Regional Connector Transit Project Community Leadership Council. 2 nd Hope Station & Flower St Committees January 17, 2017

Similar documents
Regional Connector Transit Project Community Leadership Council

25 th Avenue Grade Separation. December 13, 2017

25 th Avenue Grade Separation. September 13, 2017

Hospital Link Project Project Update September 2015

Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.

Astoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017

Astoria Boulevard ADA and Station Renewal Track Improvements. January 30, 2019

Train to Plane Connection Construction of the Burbank Airport North Metrolink Station

25 th Avenue Grade Separation. Community Meeting November 13, 2018

Construction Staging Adelaide Street West

Exposition Light Rail Transit Project

PRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction

SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY

Ossington Station Easier Access Project - Construction & Public Art Concept Update

Hospital Link Project Project Update Winter 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018

Item # 28. Chief Capital Management Officer Report. November 20, 2008

Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

June 2017: 700 Piles 9 Weeks and 3 Days Pile Caps / Tie Beams Roof Foundations

Long water shutdown scheduled for Tuesday, September 18

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

Second Street Improvements Project Project Update Archive

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization

Transportation Supporting Dulles Airport

Stage 2 ION: Light Rail Transit (LRT) from Kitchener to Cambridge

Crenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018

State Route 8 Corridor. Northern Summit County s Path to Success

Neighbourhood Committee NDG - Westmount. September 12, 2016

Claremont Project Background and Update Community Meeting September 11, 2017

Commonwealth Avenue Bridge Deck Replacement Project. Legislative and Stakeholder Briefing. April 13, 2017

Trail # NW Tuesday, June DESIGN. Provide an Review the Provide an. Project Goals: System system. wayfinding

Sound Transit Operations August 2015 Service Performance Report. Ridership

IMPLEMENTATION OF COMPREHENSIVE DEVELOPMENT AGREEMENT (CDA) PROJECTS:

Blackburn Road Blackburn Level Crossing Removal. Frequently Asked Questions August 2014 GENERAL

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation

BE VE R LY HILLS CITY OF BEVERLY HILLS HUMAN SERVICES DIVISION MEMORANDUM TO: Human Relations Commission FROM:

1 Metrolinx overview. Mission We connect our communities. Vision Getting you there better, faster and easier

Sound Transit Operations March 2018 Service Performance Report. Ridership

O Hare Noise Compatibility Commission Technical Committee April 19, Proposed Interim Fly Quiet Runway Rotation Plan

Public Information Center August 12, 2010

Hampton Roads Express Lane Network

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

Madison Metro Transit System

THAT the Board approve the final proposed concept plan for the Jericho Marginal Wharf site as shown in Figure C-4 of Appendix C.

Project Overview. Hunter Mill Road Over Colvin Run Bridge Replacement Fairfax County. Get Involved. Public Information Meeting. Contact Information

LESLIE BARNS & CONNECTION TRACK. Leslieville BIA Meeting May 2, 2014

Crystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S.

LESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation

Having trouble reading this ? View it in your browser. Welcome

Noise Mitigation Program

ACCELERATED CONSTRUCTION LANE RENTAL FEES & A+B BIDDING DALLAS DISTRICT. June 7, 2018 Transportation Planning Conference June 7, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting January 31 st, 2018

Chicago St. Louis High-Speed Rail. Enos Park Neighborhood Association May 13, 2014

Important Lane Closures, April 3 9, 2011

January 2018 Air Traffic Activity Summary

QUIET ZONE IMPLEMENTATION PLAN

WHO IS METROLINX?

BUILD. Update CONSTRUCTION. In this issue: FEATURED PROJECT: KENT AVENUE ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEBRUARY 2019

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

NAIOP. Marcia McAllister Metropolitan Washington Airports Authority

Palm Beach County Traffic Report July 13 through July 20, 2012

Mason Street Bike/Pedestrian Trail Project

West Santa Ana Branch Transit Corridor. Community Meetings March 12, 13, 17 & 19, 2018

A63 Castle Street, Hull HullBID Network Lunch 24 August 2017

Kentucky Lock Project Update Inland Waterways Users Board Meeting No. 84

Sound Transit Operations January 2018 Service Performance Report. Ridership

Route 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016

Sample Estimate Reports Estimate Reports were created in XL-Pro Software

June-December TBD, to be coordinated with Accessibility Ramps Project

Sound Transit Operations February 2018 Service Performance Report. Ridership

Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April

TORONTO TRANSIT COMMISSION REPORT NO.

Raleigh Executive Jetport Master Plan Update MPAC MEETING #3 NOVEMBER 1, 2018

Exhibit 2. Preconstruction Jan Jun-19

Transportation Management Program Office Newsletter J A N U A R Y

Metro Senior. pocket guide

NDG-Westmount Neighbourhood Committee. November 16, 2015

Basic Project Information

Expo E-News. Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2. Keeping Our Community Informed

P D E C. Establishment of Opening Dates for New Carrollton Yard and College Park and New Carrollton Parking Garages

Metro Gold Line Eastside Extension Review Advisory Committee May 8, 2008

PROGRESS REPORT. OCTOBER and NOVEMBER 2013

December 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program

Phoenix Sky Harbor transit guideway bridge

PROGRESS REPORT WATERFRONT PROGRAM. Q (January - March) Highlights from Q1 2018

THE BIG PICTURE. Week of March 4, Bring your dog. Bring your kids. Bring a picnic and spend the day with us! Free and open to the public.

About the Foothill Gold Line

First rail. August 2011

China Creek North Park Upgrades and Glen Pump Station. Park Board Committee Meeting Monday, July 10, 2017

Welcome to the Cross County Trail Public Input Session!

TECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018

Construction Staging Area 19 Western Battery Road

Construction Staging Area Blue Jays Way (357 King Street West)

Transcription:

Regional Connector Transit Project Community Leadership Council 2 nd Hope Station & Flower St Committees January 17, 2017 1

EAT SHOP PLAY LOCAL 2

Eat Shop Play Local > Free Metro marketing campaign > Make it easier for the public to Eat at local restaurants Shop at local stores Play at local destinations during and after construction of the Regional Connector Transit Project 3

Eat Shop Play Local > Social Media Promotion > Monthly Newsletter > Eat Shop Play Meet-Ups > Business Spotlights > Vendor Table Opportunities at Metro Headquarters > Business Profiles on Metro.net > Community Partners 4

Eat Shop Play Fortune Fridays > Weekly Social Media Contest > Show Metro how you #EatShopPlay in #DTLA! > Win a limited edition 7-day Metro TAP card > Winners announced on every Friday > First winner: January 27 th > Visit metro.net/riding/eatshopplay 5

2nd/Hope Station CONSTRUCTION UPDATE 6

2nd/Hope Area Schedule Support of excavation (SOE) JAN FEB MAR APR MAY JUN Excavation Tieback and bracing installation Haul out material Invert (station floor) construction Forming, placement of rebar Concrete pour (mud slab, followed by invert) 7

Ongoing Activities & Current Work Hours > Excavation, support of excavation (SOE), bracing and hauling > Approximately 15 20 feet remaining > Work hours: Monday Friday: 7 am 3:30 pm; 3:30 pm 2:00 am Saturday Sunday: 8 am 8 pm 8

2nd/Hope Station PEDESTRIAN BRIDGE DESIGN 9

Station Configuration 10

Elevation View 11

Design Revised in Response to Community Feedback > Design changes include: Removed benches Removed tiered-planters Relocated planters to allow for a more direct pedestrian pathway Reconfigured pathway allows 3 & 2 people on each side of planters Added security gate Added ADA tactile path 12

Initial Design (2016) 13

Updated Design Benches Removed & Planters Relocated 14

Initial Design (2016) 15

Revised Design Benches Removed & Planters Relocated 16

Plan View with Path of Travel 17

2nd/Hope Pedestrian Bridge > Security A uniformed officer at station CCTV cameras Security gate on east end of bridge > Maintenance Metro s custodial services (trash collection, maintenance of rails, floors & glass) Segmented glass panels Trees will be maintained by The Broad through an agreement with Metro 18

Implementation Schedule Design Release January 2017 Design 2017 Construction 2019 19

Flower St/Financial District CONSTRUCTION UPDATE 20

Flower St/Financial District Ongoing/Look Ahead Schedule Activity JAN FEB MAR APR MAY JUN 24 waterline relocation south of 6th St. (nights) Deck installation 4th 5th St. and 5th St. intersection (weekends only) Pre-trenching (weekdays) and piling 5th 6th St (east side) Tieback removal at 3rd St. 6th/Flower - Power relocation (utility investigation south of 5th St) 21

Deck Installation Modified Closure Details > Open: Flower St (3rd to 5th St) and 4th St (Figueroa to Flower St) traffic lane reductions through January 20, 2017 only > Starting at 7 pm, Friday through 5 a.m., Monday > Activities include: Roadway removal Excavation Hanging of utilities Cap beam installation Deck beam installation Deck panel installation Grade deck transition 22

Deck Installation Closure Dates Modified weekend closure dates with one through lane open at Flower St: > 7 pm on January 20 5 am on January 23 Full closure of Flower St resumes and continues every weekend through March: > 7 pm on January 27 5 am on January 30 23

Decking on Flower St, 4th to 5th St > Mitigations Open one Flower St lane (3rd to 5th St); 4th St (Figueroa to Flower St) until January 20, 2017 Activities such as saw cutting, grinding and roadway removal will be performed before 9 pm Sound barriers will be in place Lights will be directed toward the work zone Use of back-up alarms will be minimized Flaggers will assist motorists In-language 24/7 hour hotline 213.922.7277 24

Ongoing Activities > Tieback removal at 3rd Street, excavation completed (on photo) > Back fill operation ongoing through first week of February 25

Ongoing Activities > 24 water line relocation on Flower St, south of 5th and 6th St intersection > Utility investigation south of 5th St in preparation for power relocation > Pile installation at 5 th St/Flower intersection 26

Pile Installation East Side Flower St, 5th to 6th St > Utility investigation Monday Friday, 9 am 3:30 pm Saturday, 8 am 6 pm > Pile Installation From 5th St/Flower intersection to south of 6 th St 27

Pile Installation East Side Flower St, 5th to 6th St March 2017 > Three south bound lanes > One left turn lane 28

STATION NAMING UPDATE 29

Station Naming Update Timeline September through December 2016 Stakeholder outreach/input November through December 2016 Online survey conducted Over 1100 responses received January 2017 Board report pending February 23, 2017 Anticipated Metro Board hearing 30

Contact Us metro.net/regionalconnector twitter.com/metroconnector facebook.com/metroregionalconnector 213.922.7277 * RegionalConnector@metro.net 31