Gruyere Gold Project Update

Similar documents
Gruyere Gold Project Development Update

Gruyere Gold Project Development Update

Gruyere Project Development Update

ON TIME AND ON BUDGET: PROCESSING PLANT OVER 90% COMPLETE AND FIRST PRODUCTION SET FOR MARCH

BALL MILL COMPLETED AHEAD OF SCHEDULE

Outlook: FY13 EBITDA guidance $28M - $29M. Pursuing contracted 300MW in 2013 growth strategy. FY13 maiden franked dividend payment expected

First Thunderbox gold now anticipated in June Quarter 2016

Kinross Production Continues on Plan

Atlas Lifts Production Guidance and Lowers Cost Forecast After Record September Quarter

Overview. Mining projects map

Australian Securities Exchange Notice

Mine Production and Shipping

For personal use only

Curragh Operational Tour

For personal use only

ADVENT ENERGY UNCONVENTIONAL SHALE GAS AND CONVENTIONAL GAS PROSPECTIVITY IN ONSHORE BONAPARTE BASIN

December 2018 Quarterly Production Report

Haoma Mining NL A.B.N

JUNE 2017 QUARTERLY ACTIVITIES REPORT

20 November Company Announcements Australian Securities Exchange Limited Level 4, 20 Bridge Street SYDNEY NSW 2000 AUSTRALIA.

BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES. July 2002 September 2002

Correction to Quarterly Report for quarter ending June 2016

For personal use only

HARMONY GOLD AND NEWCREST FORM PAPUA NEW GUINEA GOLD JOINT VENTURE

For personal use only

Quarterly Report for the Period Ending 30 September 2014

BRIEFING PAPER APRIL 2002 MINING AREA C DEVELOPMENT PORT HEDLAND PORT & CAPACITY EXPANSION

For personal use only

Downer Rail. Monash University, Institute of Railway Technology Shaping the Future of Railway

For personal use only

Kinross acquires mining rights to land adjacent Fort Knox mine, adds more than 2 million ounces to mineral resource estimates

December 2017 Quarterly Report

Australian Securities Exchange Notice

NEWS RELEASE 8 NOVEMBER Gladstone LNG Project Arrow-AGL Joint Venture Acquires Enertrade s Gas and Pipeline Business

Kinross Gold Corporation Merrill Lynch Global Metals, Mining & Steel Conference May 13 15, 2008

For personal use only

Matilda Zircon Limited (ASX: MZI) (formerly Olympia Resources Ltd) Quarterly Activities Report for Period Ended. 30 June 2009

For personal use only

Altera Resources Ltd

Mungana Signs Agreement with Newcrest to unlock Porphyry Gold-Copper Potential at Chillagoe

Kinross Nevada tour highlights growth potential at Bald Mountain and Round Mountain

For personal use only

ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery 9 July 2015

Development Projects. Turner River Hub Project. centralised processing facility drawing feed from nearby satellite mines.

For personal use only

AUSIMM - Technical Meeting & AGM

For personal use only

ASX Announcement. Appointment of Preferred Contractor for CHPP Construction at Colton Mine

Australian Mines increases Marymia ground holding

NEWCREST LOOKING TO THE FUTURE

Kidman agrees to acquire 1Moz Mt Holland gold field in WA

CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION

dedicated to being world class

FOUR EAGLES JV FORMALISED SEISMIC AND DRILLING PROGRAMME COMMENCES

Terms of Reference: Introduction

For personal use only

MOUNT GIBSON IRON LIMITED QUARTERLY REPORT FOR THE PERIOD ENDED 31 MARCH April 2018

Investor Update April 2009

2 September The Manager Market Announcements Australian Securities Exchange 20 Bridge Street SYDNEY NSW 2000 AURORA TANK PROJECT

BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES. September 2002 December 2002

Inca de Oro Copper-Gold Project and Carmen deposit sale process

INTERIM REVIEW OF AUSTRALIAN CONSTRUCTION MARKET CONDITIONS JULY 2015

Uniquely positioned to be Australia s next coal producer

INTERIM REPORT JANUARY-JUNE 2013

Crown Resorts Limited

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

For personal use only

Chapleau Mining Readiness and Growth Strategy Addendum Number 1 February 27 th, 2017

EL LIMON MINE: EMPLOYEES & CONTRACTORS 133

For personal use only

BHP Billiton Iron Ore. Asset Development Projects

For personal use only

For personal use only

ASX Announcement. Company Update

DEXUS Property Group (ASX: DXS) ASX release

Greg Steinepreis EXECUTIVE SUMMARY. Partner, Perth T

BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES. July September 2001

ASX RELEASE. Erdenet to Ovoot Concession Agreement Executed

WÄRTSILÄ CORPORATION RESULT PRESENTATION JANUARY Björn Rosengren, President & CEO. Wärtsilä

HY 2016 Results February 2016

City Council Report. Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering

December Quarterly Report 17 February 2014

For personal use only

WÄRTSILÄ CORPORATION

For personal use only

CROWN ANNOUNCES 2017 FULL YEAR RESULTS

Introduction Financials The Market Honey Supply Beekeeping Enterprise Outlook

This is a submission to Council s Delivery Plan and Operational Plan

WÄRTSILÄ CORPORATION

CROWN ANNOUNCES 2018 HALF YEAR RESULTS

Aker companies investor day, London Jan Arve Haugan, President & CEO Eiliv Gjesdal, CFO

For personal use only

For personal use only

INTERIM REPORT JANUARY-JUNE 2012 BJÖRN ROSENGREN, PRESIDENT & CEO 18 JULY 2012

Lihir Operations PNG Mining and Petroleum Conference 24 November Peter Aitsi Country Manager, PNG

Press Release Regulated Information. Trading Update

Maximum Levels of Airport Charges

For personal use only

For personal use only

For personal use only

Transcription:

ASX Announcement 30 July 2018 Gruyere Gold Project Update First gold remains scheduled for the June quarter 2019 Revised Project Final Forecast Capital cost estimate of $621 million (level of accuracy range 2% / +2%) Gold Road s estimated share to date of agreed scope changes and force majeure costs is $15 million (50% basis) As at 27 July 2018, overall Project engineering and construction was 94% and 61% complete respectively with EPC construction (process plant and associated infrastructure) 39% complete Construction workforce currently 440, planning to peak during the September 2018 quarter at 600 CONTACT DETAILS Gold Road Resources Ltd Level 2, 26 Colin St West Perth WA 6005 www.goldroad.com.au perth@goldroad.com.au T +61 8 9200 1600 ASX Code GOR Gold Fields Level 5, 50 Colin St West Perth WA 6005 www.goldfields.com T +61 8 9211 9203 JSE:GFI NYSE: GFI Yamarna Gas Pipeline and Gruyere Power Station completed ahead of schedule, with commissioning anticipated in the September 2018 quarter Primary Bulk Earthworks Contract carried out by MACA has been extended with the award of final TSF work and ROM pad earthworks Gold Road Resources Limited (Gold Road) and Gruyere Mining Company Pty Ltd, a member of the Gold Fields Limited group (Gold Fields), reports the independent third party review of the Definitive Estimate (DE) for the Gruyere Gold Project (the Project) including the Final Forecast Capital (FFC) cost estimate has now been completed. The Joint Venture partners also provide an update on construction activities at the Gruyere site located approximately 200 kilometres east of Laverton in Western Australia. Review of Definitive Estimate, and completion of Final Forecast Capital Cost The independent third party review of the DE cost and schedule has now been completed. The review process with an independent third party confirmed forecast first gold remains scheduled for the June 2019 quarter which is in line with the guidance issued in the April 2018 Project Update 1. The review highlighted areas in the cost estimate requiring further assessment which were also identified and updated by the Owners Team. The Owners Team reviewed the DE in parallel to the independent third party review (Review), and have now completed the FFC estimate, taking account of the Review recommendations and further Project enhancements. It is now estimated the FFC will be $621 million (level of accuracy range 2% / +2%) which includes: scope changes and force majeure costs of $30 million; and contingency of $30 million. 1 Refer Gold Road ASX announcement dated 23 April 2018 Page 1 of 6

The FFC represents an increase of 10% (including contingency) to the $532 million capital cost estimate issued in June 2017 2, after adding the $30 million in agreed scope changes and force majeure costs (i.e. $562 million). Key contributors to the FFC increase (before contingency) include: Agreed Project scope changes. Since the last approved budget, in June 2017, the Owners have agreed to a range of scope changes that: improve operability and maintainability of the process plant and infrastructure bring forward operating and capital expenditure,' including the purchase of additional equipment previously intended to be hired. Force majeure costs as result of the extreme 2018 rainfall events. TSF design change and increase in Schedule of Rates. Increased provisional costs of certain equipment, which are for the Project s account, due to price inflation (eg steel, copper, oil) with original costs estimated on mid 2016 vendor quotes. Changes in Project Owners Team and roster changes to improve retention in an increasingly tight labour market, resulting in higher labour costs. Increases in camp and certain logistical costs. Gold Road s estimated share of scope changes and force majeure costs to date is $15 million (50% basis). Accordingly, Gold Road anticipates funding a total share of the FFC of $284 million 3 representing a 8% increase on budget 2, and which is expected to be funded from Gold Road s existing cash and working capital facilities. The remainder of the increased capital cost is to be funded by Gold Fields under the terms of the Joint Venture Agreement 4, which was negotiated as part of Gold Fields acquisition of a 50% interest in the Gruyere Gold Project in 2016 5. The FFC for the Project is an estimate of costs to the end of Project commissioning. This excludes budgeted Joint Venture support costs for the Project which are shared equally. These costs include Joint Venture management fees, amortisation of gas and power station capital costs before Project commissioning, and native title and community relations costs. The Joint Venture support costs are now budgeted at $35 million from commencement of Project to the end of Project commissioning compared to the April 2018 estimate of $35 $40 million. As the Project enters the critical phase of construction and development, the Owners Team has been enhanced by project delivery experience and capacity ensuring the team is best placed to facilitate the timely delivery of the Project in line with the FFC cost and revised schedule. 2 Refer Gold Road ASX announcement dated 21 June 2017 3 If the capital cost exceeds $614 million (based on the current agreed $30 million of agreed scope changes and force majeure costs), Gold Road will need to share any excess cost as the cost overrun facility would be fully utilised 4 Gold Fields will fund the costs associated with Cyanide Code compliance and up to $50.7 million of costs overruns, excluding scope changes and force majeure costs 5 Refer to Gold Road ASX announcement dated 7 November 2016 2

EPC Construction Progress All long lead items for the Gruyere process plant, including SAG and Ball mills, have been transported to site from Perth and are awaiting installation by the EPC contractor, Amec Foster Wheeler Civmec Joint Venture (ACJV). Activities by the ACJV on the Yeo borefield continue, with a significant portion of the pipes welded and pressure testing in progress. The installation of the overhead powerlines is well advanced, with the majority of poles installed and conductor installation approximately 50% complete. A small section in the north of the Yeo Borefield remains impacted by flooding and no activities have commenced in this area. This is not expected to impact completion and start up of the plant. Flow rate testing on the Yeo water bores shows flow rates in line to slightly above Feasibility Study estimates. Commissioning planning is well advanced with early commissioning activities to commence in the final quarter this year. Mining and Infrastructure Construction of the 198 kilometre Yamarna Gas Pipeline, being carried out by Nacap Australia Pty Ltd on behalf of APA Group, which will own and operate the asset, was completed ahead of schedule in June. The pipeline has now been connected to the 45MW Gruyere power station, which was also completed during the quarter. Integrity testing is in progress ahead of anticipated commissioning of the power station in the September 2018 quarter. MACA Limited (MACA) completed the main bulk earthworks package in June and is now busy on a second package of work, mostly associated with the lining of the TSF. Appointed mining services contractor Downer EDI is progressing well with the construction of its mining and workshop facilities expected to be completed in the September 2018 quarter. The bulk of the Downer workforce are scheduled to mobilise to site in the December 2018 quarter in time to start pre strip activities on the Gruyere open pit in early 2019. 3

Aerial view of Power Station (foreground), Process Plant (background) Aerial view of CIL tanks, pre leach thickner and base structure for the SAG and Ball Mills Installation of SAG and Ball Mills 4

CIL Tanks and Pre Leach Thickner Crusher Chamber Coarse Ore Stockpile Mining Infrastructure Area 5

Community To celebrate NAIDOC week, around 120 representatives from Gruyere construction/ operations and Gold Road exploration teams attended a Community NAIDOC day hosted by members of the Yilka and Cosmo Newberry communities. The day involved learning how to hunt, and gather bush tucker such as witcherty grubs and honey ants as well as preparing and cooking traditional meats (Kangaroo and Emu). The day concluded with all enjoying the bush tucker lunch. Above: the group ready for lunch Far Left: preparing the meat for cooking Left: Children from Cosmo Newberry Below Left: Digging for bush tucker Below: tasty treat witcherty grub For further information, please visit www.goldroad.com.au or contact: Gold Road Ian Murray Managing Director & CEO Duncan Hughes Manager Business Development & Investor Relations Tel: +61 8 9200 1600 Gold Fields Stuart Mathews Executive Vice President: Australasia Tel: + 61 8 9211 9203 Media Cannings Purple Warrick Hazeldine whazeldine@canningspurple.com.au Tel: +61 417 944 616 Peter Klinger pklinger@canningspurple.com.au Tel: +61 411 251 540 6