Sunshine Coast Airport Master Plan September 2007

Similar documents
2 Aviation Demand Forecast

TERMINAL DEVELOPMENT PLAN

8 Aviation Support. 8.1 Aerodrome Rescue and Fire Fighting Services. 8.2 Aircraft Refuelling. 8.3 Air Cargo

MASTER PLAN 2010 ADDENDUM REPORT

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands.

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP)

A Master Plan is one of the most important documents that can be prepared by an Airport.

Airport forecasting is used in master planning to guide future development of the Airport.

Aviation Development

BNA Master Plan Update Public Meeting No. 2

Birmingham Airport 2033

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

CHAPTER 9 RUNWAYS AND AIRFIELD DEVELOPMENTS

Alternatives. Introduction. Range of Alternatives

FORECASTING FUTURE ACTIVITY

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Connecting People Building Opportunities BRISBANE AIRPORT 2014 MASTER PLAN

AIRPORT MASTER PLAN UPDATE

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

Westover Metropolitan Airport Master Plan Update

BNA Master Plan Update Community Advisory Committee Meeting No. 5

2 THE MASTER PLAN 23

Badgery s Creek Airport Presention. Revised from NAN 2015 AGM

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1

Whangarei Airport. Prepared by Carine Andries 10/20173

Chapter 1 Introduction and Project Overview

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D

Airport Master Planning Process & Update


Ted Stevens Anchorage International Airport

Master Plan Update Technical Advisory Committee Meeting

Ted Stevens Anchorage International Airport

Addendum - Airport Development Alternatives (Chapter 6)

NORTHERN ROCKIES REGIONAL AIRPORT Terminal Expansion ANALYSIS 31 st August 2012

IAA Submission on the Commission for Aviation Regulation s Draft 2014 Determination of Maximum Level of Charges at Dublin Airport

2006 ANNUAL GENERAL MEETING

Appendices. Appendix A Schedule of Consultation. Appendix B SCA Public Participation Program Report (dated September 2006)

Lake Tahoe Airport Master Plan

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

CHAPTER 1: INTRODUCTION

Proposed amendments to the Air Navigation (Essendon Airport) Regulations 2001

Preferred Alternative Summary

Q: How many flights arrived and departed in 2017? A: In 2017 the airport saw 39,300 air transport movements.

1) Rescind the MOD (must meet the standard); 2) Issue a new MOD which reaffirms the intent of the previous MOD; 3) Issue a new MOD with revisions.

Chapter 1: Introduction Draft


Study Design Outline. Background. Overview. Desired Study Outcomes. Study Approach. Goals (preliminary) Recession History

ENVIRONMENT ACTION PLAN

Master Plan Update Community Advisory Committee Kick-off Meeting

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

Chapter 1: Introduction

Consultation on Draft Airports National Policy Statement: new runway capacity and infrastructure at airports in the South East of England

Meeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited

Technical Memorandum. Synopsis. Steve Carrillo, PE. Bryan Oscarson/Carmen Au Lindgren, PE. April 3, 2018 (Revised)

Bankstown Airport. Master Plan 2004/05

Yakima Air Terminal/McAllister Field Airport Master Plan Update

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i

Communication and consultation protocol

Terms of Reference: Introduction

Airways New Zealand Queenstown lights proposal Public submissions document

DRAFT. Master Plan RESPONSIBLY GROWING to support our region. Summary

Darwin International Airport. Final Master Plan

Ronan Delaney. DELANEY_RONAN_AVIATION_JUN_2018.DOCX

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

STUDY WORK GROUP MEETING No. 3. November 29, 2016

REVIEW OF PERTH AIRPORT Noise Abatement Procedures

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3

Wakatipu Area Strategy Plan

> Aircraft Noise. Bankstown Airport Master Plan 2004/05 > 96

COMMERCIAL AND GENERAL AVIATION

Darwin International Airport MASTER PLAN Preliminary Draft

STUDY WORK GROUP MEETING No. 4. July 12, 2017

Sydney Airport Master Plan

What is an Airport Master Plan?

LAMP 2 - FASI(S) Network

Current and Forecast Demand

Note 3 - The following assumptions have been made for the purposes of this information article only:

CHAPTER 1 EXECUTIVE SUMMARY

Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM

About ABTA. Executive summary

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update

Sunshine Coast and Caloundra Airports Aircraft Noise Information Report

Tauranga Airport Airport Masterplan and Associated Revenue and Expenses 2016/17

REGION OF WATERLOO INTERNATIONAL AIRPORT AIRPORT MASTER PLAN EXECUTIVE SUMMARY MARCH 2017

AIRPORT WITH NO RUNWAYS IS A MALL

Table of Contents. Overview Objectives Key Issues Process...1-3

CAIRNS RECTANGULAR PITCH STADIUM NEEDS STUDY PART 1 CAIRNS REGIONAL COUNCIL DRAFT REPORT SEPTEMBER 2011

Chapter 4.0 Alternatives Analysis

6.0 AIRFIELD DEVELOPMENT PLAN

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

Regular Board Meeting August 4, 2015

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Transcription:

Sunshine Coast Airport Master Plan September 2007

Contents CONTENTS... I ACKNOWLEDGEMENT... II DISCLAIMER... III 1 EXECUTIVE SUMMARY...IV 1 INTRODUCTION... 1 2 AVIATION DEMAND FORECAST... 5 3 AIRCRAFT APRONS... 12 4 PASSENGER TERMINAL... 15 5 SURFACE ACCESS AND PARKING... 18 6 RUNWAYS... 21 7 TAXIWAYS... 25 8 AVIATION SUPPORT... 26 9 MASTER PLAN... 31 10 ENVIRONMENTAL IMPACTS... 33 11 STAGED DEVELOPMENT... 44 APPENDICES... 1 I

Acknowledgement This Master Plan has been prepared in close consultation with the airline industry, airport tenants, Federal, State and Local Government agencies as well as the local community. Sunshine Coast Airport gratefully acknowledges the cooperation and input from all organisations and individuals who participated in the preparation phase. II

Disclaimer Disclaimer Whilst every care has been taken in preparing this document, Maroochy Shire Council (MSC) does not make any representation to any party and will not accept responsibility or liability to any person or corporation seeking to rely on any information, advice or opinion provided in this report or otherwise given in any manner by the officers, servants or agents of MSC for any loss or damage of whatever nature suffered by any such person or corporation. Copyright The information contained in this document may only be used with the explicit written consent of MSC and then only in whole and not in part and without modification. Any entity that wishes to copy the document must submit a written request to MSC. Requests should be addressed to the Airport Manager, Sunshine Coast Airport. III

1 Executive Summary 1.1 Introduction A Master Plan is a strategic document intended to guide future development decisions to achieve the Sunshine Coast Airport (SCA) strategic intent. Its purpose is to reserve land for future airport activities based on the forecast growth of the airport business at the time of writing. The Master Plan is not intended to detail individual facilities or specific time frames for the implementation of the Plan; rather it sets the foundation upon which further analysis and planning is based. This Master Plan is the product of changes made to the Master Plan Preliminary Draft Report February 2006 and has been written to address feedback received during the public consultation process and Councils review of that plan. This Master Plan - September 2007 sets the direction for the development of SCA from 2007 through to 2020. The preferred long term development objective for the airport is to build a new runway to facilitate new international routes and support the growing regional economy of the Sunshine Coast. This new runway is likely to be constructed at some time towards the end of the planning horizon (2020) or shortly thereafter. Due to community concern with extending, and constraints on the ability to widen the existing Runway 18/36, no interim changes will be made to the existing runway. However, during the Master Plan time frame upgrades will be made to the taxiways, aprons, terminal and infrastructure to support the growth associated with the current runway. It is envisaged that this plan will set the framework for a more detailed study of design, infrastructure planning, land use planning and environmental impacts required to achieve the long term planning objective. 1.2 Consultation A comprehensive program of consultation was undertaken at the commencement of the study and at appropriate stages throughout the study period, with a wide range of stakeholders. 1.3 Aviation Forecasts 1.3.1 Passenger Movements With the introduction by low cost carriers (Virgin Blue and Jetstar) of regular direct services between the Sunshine Coast and Sydney, Melbourne and Adelaide, traffic has grown rapidly to the current level of some 880,000 annual passenger movements. Historic and forecast annual passenger movements are shown at Figure 1-1 below. FIGURE 1-1 FORECAST ANNUAL PASSENGER MOVEMENTS IV

Figure 1-1 shows base case forecasts of some 1.9 million passenger movements by 2020, with high and low forecasts of some 2.3 and 1.6 million respectively. 1.4 Aircraft Movements Historic and forecast total fixed wing (RPT plus GA) aircraft and helicopter movements are shown at Figure 1-2. FIGURE 1-2 HISTORIC AND FORECAST ANNUAL AIRCRAFT MOVEMENTS Fixed wing aircraft movements (including both RPT and GA) represent approximately 50 percent of total aircraft movements, additionally: Base case forecasts predict some 86,000 annual aircraft movements (41,000 fixed wing and 45,000 helicopter movements) by 2020; the high and low forecasts range between 99,000 (45,000 and 54,000) and 62,000 (32,000 and 30,000) annual aircraft movements respectively. RPT annual aircraft movement forecasts at 2020 are: High 13,396 Base Case 10,891 Low 9,219 1.5 Busy Hour Passengers Busy hour passenger forecasts were prepared to allow sizing of the future passenger terminal. The forecasts were based on a growth rate equal to the baseline annual passenger movement forecasts, as well as assuming a growth rate 1% per annum less than the baseline annual passenger movement growth rate. The forecasts are shown in Figure 1-3 below. The busy hour passenger arrivals and departures are forecast to reach some 1,400 by 2020. In practice, it is likely SCA would negotiate with the airlines to encourage them to introduce new services outside the peak period, in order to minimise terminal and apron expansion facilities which would be underutilised much of the time. V

1.6 Peak Stand Demand FIGURE 1-3 BUSY HOUR PASSENGER MOVEMENTS Peak stand demand forecasts for RPT jet aircraft, using B737-900 as the design aircraft are provided below. Year Active Stand Demand Buffer (1) Total Stands 2007 (Current) 3 1 (2) 3 2010 3 1 4 2015 4 1 5 2020 6 1 7 TABLE 1-1 PEAK STAND DEMAND Notes: 1. Makes provision for off-schedule and itinerant aircraft 2. Boeing 737-300 Maximum on Bay 3 1.7 RPT Apron The current RPT apron can accommodate four aircraft although aircraft cannot access all parking bays independently, nor is there sufficient space to accommodate future demands for aircraft stands. An apron parking layout with seven bays to accommodate B737-800 (design aircraft) is shown at Figure 1-4 below. The layout includes angled bays to ensure clearance of the Runway 18/36 transitional surface; all bays can be accessed independently using aircraft power without the need for push back tugs. 1.8 Passenger Terminal A terminal concept to accommodate the projected 2020 busy hour passenger numbers, including accommodating international (trans-tasman) traffic, is shown at Figure 1-5 below. VI

FIGURE 1-4 RPT APRON LAYOUT FIGURE 1-5 PROPOSED TERMINAL LAYOUT 1.9 Parking The existing car park, with a total capacity of 715 paved spaces. The long term car park currently fills to overflowing during peak periods, with overspill parking being accommodated in the short term car park. Forecast parking demand, is shown at Table 1-2 below. VII

TABLE 1-2 PARKING DEMAND FORECAST Year Short-term Long-term Rental Staff Coaches / Shuttles 2007 (4) 321 166 140 80 8 2010 300 200 165 62 10 2015 400 270 190 75 12 2020 490 320 210 85 14 A concept for layout of the car park and terminal access road system to accommodate the 2020 demand, coupled by provision for terminal expansion and assuming that the control tower remains throughout the planning horizon, is shown at Figure 1-6 below. FIGURE 1-6 PROPOSED CARPARKING FACILITIES 1.10 Surface Access The Department of Main Roads is proposing a new link road from the Sunshine Coast Motorway to David Low Way, linking into the latter at its intersection with Runway Drive. In addition, a new internal access road is proposed from David Low Way to the passenger terminal and other airport precincts. This arrangement is shown at Figure 1-7 below. 1.11 Runway Requirements The existing main Runway 18/36 is 1,797m long x 30m wide; operations are restricted to narrow body aircraft types (B737-700/800 and A320) operating services to eastern Australian destinations, and possibly trans-tasman, at reduced payload. This plan recommends that no further work or extensions be made to the existing runway 18/36 and that the future Runway 13/31 be protected for the longer term development of the airport. Further, that detailed planning commences to confirm the construction triggers and impacts of the proposed runway. It is anticipated that this body of work may indicate the requirement for the runway construction towards the end of this Master Plan horizon (2020) or shortly there after. The proposed runway 13/31 will provide a take-off distance of 2,450m in each direction and with a runway width of 45m, wide bodied international VIII

operations will be possible by a range of aircraft. Typical ranges from this runway are shown at Figure 1-8 below. FIGURE 1-7 PROPOSED SURFACE ACCESS FIGURE 1-8 INDICATIVE RANGE CIRCLES IX

1.12 2020 Master Plan A layout showing the 2020 Master Plan boundaries required to accommodate forecast traffic is shown at Figure 1-9 below. FIGURE 1-9 SCA 2020 AIRPORT BOUNDARY Key features of the Master Plan are Runway 13/31, a revised RPT apron and expanded passenger terminal facilities. The car park layout is revised, a new airport access road from David Low Way is constructed and the commercial precinct is expanded. 1.13 Aircraft Noise Aircraft noise scenarios based on development of future Runway 13/31 were conducted and an ANEF was prepared to allow external land use planning to protect for the existing Runway 18/36 and the future Runway 13/31. 1.14 Obstacle Limitation Surfaces An Obstacle limitation surface (OLS) drawing based on the existing Runway 18/36 and future Runway 13/31 was prepared to protect airspace associated with the airport in the long term. The OLS will be incorporated into the town planning scheme for areas surrounding the airport. 1.15 Staged Development Operational requirements, funding limitations and other considerations usually dictate that provision of expanded or new facilities is undertaken in a staged manner. Development of facilities is driven by traffic conditions or other triggers that can be defined as part of the planning process ahead of the time the facilities are likely to be required. X

Thus, the desired airport developments will be achieved in a series of stages that are tailored to match traffic growth and required service levels, with the basic philosophy being to ensure that maximum use is made of existing infrastructure in subsequent development stages. Three development stages of ongoing development of the existing airport were prepared as follows: Stage 1 (short term) 0 5 years Stage 2 (medium term) 6-10 years Stage 3 (long term) 11 15 years. The above time periods are indicative and do not represent a commitment to undertake the developments. Major work items within each development stage are as follows: Stage 1 Secure and preserve the land required for the future east/west runway, associated infrastructure and its surrounding buffer zones. Reconfigure RPT apron Develop retail departure lounge in passenger terminal Establish new airport access road Expand landside road system Expand car parking facilities Provide serviced commercial sites Commence detailed studies for the development of Runway 13/31 Stage 2 Expand RPT apron Construct partial parallel taxiway Expand passenger terminal Expand car parking facilities Expand GA aprons Review Runway 13/31 construction triggers Stage 3 Expand RPT apron Expand car parking facilities Expand GA aprons Extend parallel taxiway Commence construction on new runway (subject to economic, social, environmental study outcomes) XI