July 5, Re: Contract ID Plan, & Proposal July 11, 2017 Letting. The Contractor is hereby advised of modifications to the bid documents.

Similar documents
2012 WATER & SEWER ALLEY CONSTRUCTION CONTRACT, PACKAGE II SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B DD

BID FORM. Bid by: Name of Bidder. Address: Address: To the Texas Department of Transportation hereinafter called the Agent.

LAKE MOUNTAIN PRELIMINARY

ADVANCED WARNING SYSTEM FOR SHARED USE CROSSING ON HOWARD STREET EAST OF NORDICA AVENUE

General Highway System SHEET 1 HILTON HEAD ISLAND URBAN AREA

845 North Hills Blvd.

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017

CITY OF IMPERIAL TOTAL BID PROPOSAL. 1. Mobilization / Bonds / Insurances LS 1 $ $ 2. Preparation/Implementation Traffic Control Plan LS 1 $ $

Program Manual. January 1, EarthCraft House Single Family Program. Viridiant 1431 West Main Street Richmond, VA

ADDENDUM NO. TWO AB

City of Redding Airports

Hospital Link Project Project Update Winter 2018

Installation Instructions

Community Development Department Council Chambers, 7:30 PM, December 20, 2012

PSEG Long Island. Community Distributed Generation ( CDG ) Program. Procedural Requirements

City of Fort Lauderdale. Frequently Asked Questions. Proposed Sea Wall Ordinance

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

Community Development Department Council Chambers, 7:30 PM, October 4, Related Case P: Site Plan Approval

Mason Street Bike/Pedestrian Trail Project

EXPERIMENTAL OPERATING LIMITATIONS EXHIBITION GROUP I1

CITY OF NORTH LAUDERDALE PARKS AND RECREATION DEPARTMENT. New Turf - Jack Brady Sports Complex Field 4 and Highland Park

Hospital Link Project Project Update September 2015

SUPPLEMENTARY CONDITIONS APPLICABLE TO TOWER CRANES 2012

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

OLD AIRPORT (PFN) RW 05/23 RW 14/32. 4,884-FEET X 150-FEET MIRL 4-BOX VASIs (5 & 23 APPROACHES) REILS

PUBLIC WORKS DEPARTMENT

PROJECT UPDATES October 26, 2017

PUBLIC WORKS DEPARTMENT

SUMMARY OF QUANTITES NO. ITEM DESCRIPTION UNIT QUANTITY DRAWING NUMBER TITLE GENERAL ELECTRICAL

TENDER NO. T WESTDALE ROAD SANITARY SEWER UPGRADE ADDENDUM NO. 1

PROJECT UPDATES February 1, 2018

Department of Public Works

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

GARFIELD BRIDGE. Building A Bridge to No-Where

Picnic Units A picnic unit is a part of a picnic area

CAUTION - NOTICE TO CONTRACTOR

Legal Notice. Columbus and Franklin County Metro Parks Request for Statement of Qualifications (RFQ): Professional Design and Engineering Services

? 0-? WA", ilp. Y ON 1Z Cond 1 0 AIRPORT COMMISSIONERS BOARD REPORT TO THE Los Angeles World Airports 0*1-

Hutchinson Regional Airport Request for Proposals for Hangar Lease RFP #15-163

REPORT A-017/2010 DATA SUMMARY

PROJECT UPDATES: March 15, th Street Water Tower Painting Project:

March 4, Mr. H. Dale Hemmerdinger Chairman Metropolitan Transportation Authority 347 Madison Avenue New York, NY Re: Report 2007-F-31

Foreign Air Carrier Family Support Act. August, 2011

TECHNICAL INSTRUCTION MANUAL: TRADITIONAL PARTY CANOPIES

CAUTION - NOTICE TO CONTRACTOR

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018

Agenda Report. Spruce Street Outlet Drainage Improvements Tower Road Relief Sewer

Required Showing for Route 205 Mattox Creek Bridge Replacement F07 Contract Project Number: , C501 - UPC Thursday January 16, 2014

SSRCC Field and Safety Rules

Lancaster County School District

Poly Shelters. Instruction Manual. Sunblocker Shade House 10' Wide x 30' Long SKU #1030SPC. Note: Photo may be of a different but similar model

Public Works Committee City Hall 200 NE Moe Street 2nd Floor Conference Room

Second Street Improvements Project Project Update Archive

Addendum No. 1 Acknowledgement of Receipt

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation

INVITATION TO BID PURCHASING DEPARTMENT P.O. BOX N. PATTERSON ST. VALDOSTA, GEORGIA

AGRITOURISM PERMIT APPLICATION PROCEDURES

10' x 20' MAX AP CANOPY Assembly Instructions

MEMORANDUM VILLAGE OF NORTHBROOK

Correction to Council Resolution No , dated June 25, Please add the following correction as part of the permanent record:

The lowering of the existing watermain was added to the Catenary B Contract through a change

Report to the Strategic Development Committee. Ronald Reagan Washington National Airport Project Journey. June 2018

Natare Stainless Steel Pools & Spas Elevated Pools, Whirlpools, Spas, Hydrotherapy, Competition, Recreation and Instructional Pools

STEPS REQUIRED TO OBTAIN A BUILDING PERMIT. 1. Obtain copy of Building Guidelines for River Ridge and Building Permit application.

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

Mainelli Wagner & Associates, Inc.

NCUTCD Proposal for Changes to the Manual on Uniform Traffic Control Devices

WHEREAS, the City operates and manages Rapid City Regional Airport (RAP); and

Los Angeles World Airports

ADDENDUM 1 FOR REQUEST FOR BID For REPLACEMENT OF PASSENGER BOARDING BRIDGES 7 AND 4 At ORLANDO MELBOURNE AIRPORT AUTHORITY RFB

Projected Advertisement Date

C. APPROACH FOR IDENTIFYING THE BEST ROUTES FOR THE NEEDED TRANSMISSION SYSTEM IMPROVEMENTS

CONSTRUCTION COMMITTEE MEETING AGENDA

DATE: Wednesday, July 31, ACTION: Interim rule with request for comments.

- Tents larger than 10 x 12 require a permit from Santa Rosa Island Authority and may require a permit from Escambia County, for inquiry.

SWAN CREEK VILLAGE HOMEOWNERS ASSOCIATION. P.O. Box Bountiful, UT

RESOLUTION No APPROVAL OF WAYNE COUNTY AIRPORT AUTHORITY FISCAL YEAR 2018 BUDGET. By Board Member Mark Ouimet

York Region Rapid Transit Corporation Board of Directors. Mary-Frances Turner, President

SUPERSEDED. [Docket No. 99-NM-121-AD; Amendment ; AD ]

THREE MILE PLAN TOWN OF SUPERIOR COLORADO

CHECK REGISTER FOR 5/1/2013 TO 5/31/2013 & CHECK NUMBERS 0 TO /02/ BOND REFUND 1,037.50

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

Part 9 MAINTENANCE MANUAL. Distribution Construction Standards Handbook

GUERNSEY ADVISORY CIRCULARS. (GACs) EXTENDED DIVERSION TIME OPERATIONS GAC 121/135-3

Installation Instructions

10' x 20' MAX AP CANOPY EXTENSION KIT Assembly Instructions

14' x 32' x 12' Round Top Round Style Shelter Assembly Instructions

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release.

HIRING OF HOTEL SERVICES FOR ACCOMMODATING PIA TRANSIT & DELAYED FLIGHT PASSENGERS AT KARACHI INSTRUCTIONS TO BIDDERS

LANDING GEAR - REPLACEMENT OF NOSE LANDING GEAR RETRACT PLUNGER ASSEMBLY

CHAPTER 61 SHEBOYGAN COUNTY MEMORIAL AIRPORT

LAS VIRGENES MUNICIPAL WATER DISTRICT AIR-VACUUM POTABLE WATER DEVICE RELOCATION PROJECT

AC Bid Upgrade. Terms and Conditions

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018

Grounding Clamp. Pins and Ball-Socket Clamps for Temporary Grounding

CertainTeed. Access Covers and Gratings. REXUS Manhole Covers

Pilot RVSM Training Guidance Material

RESCUE SUPPORT SYSTEMS TRIPOD CONVERSION KIT PN

DEVELOPMENT PLAN REVIEW PROCESS and APPLICANT GUIDELINES

Transcription:

July 5, 2017 Dear Prospective Bidders: Re: Contract ID 2688050 Plan, & Proposal July 11, 2017 Letting The Contractor is hereby advised of modifications to the bid documents. The Proposal has been modified: The attached Special Provision is hereby added to the Proposal. The Plan has been modified: The following sheets have been modified: Sheet No. U5 U8 Description UTILITY COORDINATION PLAN SHEETS The revised plans are located on SCDOT s Construction Extranet. The revisions to the Proposal will be incorporated into the Contract. Hard copies are also available from SCDOT s Engineering Publications office upon request. Your usual cooperation will be appreciated. MHA;afg attachment File:PC/MHA Mark H. Anthony Letting Preparation Engineer www.scdot.org Post Office Box 191 An Equal Opportunity 955 Park Street Affirmative Action Employer Columbia, SC 29202-0191 855-GO-SCDOT (855-467-2368)

SECTION 108: COORDINATION OF UTILITY RELOCATION WORK WITH BRIDGE CONSTRUCTION: WITHERS SWASH BRIDGE REPLACEMENT WEST BROADWAY STREET, MYRTLE BEACH, SC Utility Company Contact Name Phone Number Santee Cooper Power (Distribution) Clark Lange 843.347.3399 EXT 3057 City of Myrtle Beach Water & Sewer Mike Petrakis 843.918.2013 SCE&G - Gas Michael Barnhill 843.745.7991 Horry Telephone Cooperative Frankie Moore 843.369.8198 Time Warner Cable Bill Moore 843.913.7941 Frontier Joe Greene JW Mullins 843.443.3532 843.997.5956 For informational purposes only, utility relocation plans are included in the contract construction drawings for this project and are available for review at SCDOT District 5 Office located at 612 E. Palmetto Street, Florence, SC 29506. These plans are for illustration purposes only, so the contractor can visualize the utility relocations. For detailed construction utility relocation plans, the contactor will need to coordinate with the utility owners to obtain copies. It is the responsibility of the Contractor to call SC811 and the non SC811 member utilities three (3) days prior to work so that the existing utilities can be properly marked. All utility relocation work for those who are inside the project limits will be verified and coordinated by the contractor during construction. UTILITY AS-BUILTS: The roadway contractor shall be responsible for the collection and incorporation of the utility asbuilts in their final submittal. All existing, proposed, and abandon lines must be shown. UTILITY RELOCATIONS: Santee Cooper Power (SC) (OH1/E1) (Power Distribution) Santee Cooper Power has an overhead 3-phase power line along the north side of West Broadway Street from project beginning around STA 14+00 35 LT and continues east to the end of the project around STA 23+60 30 LT. At STA 19+35 XL and 20+10 XL SC has overhead crossings towards Collins Street. The two overhead crossings connect at the pole at STA 10+48 18 RT on Collins Street and continues south on the west side to STA 12+70 23 RT. At STA 11+68 XL on Collins Street, there is a single phase overhead crossing. At STA 22+24 XL on West Broadway Street there is an overhead single phase crossing. Communication companies are attached on all legs of the SC s overhead distribution network.

It is intended before construction is to begin, SC will remove their overhead facilities from the pole at STA 16+77 30 LT on West Broadway Street to pole at STA 20+17 29 LT. SC will remove the overhead crossing at STA 19+35 XL and 20+10 XL. SC will remove the pole at STA 10+48 18 RT on Collins Street. SC will install a new pole at STA 20+03 27 LT and make a new span to the pole at STA 11+14 20 RT on Collins Street. SC will install a new span between the poles at STA 20+03 27 LT and STA 22+25 30 LT. Once SC receives an approved encroachment permit, work authorization letter, and the right-of-way is staked, SC will schedule their next available crew to perform their relocations. It will take SC 2 weeks to complete the relocations. Contractor to confirm time frames and relocation status. City of Myrtle Beach Water (COMB-W) (W1) City of Myrtle Beach Water has a 10-in PVC water main that runs along the south side of West Broad Street from project beginning and continues east to STA 21+83 21 RT where it crosses to the north side. It then continues east to the project end. This line is bored under the swash. At STA 10+26 18 LT on Collins Street, a 6-in PVC water main branches off the 10-in water main and continues south along Collins Street on the east side to the end of the project. At STA 10+43 22 RT on Collins Street, there is an existing fire hydrant. The 10-in water main will remain in place as is. At STA 10+50 15 LT, the 6-in water main will need to be dropped in place to accommodate the proposed drainage. Otherwise, the 6- in water main will remain in place as is. For the 6-in water main drop, adjustment of valves, meters and services, and any unforeseen construction conflicts, the City of Myrtle Beach will need 2 weeks notice before the relocation is needed and 5 days to complete the relocation. Contractor to confirm time frames and relocation status. City of Myrtle Beach - Sewer (COMB-S) (FS1A / FS1B) City of Myrtle Beach Sewer has a 20-in force sewer main that runs along the north side of West Broadway Street throughout the project limits. Through the area of the swash, the 20- in force main is attached to two (2) utility piers for a crossing over the swash. COMB-S has a 24-in force main that perpendicularly crosses West Broadway Street at STA 20+07 XL and then continues east along West Broadway Street to the project end. This 24-in force main also continues along the west side of Collins Street from STA 10+15 15 RT to project end. COMB-S also has a gravity system along the south side of West Broadway Street from STA 21+19 29 RT to STA 22+61 31 RT with a crossing at STA 22+39 XL. The 24-in force main will remain in place. Special drainage structures have been designed to accommodate the 24-in force main. See the drainage plans and details. The 20-in force main will be relocated between STA 16+67 18 LT and STA 19+68 20 LT. Valves at STA 19+90 18 LT and 19+99 21 LT will need to be adjusted to the new grade regardless of which relocation option is chosen below. For the valve work, the City of Myrtle Beach will need 2 weeks notice before the adjustments are needed and 5 days to complete the work. This will be performed by the City s in-house personnel.

The City is currently bidding 2 relocation options. The details are listed below. It is anticipated that the project will be under construction by September 1, 2017. It is the responsibility of the contractor to verify if this work has started and which option was chosen. The 3-week utility window allotted under this contract will apply to both options. The 3-week window will begin once the full detour is in place. Option A (FS1A): The proposed relocation route will cross West Broadway Street at STA 16+67 XL to the south side of West Broadway Street, then continue east and be bored under the swash about 60 from the relocated center line, then cross back over West Broadway Street at STA 19+67 and tie back into the existing force main. The existing force main crossing over the swash will be removed as well the piers and attached duct bank. The City of Myrtle Beach intends on completing the jack and bore of the 20-in force main under Withers Swash prior to construction beginning. However, for the two (2) crossings on West Broadway Street and the tie in work, the City of Myrtle Beach will perform those items once the project detour is active. The City s contractor will perform the east crossing first. The City of Myrtle Beach will need 2 weeks to complete the crossings, tie-ins, and pier removal. Option B (FS1B): The proposed relocation route will begin at STA 17+37 LT and tie-in at STA 19+86 LT. The force main will be located on a beam structure between STA 18+10 LT to STA 18+80 LT for an aerial crossing over the swash. The City of Myrtle Beach intends on completing the aerial crossing option prior to construction beginning. SCE&G - Gas (SCE&G) (G1) SCE&G has a 2-in steel gas line that ends at STA 14+25 10 RT on West Broadway Street. SCE&G has a 2-in steel gas line at STA 20+67 16 RT that continues east along West Broadway Street on the south side to the project end around STA 23+00 21 RT. Along the east side of Collins Street heading south, SCE&G has a service line. The service line will need to be adjusted to allow for the drainage installation at STA 10+54 26 LT. Otherwise, the gas lines are to remain in place. SCE&G will need 2 weeks notice before the relocation is needed and 5 days to complete the relocation. Contractor to confirm time frames and relocation status. Horry Telephone Cooperative Communications (HTC) (OH1/DB1) HTC has aerial facilities attached to the Santee Cooper pole line along the north side of West Broadway Street. HTC will relocate into a joint duct bank led by Frontier from STA 16+77 30 LT to STA 20+03 27 LT. HTC will also transfer to the new span between the poles at STA 20+03 27 LT and STA 22+25 30 LT on West Broadway Street.

It is the intention of HTC to perform this relocation prior to bridge construction. Once HTC is able to access SCDOT proposed right-of-way (Tract 2), it will take 4-6 weeks to complete the bore, pulling fiber, and splicing. Contractor to confirm time frames and relocation status. Charter Spectrum (f.k.a. Time Warner Cable) (Charter) (TV1/DB1/OH1) (CATV) Charter has aerial facilities attached to the Santee Cooper pole line along the north side of West Broadway Street. Charter also has aerial facilities along the west side of Collins Street and an underground service at STA 11+13 XL. Charter will relocate into a joint duct bank led by Frontier from STA 16+77 30 LT to STA 20+03 27 LT. Charter will also transfer to the new span between the poles at STA 20+03 27 LT and STA 22+25 30 LT on West Broadway Street and the new span between poles at STA 20+03 27 LT and the pole at STA 11+14 20 RT on Collins Street. It is the intention of Charter to relocate into the duct bank and transfer to Santee Cooper s new pole line prior to bridge construction. Once the conduit and Santee Cooper s new pole line are available, Charter will need 2 weeks to complete their relocations. Contractor to confirm time frames and relocation status. Frontier Communications (T2/DB1/OH1) Frontier has aerial facilities attached to the Santee Cooper pole line along the north side of West Broadway Street. Frontier also has an abandoned duct bank along West Broadway Street from project beginning around STA 13+95 15 LT to 24+73 43 LT. Frontier has a manhole at STA 18+98 27 LT which a 400 PR copper cable exits and heads east along West Broadway Street and then crosses to the south side of West Broadway Street at STA 20+25 XL and continues east to the project end around STA 23+15 20 RT. Frontier also has a service cable along the east side of Collins Street. Frontier will relocate into a joint duct bank led by themselves from STA 16+77 30 LT to STA 20+03 27 LT. Frontier will then transfer to the new span between the poles at STA 20+03 27 LT and STA 22+25 30 LT on West Broadway Street and continue aerially to the pole at STA 24+69 34 LT, where they will then transition to their existing manhole at STA 24+73 43 LT. The abandon duct bank crossing over the swash will be removed with the sewer work. It is the intention of Frontier to perform this relocation prior to bridge construction. Once the proposed SCDOT right-of-way is available, Frontier will need 6 weeks to complete the relocations. Contractor to confirm time frames and relocation status.