Wind Energy in South-east Europe: Seminar III: WIND ENERGY PROJECT DEVELOPMENT. Mostar,

Similar documents
Energy Community Regulatory Board Status review of transmission tariffs and treatment of cross - border transmission flows and recommendations By

CROSS-BORDER TRADE IN SERVICES

REPUBLIC OF BULGARIA MINISTRY OF TRANSPORT, INFORMATION TECHNOLOGY AND COMMUNICATIONS

Safety Regulatory Oversight of Commercial Operations Conducted Offshore

EU ECOLABEL USER MANUAL TOURIST ACCOMMODATION Commission Decision for the award of the EU Ecolabel for tourist accommodation (2017/175/EC)

Pumped storage hydroelectric power plants: Issues and applications BIH Case Study

WORLD TRADE ORGANIZATION

Porto Alegre International Airport Salgado Filho Airline Incentive Program

Application for ATO Approval in accordance with ORA.ATO.105

Third Environmental Performance Review of Bosnia and Herzegovina: recommendations

Sida 1 av 7 Ivan Forsman SGHA externa flygbolag doc

A. TARIFF SCHEDULE OF PORT SERVICES

DaHar Danube Inland Harbour Development

Notification to Suppliers

Brexit Preparedness seminar on transport. Council Working Party (Article 50 Format) 29/11/2018

Conference: FOOD CHAIN IN THE DIGITAL SINGLE MARKET Organised jointly with the Slovak Presidency of the Council

Municipal Drone Operations Ben Roper City of College Station

The Ever Changing Faces of Internet Gambling Regulation. Discovery 2011

Abruzzo Airport. Commercial Policy Development Routes

Sida 1 av 7 Ivan Forsman SGHA HMV Kopia

Ministry of environment, mining and spatial planning activities and methane action plan of republic of Serbia Dragana Mehandžić Ministry of

LOCAL CONTENT IN MOZAMBIQUE

Transport Learning Week 2006 Maritime & Air Transport

COMMISSION OF THE EUROPEAN COMMUNITIES. Draft. COMMISSION REGULATION (EU) No /

Supplement No. 17 published with Gazette No. 22 dated 25 October, THE AIR NAVIGATION (OVERSEAS TERRITORIES) ORDER 2007, S.I No.

Importing/Certifying an Aircraft

The Electric Power System

Guidelines and Application Form

HYDROELECTRIC POWER PLANTS ON THE LOWER SAVA RIVER

Public Seminar 30 October 2018, Lisbon. Water sector in B&H

Appendix A - Definitions

HCSS Travel Guidelines

The Potential of Renewable Energy Sources in Bosnia and Herzegovina

Submission to Queensland Competition Authority on Regulated Retail Electricity Prices for regional Queensland

The role of Serbia in the security of supply in Europe

COMMISSION IMPLEMENTING REGULATION (EU)

The DAAO Inspectors should be thoroughly familiar with the regulatory and advisory references when using these instructions.

Short Project Summary Cebren & Galiste Hydropower Project Republic of Macedonia

Aerodrome s Inspector Workshop Sint Maarten 11 to 15 June 2012

CHG 0 9/13/2007 VOLUME 2 AIR OPERATOR AND AIR AGENCY CERTIFICATION AND APPLICATION PROCESS

Load-following capabilities of Nuclear Power Plants. Erik Nonbøl

EASA rulemaking in ATM/ANS. Entry Point North annual AFIS Seminar 5th and 6th of September 2012, Malmö

(Non-legislative acts) REGULATIONS

N Registry Airworthiness & Maintenance Requirements

Brazil and the international electric integration:

CIVIL AVIATION REQUIREMENT SECTION 3 AIR TRANSPORT SERIES C PART I ISSUE IV, 24 th March 2017 EFFECTIVE: FORTHWITH

Elektroprivreda BiH. 6th South East Europe Energy Dialogue (6th SEEED) Redefining SE Europe s Energy Map

Act on Aviation Emissions Trading (34/2010; amendments up to 37/2015 included)

RMT.0464 ATS Requirements The NPA

Briefing for non-ccaa Examiners

Cooperative Development of Operational Safety Continuing Airworthiness Programme. COSCAP-Gulf States. Training of Airworthiness Inspectors

Official Journal of the European Union L 146/7

GUIDE TO AIRCRAFT REGISTRATION AND FINANCING IN THE ISLE OF MAN

Official Journal of the European Union L 186/27

IEEJ: June 2010 JICA JFY 2010 Energy Policy (B) NO. J / ID Country Report: Bosnia and Herzegovina March 2010 Prepared by JICA trainee

Reforms in Kosovo s power System

Unmanned Aircraft: Regulatory Framework in the EU EASA team High Level Conference on Drones Warsaw 24 November 2016

Safety & Airspace Regulation Group Code of Practice. Issue 13, August 2013 CAP 1089

The registration of foreign owned vessel under the Nigerian Cabotage Act 2003

THE TARIFF OF PORT FEES AND CHARGES SZCZECIN AND ŚWINOUJŚCIE SEAPORTS AUTHORITY

PUBLIC SERVICE OBLIGATION LEVY 2016/17

Online Handbook Part-66 AML

THE CHICAGO CONVENTION AS A SOURCE OF INTERNATIOINAL AIR LAW

Official Journal L 362. of the European Union. Legislation. Non-legislative acts. Volume December English edition. Contents REGULATIONS

Aircraft Maintenance Engineer Licensing

Load-following capabilities of nuclear power plants

Frequently Asked Questions. Free allocation from the Special Reserve (Art 3f ETS Directive 1 )

City of Reykjavík Data center locations. March 2018 Department of Economic Development City of Reykjavik

Black Start Ancillary Service Schedule

From: OECD Tourism Trends and Policies Access the complete publication at: Slovenia

CONFERENCE ON THE ECONOMICS OF AIRPORTS AND AIR NAVIGATION SERVICES

Bosnia and Herzegovina

Aircraft Maintenance Personnel Licensing

COMMISSION OF THE EUROPEAN COMMUNITIES. Draft. COMMISSION REGULATION (EU) No /2010

REGULATIONS FOR DECLARATION AND DISPOSAL OF UNCLAIMED ITEMS OF THE PIRAEUS CONTAINER TERMINAL S.A. IN THE PIRAEUS FREE ZONE

CARICOM FRAMEWORK ON PUBLIC PROCUREMENT

An advisory circular may also include technical information that is relevant to the rule standards or requirements.

COMMISSION DECISION 29/03/2005

of 24 November 1994 (Status as of 1 January 2019)

An advisory circular may also include technical information that is relevant to the rule standards or requirements.

The entry into force of the EU-US. US Open Skies Agreement. Pablo Mendes de Leon Airneth Annual Conference, 17 April 2008

Tariff Regulations at Torp Sandefjord Airport

of 24 November 1994 (Status as of 12 October 2017)

Advice for brokers about the ATOL Regulations and the ATOL scheme

Annex 5: Technical Terms and Conditions for Lot IV: Committee of the Regions

ICAO Technical Cooperation Progress and Future Potential Program on Environmental Sustainable Air Transportation in Indonesia

OPEN SEASON Phase 2 Rules. Project on the development and expansion of Bulgartransgaz EAD gas transmission system (GTS)

Tariff Regulations 2018

EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Customs Policy, Legislation, Tariff Customs Legislation

9th INTERNATIONAL CONFERENCE AND EXHIBITION OIL & GAS < and primary energy >

Better regulation for general aviation (update July 2010) July 2010 Better regulation for General Aviation 1

The Organizer rents empty exhibition space (minimum area 9 sq. m) for the whole duration of the Exhibition and provides with the following services:

PRIVATE DEED BETWEEN. in ( ) ZIP code Adress No. phone fax. . provided with licence/exercise authorization No. issued by on IATA code

Republika e Kosovës Republika Kosova-Republic of Kosovo Qeveria - Vlada - Government New Kosovo Project

Unmanned Aircraft System (Drone) Policy

Vision. MEGA programme Marth 1 st 2010, Belgrade. Presented by: Agency for Local Economic Development. Vladimir Kostic.

TOURISM GOVERNANCE IN SLOVENIA

Official Journal of the European Union L 59/1. (Non-legislative acts) REGULATIONS

Page 1 sur 19 LFTH

HERNE BAY AREA MEMBER PANEL 16 TH JANUARY This report is open to the public.

Transcription:

Wind Energy in South-east Europe: Seminar III: WIND ENERGY PROJECT DEVELOPMENT UNIVERSITY OF SPLIT FACULTY OF ELECTRICAL ENGINEERING, MECHANICAL ENGINEERING AND NAVAL ARCHITECTURE Wind Project Development in Croatia Ranko Goić, Ph.D. Head of Power System Department Faculty of Electrical Engineering, Mechanical Engineering and Naval Architecture, University of Split, Croatia rgoic@fesb.hr www.fesb.hr/~rgoic Mostar, 31.5.2007.

Contents 1. Current energy situation in Croatia 2. Brief history of wind development in Croatia 3. Legal procedure for building approvals R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 1

1. Current energy situation in Croatia Generation mix and electric energy balance Regulatory framework: main energy laws, sub-laws and technical codes Main energy related institutions in Croatia and their role: Ministries, HEP Group and subsidiaries, Regulatory Agency, Market Operator, Local authorities R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 2

Generation mix and electric energy balance in Croatia (1) Primary energy production Energy import dependency R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 3

Generation mix and electric energy balance in Croatia (2) Electricity balance R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 4

Generation mix and electric energy balance in Croatia (3) Electricity prices (excluding VAT, including inflation 2005. basis, 1 =7.4kn) Average selling price in 2005: 7 c/kwh + VAT R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 5

Generation mix and electric energy balance in Croatia (4) Generation mix in Croatia (excl. industrial plants): Hydro 2060 MW Thermal 591 MW Nuclear 338 MW (in Slovenia) Wind 17 MW Total: 4006 MW Peak load: 3200 MW R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 6

Regulatory framework (1) Basic energy laws: The Energy Law The Law on the Regulation of Energy Activities The Law on the Electricity Market The Law on the Gas Market The Law on the Petroleum and Petroleum Products Market The Law on the Production, Distribution and Supply of Heat Energy - Entered in force in 2001., updated in 2004. - Generally harmonised with EU legislative (but not complete!) - Not implemented entirely (in practice) yet, mainly because of incompleted sub-laws and other obstacles R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 7

Regulatory framework (2) Energy Sub-laws (secondary legislation) important for wind energy development: Ordinance on the Use of RES and Cogeneration (not yet published) - Specify RES to be used for energy production, conditions and possibilities for their use (type, technology) Regulation on Minimum Share of Electricity Produced From RES and Cogeneration (published; in force from 7/2007) - Specifies a minimal share of electricity produced from RES and cogeneration, which the supplier is obligated to purchase (to the end of 2010): 5.8% of total electricity consumption (900 GWh now, aprox. 1050 GWh in 2010) Ordinance on the conditions/criteria for obtaining the status of an eligible (privileged) producer (not yet published) - Stipulate the types of plants for granting the energy subjects the status of beneficial electric energy status, minimal conditions for granting the status etc R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 8

Regulatory framework (3) Tariff System for Electricity Production from RES and Cogeneration (published; in force from 7/2007) - Determine the producer's right to an incentive price payable by the market operator for energy supplied (feed-in tariffs, 12 year duration) Compensation (charge) for Providing Incentives for RES and Cogeneration (published; in force from 7/2007) -Cost coverage of the market operator in view of implementation of the tariff system for RES generation and cogeneration: final customer pays additional ~ 1.7% in 2007 and 6.7% in 2010 Mix of quota and feed-in system + authorization for power plant building R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 9

Renewables feed-in tariffs: Regulatory framework (4) Up to 1MW installed power kn/kwh c/kwh Photovoltaic (depending on size) 2.10-3.40 28.38-45,95 Hydro 0.69 9,32 Wind 0.64 8,65 Biomass from forestry and agriculture 1.20 16,22 Biomass from wood industry 0.95 12,84 Geothermal 1.26 17,03 Liquid biofuels 0.36 4,86 Landfill gas and facilities from wastewater treatment 0.36 4,86 Over 1MW installed power kn/kwh c/kwh Hydro (up to 10MW installed power, depending on annual production) 0.42-0.69 6.68-9.32 Wind 0.65 8,78 Biomass from forestry and agriculture 1.04 14,05 Biomass from wood industry 0.83 11,22 Geothermal 1.26 17,03 Liquid biofuels 0.36 4,86 Landfill gas and facilities from wastewater treatment 0.36 4,86 Note: Prices are given for 100% domestic components used for equipment (penalization up to 7%) R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 10

Regulatory framework (5) A) Sub-laws / technical codes for network connection and use (all in force) Grid Code technical conditions and rules for network connection on transmission and distribution network annex for wind power plants in preparation General conditions for electric energy supply procedure and rules for obtaining preliminary and final network connection permit procedure and rules for network usage agreement Network connection charges principles for determining network connection charges tariffs for network connection B) Other (very!) important laws Spatial (physical) planning law Environmental protection law Building law (Concession law?) R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 11

Main energy related institutions in Croatia Founder of R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 12

2. Brief history of wind development in Croatia History and future Example of wind charactaristics R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 13

History and future (1) Early stage (up to 2001): No success After 2001 (2001 till now) Waiting for energy sub-laws Expansion of developers activities Two isolated successful case: Wind park Ravne (Pag island), 5.95 MW, 7x850 kw Vestas Wind park Trtar-Krtolin (near Šibenik), 11.2 MW, 14x800 kw Enercon both build on basis of old legislative framework! Future (after completing energy sub-laws, probably during this year): Optimistic expectations on long-term basis: good wind conditions on many locations Constrained on short-term basis imposed by mixed quota/feed-in system and network restrictions Expecting aprox. 400 MW till end of 2010 R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 14

History and future (2) R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 15

History and future (3) Finished projects Projects in high phase Projects in low phase WIND PROJECTS IN CROATIA Note: This is picture from one newspaper before 6 months (there are more developers and locations ) R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 16

Example of wind charactaristics in Croatia (1) Comparison of measurement wind data for inland and coastal wind farm location Wind duration curve v 10min [m/s] 30,0 27,5 25,0 inland 22,5 coast 20,0 17,5 15,0 12,5 10,0 7,5 5,0 2,5 0,0 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 30% 25% inland coast 20% Wind frequency 15% 10% 5% 0% 0-2 2-4 4-6 6-8 8-10 10-12 12-14 14-16 16-18 18-20 20-22 22-24 24-26 26-28 28-30 > 30 v [m/s] R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 17

Example of wind charactaristics in Croatia (2) Direction Average speed WNN 40,0% 30,0% N NNE inland coast WNN 15,0 m/s 13,0 m/s 11,0 m/s N NNE inland coast 9,0 m/s WWN 20,0% NEE WWN 7,0 m/s NEE 5,0 m/s 10,0% 3,0 m/s 1,0 m/s W 0,0% E W -1,0 m/s E SWW EES SWW EES SSW ESS SSW ESS S S Inland Coast v avg (50m) 5,98 5,95 m/s v max (50m) 36,7 48,1 m/s P/A avg (50m) 320 714 kwh/m 2 W/A avg/annual (50m) 2800 6260 kwh/m 2 /year Production factor (80m) 27,5 23,5 % R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 18

3. Legal procedure for building approvals Local spatial plans as necessary condition Location permit Preliminary approval for power plant building Preliminary status of eligible producer Licence for electricity generation Final approval for power plant building Building permit Power purchase agreement and Network usage agreement (Building ) Technical inspection, usage permit and trial operation Final status of eligible producer R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 19

Local spatial plans as necessary condition Local spatial plans: County (district) spatial plan Municipality spatial plan Area for wind park have to be marked in both plans as necessary condition for obtaining location permit! If not, it is not possible to obtain any permit Wind park have to be planned inside marked area Plans are updated occasionally (not often than 5 years) R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 20

Location permit Location permit (key document!) declare possibility for building (any type of object) on exactly defined area, including all conditions/constraints based on Spatial (physical) planning law and Environmental protection law Environm. impact study Environm. protection law Commission (appointed by Ministry) Public opinion (local community) Ministry OK Preliminary technical design Spatial planning law Location permit Ministry (>20MW) or County office (<20MW) OK Preliminary approval for network connection (HEP) Approvals /conditions from other public institutions (lot s of ) R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 21

Preliminary approval for power plant building Ministry of economy, labour and enterpreneurship give preliminary approval for power plant building (any type): based on Law on the Electricity Market, Article 9-4 detail procedure for this approval will be included in sub-law Ordinance on the Use of RES and Cogeneration (not yet published) necessary conditions (from proposal): positive local community opinion network connection study (for plants > 50MW) preliminary approval for plant building is necessary condition for: legal start of measurement activities on site registration in Renewable Projects Registry different procedure for: developers witch already have measurement site(s) existing projects new developers (sites) new projects R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 22

Approval for measurement site (Government) Office for State Property Management gives approval for using land for installing measurement equipment only if land is in State ownership measurement equipment (tower) have to be certified preliminary approval for wind park building is necessary condition On private land, approval is obtained from owner R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 23

Preliminary status of eligible producer Croatian Energy Regulatory Agency (HERA), on developer s request, issue a document Preliminary status of eligible producer detail procedure will be included in sub-law Ordinance on the conditions/criteria for obtaining the status of an eligible (privileged) producer (not yet published) Necessary conditions (from proposal): preliminary technical design of wind park preliminary environmental impact assessment R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 24

Licence for electricity generation Croatian Energy Regulatory Agency (HERA), on developer s request (company registrated in Croatia), issue a document Licence for electricity generation based on Law on the Electricity Market, Article 16 detail procedure defined in sub-law Ordinance on conditions for pursuit energy activities: Technical, financial and professional qualifications of company have to be settled Different procedure for: old energy company which is owner of some energy facilities new energy company R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 25

Final approval for power plant building Ministry of economy, labour and enterpreneurship give final approval for power plant building (any type): based on Law on the Electricity Market, Article 9-4 detail procedure for this approval will be included in sub-law Ordinance on the Use of RES and Cogeneration (not yet published) from proposal: valid location permit other conditions from preliminary approval non-overlaping with other site (developer) with final approval for wind park building it is possible to agree using (renting) of State land for wind park but, it is not really possible to start building (building permit is also needed) final approval is valid 1 year (in that time building permit have to be obtained) R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 26

Building permit Building permit based on Building law issued by Ministry of environmental protection, Physical Planning and Construction or local county office (in jurisdiction of the same Ministry) necessary conditions: valid location permit land ownership - sale or rent contract with owner complete and detailed technical (project) documentation for building Final approvals from many public institutions, including final approval and network connection agreement after obtaining building permit, it is possible to start physical works on site Building permit is valid 2 years Note: beside wind park, location permit and building permit have to be issued for all objects necessary for network connection (transformer station, power lines ) for that permits are in jurisdiction of HEP R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 27

Power purchase agreement (1) Power Purchase Agreement in jurisdiction of HROTE (Croatian energy market operator) based on sub-law Tariff System for Electricity Production from RES and Cogeneration (published; in force from 7/2007) 12 year duration fixed feed-in tariff Necessary condition: valid network connection agreement and building permit R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 28

Power purchase agreement (2) Market operator Collection and distribution of incentives Invoice for delivered energy Eligible producer Other sources of incentives Invoice for delivered energy from renewables and cogeneration Payment for delivery energy Payment for delivered energy from renewables and cogeneration (incentive part) Electricity supply company Payment for part based on market price Payment additional charge for renewable and cogeneration support Customers R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 29

Network usage agreement Network usage agreement with HEP Transmission system operator (in case of connection on transmission network; >10MW) with HEP Distribution system operator (in case of connection on distribution network) based on sub-laws General conditions for electric energy supply (published; in force from 4/2006) Necessary conditions: valid network connection agreement payed connection charges R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 30

Technical inspection, usage permit and trial operation Usage permit based on Building law issued by Ministry of environmental protection, Physical Planning and Construction or local county office (in jurisdiction of the same Ministry) necessary conditions: Finished construction of object Committed technical inspection (with certificate that object is build according to specification from building permit) for that permits are in jurisdiction of HEP Trial run based on Grid code: inspection of accomplishment of proposition from network connection agreement (technical part) Inspection of accomplishment of Grid code requirements R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 31

Final status of eligible producer Croatian Energy Regulatory Agency (HERA) issue a document Final status of eligible producer detail procedure will be included in sub-law Ordinance on the conditions/criteria for obtaining the status of an eligible (privileged) producer (not yet published) Necessary conditions (from proposal): Valid location, building and usage permit, successful technical inspection and trial operation Generation plan (estimation of monthly production during next year and shutdown periods) R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 32

The End Thank you for attention Questions? R. Goić: Wind Project Development in Croatia Mostar, 31.05.2007 33