board Committee Meeting Monday, July 10, 2017 China Creek North Park Upgrades and Glen Pump Station Park Board Committee Meeting Monday, July 10, 2017 Purpose The purpose of this presentation is to: Share the results of the public engagement processes;

More information

RE: Access Fund Comments on Yosemite National Park Wilderness Stewardship Plan, Preliminary Ideas and Concepts

RE: Access Fund Comments on Yosemite National Park Wilderness Stewardship Plan, Preliminary Ideas and Concepts September 30, 2016 Superintendent Yosemite National Park Attn: Wilderness Stewardship Plan P.O. Box 577 Yosemite, CA 95389 RE: Access Fund Comments on Yosemite National Park Wilderness Stewardship Plan,

More information

City of Durango 5.8 FUNDING TRAILS DEVELOPMENT

City of Durango 5.8 FUNDING TRAILS DEVELOPMENT 5.8 FUNDING TRAILS DEVELOPMENT The City has been successful in establishing dedicated local funding sources as well as applying for grants to develop the City s trail system, having received nearly $2.4

More information

Port Bruce. Interim Management Statement

Port Bruce. Interim Management Statement Port Bruce Interim Management Statement Port Bruce Interim Management Statement August 3, 1999 This Port Bruce Provincial Park Interim Management Statement provides direction for the custodial management

More information

CHAPTER 6 NOISE EXPOSURE

CHAPTER 6 NOISE EXPOSURE CHAPTER 6 NOISE EXPOSURE FAA requires that the NEM submitted for review represent the aircraft noise exposure for the year of submittal (in this case 2008) and for a future year (2013 for OSUA). However,

More information

Rangitīkei District Council

Rangitīkei District Council Rangitīkei District Council Assets and Infrastructure Committee Meeting Agenda Thursday 9 August 2018 9:30 AM Contents 1 Welcome...3 2 Council Prayer...3 3 Apologies/leave of Absence...3 4 Members conflict

More information

Establishing a National Urban Park in the Rouge Valley

Establishing a National Urban Park in the Rouge Valley STAFF REPORT ACTION REQUIRED Establishing a National Urban Park in the Rouge Valley Date: March 29, 2012 To: From: Wards: Reference Number: Executive Committee Deputy City Manager, Cluster B All p:\2012\cluster

More information

Land Management Summary

Land Management Summary photo credit: ANGAIR Anglesea Heath Land Management Summary The Anglesea Heath (6,501 ha) was incorporated into the Great Otway National Park in January 2018. This provides an opportunity to consider the

More information

White Mountain National Forest Saco Ranger District

White Mountain National Forest Saco Ranger District United States Department of Agriculture Forest Service White Mountain National Forest 33 Kancamagus Highway Conway, NH 03818 Comm: (603) 447-5448 TTY: (603) 447-3121 File Code: 1950 Date: February 26,

More information

Fremont Point Cabin Reconstruction and Expansion Project Project Proposal & Public Scoping Documentation

Fremont Point Cabin Reconstruction and Expansion Project Project Proposal & Public Scoping Documentation Fremont Point Cabin Reconstruction and Expansion Project Fremont-Winema National Forests Silver Lake Ranger District The Silver Lake Ranger District of the Fremont-Winema National Forests is proposing

More information

Cascade River State Park Management Plan Amendment

Cascade River State Park Management Plan Amendment This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp Cascade River State

More information

The Corporation of the City of Kawartha Lakes Council Report

The Corporation of the City of Kawartha Lakes Council Report The Corporation of the City of Kawartha Lakes Council Report Report Number ENG2017-008 Date: September 12, 2017 Time: 2:00 p.m. Place: Council Chambers Ward Community Identifier: All Subject: Author Name

More information

Finn Creek Park. Management Direction Statement Amendment

Finn Creek Park. Management Direction Statement Amendment Finn Creek Park Management Direction Statement Amendment November 2013 Management Direction Statement Amendment Approved by: Jeff Leahy Regional Director, Thompson Cariboo BC Parks November 12, 2013 Date

More information

Wallace Lake Provincial Park. Management Plan

Wallace Lake Provincial Park. Management Plan Wallace Lake Provincial Park Management Plan 2 Wallace Lake Provincial Park Table of Contents 1. Introduction... 3 2. Park History... 3 3. Park Attributes... 4 3.1 Natural... 4 3.2 Recreational... 4 4.

More information

Jumbo Glacier Resort Master Plan. Appendix 3-K

Jumbo Glacier Resort Master Plan. Appendix 3-K Jumbo Glacier Resort Master Plan Appendix 3-K Letter re: Review of M. Austin s Analysis Report: Potential Impacts of the Proposed JGR on the Central Purcell Grizzly Bear Population Prepared by ENKON Environmental

More information

112th CONGRESS. 1st Session H. R. 113 IN THE HOUSE OF REPRESENTATIVES

112th CONGRESS. 1st Session H. R. 113 IN THE HOUSE OF REPRESENTATIVES HR 113 IH 112th CONGRESS 1st Session H. R. 113 To provide for additions to the Cucamonga and Sheep Mountain Wilderness Areas in the Angeles and San Bernardino National Forests and the protection of existing

More information

Disposition of Spadina Expressway Properties - Memorandum of Understanding with Infrastructure Ontario

Disposition of Spadina Expressway Properties - Memorandum of Understanding with Infrastructure Ontario GM22.32 REPORT FOR ACTION Disposition of Spadina Expressway Properties - Memorandum of Understanding with Infrastructure Ontario Date: September 8, 2017 To: Government Management Committee From: Chief

More information

Food and Agriculture Organisation (FAO) current work - global guidelines on ecolabelling and certification in capture fisheries and aquaculture

Food and Agriculture Organisation (FAO) current work - global guidelines on ecolabelling and certification in capture fisheries and aquaculture 9 August 2012 Food and Agriculture Organisation (FAO) current work - global guidelines on ecolabelling and certification in capture fisheries and aquaculture FAO descriptor on what eco-labels do: Large-scale

More information

CHAPTER FIVE PROSPECTS FOR FUTURE ECONOMIC DEVELOPMENT

CHAPTER FIVE PROSPECTS FOR FUTURE ECONOMIC DEVELOPMENT CHAPTER FIVE PROSPECTS FOR FUTURE ECONOMIC DEVELOPMENT 5.1 GENERAL The recommended type and location of future land uses in Alpine should, in part, consider potential opportunities for future economic

More information

EX28.6 REPORT FOR ACTION. Advancing Fare Integration SUMMARY. Date: October 16, 2017 To: Executive Committee From: City Manager Wards: All

EX28.6 REPORT FOR ACTION. Advancing Fare Integration SUMMARY. Date: October 16, 2017 To: Executive Committee From: City Manager Wards: All EX28.6 REPORT FOR ACTION Advancing Fare Integration Date: October 16, 2017 To: Executive Committee From: City Manager Wards: All SUMMARY In July 2016, City Council considered a current state assessment

More information

Ministry of Parks, Culture and Sport. Plan for saskatchewan.ca

Ministry of Parks, Culture and Sport. Plan for saskatchewan.ca Ministry of Parks, Culture and Sport Plan for 2018-19 saskatchewan.ca Table of Contents Statement from the Minister... 1 Response to Government Direction... 2 Operational Plan... 3 Highlights... 7 Financial

More information

PURPOSE AND NEED. Introduction

PURPOSE AND NEED. Introduction Public Scoping: Allocation of Recreation Capacity for Commercial Outfitter Guide Services on North Kruzof Island Trails (Kruzof Island Outfitter Guide) PURPOSE AND NEED Introduction The U.S. Department

More information

April 10, Mark Stiles San Juan Public Lands Center Manager 15 Burnett Court Durango, CO Dear Mark,

April 10, Mark Stiles San Juan Public Lands Center Manager 15 Burnett Court Durango, CO Dear Mark, Mark Stiles San Juan Public Lands Center Manager 15 Burnett Court Durango, CO 81301 Dear Mark, We are pleased to offer the following comments on the draft San Juan Public Lands Center management plans

More information

PRESS RELEASE CANADIAN ZINC SUPPORTS EXPANSION OF NAHANNI NATIONAL PARK

PRESS RELEASE CANADIAN ZINC SUPPORTS EXPANSION OF NAHANNI NATIONAL PARK PRESS RELEASE CZN-TSX CZICF-OTCBB FOR IMMEDIATE RELEASE CANADIAN ZINC SUPPORTS EXPANSION OF NAHANNI NATIONAL PARK PRAIRIE CREEK MINE EXCLUDED FROM ENLARGED PARK ACCESS RIGHTS TO BE PROVIDED BY NEW LEGISLATION

More information

CAIRNS RECTANGULAR PITCH STADIUM NEEDS STUDY PART 1 CAIRNS REGIONAL COUNCIL DRAFT REPORT SEPTEMBER 2011

CAIRNS RECTANGULAR PITCH STADIUM NEEDS STUDY PART 1 CAIRNS REGIONAL COUNCIL DRAFT REPORT SEPTEMBER 2011 CAIRNS RECTANGULAR PITCH STADIUM NEEDS STUDY PART 1 CAIRNS REGIONAL COUNCIL DRAFT REPORT SEPTEMBER 2011 CAIRNS RECTANGULAR PITCH STADIUM NEEDS STUDY PART 1 Cairns Regional Council September 2011 Coffey

More information

non-resident means an individual who is not a resident; and

non-resident means an individual who is not a resident; and Ontario Ministry of Natural Resources Subject Non-Resident Crown Land Camping Northern Ontario Compiled by - Branch Lands & Waters Replaces Directive Title Same Section Land Management Number Same Policy

More information

PROTECTED AREAS ZONE - POLICY

PROTECTED AREAS ZONE - POLICY PROTECTED AREAS ZONE - POLICY.1 Introduction The Protected Areas Zone applies to the land depicted on the Ruapehu District Plan Maps as: Amenity Policy Area. Protected Areas - Conservation. (c) Protected

More information

Portage Spillway Provincial Park. Draft Management Plan

Portage Spillway Provincial Park. Draft Management Plan Portage Spillway Provincial Park Draft Management Plan 2 Portage Spillway Provincial Park Table of Contents 1. Introduction... 3 2. Park History... 3 3. Park Attributes... 4 3.1 Natural... 4 3.2 Recreational...

More information

Tourism and Wetlands

Tourism and Wetlands CONVENTION ON WETLANDS (Ramsar, Iran, 1971) 43 rd Meeting of the Standing Committee Gland, Switzerland, 31 October 4 November 2011 DOC. SC43-27 Tourism and Wetlands Action requested. The Standing Committee

More information

9 CONSTRUCTION OF BATHURST STREET FROM GREEN LANE WEST TO SOUTH OF HIGHWAY 11, TOWN OF EAST GWILLIMBURY AND TOWNSHIP OF KING

9 CONSTRUCTION OF BATHURST STREET FROM GREEN LANE WEST TO SOUTH OF HIGHWAY 11, TOWN OF EAST GWILLIMBURY AND TOWNSHIP OF KING Clause No. 9 in Report No. 9 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on May 15, 2014. 9 CONSTRUCTION OF BATHURST

More information

Prior to contacting the Whitecourt Trailblazers Snowmobile Club, applicants must:

Prior to contacting the Whitecourt Trailblazers Snowmobile Club, applicants must: WHITECOURT TRAILBLAZERS Box 607 Whitecourt, AB T7S 1N7 www.whitecourttrailblazers.ca CNT AMENDMENT Restriction Code 710: See Comments Comments All applicants are required to contact: Whitecourt Trailblazers

More information

THAT the Board approve the final proposed concept plan for the Jericho Marginal Wharf site as shown in Figure C-4 of Appendix C.

THAT the Board approve the final proposed concept plan for the Jericho Marginal Wharf site as shown in Figure C-4 of Appendix C. Date: January 17, 2012 TO: Board Members Vancouver Park Board FROM: General Manager Parks and Recreation SUBJECT: Jericho Marginal Wharf Phase 2 Concept Plan RECOMMENDATION THAT the Board approve the final

More information

Appendix A BC Provincial Parks System Goals

Appendix A BC Provincial Parks System Goals Appendix A BC Provincial Parks System Goals The British Columbia Provincial Parks System has two mandates: To conserve significant and representative natural and cultural resources To provide a wide variety

More information

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET Report No. 3 of the Regional Council Meeting of March 28, 2013 1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET The recommends: 1. Receipt

More information

THRESHOLD GUIDELINES FOR AVALANCHE SAFETY MEASURES

THRESHOLD GUIDELINES FOR AVALANCHE SAFETY MEASURES BRITISH COLUMBIA MINISTRY OF TRANSPORTATION & INFRASTRUCTURE AVALANCHE & WEATHER PROGRAMS THRESHOLD GUIDELINES FOR AVALANCHE SAFETY MEASURES British Columbia Ministry of Transportation & Infrastructure

More information

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) TDD (651)

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) TDD (651) DATE: March 27, 2012 METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN 55101 Phone (651) 602-1000 TDD (651) 291-0904 TO: Metropolitan Parks and Open Space Commission FROM: Arne Stefferud, Planning

More information

Beaver Creek Provincial Park. Management Plan

Beaver Creek Provincial Park. Management Plan Beaver Creek Provincial Park Management Plan 2 Beaver Creek Provincial Park Table of Contents 1. Introduction... 3 2. Park History... 3 3. Park Attributes... 4 3.1 Natural... 4 3.2 Recreational... 4 4.

More information

Rogue River Access and Management Plan Draft Alternatives

Rogue River Access and Management Plan Draft Alternatives Rogue River Access and Management Plan Draft Alternatives The Rogue River Access and Management Plan was initiated in December, 2011 and is being led by Jackson County Parks (JCP) and Oregon Department

More information

Seek the Board s approval for the Donald Place kerb and channel renewal to progress to final design, tender and construction; and

Seek the Board s approval for the Donald Place kerb and channel renewal to progress to final design, tender and construction; and 3. DONALD PLACE - KERB AND CHANNEL RENEWAL General Manager responsible: General Manager City Environment Officer responsible: Transport and City Streets Manager Author: Michelle Flanagan, Streets Capital

More information

Municipal and Regional District Tax Imposition Bylaw No and Metro Vancouver Letter of Support

Municipal and Regional District Tax Imposition Bylaw No and Metro Vancouver Letter of Support To: From: Re: City of Richmond General Purposes Committee Andrew Nazareth General Manager, Finance and Corporate Services Report to Committee Date: October 11, 2016 File: 08-4150-03-01/2016- Vol01 Municipal

More information

Nakina Moraine Provincial Park. Interim Management Statement. Ontario. Ministry of Natural Resources

Nakina Moraine Provincial Park. Interim Management Statement. Ontario. Ministry of Natural Resources Nakina Moraine Provincial Park Interim Management Statement Ontario Ministry of Natural Resources 1999, Queen's Printer for Ontario Printed in Ontario, Canada Additional copies of this publication can

More information

Dragon Mountain Park. Management Plan. Public Review Draft

Dragon Mountain Park. Management Plan. Public Review Draft Disclaimer: This draft management plan contains preliminary proposals that are subject to change and therefore may not necessarily reflect the position of the Ministry of Environment. At the conclusion

More information

MANAGEMENT DIRECTION STATEMENT June, 1999

MANAGEMENT DIRECTION STATEMENT June, 1999 Thompson River District MANAGEMENT DIRECTION STATEMENT June, 1999 for Clearwater River Corridor (Addition to Wells Gray Park) Ministry of Environment Lands and Parks BC Parks Division ii Table of Contents

More information

Rocky Lake Provincial Park. Draft Management Plan

Rocky Lake Provincial Park. Draft Management Plan Rocky Lake Provincial Park Draft Management Plan Rocky Lake Provincial Park Draft Management Plan Table of Contents 1. Introduction... 3 2. Park History... 3 3. Park Attributes... 4 3.1 Location/Access...4

More information

TOURISM & PUBLIC SERVICES RURAL SIGNAGE POLICY

TOURISM & PUBLIC SERVICES RURAL SIGNAGE POLICY Policy and Procedures Subject Title: Tourism and Public Services Rural Signage Policy Corporate Policy (Approved by Council): X Policy Ref. No.: ROADS-01-07 Administrative Policy (Approved by CAO): By-Law

More information

Flow Stand Up Paddle Board Parkway Plan Analysis

Flow Stand Up Paddle Board Parkway Plan Analysis Regional Parks Department Jeffrey R. Leatherman, Director County of Sacramento Divisions Administration Golf Leisure Services Maintenance Rangers Therapeutic Recreation Services Flow Stand Up Paddle Board

More information

Gold Coast. Rapid Transit. Chapter twelve Social impact. Chapter content

Gold Coast. Rapid Transit. Chapter twelve Social impact. Chapter content Gold Coast Rapid Transit Chapter twelve Social impact Chapter content Social impact assessment process...235 Existing community profile...237 Consultation...238 Social impacts and mitigation strategies...239

More information

Recreation Management Plan Lake Baroon and Ewen Maddock Dam

Recreation Management Plan Lake Baroon and Ewen Maddock Dam Lake Baroon and Ewen Maddock Dam December 2013 Contents Overview... 3 The Value of Our Natural Areas... 4 Management Approach... 6 Funding... 7 Recreation Management... 8 Conditions of Access and Use...

More information