CatExes vs. EAs When and How to Prepare

Similar documents
Airport Master Plan Update June 15, 2017

Airport Master Plan Update June 15, 2017

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

Update on the Aspen/Pitkin County Airport Improvements

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION

PUBLIC SCOPING MEETING APRIL 2018

I-3 DFW Extension Public Hearing. June 2, 2011

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport

FAA RECORD OF DECISION. Appendix D FINAL EIS ADDENDUM DOCUMENTS

Session 6 Airport Finance 101 Funding Sources for Airports

Merritt Island Airport

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

OEPI OF TRANSPORTATION DOCKETS

Collier County Airport Authority. Joint Automated Capital Improvement Program

Office of Commercial Space Transportation: Notice of Availability, Notice of Public

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)

CHAPTER 1 EXECUTIVE SUMMARY

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Norfolk International Airport

2015 PURDUE ROAD SCHOOL March 11, 2015

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

Chapter 8.0 Implementation Plan

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

SouthwestFloridaInternational Airport

Master Plan Update Community Advisory Committee Kick-off Meeting

CHAPTER 3 ALTERNATIVES CONSIDERED

AIRPORT PLANNING, DEVELOPMENT AND LAND ACQUISITION

Finance and Implementation

Lake Tahoe Airport Master Plan

AIRPORT REGULATORY REQUIREMENTS THAT AFFECT ENVIRONMENTAL COMPLIANCE AND SUSTAINABILITY

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS

Airport 101 O Hare Noise Compatibility Commission July 19, 2018

2018 Appropriation Budget Table of Contents Board Approved August 18, 2017

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

Yakima Air Terminal/McAllister Field Airport Master Plan Update

2017 Appropriation Budget Table of Contents Board Approved August 19, 2016

JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 2007

Airports and UAS: Integrating UAS into Airport Infrastructure and Planning

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

AIRPORT MASTER PLAN UPDATE

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Federal Aviation Administration DCA. By: Terry Biggio, Vice President Air Traffic Services Date: June 18, Federal Aviation Administration

INITIAL ENVIRONMENTAL REVIEW. Boston-Logan Runway 4 Left Area Navigation (RNAV) Visual Flight Procedure Test

msp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010

Austin-Bergstrom International Airport Master Plan Update


Chapter 2 FINDINGS & CONCLUSIONS

1 PURPOSE AND NEED 1.1 INTRODUCTION

PREFERRED PLAN Kahului Airport Master Plan and Noise Compatibility Program Update

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update

Punta Gorda Airport Master Plan Update

Chapter 4.0 Alternatives Analysis

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment

8.0 AIRPORT LAYOUT PLANS

GREATER ORLANDO AVIATION AUTHORITY

Memorandum. Federal Aviation Administration. Date: June 19, Richard Doucette, Environmental Protection Specialist. From: To:

From concept through completion, CGA is your AVIATION engineering firm!

PFC NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT ST. THOMAS CYRIL E. KING AIRPORT SEPTEMBER 26, 2018

THE CASE OF A SUCCESSFUL PFC APPLICATION

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

INFORMATION FOR STANWELL MOOR AND STANWELL COMMUNITIES

AIRCRAFT NOISE ABATEMENT TASK FORCE MEETING ST. PETE CLEARWATER INTERNATIONAL AIRPORT. July 19, 2017

Alternatives Analysis EXECUTIVE SUMMARY

Update on FAA Standard Operating Procedures (SOP)

Addendum - Airport Development Alternatives (Chapter 6)

Airport Master Plan Update

Element 640 State of Rhode Island Airport System Plan - Overview

The San Diego Region s Air Transportation Future

State of the Airport Robert S. Bowen, Executive Director October 18, 2018

at: Accessed May 4, 2011.

FORECASTING FUTURE ACTIVITY

Dallas Love Field Update. Dallas City Council Briefing February 18, 2015

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

ENVISIONING AUSTIN s Airport of the Future

Alternatives. Introduction. Range of Alternatives

HAMPTON ROADS CROSSINGS PATRIOTS CROSSING AND HRBT

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update

Chapter Seven Implementation Plan. Tacoma Narrows Airport. Master Plan Update

Westover Metropolitan Airport Master Plan Update

Financial Plan/Capital Improvements - DRAFT 6-1

Chapter 10 FAA Compliance Review

EXHIBIT A. LOMPOC AIRPORT MASTER PLAN SCOPE OF WORK AIP Project #

CHAPTER TWO THE PROPOSAL

AIRPORT MASTER PLAN. Newport State Airport. Draft. (Colonel Robert F. Wood Airpark) THE Louis Berger Group, INC. Prepared for: Prepared by:

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures

The Law of Noise Regulation Daniel S. Reimer

Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot

Appendix 6.1: Hazard Worksheet

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN

Chapter 9 Airport Financial Plan

S p NA, illil MINNEAPOLIS- ST. PAUL INTERNATIONAL AIRPORT ( MSP) NOISE OVERSIGHT COMMITTEE ( NOC) RESOLUTION #

II. Purpose and Need. 2.1 Background

5.4 SECONDARY (INDUCED) IMPACTS

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2017

Alternatives Development and Evaluation Report

Transcription:

CatExes vs. EAs When and How to Prepare Panel: Steve Culberson, Ricondo & Associates Frank Smigelski, FAA Mary Vigilante, Synergy Tuesday December 10, 2013 Washington, DC 1

So you have a project Do I have to comply with NEPA? What type of NEPA documentation is required? Can this project be categorically excluded? Are extraordinary circumstances involved? Does this project normally require an EA (or EIS)? Who can prepare the required documentation? 2

Do I have to comply with NEPA? Is there a Federal action? Examples: Approving Federal funding for airport development Approving new public use airport Unconditionally approving Airport Layout Plan Authorizing imposition of passenger facility charge Approving use or transfer of federally-owned land for airport purposes Authorizing release of land for non-aeronautical purposes 3

What type of NEPA documentation is required? Three types of NEPA documentation: Categorical Exclusion (CatEx) Environmental Assessment (EA) Environmental Impact Statement (EIS) The Council on Environmental Quality (CEQ) allows Federal agencies to identify actions that, based on past experience with similar actions, do not individually or cumulatively have significant effects on the human environment 4

Can the project be categorically excluded? FAA Order 1050.1E, paragraphs 307-312, identifies those actions that FAA has identified as normally not requiring an EA or EIS. For airport sponsors, most projects are covered under paragraphs 307 (administrative/general actions), 309 (equipment and instrumentation) and 310 (facility siting, construction, and maintenance). If all components of the proposed project are identified in these paragraphs, the project is eligible for processing as a Categorical Exclusion But only if no extraordinary circumstances are involved. 5

CatEx Process or * See FAA Order 1050.1E, paragraphs 307-312 6

Are extraordinary circumstances involved? Exist when the proposed action may have a significant effect and involve impacts to any one of the following (FAA Order 1050.1E, paragraph 304): Air quality Coastal resources DOT Act Section 4(f) properties Natural resources and energy supply Farmlands Fish, wildlife and plants Floodplains Hazardous materials Historic, architectural, archeological and cultural resources Noise Secondary impacts Water quality Wetlands Wild and scenic rivers Likely to be highly controversial Not consistent with local, state or federal plans and policies Directly, indirectly or cumulatively create a significant impact on the human environment. 7

Does the project normally require an EA? FAA Orders 1050.1E (paragraph 401) and 5050.4B (paragraph 702) identifies those actions that FAA has identified as normally requiring an EA. Examples: Acquisition of more then 3 acres Establishment of FAA housing, sanitation systems, fuel storage and distribution systems, and power source and distribution systems New or relocated facilities such as air route traffic control centers (ARTCC), airport traffic control towers (ATCT) and off airport radar systems New or relocated instrument landing systems Federal financial participation or unconditional ALP approval: Airport location New runway Major runway extension Runway strengthening that could result in significant offairport noise increases New or revised ATC procedures which routinely route air traffic over noise sensitive areas 8

Does the project normally require an EIS? FAA Orders 1050.1E (paragraph 501) and 5050.4B (paragrah 903) identifies those actions that FAA has identified as requiring an EIS. Examples: An EA that identifies a significant impact that can t be mitigated below the significance threshold New commercial airport in a Metropolitan Statistical Area (MSA) New runway in an MSA If Action Is Not Categorically Excluded: No Significant Impacts Anticipated Unsure Whether Significant Impacts Exist Significant Impacts Expected/Major Project EA EA or EIS EIS 9

What to provide FAA? Documentation that supports the appropriate NEPA-level of analysis Categorical Exclusion Most regions have a CatEx checklist or Extraordinary Circumstances Evaluation form Define Proposed Action Identify which CatEx (FAA Order 1050.1E) is applicable Document no extraordinary circumstances exist Environmental Assessment 10

Who does what? Categorical Exclusion Airport Sponsor: Documentation FAA: Determination that project is categorically excluded Environmental Assessment Airport Sponsor: Documentation FAA: Finding of No Significant Impact Environmental Impact Statement Airport Sponsor: Supporting information FAA: Documentation and Record of Decision Agency Coordination Depends on the agency 11

Examples 1. Consolidated Rental Car 2. RNP Approach 3. Hydrant Fueling 4. Concourse Expansion 5. Runway Extension 6. Snow Storage Shed 7. New ATCT Tower 8. Runway Rehabilitation 12

Example 1 - CONRAC Airport has 2 acres of land adjacent to the airport perimeter, that when combined with 10 acres of vacant off-airport land available for sale is to be developed as a consolidated rental car facility (CONRAC) Access to what would become the CONRAC is an existing road that connects to the Airport s main entrance roadway Stormwater detention would be required for the CONRAC, but would be tied in with the existing stormwater system No endangered species, wetlands, and no historic sites would be affected The Airport area is non-attainment/maintenance for three pollutants No AIP funding, but PFCs would be used 13

Example 2 - RNP The FAA is seeking to implement a Required Navigation Performance (RNP) approach to two runways The approaches are overlays of existing tracks No change to the airport s noise abatement procedures (no change in tracks or runway use) A significant noise impact change will not occur within 65 DNL An increase in population and housing would occur at lower noise levels (<65DNL) RNP would result in a fuel burn savings from track mile savings There is an active watchdog citizen group because of past and ongoing noise concerns 14

Example 3 Hydrant Fueling Airport wishes to add Hydrant fueling to its existing gates on the main concourse Currently, fueling is done through tanker trucks Hydrant lines will meet state-of-the-art standard and will connect to the existing storage tanks on the Airport s perimeter. Area is non-attainment for ozone and project would reduce NOx emissions No AIP funding, and airport is not clear if PFCs would be used. 15

Example 4 Concourse Exp. The Airport wishes to extend one of its concourses to add 4 gates, boarding area, and concession space. The Airport currently has 47 gates, spread across three concourses Expansion would occur over existing apron area, and the apron would be expanded to serve gates 0.4 acre of wetland would be filled for the expanded apron Area is non-attainment for ozone and carbon monoxide No AIP funding, and unclear if PFCs will be used 16

Example 5 - Rwy Extension General aviation airport located in a rural (non-smsa) seeks to extend the their 4,000 ft single runway by 1,000 feet Airport owns land for runway, but would have to acquire 10 acres for approach protection Runway extension would allow more aircraft and larger aircraft to operate at the Airport Runway extension would fill 10 acres of low quality wetland Project would require relocating a major arterial or tunneling the road Area is attainment for all pollutants AIP funding will be used. 17

Example 6 Snow Shed Airport acquired 100 acres of nearby residential land due to noise about 10 years ago All residences were demolished, but 2 commercial buildings were retained and used by Airport Airport wishes to demolish one of the commercial buildings and build a snow equipment storage shed The commercial building has been deemed eligible for the national register of historic sites. No AIP, and no PFCs. 18

Example 7 New Tower The FAA wishes to build a new air traffic control tower The tower will replace the existing tower that does not allow sufficient space for controllers The new tower site will require displacement of a cargo building A site for the cargo facility has not been identified AIP funding will be pursued 19

Example 8 Rwy Rehab The Airport expects to rehab its primary runway over a 12 month period (7 months in 1 year, and 5 months in the following year) During rehab, the runway will be brought up to standards (lights and shoulders) This is one of a three runway airfield Noise during the construction period would produce an average annualized DNL increase of 1.5 to noise sensitive uses in the 65 DNL. AIP and PFC funding would be used. 20