Chippewa-Eau Claire Metropolitan Planning Area Long Range Transportation Plan

Similar documents
Source: Chippewa Valley Regional Airport ASOS, Period of Record

CHAPTER 1 INTRODUCTION AND BACKGROUND

Facility Requirements

DRAFT MASTER PLAN UPDATE

ADVISORY CIRCULAR ON CALCULATION OF DECLARED DISTANCES

CHAPTER 1 BACKGROUND AND PROPOSED ACTION

Preliminary Findings of Proposed Alternative

Hartford-Brainard Airport Potential Runway Closure White Paper

MASTER PLAN CONCEPT 1 DRAFT

FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW

6.1 INTRODUCTION 6.2 AIRSIDE ALTERNATIVES NORTH PERRY AIRPORT MASTER PLAN UPDATE RUNWAY LENGTH REQUIREMENTS SECTION 6: ALTERNATIVES ANALYSIS

Study Committee Meeting. September 2015

Facility Requirements

Chapter 5 Facility Requirements

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016

CHAPTER 3 ALTERNATIVES CONSIDERED

TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan

CHAPTER 5 - FACILITY REQUIREMENTS

Table of Contents. Overview Objectives Key Issues Process...1-3

Appendix A - Glossary

3 INTRODUCTION. Chapter Three Facility Requirements. Facility Requirements PEAKING CHARACTERISTICS

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Public Information Meeting. September 2015

CATCODE ] CATCODE

C > Capacity Analysis and Facility Requirements

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Chapter 4 Airport Capacity Assessment and Identification of Facility Needs

CHAPTER FOUR AIRPORT ALTERNATIVES

AIRPORT FACILITY REQUIREMENTS

Chapter 9 - AIRPORT SYSTEM DESIGN

Chapter 5 Facility Requirements

RECOMMENDED MASTER PLAN CONCEPT

CHAPTER 3 FACILITY REQUIREMENTS

Runway Length Analysis Prescott Municipal Airport

Pierre Regional Airport Airport Master Plan. Kickoff Meeting April 7, 2017

1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION

AIRPORT LAYOUT PLAN FUTURE LEGEND: REVISIONS BUILDING AIRPORT PROPERTY RUNWAY PROTECTION ZONE (RPZ) AIRCRAFT PAVEMENT

Addendum - Airport Development Alternatives (Chapter 6)

TECHNICAL REPORT #3 Palm Beach International Airport Demand/Capacity and Facility Requirements

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport

CHAPTER 1 EXECUTIVE SUMMARY

Chapter 4 Airport Facility Requirements

CHAPTER 1: INTRODUCTION

JANUARY 2013 Friedman Memorial Airport Pomeroy, Chris

DATE OF AERIAL PHOTOGRAPHY:

R FAA

Navigation - Runways. Chap 2, Nolan

BELFAST MUNICIPAL AIRPORT OVERVIEW

AIRSIDE CAPACITY AND FACILITY REQUIREMENTS

Winona Runway Shift Project

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

Chapter One INVENTORY

CHAPTER D Capacity Analysis and Facility Requirements INTRODUCTION

GLOSSARY A.1 ABBREVIATIONS/ACRONYMS

5.0 ALTERNATIVES ANALYSIS

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

STUDY WORK GROUP MEETING No. 3. November 29, 2016

New Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together

3.1 Facility Requirements Overview Airfield Facility Requirements... 1

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Acronyms. Airport Layout Plan Report Appendix A A-1

Reliever Airports: NOISE ABATEMENT PLAN Flying Cloud Airport (FCM)

Table of Contents Facility Requirements Overview Airport Capacity and Delay Analysis... 1

Inventory of Existing Conditions

AIRPORT LAYOUT PLAN FOR FRIEDMAN MEMORIAL REPLACEMENT AIRPORT - SITE 12 FRIEDMAN MEMORIAL AIRPORT AUTHORITY INDEX OF SHEETS SHEET TITLE

Chapter 4 Facility Requirements

Agenda: SASP SAC Meeting 3

CHAPTER 3. Airside Facilities

LAFAYETTE REGIONAL AIRPORT AIRPORT MASTER PLAN JUNE 2015 (REVISED NOVEMBER 2015)

Airport Master Plan. Hutchinson Municipal Airport Butler Field (HCD) Hutchinson, Minnesota. July 2015

Dallas Executive Airport

C H A P T E R 1. Inventory

B GEORGIA INFRASTRUCTURE REPORT CARD AVIATION RECOMMENDATIONS DEFINITION OF THE ISSUE. Plan and Fund for the Future:

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

General Aviation Master Plan Update

Inventory of Existing Conditions.

CHAPTER 2 INVENTORY EXISTING CONDITIONS 2.1 AIRFIELD FACILITIES Airspace

Billy Bishop Toronto City Airport; Porter Airlines Proposal Review; Interim Results/Findings, Airbiz, 26 June 2013

APPENDIX E AIRFIELD PLANNING, DESIGN, & CONSTRUCTABILITY REVIEW

Yolo County Airport. ALP Narrative Report. April Prepared by Mead & Hunt, Inc. for the County of Yolo, California

CEE 5614 and CEE Aircraft Classifications. Spring 2013

Airfield Geometric Design Prof. Amedeo Odoni

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Dallas Executive Airport Town Hall Meeting April 3, 2014

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

ACTION TRANSMITTAL

Airfield Geometric Design Prof. Amedeo Odoni

Airport Master Plan Open House Front Range Airport February 23, 2017

Metropolitan Airports Commission. Flying Cloud Airport (FCM)

Chapter One PROJECT DESCRIPTION

Chapter 5 Facility Requirements

JOHNSTON COUNTY AIRPORT AUTHORITY

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i

II. Purpose and Need. 2.1 Background

CESSNA CITATION IIB PW JT15D-4 INTRODUCTION. Runway Analysis provides the means to determine maximum allowable takeoff and landing weights based upon:

CHAPTER 1. INTRODUCTION

Chapter 4: Facility Requirements

Transcription:

1.2.7 2010 Eau Claire County Comprehensive Plan According to Eau Claire County s most recent comprehensive plan, the County will limit land use development adjacent to EAU in order to preserve the ability of the Airport to continue to grow to meet the future demands of the region. The County supports increased levels of service at EAU for passenger air travel to a greater number of destinations, and also supports the Airport s promotion of compatible land uses neighboring the Airport. 1.2.8 2010 Chippewa County Comprehensive Plan The Chippewa County Comprehensive Plan identifies EAU as one of two publicly-owned airports in Chippewa County. The other publicly-owned airport is Cornell Airport, which is designated as a Basic Utility-A airport by the 2000 Wisconsin SASP. The plan does not identify any specific goals or objectives with relation to the Airport; however, no land use conflicts or policy differences were identified with any state, regional, or county plans and programs. 1.2.9 2010 Chippewa-Eau Claire Metropolitan Planning Area Long Range Transportation Plan The Chippewa-Eau Claire Metropolitan Planning Organization (MPO) was established in 1982 to carry out transportation planning for the metro area. The MPO is comprised of representatives from the numerous cities, villages, townships, and counties in the metropolitan area, including those listed in Table 1-3. Table 1-3: Chippewa-Eau Claire MPO Member Jurisdictions City of Eau Claire City of Chippewa Falls City of Altoona Village of Lake Hallie Eau Claire County Chippewa County Brunswick Township (Eau Claire County) Eagle Point Township (Chippewa County) Pleasant Valley Township (Eau Claire County) Hallie Township (Chippewa County) Seymour Township (Eau Claire County) Lafayette Township (Chippewa County) Union Township (Eau Claire County) Tilden Township (Chippewa County) Washington Township (Eau Claire County) Wheaton Township (Chippewa County) Although its main focus is on streets, highways, public transit, and bicycle/pedestrian facilities, the MPO s 2010 Long-Range Transportation Plan includes a specific objective to consider freight rail, passenger rail, and airports as vital parts of our transportation network. The plan recommends that the Airport continue its efforts to expand intercity passenger air travel options. The plan states that previous highway access problems related to the Airport were alleviated by completion of a U.S. Highway 53 bypass and extension of Melby Street, completed in 2006. The plan also recommends that development activities surrounding the Airport be regulated to maintain its operational effectiveness of the Airport. The Airport is praised in the plan for its recent improvements undertaken in an effort to attract additional air passenger service and recommends that efforts are continued and combined with intercity passenger travel options available to potential air travelers. Chippewa Valley Regional Airport Master Plan (May 2013) 1-16

1.3. EXISTING AIRPORT FACILITIES The FAA airport diagram for EAU is presented in Figure 1-8 and an inventory of major existing facilities at EAU is presented in Figure 1-9. Airside facilities include runways, taxiways, aprons, electronic and visual navigational aids, and weather observation equipment. Landside facilities consist of buildings, roads, and automobile parking lots. The following sections describe existing airport facilities and associated design standards at EAU, as well as current anchor tenants. 1.3.1 Runway Design Code It is important to determine the most demanding aircraft operating at an airport, or design aircraft, as these aircraft have a direct influence on airfield geometric design standards and safety criteria. The design aircraft for an airport are identified by a Runway Reference Code (RRC) and Runway Design Code (RDC). The RRC signifies the current operational capabilities of a runway and its associated parallel taxiway, and the RDC signifies the standards to which the runway is to be built. The RRC and RDC for a particular aircraft consist of two components: approach category (based on approach speed) and design group (based on wingspan and tail height). FAA standard definitions for aircraft approach categories and design groups are listed in Table 1-4. Table 1-4: Aircraft Approach Category and Design Group Definitions Approach Category A Less than 91 Approach Speed (knots) B 91 or greater, but less than 121 C 121 or greater, but less than 141 D 141 or greater, but less than 166 E 166 or greater Design Group Wingspan (feet) Tail Height (feet) I <49 <20 II 49 - <79 20 - <30 III 79 - <118 30 - <45 IV 118 - <171 45 - <60 V 171 - <214 60 - <66 VI 214 - <262 66 - <80 Source: FAA AC 150/5300-13A, Airport Design Chippewa Valley Regional Airport Master Plan (May 2013) 1-17

Source Information: FAA Aeronautical Navigation Products Figure 1-8 Airport Diagram PREPARED BY: MASTER PLAN CHIPPEWA VALLEY REGIONAL AIRPORT (EAU) EAU CLAIRE/CHIPPEWA FALLS, WI May 2013 1-18

Source Information: Mead & Hunt Inc. Figure 1-9 Airport Facility Inventory PREPARED BY: MASTER PLAN CHIPPEWA VALLEY REGIONAL AIRPORT (EAU) EAU CLAIRE/CHIPPEWA FALLS, WI May 2013 1-19

The existing (RRC) and ultimate (RDC) codes for each runway at EAU are listed in Table 1-5. Table 1-5: EAU Runway RRC/RDC Assignments Runway Existing RRC Representative Aircraft Ultimate RDC Representative Aircraft Runway 4/22 D-II Bombardier CRJ200 D-III Boeing 737-800 Runway 14/32 B-II Citation II/Bravo B-II Citation II/Bravo Sources: Airport Layout Plan; Enhanced Traffic Management System Counts 1.3.2 Runways, Taxiways, and Aprons EAU has two runways, Runway 4/22 and Runway 14/32. Runway 4/22 is constructed of treated wirecombed concrete, while Runway 14/32 is constructed of concrete and asphalt. Runway 4/22 is considered the primary runway due to its longer length, superior pavement strength, and available instrument approach procedures. Table 1-6 lists characteristics of each runway, including length, width, lighting, visual glide slope indicator types, weight-bearing capacities, and runway gradients. Table 1-6: EAU Runway Information Runway Length x Width Lighting Visual Glide Slope Indicator 4 REIL, HIRL PAPI 8,101' x 150' 22 MALSR, HIRL PAPI 14 REIL, MIRL PAPI 5,000' x 100' 32 MIRL PAPI Weight-Bearing Capacity (hundreds of pounds) Effective Gradient S100, D180, ST175, DT320 0.33% HIRL = High Intensity Runway Edge Lights MIRL = Medium Intensity Runway Edge Lights REIL = Runway End Identifier Lights MALSR = Medium Intensity Approach Lighting System with Runway Alignment Indicator Lights PAPI = Precision Approach Path Indicator Weight-Bearing Capacity: S-Single Wheel, D-Dual Wheel, ST-Single Tandem, DT-Dual Tandem Source: FAA Airport Facility Directory, 2 MAY 2013 to 27 JUN 2013; FAA Form 5010-1 S40, D60 0.09% The Runway 4 (southwest) threshold for Runway 4/22 is currently displaced by 800 feet in order to provide a compliant RSA, resulting in declared distances for takeoff and landing operations on this runway as shown in Table 1-7. The current Runway 4/22 declared distances, as published as of May 2013, are illustrated in Figure 1-10. Table 1-7: Runway 4/22 Declared Distances Runway TORA TODA ASDA LDA 4 8,101 8,101 8,101 7,301 22 7,301 7,301 7,301 7,301 Note: All distances listed in feet TORA = Takeoff Run Available TODA = Takeoff Distance Available ASDA = Accelerate Stop Distance Available LDA = Landing Distance Available Source: FAA Airport Facility Directory, 2 MAY 2013 to 27 JUN 2013 Chippewa Valley Regional Airport Master Plan (May 2013) 1-20