PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

Similar documents
FORECASTING FUTURE ACTIVITY

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Lake Tahoe Airport Master Plan

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Westover Metropolitan Airport Master Plan Update

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

CHAPTER 1 EXECUTIVE SUMMARY

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)

Chapter 4.0 Alternatives Analysis

BNA Master Plan Update Community Advisory Committee Meeting No. 5

CHAPTER 3 ALTERNATIVES CONSIDERED

Regular Board Meeting August 4, 2015

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport

BNA Master Plan Update Public Meeting No. 2

Chapter 1 Introduction and Project Overview

Addendum - Airport Development Alternatives (Chapter 6)

CHAPTER 4: ALTERNATIVES

AIRPORT WITH NO RUNWAYS IS A MALL

2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP)

CHAPTER 5: Landside Facility Requirements and Development Concepts

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

B GEORGIA INFRASTRUCTURE REPORT CARD AVIATION RECOMMENDATIONS DEFINITION OF THE ISSUE. Plan and Fund for the Future:

Appendix 6.1: Hazard Worksheet

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

AIRPORT MASTER PLAN UPDATE

STUDY WORK GROUP MEETING No. 3. November 29, 2016

Alternatives Analysis EXECUTIVE SUMMARY

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

STUDY WORK GROUP MEETING No. 4. July 12, 2017

Merritt Island Airport

General Aviation Master Plan Update

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

Alternatives. Introduction. Range of Alternatives

The offers operators increased capacity while taking advantage of existing airport infrastructure. aero quarterly qtr_03 10

Airport Master Plan Open House Front Range Airport February 23, 2017

An Overview of GMR Megawide Consortium s Unsolicited Proposal. March 2018

Chapter 9 Airport Financial Plan

AIRPORT MASTER PLAN FOR. charles B. WHEELER DOWNTOWN AIRPORT KANSAS CITY, MISSOURI

Chapter 2 FINDINGS & CONCLUSIONS

Finance and Implementation

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update

AIRSIDE CAPACITY AND FACILITY REQUIREMENTS

Punta Gorda Airport Master Plan Update

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

RESOLUTION NO

Yakima Air Terminal/McAllister Field Airport Master Plan Update

Update on the Aspen/Pitkin County Airport Improvements

DALLAS LOVE FIELD MAY 2015 DRAFT

2015 PURDUE ROAD SCHOOL March 11, 2015

Yolo County Airport. ALP Narrative Report. April Prepared by Mead & Hunt, Inc. for the County of Yolo, California

What is an Airport Master Plan?

Chapter 5 Airport Development Alternatives

10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM

Fort Wayne International Airport Master Plan Study. Executive Summary

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 4g ACTION ITEM Date of Meeting February 9, 2016

FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW

AIRPORT MASTER PLAN ADVISORY COMMITTEE MEETING #2 AGENDA

SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES

Hartford-Brainard Airport Potential Runway Closure White Paper

Airport Master Plan Update June 15, 2017

Airport Master Plan Update June 15, 2017

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN

BELFAST MUNICIPAL AIRPORT OVERVIEW

Port of Seattle Sea-Tac Airport Master Plan An Economic Engine for Washington State. Kurt Beckett Deputy Chief Executive Officer

Planning Advisory Committee November 20, 2014

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3

JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 2007

APPENDIX B: NPIAS CANDIDATE AIRPORT ANALYSIS

DRAFT MASTER PLAN UPDATE

3.9 AIRPORT SUPPORT FACILITIES

Current and Forecast Demand

AIRPORT FUND. Description. Summary

Master Plan Update Community Advisory Committee Kick-off Meeting

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

Chapter 8.0 Implementation Plan

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

Table of Contents. Overview Objectives Key Issues Process...1-3

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM

Runway Length Analysis Prescott Municipal Airport

Correction to Council Resolution No , dated June 25, Please add the following correction as part of the permanent record:

8.0 AIRPORT LAYOUT PLANS

Grove Field Airport Environmental Assessment

Public Notice July 14, 2017

Transcription:

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February 1932 Airport classification: Primary non-hub Alaska Airlines service to Seattle (four flights daily) 2015 Total Passengers: 100349 (+20% over 2014) Up 42 percent for January/February 2016 over January/February 2015 2015 enplaned passengers: 50434 Up 42 percent for January/February 2016 January/February 2015 Charter operations supporting university athletics PUW captures just 72 of 220 charter flights, due to insufficient runway length and all-weather reliability Corporate general aviation More than 720 annual jet operations by large aircraft with maximum take-off weight up to and including 60,000 pounds General aviation Over 38,000 operations in 2015 73 based aircraft in 2015 Government, military and medical Training Emergency response WA and ID Air National Guard US Forest Service Fire Response Medical Flights (5-6 per week serving three hospitals) US Department of Agriculture Serves universities students, faculty, and research Washington State University (WSU) enrollment: 19,243 WSU faculty and staff: 4,697 WSU annual research and development expenditures:$389 million University of Idaho (UI) enrollment: 13,750 UI faculty and staff: 3,124 UI annual research and development expenditures: $100 million

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project TRANSPORTATION GATEWAY TO THE WORLD PUW is a transportation gateway to the world. The lines on the map show actual flights that happened in 2010. The scheduled, commercial air service allows travelers to connect to national destinations. Commercial flights are shown with the green lines. From Seattle, there are international connections to Mexico, Europe and Asia. International connections are shown with the red lines. The blue lines represent flights made by private aircraft traveling to and from the airport. The cities of Pullman and Moscow are a six-hour drive to Seattle and Boise. Air Service from PUW reduces these trips to one hour. STATE ECONOMIC BENEFITS On an annual basis, PUW contributes to the economies of Washington and Idaho. The runway realignment construction project will also have a significant economic impact to both states. Annual economic benefits Local Jobs: 300 Gross Regional Product: $17.4 million Local and State Taxes Annually: $2.72 million Source: Steven Peterson, Clinical Assistant Professor, Economics College of Business and Economics, University of Idaho

CONSTRUCTION ECONOMIC BENEFITS PUW RUNWAY REALIGNMENT CONSTRUCTION IMPACT (2015-2019) Category Total Total Jobs Total Compensation Sales Gross Regional Product Local Taxes State Taxes 226 $14,305,791 $46,615,102 $20,099,201 $499,643 $2,467,000 Source: Steven Peterson, Clinical Assistant Professor, Economics College of Business and Economics, University of Idaho PUW LIMITATIONS PUW does not meet FAA design standards for commercial and charter aircraft currently using the airport. Existing runway centerline to taxiway centerline separation does not meet FAA design standards PUW is currently operating under a Modification to Design Standards from the FAA. This agreement permits commercial operations to continue, provided the airport works towards a long-term solution to meet the required design standards. All-weather reliability limited due to runway alignment 124 cancellations or re-routing annually 80% of cancellations occur in winter months Existing runway length is inadequate for some existing airport users. Terminal building is inadequate to support existing demand. PUW passenger enplanements are growing at a rapid pace, which has resulted in an inadequate terminal building. The existing terminal building is 50% of the size it should be to accommodate existing passengers and security requirements.

Not to scale PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project PUW SOLUTIONS A runway realignment will significantly improve all-weather reliability of the airport. Realign runway to meet FAA design standards for runway/taxiway separation PUW and the FAA have evaluated more than 20 alternatives to correct design standard issues. An airport master plan was completed that established a preferred runway alignment at the existing airport site. The runway realignment will achieve compliance with FAA design standards and lower approach procedure minimums to improve all-weather reliability. The FAA has approved a runway extension to 7,100 feet, which will meet the needs of existing corporate users and improve conditions for charter aircraft serving Washington State University, the University of Idaho, and other Pac-12 university athletic programs. An ultimate runway length of 8,000 feet is planned. A terminal area plan is being prepared to present terminal expansion or relocation alternatives to meet the existing and projected passenger demands. The preferred runway development program rotates the existing runway and taxiway system approximately 5.5 degrees counterclockwise and shifts the new runway south to allow for future landside development on airport property. The program provides for a 7,100 foot realigned runway with an ultimate length of 8,000 feet. ULTIMATE DEVELOPMENT CONCEPT LEGEND Future runway: 7,100 feet x 100 feet Future airport facilities Future passenger terminal rebuild Ultimate runway: 8,000 feet x 100 feet Future hangar development Future business park Future taxiway Future tie-downs Future airport road Future apron Future parking lot expansion

PREFERRED DEVELOPMENT PROGRAM CHALLENGES The airport master plan identified multiple challenges associated with the realignment of the airport s only runway. PUW is located in the rolling hills of the Palouse region where large areas of level land are rare, and the area around the airfield is no exception. The preferred development program will require the removal of more than 5 million cubic yards of earth, enough to fill Washington State University s Martin Stadium 16 times or the University of Idaho s Kibbie Dome 36 times. Other design challenges include: Property impacts to Washington State University s agricultural research facilities Realignment of the future State Highway 276 corridor Relocation of power lines serving the community Relocation of Airport Creek Minimizing impacts to wetlands Construction phasing to reduce airport closures PROJECT BENEFITS ADVANTAGES OF A POSITIVE RESOLUTION IMPACTS OF A NO ACTION SCENARIO The runway realignment is a crucial turning point for the airport. It makes sense for many reasons, including the economic and transportation benefits it provides to the community. On the other hand, the No Action scenario will permanently limit the services and facilities the airport can provide. Airfield meets FAA design standards for C-III aircraft Continued commercial air service Improved reliability of commercial air service Opportunity for future, expanded commercial air service Opportunity for additional charter flights Improved service, facilities and reliability to support regional economy Additional land available for development at the airport Opportunity for expanded general aviation facilities Opportunity for longer runway in the future Loss of current commercial air service Permanent operation restrictions that restrict airport operations No opportunity to extend runway length Limited improvements in all-weather reliability Limited landside development potential

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project PROJECT SCHEDULE Years Project 1999 Airport master plan Complete 2007 Airport master plan update, Phase I Complete 2012 Airport master plan update, Phase II Complete 2012-2014 Environmental assessment Complete 2014-2015 Engineering design/land acquisition/utilities In progress 2016 Phase I construction Waiting on FAA Grant Offer 2017 Phase II construction 2018 Phase III construction 2019 Phase IV construction PROJECT FUNDING The airport is responsible for 8.125 percent of all project costs, rather than 10 percent. The FAA will provide funds for 91.875 percent. FAA issued the first grant in 2015 for $16 million and has programmed the remainder of the project funding as follows: - FY 16 $25 million - FY 17 $17 million - FY 18 $23 million COMMUNITY PARTNERSHIP The success of this program thus far has not been by accident, but rather a premeditated, extremely well-organized strategy, implemented corroboratively between two cities, two counties, two states, two universities, a port district and other important local partners.

ESTIMATE OF PROBABLE COST An estimate of probable cost was completed during Phase II of the Airport Master Plan. The estimate was $66.6 million in 2011 dollars. Cost estimates are refined at specific intervals in the planning, environmental, and design process. Moving through the process, project requirements can change, more information becomes available, and refinements to the estimate of probable cost are necessary. The Environmental Assessment (EA) process included preliminary engineering to better define the project scope and associated costs. The EA estimate was completed once all of the analysis was complete and is being vetted through the Federal Aviation Administration (FAA). The level of analysis completed for this EA is unique and was completed because of the complexity of the project requirements, and to provide a refined estimate of probable cost to support the development of the local funding strategy. Below is a summary of the project refinements that have occurred since the completion of the Master Plan Phase II estimate of probable cost: PROJECT REFINEMENTS Runway width was increased from 100 to 150 to comply with changes to FAA design standards (150 runway width with 25 paved shoulders). This results in 30% increase in pavement, floodplain and storm water management requirements. Avista utility relocation was anticipated to be an in-kind replacement of above ground facilities. During the EA, it was determined that a partial underground alternative needed to be considered. Underground transmission lines are 2.5 times more expensive than above ground alternatives. The higher cost was included for budget planning purposes. The preferred Avista Alternative has not been selected. The floodplain for the Airport is unmapped by FEMA. During the planning process it was assumed that a similar floodplain and storm water management technique being utilized today would be sufficient. However, after modeling the floodplain during the EA, it was determined that a more comprehensive storm water management system was needed to avoid flooding of the terminal building and aircraft storage areas. Land acquisition cost estimates during planning were based on limited information within the WSU agricultural research area west of the Airport. A detailed analysis was completed during the EA and determined that the land acquisition costs could be higher due to the nature of the research activities occurring in this location. To enhance the all-weather reliability of the new runway, the FAA and Sponsor are including runway centerline lighting and remote visual range capabilities. Inflation has resulted in an 11.1% increase from 2011-2015 (based upon Construction Price Indeces, and projected inflation). The project is estimated to begin in 2015 and be completed in 2019 with costs increasing with inflation throughout. The fluctuating cost of oil will influence the final project cost because of the large amount of paving and grading required for the project. The EA estimate of probable cost has been prepared conservatively. A column including a 25% contingency has been added to the EA estimate to account for inflation and potential project modifications.

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project CONSTRUCTION COST ESTIMATES Construction costs for the project have been estimated based on the completed analysis and cost data gathered from similar projects. The estimates have been prepared conservatively. Overall project construction costs by project elements are presented below. Description Cost Contingency Total Land Acquisition $9.0 million $3.0 million $12.0 million Wetlands/Stream $0.9 million $0.3 million $1.2 million Relocation Floodplain Relocation $7.2 million $2.4 million $9.6 million Power Line Relocation $6.7 million $2.2 million $8.9 million Mobilization, Etc. $5.0 million $1.7 million $6.7 million Site Prep / Earthwork $21.9 million $7.3 million $29.2 million Drainage Earthwork $1.9 million $0.6 million $2.5 million Pavement $21.3 million $7.1 million $28.4 million Drainage $4.5 million $1.5 million $6.0 million Airfield Lighting $1.6 million $0.6 million $2.2 million NAVAIDS and $2.2 million $0.7 million $2.9 million Weather Reporting Equipment Fencing $1.0 million $0.3 million $1.3 million Runway Centerline $1.6 million $0.6 million $2.2 million Lighting Remote Visual Range $0.4 million $0.1 million $0.5 million Future Terminal Storm $3.1 million $1.1 million $4.2 million System Improvements Future Terminal $0.4 million $0.2 million $0.6 million Deicing System Improvements GA Deicing System Improvements $0.4 million $0.2 million $0.6 million Total Project Cost $89.1 million $29.9 million $119.0 million * Contingency was rounded to the nearest hundred thousand, therefore the contingency percentage is not always an exact 25%.

For more information, contact Tony Bean, Executive Director, tony.bean@pullman-wa.gov, 509 338-3223