March 2, The Honorable Mayor Williams D. Sessoms, Jr. Members of City Council. Subject: Coastal CIP Presentation to City Council - March 6, 2018

Similar documents
Neighborhood Dredging SSD Program. Brief to Beaches & Waterways Commission

Q1 Neighborhood Information

Norfolk District North Atlantic Division

Norfolk District North Atlantic Division

St. Augustine Port, Waterway & Beach District. St. Augustine Inlet 2013 draft Inlet Management Plan. March 19, 2013

Proposed Cherry Grove Canals Dredging Project

U.S. Army Corps of Engineers Wilmington District

Buffalo District Navigation Program Overview

SUBJECT: Newark Bay Study Area Coordination Team Meeting, 9 October 2012

Ongoing Projects 3/16/2017 2

Presented to: City of Petaluma City Council

Water Resources Update after NCGA Long Session

MANAGING COASTAL HAZARDS THROUGH BENEFICIAL REUSE OF DREDGED SAND AND AN ADAPTIVE WORKS STRATEGY

Cat Island Chain Background & Access Guide

Economic Impacts of Beach Nourishment in Texas

A Brief History of the Town of Palm Beach Coastal Protection Program. Beach nourishment occurred in Palm Beach as far back as the 1940s.

USACE GALVESTON DISTRICT PROJECT UPDATE

Annual Port Review. June 22, 2016

Mr. Jeff Keever Deputy Executive Director Virginia Port Authority May 2, 2012

2012 Texas Water Conservation Association Meeting

7/21/2014. New Jersey Waterway Debris Removal from Superstorm Sandy: Unprecedented! Superstorm Sandy. Superstorm Sandy.

HARBOR INFRASTRUCTURE INVENTORIES Erie Harbor, PA

October 7, 2016 Hurricane Matthew Rakes the East Coast of Flagler County for 18.1 Miles

30 November Randall G. Hintz Chief, Operations Support Branch Operations Division. US Army Corps of Engineers BUILDING STRONG

Port of Durban. Entrance Channel Widening & Deepening Project Completion Function. 31 March 2010

DAMAGE ASSESSMENT OF SAND FENCING GARDEN CITY, NORTH LITCHFIELD AND LITCHFIELD BEACH GEORGETOWN COUNTY, SC

Stakeholder Meeting #1. An Introduction to the Blind Pass Inlet Management Study

Amtrak service available to Virginia Beach, (800)

Georgetown-Lewes Rail/Trail Study. Rail/Trail Study: Cool Spring to Cape Henlopen State Park New Road Extension (House Resolution No.

The major parties key coastal policy initiatives

Port Everglades Overview

Introduction and Company Overview

SAN ANTONIO RIVER IMPROVEMENTS PROJECT. August 6, 2008

CORPS OF ENGINEERS ALASKA DISTRICT Dredging Projects. Michael Tencza, PE Operations Project Manager November 4, 2015

Update Report - Etobicoke Creek and South Mimico Creek Trails

4.0 Context for the Crossing Project

Waterfront Plan Working Group Meeting Maritime & Water-Dependent Uses Meeting Agenda

The Honorable William D. Sessoms, Jr. Members of City Council. Dear Council Members: RE: Hillier Fitness Park

Riverine Sand Mining/Scofield Island Restoration (BA-40)

2011 Nags Head Beach Nourishment Project Update. Tim Kana & Haiqing Kaczkowski

Baltimore Harbor & Channels, Maryland and Virginia

Central Beach Entertainment District. Public Engagement Workshop March 15, 2018

NEW TECHNOLOGIES AND THEIR IMPACT ON PORT DEVELOPMENT IN JAMAICA. Christopher Hamilton May

2. The EPA provided the following information regarding EPA s activities in Newark Bay during the meeting:

Port of Kalama, New Approach to Maintenance Dredging

Aid to Local Ports FY19 Requests

SECTION 106 ACTIVITIES ANNUAL REPORT

Port Everglades Master/Vision Plan Update

NC Dredge Studies NCBIWA Spring Conference April 23, 2018

Port Everglades: Making The Last Mile Count. AAPA Annual Convention November 3, 2015

HARBOR ACADEMY HISTORY AND FINANCE. February 28, 2019

MEMORANDUM. Honorable Mayor and City Councilmembers William S. Joynes, Sr., City Administrator

Agenda Report. Spruce Street Outlet Drainage Improvements Tower Road Relief Sewer

WELCOME! TSPE DFW MID-CITIES. January Chapter Meeting

CITY COUNCIL AGENDA MEMORANDUM

Downtown Frederick Hotel and Conference Center BRIEFING.

STREAKED HORNED LARK. Conservation of a threatened species in an industrial landscape. Cat Brown US Fish and Wildlife Service

SAME/SBA CONFERENCE. Col. Christopher W. Sallese Commander, Galveston District U.S. Army Corps of Engineers April 11, 2012

PORT EVERGLADES SAND BYPASS PROJECT

Dogpatch Community Task Force Meetings. April 24, 2017 Meeting #6

NC Dredge Studies. Sterling Baker, P.E. NCDOT James Gregson NCDEQ April 5, 2018

Clam Harbour Provincial Park

Trinity River Vision Update

The Galveston Seawall

APPENDIX 20 EFFECTS ON NAVIGATIONAL SAFETY

Coastal Management: Treasure Island - Long Key Nourishment

AIRPORT COMMITTEE MEETING AGENDA September 06, :00 PM Moorhead Municipal Airport

Galveston Bay Estuary Program. Carla G. Guthrie, Ph.D. Galveston Bay Council Member Texas Water Development Board

EFFECT OF THE COASTAL CONSERVATION DUE TO BEACH NOURISHMENT OF TOTORI SAND DUNE COAST

Superstorm Sandy: State of New Jersey Waterway Debris Removal Project. ~For Official Use Only~

Location. Location. Location. just one of many reasons that keeps Chesapeake, VA, Always Prepared to Do Business.

BOND PROGRAMS PROJECTS SCHEDULE AND DELIVERY

Header i

SAN ANTONIO RIVER IMPROVEMENTS PROJECT. April 27, 2009

Cleveland Harbor Dredged Material Management

Port Everglades. Presented to FMPOAC Freight Committee. July 23, 2015

January 25, House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

1. Overview of Aberdeen Township and Its Waterfront

Using Managed Retreat to Address Coastal Erosion in Brewster

COASTAL CONSERVANCY. Staff Recommendation March 25, 2004 SONOMA COUNTY COASTAL TRAIL, PHASE I. File No Project Manager: Richard Retecki

Holgate Taxpayers Association Spring Membership Meeting Minutes - June 2, 2018

RESORT AREA STRATEGIC ACTION PLAN (RASAP) STEERING COMMITTEE MEETING - APRIL 3, 2019

DRAFT GENERAL IMPLEMENTATION PLAN AND SPECIFIC IMPLEMENTATION PLAN MIDDLETON MUNICIPAL AIRPORT MOREY FIELD. Revised 12/12/03

COMMONWEALTH OF THE BAHAMAS MINISTRY OF PUBLIC WORKS & TRANSPORT NASSAU HARBOUR PORT IMPROVEMENT PROJECT. Nassau Harbour Port Improvement Project

2016 Regional Transportation Alternatives Program (TAP) Grant Application

MAP AMENDMENT/HEIGHT MAP AMENDMENT SUMMARY. Three stories above River Street Two stories above River Street

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

Nassau County Bridge Authority (N.Y. Public Authorities Law 651) 2011 Annual Report

www: vermilionparishpolicejury.com

PROGRESS REPORT WATERFRONT PROGRAM. Q (January - March) Highlights from Q1 2018

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET

Great Lakes Navigation System Buffalo District

REVISED DRAFT Integrated Hurricane Sandy General Reevaluation Report and Environmental Impact Statement. Atlantic Coast of New York

Nassau County Bridge Authority (N.Y. Public Authorities Law 651) 2007 Annual Report

Engineering With Nature Geographic Project Mapping Tool (EWN ProMap)

Port Everglades 2014 Master/Vision Plan Update

Jason J. Hull, P.E. Director of Engineering. Port Freeport 1100 Cherry Street Freeport, Texas

Virginia Association of Railway Patrons 2008 Annual Meeting March 1, 2008

CITY OF BROOKFIELD Capital Improvement Fund Budget

Transcription:

OFFICE OF THE CITY MANAGER (757) 385-4242 (757) 427-5626 FAX MUNICIPAL CENTER BUILDING 1, ROOM 234 2401 COURTHOUSE DRIVE VIRGINIA BEACH, VA 23456-9001 March 2, 2018 The Honorable Mayor Williams D. Sessoms, Jr. Members of City Council Subject: Coastal CIP Presentation to City Council - March 6, 2018 Dear Mayor and Councilmembers: The attached presentation provides an overview of the Public Works Department FY 2019-2024 Coastal Capital Improvement Program. The presentation provides the current status of projects within the approved CIP, and addresses future funding needs for shore protection and navigation dredging projects. This is one of several Public Works Department CIP presentations that will be provided in the coming weeks, which I believe will be helpful as you review, assess and refine the FY 2019 budget. Respectfully, David L. Hansen City Manager c: Thomas M. Leahy, Deputy City Manager Mark A. Johnson, Interim Director of Public Works

1 FY 2019-2024 COASTAL CIP COUNCIL INFORMATIONAL BRIEFING MARCH 6, 2018

COASTAL CIP SECTION PRESENTATION OUTLINE Program Overview CIP Project Details Emerging Issues and Needs 2

COASTAL CIP SECTION CORE PROGRAMS Beach Replenishment Provides storm protection Supports tourism industry Provides recreational opportunities Navigation Dredging Keeps our inlets and main channels navigable Supports waterfront/marine industry Provides recreational opportunities Underpins waterfront property value Neighborhood Navigation Dredging Restores navigation Revitalizes neighborhoods Those that receive services pay 3

COASTAL CIP SECTION BEACH REPLENISHMENT & NAVIGATIONAL DREDGING PROJECTS 8-409 Chesapeake Beach Restoration 8-010 Sandbridge Beach Restoration II 8-026 Sandbridge Beach Restoration III 8-021 Croatan Beach Restoration 8-025 Beach Replenishment II 8-020 Bay Beaches Resiliency Study and Restoration 8-015 Beach Profile Monitoring Program II 8-406 Rudee Inlet Federal Dredging II 8-407 Rudee Inlet Outer Channel Maintenance Dredging II 8-402 Replacement for Rudee Inlet Dredge 8-013 Lynnhaven Inlet Maintenance Dredging II 8-011 Various Minor Dredging Projects II 8-110 Eastern Branch Lynnhaven River Maintenance Dredging 8-405 Sandbridge Beach Access Improvements II 8-408 Pleasure House Point Mitigation 8-024 Pleasure House Point Mitigation Funds 4

8-409 CHESAPEAKE BEACH RESTORATION Major beach restoration project proposed with periodic maintenance Critical for coastal protection and resiliency, most erosive section City s coastline without a funded nourishment project in place VIMS sand study completed in December 2011 Favorable court ruling that public interest in beach does exist Final design and permitting nearly complete Construction planned for Spring 2018 $7,470,000 $4,820,000 $0 $0 $0 $0 $2,650,000 $0 5

8-010 SANDBRIDGE BEACH RESTORATION II Long-term federal beach restoration and maintenance project Local funding provided by the Sandbridge Special Service District (SSD) and Tax Increment Financing District funds (TIF) Three-year (estimated) cyclic beach replenishment and maintenance Last replenishment completed in June 2013, 2.18 million CY ASBPA 2018 Best Restored Beach Award This project will fund the next replenishment cycle planned for late 2018 $22,550,000 $22,550,000 $0 $0 $0 $0 $0 $0 6

8-026 SANDBRIDGE BEACH RESTORATION III Long-term federal beach restoration and maintenance project Local funding provided by the Sandbridge Special Service District (SSD) and Tax Increment Financing District funds (TIF) Three-year (estimated) cyclic beach replenishment and maintenance Last replenishment completed in June 2013, 2.18 million CY ASBPA 2018 Best Restored Beach Award This project will fund subsequent replenishments beyond the 2018 cycle $43,875,000 $6,050,000 $6,050,000 $6,355,000 $6,355,000 $6,355,000 $6,355,000 $6,355,000 7

8-021 CROATAN BEACH RESTORATION Provides funding for design, permitting, and initial placement Maintains minimum recreational beach width of 100-120 feet between toe of dune and MHW Restores dune volumes at erosional hot spots to minimize potential for wave overtopping during 1% annual probability storm event Final design underway Construction planned for Fall 2018 $1,760,000 $1,760,000 $0 $0 $0 $0 $0 $0 8

8-025 BEACH REPLENISHMENT II This project replaces CIP 8-008 Big Beach 2001-2002, 4.1 million CY Resort Beach from Rudee Inlet to 89 th Street Last replenished in August 2013, 1.44 million CY Fully funded project critical to leverage Federal matching funds Condition surveys indicate a need for a 2019 replenishment project $12,350,000 $2,650,000 $2,250,000 $2,350,000 $2,550,000 $2,550,000 $0 $0 9

8-020 BAY BEACHES RESILIENCY STUDY AND RESTORATION Initiates preliminary planning, design, and permitting framework necessary for a programmatic shore protection and beach management strategy for Cape Henry and Ocean Park beaches Determines need and level of protection required Provides an engineered beach required for eligibility for federal disaster relief funds Preliminary design underway $4,125,000 $125,000 $2,000,000 $2,000,000 $0 $0 $0 $0 10

8-015 BEACH PROFILE MONITORING PROGRAM II Periodic beach profile surveys of portions of the City s coastline from the NC border to Little Creek Surveys provide data used to monitor our beaches for sand replenishment projects and programs $795,000 $160,000 $110,000 $125,000 $125,000 $125,000 $75,000 $75,000 11

8-406 RUDEE INLET FEDERAL DREDGING II Periodic maintenance dredging of Rudee Inlet and connecting waterways Cost participation with U.S. Army Corp of Engineers Maintenance dredge approximately 3-4 times per year based on condition surveys Latest USACE dredging attempted January 2018, volume dredged was limited due to rough sea conditions Future maintenance dredging visit by USACE Currituck planned for April 2018 Full depth USACE contract dredging planned for Fall 2018 $5,110,000 $2,435,000 $425,000 $450,000 $450,000 $450,000 $450,000 $450,000 12

8-407 RUDEE INLET OUTER CHANNEL MAINTENANCE DREDGING II Maintenance dredging of deposition basin in the outer portion of Rudee Inlet Planned two year maintenance cycle subject to federal appropriations for contract dredging Latest dredge completed December 2013 Next dredging planned for Fall 2018 in conjunction with USACE full depth federal channel dredging. $8,025,000 $3,575,000 $700,000 $750,000 $750,000 $750,000 $750,000 $750,000 13

8-402 REPLACEMENT OF RUDEE INLET DREDGE Rudee II is a River Class dredge vessel built in 1987 and put into operation in 1988 Requires overhaul every 5 years, for engine servicing and re-painting Rudee Inlet inner channel and sand trap dredged daily Funding needed to purchase a replacement dredge and for major bulkhead repairs at the dredge operations berthing facility $5,000,000 $0 $0 $5,000,000 $0 $0 $0 $0 14

8-013 LYNNHAVEN INLET MAINTENANCE DREDGING II Periodic maintenance dredging of Lynnhaven Inlet and connecting waterways Cost participation with U.S. Army Corp of Engineers Planned three year maintenance cycle subject to federal appropriations Last full channel dredging completed December 2013 Minor dredging completed November 2017 Next major dredging planned for Fall 2018 City is pursuing a contributed funds agreement to allow full depth dredging Programmed Funding Appropriated to Date FY2019 $3,467,450 $1,242,450 $350,000 $375,000 $375,000 $375,000 $375,000 $375,000 15

8-011 VARIOUS MINOR DREDGING PROJECTS II Dredging of navigational channels in various internal waterways located throughout the City Crab Creek dredging last completed in February 2018 Next Crab Creek dredging planned for February 2019 $3,875,000 $1,500,000 $375,000 $400,000 $400,000 $400,000 $400,000 $400,000 16

8-110 EASTERN BRANCH LYNNHAVEN RIVER MAINTENANCE DREDGING Dredging of Eastern Branch Lynnhaven River main channel Project includes: Mechanical dredging and truck hauling to Whitehurst Dredged Material Management Area (located off Oceana Blvd.) Design Underway Construction of transfer facility planned for Spring 2018 $5,150,000 $5,150,000 $0 $0 $0 $0 $0 $0 17

8-405 SANDBRIDGE BEACH ACCESS IMPROVEMENTS II Beach Access improvements to provide safe access to the beach Project funded by Special Service District 2 to 3 access ways slated for improvement each year 60 access ways total identified for improvement (15 completed to date) $3,700,000 $1,775,000 $300,000 $300,000 $300,000 $325,000 $350,000 $350,000 18

8-408 PLEASURE HOUSE POINT MITIGATION Development of a wetlands mitigation facility on City owned property Mitigation Banking Instrument Under Agency Review Potential use for Neighborhood Dredging SSD projects as an option for mudflat impact mitigation Construction planned for Fall 2018 $3,020,000 $3,020,000 $0 $0 $0 $0 $0 $0 19

8-024 PLEASURE HOUSE POINT MITIGATION FUNDS Implementation start up funding Provides financial assurance required by approval agencies for perpetual maintenance Provides required funding for pre-release of credits $575,000 $0 $115,000 $115,000 $115,000 $115,000 $115,000 $0 20

COASTAL CIP SECTION NEIGHBORHOOD DREDGING SSD PROGRAM Supports City Council Goal #4: Revitalize Neighborhoods and Plan for the Future Re-establishes Use of Navigable Channels Program continues to present many challenges (real estate, wetland mitigation and dredging in leased oyster grounds) 21

1. Old Donation Creek 22. Island Lane 2. Bayville Creek 23. Channel Points Lane 3. Shadowlawn 24. Greensboro Avenue 4. Harbour Point 25. Old Shell 5. Chesopeian Colony 26. Owls Creek 6. Gills Cove 27. Pembroke Manor 7. Hurds Cove 28. Lynnhaven Acres 8. Brock Cove 29. Cedar Lane 9. Buchanan Creek West 30. Broad Bay 10. Dix Creek II 31. Little Haven Cove 11. Sea Breeze Cove 32. Jody Cove 12. Schilling Point Legend: 33. Witchduck Cove 13. Thoroughgood Cove & Dredging Completed (4) Bayville Creek West 34. Witchduck SSD Ordinance Established in 14. Hebden Cove 35. Sandy Point Permit Application Phase (3) 15. Witchduck Bay 36. Robin Hood Forest II Petition Phase (2) 16. Witchduck Point 37. Dix Creek Requesting Petition (3) 17. Oyster Bluff 38. Little Neck Creek 18. Winthrope Cove 39. Buchanan Creek Interest Phase (24) 19. Little Neck Cove 40. Thoroughgood Cove 80% Interest Not Achieved (6) 20. Brown Cove 41. Baycliff 21. River Haven 42. Robin Hood Forest 22

8-500 OLD DONATION CREEK NEIGHBORHOOD DREDGING SSD Adopted 9/13/2011 62 properties involved and approximately 26,000 CY of dredging First cycle dredging completed late Spring 2016 $1,506,475 $822,475 $0 $0 $0 $114,000 $570,000 $0 23

8-501 BAYVILLE CREEK NEIGHBORHOOD DREDGING SSD Adopted 3/27/2012 12 properties involved and approximately 14,000 CY of dredging First cycle dredging completed February 2016 $1,548,753 $1,000,753 $0 $0 $0 $92,000 $456,000 $0 24

8-502 SHADOWLAWN NEIGHBORHOOD DREDGING SSD Adopted 3/12/2103 31 properties involved and approximately 9,000 CY of dredging Project was bid with Harbour Point First cycle completed February 2017 $657,310 $406,310 $0 $0 $0 $0 $42,000 $209,000 25

8-504 HARBOUR POINT NEIGHBORHOOD DREDGING SSD adopted 1/14/2014 46 properties involved and approximately 5,000 CY of dredging Project was bid with Shadowlawn Dredging underway First cycle completed February 2017 26 Programmed Funding Appropriated to Date FY19 FY20 FY21 FY22 FY23 FY24 $412,162 $282,162 $0 $0 $0 $0 $22,000 $108,000

8-503 CHESOPEIAN COLONY NEIGHBORHOOD DREDGING SSD adopted 8/13/2013 131 properties involved and approximately 30,400 CY of dredging Dredging plans are complete, permits issued Dredging planned for Spring 2018 start $4,714,034 $2,677,034 $0 $0 $0 $0 $340,000 $1,697,000 27

8-016 GILLS COVE NEIGHBORHOOD DREDGING SSD adopted 3/25/2014 24 properties involved and approximately 13,000 CY of dredging Dredge master plan and permit application under agency review submitted Dredging planned for early 2019 $1,370,719 $781,786 $0 $0 $0 $0 $98,156 $490,777 28

8-505 HURDS COVE NEIGHBORHOOD DREDGING SSD adopted 1/20/2015 91 properties involved and approximately 59,000 CY of dredging Hydrographic survey completed, permit application is being prepared Dredging planned for early 2019 $3,462,000 $3,462,000 $0 $0 $0 $0 $0 $0 29

COASTAL CIP SECTION EMERGING ISSUES AND FUNDING NEEDS Continuation of Funding for shore protection program Beach nourishment provides the benefits of a wider recreational beach but the most critical benefit is resiliency and storm damage reduction Beach nourishment will likely become even more critical in future years as a first line of defense against Relative Sea Level Rise Interest and adoption of new Neighborhood Dredging SSD s is anticipated as more projects are successfully completed 30

31 COMMENTS & QUESTIONS