I-94 at Grand Avenue Interchange: The Ride before the Roller Coaster

Similar documents
TYPICAL SECTION OF IMPROVEMENT

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

Add-A-Lane Contract V. along a Section of I-95 includes 6 Bridges

DHS Consolidation at St. Elizabeths Master Plan Amendment. Transportation Interstate 295 / Malcolm X Avenue Interchange

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program,

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

State Project Reconstruction I-84

AGENDA ITEM I-6 Public Works

DALLAS HORSESHOE PROJECT. Project Update including the Margaret McDermott Bridge Transportation and Trinity River Project Committee February 22, 2016

2006 WEEKDAY TRAFFIC PROFILE. June 15, 2007

Public Information Center August 12, 2010

PRIORITIES COMMITTEE MEETING

Route 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016

SANTA CLARA COUNTY I-280 CORRIDOR STUDY

Pardon Our Dust Public Information Meeting

Pre-Construction Public Meeting July 2017

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015

Grove Field Airport Environmental Assessment

A VISION FOR I-95. January 12, Delaware Department of Transportation

Memorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description

MEMORANDUM. Open Section Background. I-66 Open Section Study Area. VDOT Northern Virginia District. I-66 Project Team. Date: November 5, 2015

SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER

Project Location MP A44.5 MP A38 PRELIMINARY. A A57 (Future Project) A42 - A44.5 (Fall Fall 2019) A38 - A42. A31 - A38 - In Design

Major Projects Overview

Yonge Street / Highway 401 Improvements Update. Public Works and Infrastructure Committee. General Manager, Transportation Services

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

Welcome to Dayton Parkway Interchange Open House. November 26, 2018

Community Advisory Panel Meeting #

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

FAIRBANKS NORTH POLE REALIGNMENT. Phase III Technical Analysis

Long water shutdown scheduled for Tuesday, September 18

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

State Route 8 Corridor. Northern Summit County s Path to Success

Important Lane Closures, April 3 9, 2011

QEW - ALTERNATIVE 3. Ÿ Widen QEW by one HOV lane in both direc ons through Freeman Interchange to North Shore Boulevard Interchange.

10.0 Recommendations Methodology Assumptions

I-35 Reconstruction Project

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

I-66 Inside the Beltway Feasibility Study

FDOT Treasure Coast Traffic Report through

2017 Work and Launch of the Next Phase. Information meeting, Montréal-Ouest September 14, 2017

Washington State Transportation Commission

MEMORANDUM. for HOV Monitoring on I-93 North and the Southeast Expressway, Boston Region MPO, November, 2011.

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

CALIFORNIA HIGH-OCCUPANCY VEHICLE LANE DEGRADATION ACTION PLAN

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

1.0 Purpose and Organization of the Community Impact Assessment Addendum

Construction underway. STATUS: 229 5,190 5,419 5,305 STIP REFERENCE #FR /01/2013

2 Construction Program

Lincoln Village Pedestrian Bicycle Bridge Community Meeting September 13th, 2016

Guide to. Road Construction Projects

November 21, 2012 Barbara Kelleher, (954)

395 Express Lanes Major Closure Advisory

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Chicago St. Louis High-Speed Rail. Braidwood Construction. Local Officials Briefing August 7, 2014

Baltimore Ravens Egress Study

Sierra Roadwork Schedule Sunday through Saturday, October 1-7, 2017 LONG-TERM PROJECTS

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30

* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties

Construction Update. Local Officials Briefing March 2016

FOR IMMEDIATE RELEASE February 22, 2019 CONTACT: Jen K. Ward, SALEM 69

MONTANA CONSTRUCTION REPORT 06 / 14 / 2016

I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required.

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District

1963 HISD REPORTS. Highway Mileage on State, State Toll, County and Municipal Systems by County and by District

Grade Crossings in High Speed Rail Corridors

1964 HISD REPORTS. Highway Mileage on State, State Toll, County and Municipal Systems by County and by District

Weekly construction update

Non-Motorized Transportation

El Dorado County / Tahoe Roadwork Schedule

I-94 East Corridor Performance

US 380 FEASIBILITY STUDY

Northeast Anthony Henday Drive. Bill van der Meer Urban Construction Manager - Edmonton Alberta Transportation

Project Focus Group (PFG) Meeting Notes- Final Meeting #1

INTERSTATE 395 EXPRESS LANES NORTHERN EXTENSION TRAFFIC & TRANSPORTATION TECHNICAL REPORT SEPTEMBER 2016

Work Zone. Steve Hubbard: Lane Construction Safety Training Manager. Michael Grey: Rea Contracting Project Superintendent

Hospital Link Project Project Update Winter 2018

PennDOT Interstate Work next week March 30-April 3:

HOV LANE PERFORMANCE MONITORING: 2000 REPORT EXECUTIVE SUMMARY

Alternatives Analysis City of Newport Beach Sunset Ridge Park Project December 14, 2011

Milestone: Bridge to Nowhere scheduled for demolition Aug 14

TRAFFIC COMMISSION, VILLAGE OF LINCOLNWOOD 6900 N. Lincoln Avenue, Lincolnwood, IL 60712

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road

NDG-Westmount Neighbourhood Committee. November 16, 2015

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

Commonwealth Avenue Bridge Deck Replacement Project. Legislative and Stakeholder Briefing. April 13, 2017

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District

2004 Congestion Management System Report

Introductions Overland Bridge Project Update by Bill Kays with KCCS Construction Project Update by Ron Tittle, Public Information Office

Memorandum. Roger Millar, Secretary of Transportation. Date: April 5, Interstate 90 Operations and Mercer Island Mobility

APPENDIX F List of Commitments

FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

University Region Non-Motorized Plan 2015

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

Transcription:

I-94 at Grand Avenue Interchange: The Ride before the Roller Coaster

Introduction Presenters Lanyea Griffin, Executive Project Engineer, Illinois Tollway Rob Deming, Project Manager, Primera Engineers, Ltd. Design Project Team (DSE) Primera-EJM JV: Primera Engineering Ltd. & EJM Engineering, Inc. Subconsultants: Terra Engineering, Ltd., Sanchez & Associates, P.C., Garza Karhoff Engineering, LLC, Huff & Huff, Inc. & GSG Consultants, Inc. Construction Management Team (CM) Accurate Group, Inc. Contractor (GC) F.H. Paschen SN Nielsen, Inc. 2

Agenda Project Overview Design Construction 3

Project Overview

Tri-State Tollway (I-94)/Grand Avenue Interchange 5

Major Generators Gurnee Mills Key Lime Cove M-4 Colleges, Hotels, Etc. Six Flags Great America 6

Major Generators Gurnee Mills G C H F D A B E Six Flags Great America 7

Six Flags Great America 8

Congestion 9

Project Design

Design Overview Goals for the Project Deficiencies Design Environmental Issues Stakeholder Involvement 11

Existing Conditions 12

Improvement Goals Improve Traffic flow Vehicular Safety Ramp E (Accidents) Deficiencies in geometry, drainage, safety features, and interchange lighting Complete an IDS for the following Types of interchanges Improved Full Cloverleaf Improved Full Cloverleaf with Collector- Distributer Lanes One Quadrant Partial Leaf Clover w/nb Collector-Distributer Lane 13

Project Design Schedule Design Steps Final Design with the Constraints 14

Design Deficiencies Element Noted Deficiencies Requirements Loop ramp speed 23 mph 30 mph Loop ramp radii 200 feet (28 mph) 214 feet (30 mph) Lane widths 14 feet 16 feet Auxiliary lane length 1,000 feet 1,500 feet Mainline profile grades 0.2 percent 0.3 percent Profile grades 0.02 percent 0.5 percent Superelevation Up to 10 percent 8 percent Ramp superelevation distribution 58 percent 80 percent 15

Interchange Type Study Alternate A Improved Full Cloverleaf - $30 million 16

Interchange Type Study Alternate B Improved Full Cloverleaf with Collector-Distributor Lanes - $35 million 17

Interchange Type Study Alternate C 1 Quadrant Partial Cloverleaf w/ NB Collector-Distributor Lane - $26 million 18

Design Overview Project Design Collector-Distributor Road 19

Final Design - Hybrid Replace Loop Ramps A, B, C & Directional Ramps E, F, G, H - $20 Million 20

Detour Coordination 21

Design Checks Ramp Staging 22

Six Flags Ramp Design Considerations Ramp E Traffic from Chicago area to Six Flags Great America The design extended the Ramp E 2 lane ramps 1200 and added a another 1500 single dedicated ramp lane to give additional capacity with a concrete barrier wall to separate mainline traffic with ramp traffic. The barrier will eliminate drivers from getting out of ramp traffic and trying to reenter further up during a back up. Tight Right-of-Way Had to construct a retaining wall due to the ROW. Along with the additional lane and normal shoulder, a snow shoulder was installed to create a area for the snow while leaving the shoulder open for emergencies and safety 23

Existing Versus Proposed Ramp E Ramp E Existing Ramp E Proposed 24

Environmental Considerations Wetlands and Waters of the US (WOUS) Tanker Spill 26

Tanker Spill Remediation 27

Construction

Stake Holder Involvement Multiple meetings with Tollway and major stakeholders to discuss detours, permits, maintenance of traffic and project progress IDOT LCDOT Tollway GM- 4reat M-4 Yard America Key Lime Cove Gurnee Mills Mall Gurnee Mills Mall Gurnee Mills Mall 29

Stakeholder Schedule Request Ramp G September-October Ramp F June-August 30

2014 Construction Schedule WB Grand to North on I-94 (Ramp F) South on I-94 to WB Grand (Ramp G) North on I-94 to WB Grand (Ramp B loop) EB Grand to southbound I-94 (Ramp H) 31

Staged Construction Typical Paving Train 32

Ramp H Detour 3 Loop Detour H

Off-Peak Ramp Work Four foot temp pavement section required ramp shut down during off-peak hours

The Great Cement Shortage of 2014

Ramp G Complete

Ramp F Complete

Ramp H During Winter Shutdown

Ramp B Light Pole Installation

Retaining Wall A

2015 Construction Overview WB Grand to South on I-94 (Ramp C) EB Grand to North on I-94 (Ramp A) North on I-94 to EB Grand (Ramp E) 41

Ramp B Complete

Ramp H Complete

Ramp H Merge

Ramp E Advanced Signing

Ramp E Advanced Signing (Con t)

I-94 at Grand Avenue Interchange: The Ride before the Roller Coaster Questions? 49

THANK YOU 50