PFC Application #2 Niagara Falls International Airport

Similar documents
NEW PFC APPLICATION #5

New PFC Application #13

Notice of Air Carrier Consultation Meeting for PFC Application Niagara Falls International Airport (NFIA/IAG)

Public Notice July 14, 2017

PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

PUBLIC NOTICE ***************************** New Castle Airport. Intention to File a Passenger Facility Charge (PFC) Application

14 C.F.R. Part 158. Passenger Facility Charge Program Logan International Airport. Public Notice

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS

PFC NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT ST. THOMAS CYRIL E. KING AIRPORT SEPTEMBER 26, 2018

PEE DEE REGIONAL AIRPORT AUTHORITY FLORENCE REGIONAL AIRPORT

AIRPORT WITH NO RUNWAYS IS A MALL

Passenger Facility Charge Public Notice. February 14, 2018

GREATER ORLANDO AVIATION AUTHORITY

Passenger Facility Charge Application #1

1. Review and approve minutes of regular meeting held December 10, 2015

Notice of Passenger Facility Charge (PFC) Approvals and Disapprovals

Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM

BOARD OF AIRPORT COMMISSIONERS

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018

COMMONWEALTH PORTS AUTHORITY

General Aviation Master Plan Update

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019

Chapter 8.0 Implementation Plan

FAA Reauthorization Issues & Impacts on Airports

Passenger Facility Charge: No. 7 Application. Public Notice Materials. Luis Muñoz Marín International Airport San Juan Puerto Rico.

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

AIRLINE CONSULTATION MEETING

Yakima Air Terminal/McAllister Field Airport Master Plan Update

For Airport Environmental Services. Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018

STUDY WORK GROUP MEETING No. 3. November 29, 2016

Finance and Implementation

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment

City of Tallahassee, FL Department of Aviation

Passenger Facility Charge New Application #8 Phoenix Sky Harbor International Airport

THE CASE OF A SUCCESSFUL PFC APPLICATION

PUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT

Section (a)(1). Description of Projects Impose and Use

Financial Feasibility Analysis

Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application

Chapter 2 FINDINGS & CONCLUSIONS

Beginning balance available for Priority I Projects: $1,737,029

CHAPTER 3 ALTERNATIVES CONSIDERED

BUY AMERICAN PREFERENCE A1.1 SOURCE A1.2 APPLICABILITY. Title 49 USC 50101

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport

Introduction DRAFT March 9, 2017

MassDOT Aeronautics Division Capital Improvements Presentation

COUNTY OF MUSKEGON MUSKEGON COUNTY AIRPORT Rates, Charges and Fee for FY18 October 1, 2017 through September 30, 2018

COUNTY OF MUSKEGON MUSKEGON COUNTY AIRPORT Rates, Charges and Fees for Fiscal Year 2019 October 1, 2018 through September 30, 2019

Amendments to PFC Applications C 03 LAX and C 00 LAX

Nantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

Airport. Improvement Program (AIP) Overview. Federal Aviation Administration. Texas Aviation Conference Ben Guttery, Texas ADO April 2017

AIRLINE CONSULTATION MEETING

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

Office of Airport Safety and Standards

FORECASTING FUTURE ACTIVITY

14 CFR Part 139, Certification of Airports

Session 6 Airport Finance 101 Funding Sources for Airports

Regular Board Meeting August 4, 2015

CHAPTER 1: INTRODUCTION

BURLINGTON INTERNATIONAL AIRPORT

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

WELCOME TO YOUR REGIONAL AIRPORT AUTHORITY MEETING OF THE CITY OF MERCED AGENDA

AIRPORT MASTER PLAN UPDATE

Merritt Island Airport

Public Notice Passenger Facility Charge PFC Application No. 2 Amendment No. 2 Charlotte Douglas International Airport. Effective: February 22, 2019

Appendix 6.1: Hazard Worksheet

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport

AIP Handbook Clarifications

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

Norfolk International Airport

Collier County Airport Authority. Joint Automated Capital Improvement Program

MOST aircraft need a runway for landing and takeout.

Analysis Item 71: Department of Aviation Aurora State Airport Runway Extension

Master Plan Update Technical Advisory Committee Meeting

Welcome to the Boise Airport Master Plan Update Open House

Master Plan Update Community Advisory Committee Kick-off Meeting

SouthwestFloridaInternational Airport

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3

** DETERMINATION OF NO HAZARD TO AIR NAVIGATION **

TECHNICAL ADVISORY COMMITTEE MEETING 3 SEPTEMBER 10, Airport Master Plan

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

Aviation Planning in Maine and Our Region. Stacie Haskell Aviation Coordinator & Study Manager Maine Department of Transportation April 27, 2011

BURLINGTON INTERNATIONAL AIRPORT BOARD OF AIRPORT COMMISSIONERS MINUTES OF MEETING May 22, 2017 APPROVED 6/28/17

PFC Quarterly Status Report September 30, 2016

Ronald Reagan Washington National Airport. April 18, 2012

Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot

Forecast and Overview

I. COMMUNICATIONS II. RESOLUTIONS, MOTIONS AND NOTICES

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.


Ted Stevens Anchorage International Airport

Airport Finance 101 Session 3 - Capital Funding

Ted Stevens Anchorage International Airport

GENERAL INSTRUCTIONS REQUEST FOR STATEMENTS OF QUALIFICATIONS ON-CALL AVIATION PLANNING SERVICES

Presented by Long Beach City Attorney s Office Michael Mais, Assistant City Attorney February 17, 2015

Transcription:

Public Notice Application #2 Falls International April 12, 2018

Agenda Program at the Falls International Notice to air carriers and consultation meeting Class of air carriers not required to collect Air carrier requirements Proposed new application ( #2) Project Information Process and schedule 1 Application #2#14 Falls International

Program at the Falls International imposed since 2017, $4.50 level One approved application FAA approvals for $400,289 Collection authority legal expiration: October 1, 2018 Approx. $500K annual collections 2 Application #2#14 Falls International

Notice to Air Carriers and Consultation Meeting On March 9, 2018, the Authority provided written notice to the air carriers that it would hold this consultation meeting; the notice included: Project descriptions level and total revenue Charge effective and expiration dates Class of air carrier not required to collect the Date, time, and location of air carrier consultation meeting This notice provides all information required under 14 CFR, 158.23(b) and 158.24(b) regarding consultation with air carriers and notice to the public Project descriptions and justifications level, proposed charge effective and expiration dates Estimated revenue for collection and use Detailed project financial plans Contact information for airline and public comments 3 Application #2#14 Falls International

Class of Air Carrier Not Required to Collect Air taxi / commercial operators (ATCOs) Administrative burden of collections would outweigh revenues Currently excluded from collection The following ATCOs provided service to 683 enplaned passengers at IAG in CY 2016: Tradewind Aviation, LLC Atlas Air, Inc. Eastern Airlines Group, Inc. Jet Aviation Flight Services, Inc. Sun Country Airlines Xtra Airways 4 Application #2#14 Falls International

Air Carrier Requirements In accordance with 14 CFR, 158.23, each air carrier shall provide written certification of agreement or disagreement with the proposed application by Monday, May 14, 2018. If an air carrier does not provide certification, the air carrier is considered to have certified its agreement. A certification of disagreement must contain the reasons for such disagreement; the absence of such reasons shall void the certification of disagreement. Airline certifications and public comments should be sent to: Darren Kempner Manager, Grants and Gov't Affairs Frontier Transportation Authority 181 Ellicott Street, New York 14203 Phone: 716.855.7305 E-mail: darren_kempner@nfta.com 5 Application #2#14 Falls International

Proposed New Application #2 Revenue Request $1,087,864 Collect and use May revise downward as analysis continues to refine project eligibility Application details level: $4.50 per eligible enplaned passenger Effective date: October 1, 2018 (upon expiration of #1) Estimated expiration date: October 1, 2020 Pay-as-you-go basis 6 Application #2#14 Falls International

Application No. 2 Project List Project Fiscal Year Proposed Improvement Program Additional Funding Sources Total Project Cost Proj # Description Pay-Go AIP Funds Other Revenue Total 1 Airfield Lighting Vault 047-2017 $18,126 $326,264 $18,126 $362,516 2 Part 77 Obstruction Removal, Design/Construction 2018 $79,188 $1,425,385 $79,188 $1,583,761 3 Parallel Taxiway Program - Phase I and II, Environmental Study and Design 2018 & 2020 $202,139 $3,638,500 $202,139 $4,042,778 4 Airfield Lighting Signage, Design and Construction 2019 $156,411 $2,815,397 $156,411 $3,128,219 5 SRE Building Expansion, Design 2020 $600,000 $0 $0 $600,000 6 Planning and Program Administration 2018-2020 $32,000 $0 $0 $32,000 Total $1,087,864 $8,205,547 $455,864 $9,749,274 - The following project, which was included in the March 9 th notice, has been deleted at this time and may be included in a future application. Access Road Program - Bell Aerospace Property, Land Acquisition $1,000,000 7 Application #2#14 Falls International

1. Airfield Lighting Vault Description: The NFTA is seeking the use of revenue for the local match for AIP project 3-36-0086-047-2017. The project will: replace the 480VAC/3-phase, 250KW diesel emergency generator and Automatic Transfer Switch (ATS) with a new emergency generator and ATS of the same size and capacity. In addition, the project will replace seven Constant Current Regulators (CCR) that control airfield lighting. Justification: All equipment have exceeded their useful life. The project will prevent component failure to the electrical vault. Federal State Total $326,264 $18,126 $18,126 $362,516 8 Application #2#14 Falls International

2. Obstruction Removal, Design/Construction Description: The NFTA is seeking the use of revenue for the local match for a Federal Fiscal Year 2018 AIP project. The project will include design and construction services associated with the removal of vegetative obstructions near the Runway 10L end. Justification: The removal of these obstructions to the approach/departure surfaces allow for safe and efficient use of the airspace per FAA Advisory Circular 150/5300-13A. Federal State Total $1,425,385 $79,188 $79,188 $1,583,761 9 Application #2#14 Falls International

3. Parallel Taxiway Program - Phase I and II, Environmental Study and Design Description: This project will complete the environmental study and design phases for improvements to Taxiway B, its connectors B1 and B2, and rehabilitation of former Taxiway E. The NFTA is seeking the use of revenue for the local match for Federal Fiscal Year 2018 and 2019 AIP projects. Justification: The Sustainable Master Plan proposed a Parallel Taxiway Program to improve the safety, capacity, and flow of the airfield. Federal State Total $3,638,500 $202,139 $202,139 $4,042,778 10 Application #2#14 Falls International

4. Airfield Lighting Signage, Design and Construction Description The purpose of this project is to upgrade the illuminated airfield signs, the wind cone, and control tower beacon at IAG. The NFTA is seeking the use of revenue for the local match for Federal Fiscal Year 2019 and 2020 AIP projects. Justification The existing equipment has exceeded its useful life and does not meet current FAA guidelines. Federal State Total $2,815,397 $156,411 $156,411 $3,128,219 11 Application #2#14 Falls International

5. Snow Removal Equipment Building Expansion, Design Description This project will design the expansion of the existing snow removal equipment building as recommended in the Sustainable Master Plan. The building design will conform to Advisory Circular 150/5220-18A. Justification The s snow removal equipment is currently stored in a facility that has insufficient capacity for snow removal equipment; numerous pieces of maintenance equipment are stored outside due to lack of covered storage. The expansion of the snow removal equipment building is necessary to provide sufficient storage capacity as well as outdoor space for circulation. Federal State NFTA Total $-- $-- $-- $600,000 $ 600,000 12 Application #2#14 Falls International

6. Administration Costs Description The NFTA is seeking the use of revenue for the reimbursement of reasonable and necessary costs specific to work performed for the planning and preparation of this application. The NFTA will use internal staff to perform administrative tasks within this project. Justification Under 14 CFR, 158.13(b), administrative support costs may be paid with revenues. Federal State Total $-- $-- $32,000 $32,000 13 Application #2#14 Falls International

Process and Schedule Milestone Timeframe Notice letter mailed to airlines March 9 Air carrier consultation April 12 Today Public notice April 12 Air carrier comment deadline May 14 Public comment deadline May 14 Submit final application to FAA FAA decision June - July Within 120 days after submission (Expected September) 14 Application #2#14 Falls International