NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures

Similar documents
PUBLIC INFORMATION WORKSHOP #4 / PUBLIC HEARING November 8 / 9, 2006

LAX Community Noise Roundtable Work Program A1 Review of SoCal Metroplex Proposed Procedures and Suggestions for Comment Letter.

Naples Airport Authority Board of Commissioners and Noise Compatibility Committee Special Meeting on Central/South Florida Metroplex

Noise Programs & NextGen Briefing. Stan Shepherd, Manager Airport Noise Programs

Recommendations for Northbound Aircraft Departure Concerns over South Minneapolis

Master Plan & Noise Compatibility Study Update

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update

Part 150 Update Status and Recommendation

DCA Airport Noise. MWAA WG Dec 15, 2016

Optimization of Airspace and Procedures in the Metroplex

Navigation at the. Federal Aviation Administration Crossroads

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2015

Project Consultant (PC) Alternative 5 Runway 22R/L RNAV Departures

CHAPTER 6 NOISE EXPOSURE

Partnership for Quieter Skies Report

April 4, McKinney Airport Advisory Committee Airport Master Plan Update.

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D

Partnership for Quieter Skies Report

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY FIRST QUARTER 2015

AIRPORT WITH NO RUNWAYS IS A MALL

Appendix A. Meeting Coordination. Appendix A

Atlanta NextGen PBN Activities

St. Paul Downtown Airport (STP)

Partnership for Quieter Skies Report

FAA GBAS Program Update January 29, 2010

Safety / Performance Criteria Agreeing Assumptions Module 10 - Activities 5 & 6

Partnership for Quieter Skies Report

Have Descents Really Become More Efficient? Presented by: Dan Howell and Rob Dean Date: 6/29/2017

Noise Oversight Committee

Buchanan Field. Airport Planning Program. FAR Part 150 Meeting. September 28, Master Plan FAR Part 150 Noise Study Strategic Business Plan

msp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010

SoCal Metroplex Study Area

RNP AR APCH Approvals: An Operator s Perspective

CHAPTER 1 EXECUTIVE SUMMARY

Reliever Airports: NOISE ABATEMENT PLAN Flying Cloud Airport (FCM)

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2017

NextGen Priorities: Multiple Runway Operations & RECAT

An Update on Southern California Airspace Modernization November 10, 2016 Chart Publication Date San Diego International, McClellan Palomar, Brown

Portland International Jetport FAR Part 150 Update

STAFF REPORT. Airport Land Use Plan Consistency Review: Old Town Village Mixed Use Project City of Goleta. MEETING DATE: June 18, 2015 AGENDA ITEM: 5M

Noise Oversight Committee

Applewood Heights Community Open House

Memorandum. Federal Aviation Administration. Date: June 19, Richard Doucette, Environmental Protection Specialist. From: To:

Community Noise Consortium Meeting (CNC)

Name of Customer Representative: Bruce DeCleene, AFS-400 Division Manager Phone Number:

KSFO RNAV TO GLS DEMONSTRATION

Updates to Procedures at St. John s International Airport

Federal Aviation Administration DCA. By: Terry Biggio, Vice President Air Traffic Services Date: June 18, Federal Aviation Administration

Portland International Jetport FAR Part 150 Update

FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT DRAFT

Massport and FAA RNAV Pilot Study Overview Briefing to Massport CAC. December 8, 2016

2 Purpose and Need. 2.1 The Need for the Proposed Action Description of the Problem

Martin County Airport / Witham Field Noise Abatement Departure Profile (NADP) Demonstration Technical Report March 2010

Overview of Evolution to Performance Based Navigation. ICAO PBN Seminar Overview of Evolution to Performance Based Navigation

Dallas Executive Airport Marketing Plan

A Standard for Equivalent Lateral Spacing Operations Parallel and Reduced Divergence Departures

APPENDIX H 2022 BASELINE NOISE EXPOSURE CONTOUR

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Noise Oversight Committee

Mr. Chairman, Members of the Committee, I am Chet Fuller, President GE Aviation

FAA RECORD OF DECISION. Appendix D FINAL EIS ADDENDUM DOCUMENTS

Airlines and Aircraft Noise Management & Reduction

Nantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012

Federal Aviation Administration. Air Traffic 101. By: Michael Valencia & Dianna Johnston Date: Feb. 26, 2017

Thursday, November 8, :15 p.m. 2:30 p.m. David Chetcuti Community Room Millbrae City Hall 450 Poplar Avenue Millbrae, CA 94030

Community Noise Consortium Meeting (CNC)

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION

Continuous Descent? And RNAV Arrivals

FUTURE AIRSPACE CHANGE

SoCal Metroplex Study Area

Noise Abatement 101. July 13, Regular Board Meeting / August 7, 2014 Hillsborough County Aviation Authority

Trajectory Based Operations

Don-Jacques OULD FERHAT VP Airspace and Airlines Services. Airbus. PBN Safety programs

NOISE ABATEMENT PLAN. St. Paul Downtown Airport Holman Field

APPENDIX H NOISE COMPATIBILITY PROGRAM ALTERNATIVES

MINNEAPOLIS-ST. PAUL PUBLIC INPUT MEETING 3 RD QUARTER 2016 INTERNATIONAL AIRPORT (MSP)

Review of Airport Noise Issues East Airfield Development Area

Dallas Executive Airport Town Hall Meeting April 3, 2014

COMMUNITY NOISE MITIGATION SUGGESTIONS

ARRIVALS REVIEW GATWICK

Air Navigation Bureau ICAO Headquarters, Montreal

The Law of Noise Regulation Daniel S. Reimer

VATUSA PHOENIX TRACON and VATUSA PHOENIX ATCT LETTER OF AGREEMENT. SUBJECT: Interfacility Coordination Procedures

Mr. Steve Domino began the meeting by introducing the RS&H team, the intent and scope of the project and the agenda for the presentation.

DRAFT. Master Plan RESPONSIBLY GROWING to support our region. Summary

POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW

Review of brisbane Airport Noise Abatement Procedures

Finance and Implementation

Quieter Skies Report. Partnership for. Fort Lauderdale-Hollywood International Airport. Prepared by: Broward County Aviation Department

PBN Performance. Based Navigation. Days 1, 2 & 3. ICAO PBN Seminar Seminar Case Studies Days 1,2,3. Seminar Case Studies

Minneapolis-St. Paul International Airport (MSP)

CHAPTER 3 ALTERNATIVES CONSIDERED

NextGen AeroSciences, LLC Seattle, Washington Williamsburg, Virginia Palo Alto, Santa Cruz, California

Airport Community Roundtable

CONTROLLED AIRSPACE CONTAINMENT POLICY

Analysis of Operational Impacts of Continuous Descent Arrivals (CDA) using runwaysimulator

Environmental Assessment Las Vegas Area Airspace Optimization Project

Noise Compatibility Year End Report. March 7, 2011

Transcription:

NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures DFW International Airport Sandy Lancaster, Manager Noise Compatibility October 13, 2008

OUTLINE About DFW Airport What Led to RNAV Departure Procedures at DFW How RNAV Was Implemented by FAA Operational Effects What Is Working Well What Issues, If Any Community Effects What Is Working Well What Issues, If Any 2

ABOUT DFW DFW is the 3 rd busiest airport in the World DFW ranks 7 th in the world in terms of annual passengers DFW has over 18,000 acres of land (larger than the island of Manhattan) Seven runways! 279 VFR Ops per Hour Highest in US Five Passenger terminals 155 Gates 20 Passenger Airlines serving DFW 20 Cargo Airlines; International growing at 11% annually Enough capacity to last until 2020 without building any more infrastructure 9,000 Acres of pristine, undeveloped land DFW Airport is situated halfway between its owner cities of Dallas and Fort Worth but is not contiguous to either city. 3

DFW S NOISE HISTORY Before Airport was built, North Central Texas Council of Governments commissioned a study in 1971 to create a noise contour forecasting noise exposure with 1985 level operations. Noise Contour and Draft Land Use Ordinance was promulgated to DFW s surrounding cities to control land use in flight corridors. Cities adopted and most still use TODAY! IMPLEMENTING RNAV DEPARTURE PROCEDURES AT DFW AIRPORT 4

EIS & New Runways In the late 1980s, DFW updated its Airport Development Plan, which projected a need for two new north/south runways one on DFW s east side and one on the west. DFW completed an Environmental Impact Statement in 1992 and received approval from the FAA to build the two new runways conditioned on Specified Mitigation. DFW built the East Runway which opened in 1996. There was much controversy and lawsuits on the EIS and proposed runways that was eventually resolved in the mid-1990s. The West Runway has yet to be built. Proposed West Runway Area of Required Mitigation for East Runway Proposed East Runway 5

East-Side Mitigation Program DFW was required to provide mitigation to those in the 65 DNL noise contour or higher because of the proposed runway. Before DFW could open its 7 th runway (17L/35R), the majority of the mitigation program phases had to be complete. Mitigation for approximately 1,700 parcels which consisted of: Acquisition of over 500 parcels in the 70 DNL (mandatory and voluntary) Sound insulation of 23 parcels (apartments, churches, and schools), and Acquisition of easements and additional compensation of 1,200 parcels in 65 DNL. 6

Other Approved Projects from the EIS: Expansion of Class B Airspace Metroplex Air Traffic System (MATS) Plan Airspace Redesign Approved in 1992; Implemented in 1996. Doubled Airspace Capacity by enabling aircraft to fly parallel arrival routes into DFW, regardless of weather. MAJOR AIRSPACE CHANGE went unnoticed by communities as it was dwarfed by the controversy over the two proposed new runways. 7

Other Approved Projects from the EIS: Expanded Runway Headings Expanded Runway Departure Headings and Waiver Increased options for Departure Throughput FAA did not adopt the additional fanned headings Existing Headings Expanded Headings 8

Pre-RNAV Departure Procedures IMPLEMENTING RNAV DEPARTURE PROCEDURES AT DFW AIRPORT 120 o 130 o Jets departures were spaced at 1.5 minute intervals (at a minimum) to ensure requisite separation in trail. Departing Jets turned to initial assigned headings shortly after take off, often before reaching the departure end of the runway. 155 o The initial headings were flown for 5 nautical miles or more before the jets were allowed to turn on course. 174 o ~ 5 n.m. Slower turboprop aircraft were given early turnouts to keep them clear of the faster jet traffic. Excerpt from Runway Use Plan 170 o Actual flight tracks from May 26, 2004 Subsequent ground tracks vary depending on various factors including wind. 9

RNAV Drivers: Transition from Turboprops to Jets TP s 27% TP s 5% Between 1999 and 2004, airlines replaced turboprop aircraft with Regional Jets. As jets must fly for five miles before turning, the effect was an increase in the volume of traffic on the jet corridors. Jets 73% May 1999 Jets 95% May 2004 ---- Jets ---- Turboprops ---- Props 10

RNAV DRIVERS Departure delays increased DFW Airport again called upon the FAA to implement the Expanded Fanned Headings Conventional procedures and current waivers limited FAA s ability to use the expanded headings. FAA turned to RNAV for an effective solution 11

RNAV DEVELOPMENT Local Air Traffic Control reviewed do s/don t s from other RNAV airports i.e. Las Vegas Worked closely with airlines in design SIDS linked to departure gates route assignment based on destination. Tested procedures in simulators Refined through multiple flight testing scenarios. DFW RNAV Departures are NOT Noise Abatement Procedures.. 98 EAST GATE RNAV DEPARTURES AUGUST 9, 2005 1100Z-1700Z N 12

Noise Affects of RNAV FAA requested DFW s help with NEPA requirements; DFW developed noise contours with and without RNAV Airport developed before/after RNAV contours to determine course of action: EA or Cat-X. No significant impacts with RNAV. FAA instead used data to prepare written re-evaluation of previous NEPA work. With RNAV Without RNAV 13

Communicating RNAV to the Community No requirement for public communication but DFW chose to brief local cities. FAA and DFW Noise Staff conducted briefings to cities as they desired, i.e. city staff only, city council, both. One City, Coppell, wanted Council briefed and local reporter picked up on story. Negative Headlines about Procedures went to local Coppell residents Announcing the then proposed start date of October 12, 2004. 14

Community Response: Announced Date vs. Actual Start Date 24 Complaints received week of Oct 12, 2004: Date RNAV expected to start by Coppell Residents per newspaper article. [Coppell in blue]. Eight Complaints from week of actual start date of Nov. 1, 2004: The 3 Coppell complaints of Nov. 1 were not related to departures. 15

RNAV Issues: Loss of Separation RNAV flew for 2.5 days. Issues arose with track compliance by some aircraft resulting in a loss of required separation for aircraft on parallel tracks. There were also issues with separation criteria between RNAV and non-rnav. FAA had to suspend, redesign, and resubmit for publishing. Revised procedures began September 5, 2005. Variability of turn radius between 5 mile turn and 8 mile turn resulted in loss of required 3-mile separation for aircraft on parallel tracks. 16

Redesigned RNAV Before and After RNAV Flight Corridors RNAV DEPATURE ROUTES CONVENTIONAL DEPATURE ROUTES 17

RNAV Departures - Precision Flight Paths IMPLEMENTING RNAV DEPARTURE PROCEDURES AT DFW AIRPORT 5.0 Miles RNAV Departures 1.6 Miles 354 o 354 o 1.3 Miles Conventional Departures 340 o 010 o Width of RNAV Course.25-.30 Miles Wide with 150-250 departing jets within the corridor. 18

Before and After RNAV Track Density NON-RNAV DEPATURES IMPLEMENTING RNAV DEPARTURE PROCEDURES AT DFW AIRPORT RNAV DEPATURES 19

RNAV Operational Effects What Works Well 14% Increased Departure Throughput: Turbojet flows increased from 2 to 4 Aircraft departing at <1.5 min. intervals. 95% of Fleet equipped Precise, consistent flight patterns Reduced Frequency Congestion More direct routing Enhances capability to segregate aircraft by route; less in trail 20

RNAV Operational Effects Issues Related to Increased Track Distance PRE-RNAV ROUTE TO SOLDO FIX RNAV procedures are published routes with built-in separation with other RNAV routes; In four specific cases, it lengthens the routes over conventional SIDS; To reduce flight time/fuel burn, FAA often vectors RNAV aircraft if there is no other aircraft on the parallel track. RNAV ROUTE TO SOLDO FIX Before RNAV, Aircraft flew an initial heading for 5 miles and then turned and were vectored to their departure gate 21

RNAV Operation Effects American Airlines Proposed Solution Proposed Route Existing Route 22

RNAV Operational Effects Issues Related to Flexibility During Weather 23

RNAV Operational Effects Issues Related to Flexibility During Weather 24

RNAV Community Effects Issues with Proximity of RNAV Corridors in NE Conventional Departure Tracks RNAV Departure Tracks 25

RNAV Community Effects Issues with Proximity of RNAV Corridors in SE Conventional Departure Tracks RNAV Departure Tracks 26

RNAV Noise Effects What Worked Well Advanced Notification of Community Leaders and Continued Transparency Enhanced Acceptance of Procedural Change Reduced Population Exposed in 65 DNL by 22% (mostly in multi-family) Substantially Reduced Areas of Overflights Areas where noise increased were less than FAA Thresholds Complaints Continued to Decline 27

DFW Noise Complaint Trends Today ay IMPLEMENTING RNAV DEPARTURE PROCEDURES AT DFW AIRPORT RNAV Implemented: September 2005 2008 Complaints Year To Date = Only 82 (as of Oct. 10, 2008) 28

Summary RNAV Departure Procedures has greatly enhanced FAA s ability to optimize DFW s airfield and the DFW Airspace. RNAV could have been a very controversial implementation. RNAV s acceptance by the local communities is believed to be the direct result of good relations forged with local cities in the mid-1990s and continually nurtured today. DFW expects to incorporate RNAV or RNP into its arrival procedures in the future as part of the NextGen Evolution. 29

Thank You! FOR MORE INFORMATION CONTACT: SANDY LANCASTER slancaster@dfwairport.com PHONE: 972-973-5573