Alternatives Analysis EXECUTIVE SUMMARY

Similar documents
BNA Master Plan Update Community Advisory Committee Meeting No. 5

AIRPORT MASTER PLAN UPDATE

BNA Master Plan Update Public Meeting No. 2

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

Westover Metropolitan Airport Master Plan Update

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

CHAPTER 4: ALTERNATIVES

SouthwestFloridaInternational Airport

Tampa International Airport Master Plan Update. December 12, 2012

Norfolk International Airport

What is an Airport Master Plan?

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4

Current and Forecast Demand

STUDY WORK GROUP MEETING No. 4. July 12, 2017

FORECASTING FUTURE ACTIVITY

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway

Master Plan Update Community Advisory Committee Kick-off Meeting

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

STUDY WORK GROUP MEETING No. 3. November 29, 2016

GREATER ORLANDO AVIATION AUTHORITY

City of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport.

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan

8.0 AIRPORT LAYOUT PLANS

Fort Wayne International Airport Master Plan Study. Executive Summary

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT

The CLE Master Plan Includes:

General Aviation Master Plan Update

Savannah / Hilton Head International Airport Master Plan Update

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

2 Existing Facilities and Conditions

Westshore Development Forum Presented by: Alice J. Price, AICP, Senior Project Director

Charles H. Ada II Executive Manager A.B. Won Pat International Airport Guam

CHAPTER 1 EXECUTIVE SUMMARY

State of the Airport Robert S. Bowen, Executive Director October 18, 2018

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Punta Gorda Airport Master Plan Update

2015 PURDUE ROAD SCHOOL March 11, 2015

MASTER PLAN CONCEPT 1 DRAFT

City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.

Addendum - Airport Development Alternatives (Chapter 6)

Table of Contents. Overview Objectives Key Issues Process...1-3

3.9 AIRPORT SUPPORT FACILITIES

Hartsfield Jackson Update prepared for:

Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM

CHAPTER 5: Landside Facility Requirements and Development Concepts

PUBLIC NOTICE ***************************** New Castle Airport. Intention to File a Passenger Facility Charge (PFC) Application

AIRPORT DEVELOPMENT PLAN. Design-Build Institute of America September 8, 2015

2012 AIRPORT MASTER PLAN 2016 ADDENDUM VOLUME 1 SUBMITTED ON: SEPTEMBER 22, 2017

OPERATING DIRECTIVE Number: D Aviation Authority Revised: 03/25/15

msp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010

Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

Aviation Planning in Maine and Our Region. Stacie Haskell Aviation Coordinator & Study Manager Maine Department of Transportation April 27, 2011

SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

SAN JOSÉ INTERNATIONAL AIRPORT

Chapter 5 Airport Development Alternatives

IDENTIFICATION AND EVALUATION OF ALTERNATIVES ST. PETERSBURG-CLEARWATER INTERNATIONAL AIRPORT

PFC Quarterly Status Report September 30, 2016

Study Committee Meeting. September 2015

TO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Meeting #4 Presentation Material DATE: July 18, 2017

MASTER PLAN UPDATE GRANT NUMBER

PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM

Los Angeles International Airport (LAX) Airside $907M

8 Aviation Support. 8.1 Aerodrome Rescue and Fire Fighting Services. 8.2 Aircraft Refuelling. 8.3 Air Cargo

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

Table E-3 Phased Capital Improvement Program...E - 11

Lake Tahoe Airport Master Plan

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Public Information Meeting. September 2015

What is the ABIA 2040 Master Plan?

2017 Appropriation Budget Table of Contents Board Approved August 19, 2016

ENVISIONING AUSTIN s Airport of the Future

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019

Grants Pass Airport Master Plan & Airport Layout Plan Update

Alternatives. Introduction. Range of Alternatives

Executive Summary DRAFT

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)

Kansas City Aviation Department. Update to Airport Committee Customer Service

EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE

COMMERCIAL AND GENERAL AVIATION Historic and forecast FDOT aviation activity information on file for Pensacola Regional Airport:

CatExes vs. EAs When and How to Prepare

MASTER PLAN GEORGE BUSH INTERCONTINENTAL AIRPORT/HOUSTON. Houston Airport System Houston, Texas DRAFT TECHNICAL REPORT.

Regular Board Meeting August 4, 2015

TERMINAL DEVELOPMENT PLAN

Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, Shannon Eibert, C&S Companies

A. CONCLUSIONS OF THE FGEIS

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Chapter 2 FINDINGS & CONCLUSIONS

Birmingham Airport 2033

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS

AIRPORT IRREGULAR OPERATIONS (IROPS) PLAN. South Bend International Airport (SBN) St. Joseph County Airport Authority

DETROIT METROPOLITAN WAYNE COUNTY AIRPORT (DTW) & WILLOW RUN AIRPORT (YIP) MEDIA ACCESS GUIDE

Transcription:

Alternatives Analysis EXECUTIVE SUMMARY Alternative development plans were created as part of the Master Plan for Harrisburg International Airport. The aim is to provide sufficient capacity for projected long-range activity and to address any previously identified operational or capacityrelated deficiencies over the next 20 years. A full description of the alternatives analysis is provided in Interim Report #3 Alternatives Analysis, submitted to the Airport in September 2014. The alternatives were developed to a level of detail appropriate for conceptual planning of airfield, passenger terminal, landside access and parking, air cargo functions, fixed-base operator (FBO) facilities, and the Pennsylvania Air National Guard (PaANG). Each set of alternatives included a preliminary evaluation. The purpose of the evaluation is to aid Airport leadership in identifying factors that should be considered in the selection of a preferred alternative. A preliminary evaluation of the FIS alternatives is included on page 2. All other preliminary evaluations are shown on page 8. Some generalized evaluation criteria include: Duration the length of time during which the alternative meets demands Customer Service the level of service a customer experiences Flexibility the amount of area remaining for (a) expansion beyond the planning period or (b) for alternative uses Cost the estimated construction cost of the alternative, including soft costs (e.g., project management, design, contingencies, etc.) Implementation potential impacts on the implementation of an alternative, such as environmental impacts, contractual impacts, etc. Other additional impacts that may not be categorically included in the previous criteria Airfield The existing airfield facilities provide ample capacity for projected aircraft operations. The following taxiway improvements should be undertaken to comply with existing design standards: Meet surface gradient standards for Aircraft Approach Category D for fillets between Taxiway A and Taxiways D and F (although the FAA has approved a modification of standards, the Airport should not view it as a permanent situation as they FAA could change that designation). Widen shoulder widths on Taxiway A to 25 feet wide to meet Taxiway Design Group 5 criteria. The airport would also like to provide airfield access to the Crawford Station site, near the threshold of Runway 31. Private developers have previously presented conceptual development ideas to the Airport and the Airport would like to ensure that the site will be accessible to the airfield.

Federal Inspection Services(FIS) Facility Alternatives The existing terminal meets projected longrange demand for all but three functions: (1) the security screening checkpoint, (2) post-security concessions, and (3) post-security restrooms. The deficiencies for these three functions can be met with minor modifications to the existing building. The Airport currently does not have an Federal Inspection Services facility and can only support scheduled or chartered international services that are pre-cleared for U.S. entry. Alternatives for constructing a mini-fis facility at the Airport are shown on this page. This facility includes space required for primary processing (immigration check), secondary processing (baggage claim and customs), and support and administrative spaces for the U.S. Customs and Border Protection Agency (CBP). Passenger Terminal, Level 1 LEGEND Partition wall for domestic use Partition wall for international use Primary and secondary processing Support facilities 2 ALTERNATIVES ANALYSIS, Harrisburg International Airport

Ground Transportation and Parking Alternatives The Airport roadways, curbsides, and rental car facilities are expected to provide the necessary capacity to meet longterm demand. It is contemplated that the Airport will provide a connection between the new Amtrak station in Middletown and the terminal. This connection is expected to be provided via a bus route. It is recommended that the bus route be provided via a mini-bus on a 3.5 mile loop on Airport Drive. Existing parking facilities provide approximately 6,920 spaces, which provide ample capacity for both employee and public parking demands through the planning period. The figure below shows the existing parking facilities, both open and closed. There are various potential utilizations of the existing parking facilities that might improve revenue, the customer experience, or operational costs: Alternative 1 continue utilizing the existing garage for close-in and shortterm parking and the existing longterm/economy parking lot. Option A Continue operations as-is, maintaining a busing operation. Option B Divide the existing garage into two parking products, charging less for parking on the uncovered Level 4 in an effort to attract parkers from the Economy Lot to the garage. Alternative 2 move economy/ long-term parking to the Old Terminal Lot. Prices would be adjusted to encourage a larger proportion of parkers to use the garage. Option A The garage remains as currently operated and the Old Terminal Lot is used as an independent long-term/economy parking facility. Busing to/from the Old Terminal Lot is not provided. Option B The same as Option A, but providing busing to/from the Old Terminal Lot. Option C The same as Option A, but split the garage into two parking products, as described in Alternative 1B. Option D All public parking is charged at a single price, with the Old Terminal Lot serving as overflow parking from the garage, only occupied during peak periods. ALTERNATIVES ANALYSIS, Harrisburg International Airport 3

Air Cargo, General Aviation, PaANG Alternatives Air Cargo The demand/capacity and facility requirements analysis identified six items in the air cargo complex that should be considered in the alternatives analysis. These include: The number of aircraft parking positions adjacent to the cargo building is inadequate within 15 years. The existing warehouse area will not meet estimated demand within 5 years. The current landside area corresponding to the cargo facilities is inadequate for semi-truck maneuvering and parking. The cargo tug route to/from the Crossgates Building crosses Olmsted Drive, which creates conflicts between cargo tugs and vehicular traffic on Olmsted Drive. Vehicular traffic on Olmsted Drive includes semi-trailer trucks and high peak period traffic volumes at the Air National Guard Base. The military barracks building is deteriorating and should be demolished. The intersection between Olmsted Drive and Airport Drive, located in front of the Old Military Headquarters, is complex and creates unnecessary conflicts and confusion. Replacing it with a simple t-intersection is preferred. The short-listed alternatives on page 5 address these issues. General Aviation An analysis of the FBO facilities indicates AvFlight requires more apron and hangar space than it has today. The alternatives on Page 6 address these deficiencies. Alternative 1 constructs a new hangar facility and expand the existing FBO apron. Alternative 2 constructs a new FBO complex on the site of the old terminal. Alternative 3 constructs a new FBO complex on the Crawford Station site. PaANG Base Parking Current employee auto parking on the base does not meet anti-terrorism and force-protection perimeter and standoff standards. The base is not permitted to modify an existing building unless it meets the standards. As a result, the base would prefer to relocate base parking to outside the existing base perimeter. Alternative ways to meet these needs are shown on page 7. Alternative 1 construct a new serpentine road within the current base perimeter and construct a new parking lot on Crawford Station, which would address the environmental treatment requirements for environmentally hazardous ash pits. Alternative 2 construct a new serpentine road stretching east into Crawford Station and constructing a new parking lot further east on Crawford Station, further addressing the ash pit environmental requirements. Alternative 3 convert a portion of the existing long-term/economy parking lot into base parking. Alternative 4 convert the longterm/economy parking lot overflow into base parking. 4 ALTERNATIVES ANALYSIS, Harrisburg International Airport

Air Cargo Complex Alternatives Alternative 1 Alternative 2 Alternative 3 Alternative 4 Alternative 5 ALTERNATIVES ANALYSIS, Harrisburg International Airport 5

General Aviation Alternatives Alternative 1b Alternative 3 Alternative 2a Alternative 2c Notes: Alternative 1a includes the same hangar expansion as 1b, but includes a much smaller apron expansion. Alternative 2b is similar to Alternative 2a, but locates the FBO offices on the east end of the new hangar. 6 ALTERNATIVES ANALYSIS, Harrisburg International Airport

Pennsylvania Air National Guard (PaANG) Alternatives Alternative 1 Alternative 2 Alternative 3 Alternative 4 ALTERNATIVES ANALYSIS, Harrisburg International Airport 7

For further information, please contact: David E. Spaulding, Deputy Director for Engineering and Planning Susquehanna Area Regional Airport Authority email: DSpaulding@saraa.org