PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016

Similar documents
PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 4g ACTION ITEM Date of Meeting February 9, 2016

TORONTO TRANSIT COMMISSION REPORT NO.

Port of Seattle Sea-Tac Airport Master Plan An Economic Engine for Washington State. Kurt Beckett Deputy Chief Executive Officer

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019

TORONTO TRANSIT COMMISSION REPORT NO.

Birmingham Airport 2033

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis

Implications of Construction Cost Escalation

PORT OF SEATTLE PRESENTATION TO THE WESTERN STATES INSTITUTIONAL INVESTORS CONFERENCE MAY 15, 2018

Westover Metropolitan Airport Master Plan Update

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

Alternatives. Introduction. Range of Alternatives

Love Field Modernization Program Update: Master Planning Recommendations

STUDY WORK GROUP MEETING No. 4. July 12, 2017

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport

Planning, Development and Environment Committee

PUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport

CHAPTER 4: ALTERNATIVES

Preliminary Draft Budget FY Airline Rates and Charges. Sea-Tac International Airport

The CLE Master Plan Includes:

Agenda Item No. 3.4 AGENDA ITEM BRIEFING

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, Shannon Eibert, C&S Companies

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway

Tampa International Airport Master Plan Update. December 12, 2012

AIRPORT MASTER PLAN UPDATE

Kansas City Aviation Department. Airport Committee July 19, 2018

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor June 11, :30 a.m.

Fort Wayne International Airport Master Plan Study. Executive Summary

THE AIRTRAIN AIRPORT ACCESS SYSTEM JOHN F. KENNEDY INTERNATIONAL AIRPORT AIRPORT ACCESS SERVICE

Fort Lauderdale Hollywood International Airport

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT

Midfield Satellite Concourse (MSC)

City of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport.

TERMINAL DEVELOPMENT PLAN


BNA Master Plan Update Community Advisory Committee Meeting No. 5

Salt Lake City International Airport April 23, 2013 Budget Briefing. Page 1

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

THIRTEENTH AIR NAVIGATION CONFERENCE

AIRPORTS DIVISION. The Hawaii Airports System Is Self-Supporting

IRREGULAR OPERATIONS AIRPORT CONTINGENCY PLAN

Study Design Outline. Background. Overview. Desired Study Outcomes. Study Approach. Goals (preliminary) Recession History

CHAPTER 1 EXECUTIVE SUMMARY

Alternatives Analysis EXECUTIVE SUMMARY

TORONTO TRANSIT COMMISSION REPORT NO.

INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE

SAN JOSÉ INTERNATIONAL AIRPORT

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

Newark Liberty International Airport. Terminal One Redevelopment. Briefing Book.

BOARD ITO Aide REPORT TO THE AIRPORT COMMISSIONERS

Master Plan Phase 2 Workshop

Amended & Restated Lease of Terminal Building Premises (Airport Use & Lease Agreement)

New PFC Application #13

AIRPORT IRREGULAR OPERATIONS (IROPS) PLAN. South Bend International Airport (SBN) St. Joseph County Airport Authority

MELBOURNE AIRPORT AUTHORITY B R I E F REGULAR MEETING of April 27, :30 AM MELBOURNE INTERNATIONAL AIRPORT BOARD ROOM

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

Table E-3 Phased Capital Improvement Program...E - 11

SouthwestFloridaInternational Airport

State of Hawaii Dept. of Transportation Airports Division Capital Improvement Program Update

Greater Orlando Aviation Authority Orlando International Airport One Jeff Fuqua Boulevard Orlando, Florida Memorandum TO: FROM:

PUBLIC SCOPING MEETING APRIL 2018

Region of Waterloo Planning, Development and Legislative Services Region of Waterloo International Airport Office of Economic Development

Regular Board Meeting August 4, 2015

? 0-? WA", ilp. Y ON 1Z Cond 1 0 AIRPORT COMMISSIONERS BOARD REPORT TO THE Los Angeles World Airports 0*1-

PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan

Hartsfield Jackson Update prepared for:

IAH Terminal Redevelopment Project. Memorandum of Agreement with United Airlines

FORECASTING FUTURE ACTIVITY

Feasibility Study Federal Inspection Service Facility at Long Beach Airport

GREATER ORLANDO AVIATION AUTHORITY

Agenda: SASP SAC Meeting 3

City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018

RONALD REAGAN WASHINGTON NATIONAL AIRPORT NOVEMBER 2016

VIRGIN ISLANDS PORT AUTHORITY (VIPA) 2016 PUBLIC HEARING ON PROPOSED TARIFF INCREASE. ! July

Master Plan Update Technical Advisory Committee Meeting

Current and Forecast Demand

CIVIL AVIATION AUTHORITY

Los Angeles International Airport (LAX) Airside $907M

Madison Metro Transit System

CHAPTER 1: INTRODUCTION

Port Everglades Master/Vision Plan Update

Technical Advisory Committee Briefing #3

BNA Master Plan Update Public Meeting No. 2

Chapter 1: Introduction Draft

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.

Master Plan Update Community Advisory Committee Kick-off Meeting

FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING

Logan International Airport Right Sizing and Good Terminal Planning

TORONTO TRANSIT COMMISSION REPORT NO.

Meeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012

AVIATION DIVISION. Percent ($ in 000's) 2015 of Total

Brief Recap of Project to Date

Introduction DRAFT March 9, 2017

Transcription:

PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016 DATE: TO: FROM: Michael Ehl, Director, Airport Operations Wayne Grotheer, Director, Aviation Project Management Group SUBJECT: Concourse D Hardstand Terminal (CIP #C800769) Amount of This Request: $38,255,000 Source of Funds: Airport Development Est. Total Project Cost: $38,400,000 Fund ACTION REQUESTED Request Commission authorization for the Chief Executive Officer to: (1) develop, advertise, and execute an alternative public works delivery using the design-build (DB) method for the Concourse D Hardstand Terminal Project at Sea-Tac International Airport with a total project cost estimated at $38,400,000 and (2) authorize the use of Port crews for preliminary work in support of the project. SYNOPSIS The airport is currently experiencing a shortage of gates and the related ability to accommodate passenger loading/unloading at remote facilities. With the temporary loss of gates during the construction of the International Arrivals Facility (IAF), North Satellite Expansion (NSAT) and other future projects, compounded with the unprecedented growth in passenger traffic, this shortage will be exacerbated. It is widely accepted that it will be necessary to operate inbound and outbound aircraft from remote hardstand locations, busing passengers to and from the terminal building. In order to accommodate these passengers, additional facilities with dedicated holdroom and passenger processing space are needed. To provide for remote hardstand operations, this project will construct a 32,500 Square Foot (SF) building on the east side of Concourse D in the existing North Ground Transportation (GT) Lot. This facility will house up to seven gate lobbies, or holdrooms, for hardstand operations. It is expected that extensive hardstand operations will be required prior to summer of 2018. In order to meet this schedule, staff recommends a design build alternative public works delivery method. It is anticipated that this facility will have a useful life of 20 years. Template revised May 30, 2013.

Page 2 of 7 BACKGROUND AND JUSTIFICATION Passenger traffic at Sea-Tac Airport continues to break records and has increased each month for the past 31 straight months (since November 2013). Passenger traffic is up 10 percent for 2016 compared to 2015. This growth in passenger traffic is mirrored in growth in the number of airline operations as well. This year, the number of flights arriving during peak periods is greater than the number of available contact gates where aircraft can be connected through a passenger loading bridge to the terminal building. In 2015 and 2016, airlines have participated in limited trial operations at remote hardstands. In 2017, construction activities for two large projects, IAF and NSAT, will take existing gates out of service for several years. To accommodate operations when sufficient gates are not available, the airport will institute hardstand arrivals and departures where passengers are bused between the terminal building and remotely parked aircraft. Since every gate will be in use and every holdroom will be occupied when hardstand operations are activated, the airport must construct associated waiting areas for passengers for these flights. Today, the airport has two locations where buses from remote hardstands can drop arriving passengers into the terminal building: Gates S1A and A6A. Both locations are adjacent to functioning terminal connected contact gates. Both locations offer a sloped walkway ramp between the bus drop off location and the terminal building concourse. Because both gate holdrooms were designed solely to accommodate their primary gated flights, neither gate has separate holdroom facilities for a departing hardstand bus operation. Departing flights from a remote hardstand require four basic elements: 1) Holdroom facilities to process and hold passengers waiting to board their flights; 2) Ground access for passengers to board the buses; 3) Buses to transport passengers to the hardstand aircraft parking (along with boarding equipment) and, 4) Ground Service Equipment (GSE) for servicing aircraft at the hardstand location. This past year the Airport began two capital projects to provide remote hardstand operations capacity. The first is the Gate D6 Holdroom Improvements project (C800771). The design is complete and is scheduled to be in use March 2017. This will provide an additional sloped walkway ramp and make use of an otherwise vacant 2500 SF holdroom on Concourse D for up to two staggered flights. The other is Concourse B Ramp Level Holdroom project (C800761), for which the Commission authorized construction in July 2016 and is scheduled to be occupied in May 2017. It will provide holdroom space of 3,400 SF to serve up to two staggered flights and ramp access to bus transport. In 2015, AV Planning and Operations staff determined that the hardstand peak demand could eventually rise to 11-13 simultaneous operations in the 2018-19 timeframe. Airport staff agreed that the North Ground Transportation lot adjacent to Concourse D was the best location for a holdroom facility to support these operations.

Page 3 of 7 The Concourse D Hardstand Terminal will be directly linked to Concourse D by a bridge and to the North Satellite Train System (STS) Main Station landing through a passenger covered walkway. This location also allows for the simultaneous circulation of sufficient numbers of dedicated buses to/from remote hardstands for the six to seven holdrooms without impeding existing gates and ramp activities. Construction and use of the Concourse D Hardstand Terminal will require the relocation of all operations utilizing the North Ground Transportation lot. Preliminary planning with Airport Landside Operations has determined that these Ground Transportation operations can be accommodated in other Main Terminal adjacent facilities and areas. Staff will be seeking authorization shortly via an additional request to procure equipment necessary to support remote hardstand operations. This will include additional dedicated airfield passenger ramp buses and ground support equipment such as boarding stairs, ground power units and PC Air units. PASSENGER EXPERIENCE AND PROJECT DETAILS Passengers departing via the Concourse D Hardstand Terminal would begin their journey in the same way as any passenger with a flight departing from Concourse D. They would walk through Concourse D and across a connector bridge onto the upper level mezzanine of the new two-story Concourse D hardstand terminal. From the mezzanine, passengers will be able to view out into the entire space of the building and locate their gate. The building will be light and airy with a sky-lighted curved roof structure, and display colors and patterns with a Pacific Northwest feel. The mezzanine will provide modest concessions and a place to sit and relax. From the mezzanine, one will be able to walk down the stairs or a gently sloped ramp to the ground level and departure gates. On the ground level, there will be a number of amenities for passengers to use while waiting, such as electric charging stations, free Airport Wi-Fi, concessions and restrooms. Passengers would depart by walking through the gate door to a waiting bus instead of directly onto the aircraft. The bus will then take passengers to the waiting remotely parked aircraft. The expected utility of the Concourse D Hardstand Holdroom is 20 years. Based on current forecasts and development plans, staff anticipates it will be used as hardstand holdroom for 10 to 15 years depending on how long it will take to provide additional gate capacity connected to a new North Terminal as envisioned under the Sustainable Airport Master Plan (SAMP). When the facility is no longer needed for passenger operations, an evaluation of the facility use, forecasted needs and the development plans of the airport should be undertaken to determine next steps for the building, likely removal.

Page 4 of 7 Project Objectives Provide a dedicated common-use holdroom and passenger processing space for six to seven hardstand operations. Provide an efficient and seamless hardstand and busing operation. Provide and create a positive passenger experience. Pursue a LEED vs.4 Silver building certification. Start operations by summer of 2018.. Scope of Work This project will construct a 32,500 SF building on the East side of Concourse D in the existing North Ground Transportation Lot. This facility will be a metal building system and will house six to seven holdrooms for the hardstand operations connected to Concourse D by a connector bridge. The project will install common use casework and passenger processing equipment as well as passenger amenities including seating, Wi-Fi, restrooms and limited concessions. Outside the building, the project will delineate passenger load and drop off zones for the airfield passenger buses. The project will also add a passenger ramp and covered walkway down to the mid-level of the North Main (STS) Station. The relocation of the American Airlines storage shed and the POS garbage compactor will be required as enabling projects. Schedule Issue Notice to Proceed: 2 nd Qtr. 2017 Construction Complete: 2 nd Qtr. 2018 FINANCIAL IMPLICATIONS Budget/Authorization Summary Capital Expense Total Project Original Budget $2,000,000 $2,000,000 Budget Increase $36,000,000 $400,000 $36,400,000 Revised Budget $38,000,000 $400,000 $38,400,000 Previous Authorizations $145,000 $0 $145,000 Current request for authorization $37,855,000 $400,000 $38,255,000 Total Authorizations, including this request $38,000,000 $400,000 $38,400,000 Remaining budget to be authorized $0 $0 $0 Total Estimated Project Cost $38,000,000 $400,000 $38,400,000 Project Cost Breakdown This Request Total Project Design/Construction $35,879,000 $35,879,000 Sales Tax $2,521,000 $2,521,000 Total $38,400,000 $38,400,000

Page 5 of 7 Budget Status and Source of Funds This project was included in the 2016-2020 capital budget and plan of finance as a placeholder with a budget of $2.0 million. A budget increase of $36 million was transferred from C800404 Aeronautical Allowance resulting in no net change the Airport s capital budget. The funding source for this project will include the Airport Development Fund. Financial Analysis and Summary CIP Category Renewal/ Enhancement Project Type Infrastructure Upgrade Risk adjusted discount rate N/A Key risk factors N/A Project cost for analysis $38,400,000 Business Unit (BU) Terminal Building Effect on business performance NOI after depreciation will increase IRR/NPV N/A CPE Impact.12 in 2018 Lifecycle Cost and Savings The expected life of the Concourse D Hardstand Terminal is 20 years, all assets associated with this project will be determined with this in mind. The major assets associated with this project will be associated with the mechanical, electrical, building envelope, selection of fixtures and materials. Aviation maintenance anticipates there will be some incremental costs associated with the construction of this facility. STRATEGIES AND OBJECTIVES This project supports the Port s Century Agenda objectives of meeting the region s air transportation needs at the Airport for the next 25 years by providing critically needed passenger holdroom space with passenger processing equipment and a busing area to facilitate hardstand/off-gate aircraft operations. This project will also seek to support the Port s Century Agenda objective to be the greenest and most energy efficient port in North America and the strategy for a sustainable Airport to pursue LEED Certification for all new Port projects by seeking LEED vs. 4 Silver Certification. There are opportunities to meet increased energy needs through conservation and renewable resource, meet agency requirements for storm water and reduce air pollutants and carbon emissions. This facility will be designed and built to meet current building, electrical, mechanical and energy codes. The restrooms water closets will be low-flow. Interior finishes will include all paints and adhesives that are low in Volatile Organic Compounds (VOCs), and various interior materials, as applicable, will use recycled content materials.

Page 6 of 7 The construction of this project presents a number of small business opportunities. The project team is working with the Port s Economic Development Division s Small Business Team to maximize small business utilization efforts for this project. ALTERNATIVES AND IMPLICATIONS CONSIDERED Alternative 1 Status Quo Do not design or construct a hardstand terminal Cost Implications: $0 This option does not provide new facilities in the terminal for facilitating hardstand operations. During times of gate shortage, airlines would be required to wait on the ramp until a gate is available or run hardstand operations without a dedicated facility for processing hardstand passengers. This alternative does not require a capital investment. This alternative would potentially delay aircraft arrivals and departures, significantly degrading the quality of passenger experience at Sea-Tac. This alternative would potentially lead to airlines having to process departing hardstand passengers in severely congested holdrooms already being used for other flights. This alternative does not give airlines a dedicated space to provide customer service and process passengers for hardstand departures. This is not the recommended alternative. Alternative 2 Build a Hardstand Terminal in an alternate location. Cost Implications: Central Terminal Location = $25 - $30M; Cargo 4 South=$65-$80M. Preserves the North GT Lot for Ground Transportation functions. A decision analysis was completed in consultation with airlines and all other potential locations for this facility were ruled out due to cost, operational impact or customer service degradation. Specific concerns with the Central Terminal location are the loss of aircraft parking positions and traffic congestion (Vehicular and Aircraft) at a critical central point of the ramp. The airlines consider these fatal flaws with the location. Specific concerns with Cargo 4 South location are remoteness and overall cost. Staffing and customer service would most likely be impacted. This is not the recommended alternative.

Page 7 of 7 Alternative 3 Build the Concourse D Hardstand Terminal via Design-Bid-Build procurement method. Cost Implications: $40.6M Traditional construction delivery method This alternative would not provide a Concourse D hardstand terminal until 1 st Qtr. 2019 and does not meet the summer 2018 in use date required to meet operational demands. This is not the recommended alternative Alternative 4 Build Concourse D Hardstand Terminal via Design-Build procurement method. Cost Implications: $38.4M This alternative meets the schedule required to meet operational demands by having an in-use facility in the summer of 2018. Passengers will need to depart the holdroom and go up to the Concourse Level in order to reach amenities like dining or retail, some concession will be located in the new building. Eliminates North GT Lot for airport charters and Cruise ship bus operations. Alternatives are in process for the relocation of these functions. Design Build will require the need to decide specifically what we want early in the process and stick to it, in order to get the cost and schedule efficiencies of the method. This is the recommended alternative. ATTACHMENTS TO THIS REQUEST Computer slide presentation. PREVIOUS COMMISSION ACTIONS OR BRIEFINGS None