Coastal Management: Treasure Island - Long Key Nourishment

Similar documents
U.S. Army Corps of Engineers Wilmington District

Norfolk District North Atlantic Division

A Brief History of the Town of Palm Beach Coastal Protection Program. Beach nourishment occurred in Palm Beach as far back as the 1940s.

Port of Kalama, New Approach to Maintenance Dredging

Edisto Beach Renourishment and Groin Lengthening Project. Tim Kana Coastal Science & Engineering

Riverine Sand Mining/Scofield Island Restoration (BA-40)

Norfolk District North Atlantic Division

2. The EPA provided the following information regarding EPA s activities in Newark Bay during the meeting:

SAN FRANCISCO DISTRICT FY 2018 NAVIGATION PROGRAM

Stakeholder Meeting #1. An Introduction to the Blind Pass Inlet Management Study

Proposed Cherry Grove Canals Dredging Project

Buffalo District Navigation Program Overview

30 November Randall G. Hintz Chief, Operations Support Branch Operations Division. US Army Corps of Engineers BUILDING STRONG

CORPS OF ENGINEERS ALASKA DISTRICT Dredging Projects. Michael Tencza, PE Operations Project Manager November 4, 2015

CITY COUNCIL AGENDA MEMORANDUM

Amended Maintenance Dredge Spoil Management Plan. Shute Harbour Marina Resort

MOBILE DISTRICT 2018 DREDGING PROGRAM

USACE GALVESTON DISTRICT PROJECT UPDATE

DAMAGE ASSESSMENT OF SAND FENCING GARDEN CITY, NORTH LITCHFIELD AND LITCHFIELD BEACH GEORGETOWN COUNTY, SC

Figure 1: Little Dry Creek Trail Crossing

Presented to: City of Petaluma City Council

January 2018 Air Traffic Activity Summary

St. Augustine Port, Waterway & Beach District. St. Augustine Inlet 2013 draft Inlet Management Plan. March 19, 2013

Capital Program Delivery

Long water shutdown scheduled for Tuesday, September 18

PROGRESS REPORT WATERFRONT PROGRAM. Q (January - March) Highlights from Q1 2018

Item # 28. Chief Capital Management Officer Report. November 20, 2008

New Orleans Municipal Yacht Harbor

March 2, The Honorable Mayor Williams D. Sessoms, Jr. Members of City Council. Subject: Coastal CIP Presentation to City Council - March 6, 2018

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

Campus Construction Program Report WLAC Monthly Facilities Committee Meeting November 16, 2015

BENEFICIAL USE OF DREDGED MATERIAL DISPOSAL HISTORY HOUMA NAVIGATION CANAL, LA

DASHBOARD DEC YOUR MONTHLY UPDATE FOR IOWA ONE CALL

Appendix N MAINTENANCE DREDGING STATEMENT OF NEED & PERMIT COMPLIANCE. North Thousand Islands Management Plan Appendices

Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application

Figure 7. Dragline at Cape Coral, Figure 8. Cape Coral oblique aerial photograph, 1959.

EFFECT OF THE COASTAL CONSERVATION DUE TO BEACH NOURISHMENT OF TOTORI SAND DUNE COAST

Hertfordshire Business Barometer April 2018

Virgin Islands Port Authority Marine Tariff Rate Amendments August 30, 2017 Public Hearing

CHAPTER 241. SAND BYPASSING TO "PLAYA DE CASTILLA" (HUELVA SPAIN) Jose Fernandez (1) Gregorio Gomez Pina (2) Angel Mufloz (3)

Figure 1. Overview map of Burrard Inlet, showing location of False Creek inlet.

SUMMARY OF THE MEETING OF THE WOODS HOLE, MARTHA S VINEYARD AND NANTUCKET STEAMSHIP AUTHORITY. September 25, 2018

Manigurr-ma Palmerston partnership showcases city

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation

Kentucky Lock Project Update Inland Waterways Users Board Meeting No. 84

The Galveston Seawall

MANAGING COASTAL HAZARDS THROUGH BENEFICIAL REUSE OF DREDGED SAND AND AN ADAPTIVE WORKS STRATEGY

Completion: August 2011 LS #321 Design LS #8

FURTHER TO AUTHORITY MEETING #5/13 To Be Held June 21, 2013

Marine Transportation Safety Investigation Report M17P0406

TORONTO TRANSIT COMMISSION REPORT NO.

Introduction and Company Overview

Meeting held at FCC Environment Offices Thursday 12 th March 2015

26 October 2017 Icelandair Group Interim Report NET PROFIT USD 101 MILLION IN THIRD QUARTER

SUBJECT: Newark Bay Study Area Coordination Team Meeting, 9 October 2012

SAME/SBA CONFERENCE. Col. Christopher W. Sallese Commander, Galveston District U.S. Army Corps of Engineers April 11, 2012

Ideal RV Park in One of the Most Beautiful, Charming Small Mountain Towns

Hampton Roads Express Lane Network

Fire Station No. 1 Presentation MAY 16, 2016

Research and Statistics Department FOR RELEASE 8:50 A.M. Friday, February 23, 2018

BOND 2012 PROPOSITION 1

NC Dredge Studies NCBIWA Spring Conference April 23, 2018

Airport Noise Advisory Panel (ANAP)

EX USS SHADWELL Disposal Wreck in Place

Number of New MLS Listings Single-Family Residential Breakdown 21.8%

FROM: Donald J. Polmann, Director of Science and Engineering ( New Water Plan - Quarterly Report - Approve Submittal to SWFWMD

CAPACITY PLANNING. CALENDAR OF MILESTONE DATES DECEMBER 2019 and MAY 2020 TIMETABLES (PRODUCTION SCHEDULE)

GALVESTON DISTRICT O&M NAVIGATION MISSION & RESPONSE TO HURRICANE HARVEY

Pump Stations...more than just pumps

DTTAS Quarterly Aviation Statistics Snapshot Quarter Report

COMMONWEALTH OF THE BAHAMAS MINISTRY OF PUBLIC WORKS & TRANSPORT NASSAU HARBOUR PORT IMPROVEMENT PROJECT. Nassau Harbour Port Improvement Project

Design Meeting Presentation

CAPACITY PLANNING. CALENDAR OF MILESTONE DATES DECEMBER 2018 and MAY 2019 TIMETABLES (PRODUCTION SCHEDULE)

Beach Monitoring and Hotspots

October 7, 2016 Hurricane Matthew Rakes the East Coast of Flagler County for 18.1 Miles

CITY OF BROOKFIELD Capital Improvement Fund Budget

Agenda Report. Spruce Street Outlet Drainage Improvements Tower Road Relief Sewer

Holgate Taxpayers Association Spring Membership Meeting Minutes - June 2, 2018

CODE ENFORCEMENT SPECIAL MAGISTRATE PUBLIC HEARING CITY OF ST. PETE BEACH

2018 Goldwedge Mines Inc. Licence of Occupation Management Plan. Photo: xxxx. Goldwedge Mines Inc.

City of Sutherlin Planning Commission Meeting Tuesday, September 15, :00 p.m. Sutherlin Civic Auditorium Agenda

Public Information Exchange

City of Chelan Comprehensive Plan Update. Vision Workshop. Agenda

Surgical Services and Observation Unit Project Given by Highland Hospital to the Highland Park Community.

HOTEL INDUSTRY OVERVIEW. Texas

CONSOLE SUNSHINE COAST: CONSTRUCTION INDUSTRY ACTIVITY AND WORKFORCE PROFILE

Impact of Offshore Directed Forcing on Sediment Transport and Structural Integrity at Packery Channel, Corpus Christi Texas

City Council Report. Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering

Dredging 101. Why, Who, How and So What! 2015 WAMSI Research Conference. 30 March 2015

DISTRICT EXPRESS LANES ANNUAL REPORT FISCAL YEAR 2017 JULY 1, 2016 JUNE 30, FloridaExpressLanes.com

SECTION 106 ACTIVITIES ANNUAL REPORT

LESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation

BOND 2012 PROPOSITION 1

Tamanend Park Day FREE FAMILY EVENT! Saturday, September 9, :00 AM - 2:00 PM. Down on the Farm TAMDAY2017. Schedule of Events

Planned Procurement Opportunities Report. March 2017

China Creek North Park Upgrades and Glen Pump Station. Park Board Committee Meeting Monday, July 10, 2017

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited

BUSINESS BAROMETER December 2018

Ohio Department of Transportation Construction Update

PennDOT Interstate Work next week March 30-April 3:

Transcription:

Coastal Management: Treasure Island - Long Key Nourishment Project Completed - October 20, 2010 The nourishment of Treasure Island and Long Key (TI/LK) beaches began in late July of 2010. The previous 2006 TI/LK nourishment project was done after the 2005 hurricane season, utilized a total of 270,000 cubic yards of sand, and was completed in about 2 months (August - September). The 2010 project utilized material from two borrow areas: 1) John's Pass to fill Sunshine Beach and Sunset Beach located on Treasure Island, and 2) Blind Pass to fill Upham Beach on the north end of Long Key (St. Pete Beach). The project used: 127,260 cubic yards of sand to fill 3,000 feet of shoreline on Sunshine Beach, 125,423 cubic yards of sand to fill 4,000 feet of shoreline on Sunset Beach, and 159,572 cubic yards of sand to fill 2,000 feet of shoreline on Upham Beach. The streets that corresponded to the fill limits are indicated on the map below. Work progressed from north to south (Sunshine Beach, to Sunset Beach, and to Upham Beach) over 4 months. Sand was pumped through pipes from the borrow areas to the beaches. At Treasure Island Beach, the construction contractor provided Americans with Disabilities Act (ADA) accessibility to the water throughout the project. During the project, pipe was laid across the beach at the Treasure Island Beach at 112th Avenue. To allow easy public access to the water, a section of pipe was buried in the sand. After Upham Beach was nourished, a second contractor mobilized and begin a project to repair damaged geotextile T-Groins originally placed on the north end of Upham Beach by 2006. See attached reports

Project Status Report TI/LK Nourishment Project Revised October 20, 2010 Activity Updates October 20, 2010 Upham Beach was completed at 1 a.m. this morning, a couple of weeks earlier than anticipated. The permitted borrow areas were swept completely clean of all available sand. The contractor has begun demobilizing their boats, barges, and other equipment and they will be off the beaches and moved out of the area by the end of next week. Upham Beach should be clear of pipes and equipment by this Friday (October 22). Within the next few weeks, another contractor is expected to be mobilizing equipment at Upham Beach to begin a 2-3 month job repairing the damaged T-Groin structures. October 6, 2010 The dredger finished dredging inside Blind Pass north of the inlet on October 3 and will be dredging at the mouth -- and slightly westward of inlet mouth -- during the remainder of the project. The filling of Upham Beach is proceeding from the Jetty northward and is currently located in front of the Starlite Towers Condominium. September 29, 2010 The filling of Sunset Beach was completed by September 21, 2010. The Corps officially deemed Sunset Beach complete on September 23 after confirming the sand volumes placed on the Treasure Island beaches met contract requirements. The fill volumes measured on Sunshine and Sunset beaches were 127,260 cubic yards and 125,423 cubic yards, respectively. The pipeline, dredge, and other associated boats and supplies needed for the next phase have been moved to Blind Pass and Upham Beach. The dredging of Blind Pass and filling of Upham Beach will begin today. September 15, 2010 The Corps determined, due to lack of available sand, that additional fill cannot be placed on the beach north of 88 th Street. Demobilization of equipment and pipes from Sunset Beach and Treasure Island is expected to begin by September 23 rd. The filling of Upham Beach is projected to begin during the first week of October and be completed 4-5 weeks later weather permitting. September 14, 2010 The project is at about 83rd Avenue today. The contractor is expected to complete Sunset Beach to 77th Avenue by Sept 19th. The Corps may issue a change order to the contractor to extend the fill template north of 88 th Avenue with a limited amount of sand remaining from the Borrow Area. August 31, 2010 The contractor is finishing up Sunshine Beach today and may start filling Sunset Beach as early as tomorrow beginning at 88 th Avenue. The sand will be pumped from John s Pass along the beach to Sunset Beach. Some portions of the pipe will be buried to minimize impacts to beach users. August 26, 2010 The project has slowed due to the weather and is currently located at 121 st Avenue with about 1000 feet more beach to fill before completing Sunshine Beach which is expected within a week. Approximately 87,600 cubic yards of sand has been pumped to Sunshine Beach. Pipe is being laid between Sunshine and Sunset beaches and the booster pump located on the beach at 108 th Avenue is being prepared for operation. The booster pump and piping will be used to move sand from the dredge near John s Pass to Sunset Beach.

August 18, 2010 The project was shut down for 4 days and is currently located at 124 th Ave. Approximately 55,000 cubic yards of sand has been pumped to Sunshine Beach. About 7-10 working days remain to complete Sunshine Beach. August 13, 2010 The project shut down between 124 th Ave and 125 th Ave at 5 pm August 10th due to poor weather. Work is expected to restart August 14 if weather conditions improve. About 40,000 cubic yards of sand has been pumped onto Sunshine Beach to date. Contractor expects to complete Sunshine Beach in 10 more working days and start filling Sunset Beach by late August if there are no further shut downs. August 6, 2010 The project moved about 100 feet south from 127 th Avenue after the first day of operation which began early evening on August 4. The project work area is expected to move south at about 100 feet each day and should be at or near 126 th Avenue by Monday or Tuesday next week. August 4, 2010 This morning the Southwind Construction Corp. Dredge is moving to the borrow area located about ¼ mile west of the 127 th Avenue beach access. Filling at the north end of Sunshine Beach is expected to begin this evening. August 2, 2010 - The construction contractor has revised the dredging and beach fill start date and now expect to begin filling Sunshine Beach at 127 th Avenue on August 4 th or 5 th. July 27, 2010 Construction contractor is fusing 500 foot sections of pipe together at 77 th Avenue and then dragging them north to a staging area at about 108 Avenue near their booster pump. The dredge is expected to arrive at John s Pass by July 29. Later this week, the Corps will be doing pre-construction bathymetric surveys of the borrow areas at John s Pass and profiles of the fill area at Sunshine beach. The public is urged to stay clear of work areas. July 19, 2010 Preconstruction meeting held today. The Notice to Proceed was issued. Mobilization of pipes and other equipment is ongoing at Sunset Beach s 77 th Avenue parking lot and adjacent beach. A large booster pump has been delivered to Treasure Island Beach at 112th Avenue. The dredging of John s Pass and filling of Sunshine Beach is scheduled to begin August 2. July 12, 2010 County mailed post cards with general project information and the tentative construction schedule to beachfront property owners and occupants along the Treasure Island beaches and Upham Beach July 2, 2010 Contractor begins placing equipment and pipes on Treasure Island for project. Notice to Proceed scheduled for July 19, 2010. July 1, 2010 Construction contract awarded June 9, 2010 Construction project bid opened May 10, 2010 U.S. Army Corps of Engineers (Corps) advertised bid solicitation for beach nourishment construction project contractor March 29, 2010 FDEP Permits issued to dredge sand from John s Pass to fill Sunshine and Sunset beaches (in Treasure Island) and to dredge sand from Blind Pass to fill Upham Beach (in St. Pete Beach on Long Key)

Treasure Island & St. Pete Beach (Long Key) 2010 Nourishment Proposed Project Schedule Current as of October 20, 2010 The project schedule is subject to change depending upon weather and other unforeseeable events. Milestone Move dredge and equipment to John s Pass and Sunshine Beach Nourish Sunshine Beach (~40-day task) Move equipment from Sunshine Beach to Sunset Beach Nourish Sunset Beach (~30-day task) Move dredge and equipment to Blind Pass and Upham Beach Nourish Upham Beach (~35-day task) Note: A second contractor will repair the existing Upham Beach geotubes Start Month/Week End Month/Week Complete (X) July / Week 2 July / Week 4 X Aug / Week 1 Aug / Week 4 X Aug / Week 4 Sept / Week 1 X Sept / Week 1 Sept / Week 3 X Sep / Week 3 Sep / Week 4 X Oct / Week 1 Oct / Week 3 X Mid Nov 2010 Feb 2011

Upham Beach facing northwest (10-20-10)

Upham Beach facing west (10-20-10)

Upham Beach facing southwest (10-20-10)

Upham Beach facing south (10-20-10)

Upham Beach S to N (9-15-10) Upham Beach (9-15-10)

Sunset Beach N to S (9-15-10) Sunset Beach S to N. (9-15-10)

Sunset Beach S to N (9-1-10) Sunshine Beach N to S (9-1-10) Sunset Beach N to S (9-1-10) Sunset Beach S to N. (9-1-10)

Southwind Construction Corp. Dredge (Wilko) in Blind Pass (9-29-10)

Booster Pump on beach at 112 th Avenue, Treasure Island Piping along Sunset Beach at 77 th Avenue, Treasure Island Photo date: July 19, 2010

Construction Site at 127 th Ave, Treasure Island Pipe Discharging Sand Slurry at 127 th Ave, Treasure Island Dredge on Ebb Shoal at John s Pass Photo Date: August 5, 2010