WORK EXPERIENCE (Graphical report) David Manchón Frías Telephone: +34619935043 E-mail: dmfrias@hotmail.com
1. WORK PROFILE HANDLED: Site Manager PROJECTS WORKING ON 1. BUILDING PROJECTS: Urbanization and building of an industrial workshop for an aluminium processing company GAP (Grupo Aluminios de Precisión) Refurbish Works in two office buildings to update them according to the new company organization for ADISSEO International. 2. GENERAL CIVIL PROJECT: Works of Urbanization and updating in Quintanadueñas (Burgos) Works of Urbanization in Castrillo de Matajudios. Works of building of a new Water Regulation Tank in Escobados de Arriba. Works of Urbanization of Bulevar Ferroviario de Burgos Sectors 2-3 and 5 designed by Architect team Herzog & de Meuron. Urbanization Project of José Luís Talamillo Sports Center. Urbanization Project of Bulevar Ferroviario de Burgos in sector 2_accesos sector 27 ciudad del AVE by Herzog & de Meuron. Study of Project and budget for the Urbanizations Works in streets LEÓN Y GLORIA FUERTES, city of Burgos. Planning of works, requirement of budgets, traffic access and regulation study, redaction of final report of Works Execution Project of " Marina San Vicente de la Barquera
Grupo Aluminios de Precisión GAP Urbanization and building of an industrial workshop for an aluminium processing company, Budget 12.100.000. Aims: Economic: Total benefit 23 % (of the invoiced) Site Quality: 99% Security: No accident at work Execution Time: Planned: 12 months (civil works) Used royal time: 8 months (civil works) Number Subcontracted companies: 42 companies Relation with Administrations: Private Site
Grupo Aluminios de Precisión GAP Finished work Air sight of foundations plant Pits machinery and Bombs counter fires
Bulevar Ferroviario de Burgos Sectors 2-3 and 5 Sectors 2-3: 60.849 m 2 Works of Urbanization (Study of initial budget and Project, Planning of Civil Works) Designed by Architect team Herzog & de Meuron Budget sectors 2-3 and 5: 21.400.000
Bulevar Ferroviario de Burgos Sectors 2-3 and 5 Sector 5: 182.348 m 2 Aims: Economic: Adjudication Fall: 8 % Estimated benefit: 6 % (after the adjudication Fall) Site in execution Relation with Administrations: Local administration
Bulevar Ferroviario de Burgos ACCESOS sector 27 CIUDAD del AVE Aims: Works of Urbanization Designed by Architect team: Herzog & de Meuron Budget: 5.900.000. Economic: Total benefit 6 % (of the invoiced) Site Quality: 90% Security: No accident at work Execution Time: Planned: 10 months Used royal time: 12 months Number Subcontracted companies: 25 companies Relation with Administrations: Local Administrations and Private Companies
Bulevar Ferroviario de Burgos ACCESOS sector 27 CIUDAD del AVE
Urbanization Project: CALLE LEÓN Y GLORIA FUERTES Aims: Study of Project and budget for the Urbanizations Works (Planning of works, study and requirement of budgets, traffic access and regulation study, redaction of final report of Works, etc). Designed by PROINTEC (Consulting Company) Budget: 4.100.000 Economic: Total benefit 5,5 % (Adjudication Fall: 9% and Estimated benefit: 4 % after the adjudication Fall) Site Quality: 93% Security: No accident at work Execution Time: Planned: 9 months Used royal time: 10 months Number Subcontracted companies: 5 companies Relation with Administrations: Local Administrations
Urbanization Project: CALLE LEÓN Y GLORIA FUERTES
Different Sites: ADISSEO International: Refurbish Works in two office buildings to update them according to the new company organization (Budget: 134.500 ). Administration Building Technical building
Different Sites: Works of Urbanization Castrillo de Matajudios. (Budget: 260.000 ) Works of Urbanization and updating in Quintanadueñas (Burgos) (Budget: 280.000 )
Different Sites: Urbanization Project of José Luís Talamillo Sports Center (Budget: 365.000 ). Works of building of a new Water Regulation Tank in Escobados de Arriba (Budget: 50.000 ).
2. WORK PROFILE HANDLED: Project Manager PROJECTS WORKING ON 1. BUILDING PROJECTS: Since 11/2009 till 03/2010 Cooperation, supervision and assessment on the design of work reform on a flat located in downtown of Bilbao, another one in Av. America (Madrid), another one in Sector S3 in Burgos. Execution Project of " Regional Center of musical Creation and Production" Former Hangars RENFE's station of Burgos. City hall of Burgos. 2. GENERAL CIVIL PROJECT: Urbanization Project on the U.A.29.01.1 y la U.A.29.01.2 del Plan Especial de la Estación de Burgos Urbanization Project on the SECTOR SAUI-1 de Villagonzalo de Pedernales (Burgos)
U.A.29.01.1 y U.A.29.01.2 del Plan Especial de la Estación Brugos Study, Design and Project direction in phase of project execution. Project Manager in phase of site execution. Budget: 9.500.000 Aims: Economic: 0% Difference between initial budget of bidding and final certification delivered by the construction company Site Quality: 100% Security: No accident at work Execution Time: 2 years Number Subcontracted companies: 2 companies Relation with Administrations: Local administrations and the Private Companies
U.A.29.01.1 y U.A.29.01.2 del Plan Especial de la Estación Brugos
Urbanization Project on the SECTOR SAUI-1 de Villagonzalo de Pedernales (Burgos) Study, Design and Project direction in phase of project execution. Aims: Economic: 5 % Difference between initial budget of biddingand final certification delivered by the construction company Site Quality: 100% Security: No accident at work Execution Time: 1,5 years Relation with Administrations: Local administrations and the Private Companies
Execution Project of " Regional Center of musical Creation and Production" Execution Project of " Regional Center of musical Creation and Production" Former Hangars RENFE's station of Burgos. City hall of Burgos. Study, Design and Project direction in phase of project execution. Project Manager in phase of site execution. Budget: 2.500.000 Gatherings and sections Foundations Flat Counter fires Installation
Execution Project of " Regional Center of musical Creation and Production" Aims: Economic: Precise study of the project and budget, in order the best relation and economic cost offers quality, design Security: No accident at work Execution Time: 1 years Number Subcontracted companies in project execution: 3 companies Relation with Administrations: Local and regional administrations
Execution Project of Marina San Vicente de la Barquera Execution Project of " Marina San Vicente de la Barquera Study, Design and Project direction in phase of project execution. Budget: 4.600.000 Project alternatives: Project: