District Letter Dated Project % to ADA Amount Granted Buffalo Grove March 10, 2014 Woodland Park - asphalt path 100% $4,500.00 Buffalo Grove March 10, 2014 Wellington Commons Bike path repairs including: repair of slope and cross slope issues and truncated domes installed in areas 4 & 5 62.5% $15,376.00 Buffalo Grove March 10, 2014 Kilmer Park - asphalt path 100% $83,485.00 Olmsteak Park - replace existing walkway from parking lot to exisiting tennis courts, relocate curb cuts and provide two handicap van accessible parking spaces. 100% $11,943.00 Willow Rec Park - remove and replace concrete walks, ramps and walkways at Willow Recreation Center to meet ADA standards. 60% $7,612.00 Willow Rec Park - remove and replace concrete walks, ramps and walkways at Willow Recreation Center to meet ADA standards. 100% $638.00 Seascape Aquatic Park - remove and replace existing concrete curb, re-pave and level asphalt to reduce side slopes greater than 2% in existing handicap stalls. 100% $8,745.00 River Trails May 28, 2014 Mount Prospect June 25, 2014 Palatine Park District September 3, 2014 Poplar Park - remove and replace concrete walks and ramps not in conformance with ADA minimum standards 100% $14,240.00 Cottonwood Park - remove and replace concrete walks and ramps not in conformance with ADA minimum standards and supply tactile surface plate. 100% $5,506.00 Locust Park - remove and replace concrete walks and ramps not in conformance with ADA minimum standards. 100% $1,798.00 Maple Trails Park - curb cut and ADA ramp on north side leading to gate, connecting path on south side and resurfacing court 100% $15,500.00 RecPlex - renovation of eight handicap accessible parking spaces and four concrete squares that are part of the accessible route to the facility. 100% $13,132.30 Parkside Preschool - removal and replacement of the walkway to access each facility. Fred Hall Ampitheater - deck overlooking ampitheater 100% $6,402.00
Mount Prospect September 2, 2014 Mount Prospect Golf Club - excavation and installation of a continuous cart path system and range tees. 100% $226,927.00 Palatine Park District October 10, 2014 Install surfacing to allow patrons with mobility disabilities to access the table. 100% $2,756.26 Elk Grove November 17, 2014 Shenandoah Park - seating and picnic tables were relocated near the playground and a concrete access ramp brings visitors on the engineered wood fiber safety surface 20% $4,882.44 Hoffman Estates March 6, 2015 Triphahn Center - remove and replace existing concrete walks and ramps with existing cracks greater than 1/2" and rise greater than 1/4". Install tactile plats, level asphalt to reduce running and side slopes greater than 2% in handicap parking stalls. 82% $65,000.00 Hoffman Estates March 6, 2015 Joseph Fabbrini Park - rebuild existing pathway network to eliminate running slopes greater than 5% and cross slopes greate than 2%. 99% $250,000.00 Willow Stream Parking Lot - 5' width of the sidewalk work, curb and gutter work and detectable warnings, hadicap parking stalls and signage for those stalls. 100% $34,295.20 Alcott Center Park - 5' width of the 6' wide sidewalk installation. 83% $12,396.70 Willow Stream Park - mulit use trails and sidewalks. 62.50% $76,578.87 Willow Stream Park - trail asphalt and concrete removal 62.50% $16,184.06 Reservoir 7 - fence work, concrete removal, 5' wide sidewalk installation, detectable warnings and turf restoration. 100% $8,644.98 Community Arts Center - ADA ramp (labor & materials), guardrail/handrail. 100% $15,705.22 Salt Creek Janaury 20, 2015 Concrete ramps/curbs and asphalt repair. 100% $56,759.00 Mount Prospect May 19, 2015 Aceessibility improvements to thewalking Path as well as to Friendship Park and Studio parking lots. 100% $46,952.20 Palatine May 15, 2015 Ost Field playground - remove the seating area and entrance walk and replace with concrete. In addition a connecting concrete walk will be installed so the playground will be accessible from the track and the sidewalk. An accessible family picnic table will also be installed. 100% $9,045.00
Palatine June 24, 2015 Palatine Senior Center - removal and replacement of the walkway and install ADA tactile strips to the northwest entrance. 100% $3,000.00 Mount Prospect September 2, 2015 Einstein Park Playground - improvements to accessible routes of travel 100% $4,587.91 Mount Prospect August 28, 2015 Meadows Ballfields - accessible routes of travel to viewing area and athletic fields. 100.00% $8,042.00 Palatine August 19, 2015 Willowwood Park - accessible path installed from the existing park path to the ball field, entry ramps constructed at the depressed curb for each playground space, a depressed curb contructed for the existing swing area and ashphalt pathway to ballfield. 100% $6,328.47 Palatine August 5, 2015 Plum Grove Reservoir - replacement of walkway and parking area. 100% $8,500.00 River Trails May 22, 2015 Maple Trails Park - safety surfacing and asphalt path. 100% $21,598.00 Mount Prospect November 13, 2015 Melas Park - route of travel from Weller Lane across 100% $11,709.31 Elk Grove November 12, 2015 Audubon Park - concrete walks to provice an accessible route to playground and equipment 100% $9,000.00 Elk Grove November 12, 2015 Johnson Park - concrete access ramp and walk 100% $11,660.00 Elk Grove November 12, 2015 Mead Park - replace concrete and provide smooth 100% $7,600.00 Hoffman Estates January 5, 2016 Canterbury Place Park - concrete walks and ramp 100% $23,118.00 Hoffman Estates Janaury 5, 2016 Victoria Playground - replacement ramps and decks 17% $6,568.00 Schaumburg February 26, 2016 Mraz Park - concrete curbing 19% $9,900.00 Buffalo Grove February 29, 2016 Cherbourg Park remove and replace 5 width of the 8 wide sidewalk installation 62.50% $3,210.94 Palatine July 21, 2016 Palatine July 21, 2016 Mount Prospect July 19, 2016 Mount Prospect July 19, 2016 Palatine September 16, 2016 Celtic Park accessible walkway from the southwest sidewalk to the northwest sidewalk 100% $45,567.00 Dutch Schultz Recreation Area installation of accessible walkway from parking lot to tennis courts 100% $32,775.02 Clearwater Park - earth excavaion, hot mix ashphatl pavement removal, Portland cement concrete sidewalk, hot mix asphalt pavement and engineered wood fiber 100% $37,677.00 We-Go Park - earth excavaion, hot mix ashphatl pavement removal, Portland cement concrete sidewalk, hot mix asphalt pavement and engineered wood fiber Tom T. Hamilton Sports Complex - sawcut, misc. 100% $17,555.00 removals and concrete paving 28% $2,914.00
Palatine September 16, 2016 Palatine Park District (north section) - site grading and prep, concrete paving, sloped playground entry and intregal curb to playgroud 30% $16,021.00 Prospect Heights November 3, 2016 Lions Park - woodfiber 100% $2,050.00 Audubon Park - accessible routes to ballfield 24% $1,500.00 Appleseed Park - accessible route to spectator area along first base side 75% $1,500.00 Roosevelt Park - accessible route from ball field and playground to acceible portable toilet 93% $1,500.00 Hattendorf Park - overlay the area when new inclusive playground was installed 100% $1,700.00 Andrews Park - 2 concrete walks to provide an accessible route to playground and equipment 18% $5,915.00 Raven Park - installation of new 5' - 9' wide accessible concrete walks, concrete pads for player's bnesches and bleachers around the southwest baseball field, concrete pad for an accessible portable toilet unit and concrete pads for new site amenities. 91% $93,294.73 Arlington Heights February 24, 2017 Arlington Lakes - accessible 8' asphalt paths throughout the golf course. 50% $205,029.95 Hasbrook Park - baseball field #1 installation of a new 5' wide concrete walk from existing park path fo the baseball field, baseball field #2 installation of a new 9' wide concrete walk and concrete pads for player's benches and bleachers. 57% $22,808.68 Recreation Park - installation of an asphalt overlay for an exisiting driveway/drop off area. 20% $4,589.60 Buffalo Grove March 9, 2017 Willow Stream - path renovation 5' of 8' path 100% $4,320.60 Buffalo Grove March 9, 2017 Winfield Park - removing and relocating a 6' wide asphalt path to make the path ADA compliant with a 5% slope and a cross slope of 2%. 100% $15,733.00 Victoria Park - remove existing asphalt and concrete surfaces and re-grade subgrade so as to conform to less than the maximum running and cross slope requirement. Re=pave surface with asphalt, 5/8 of the 8-foot wide path width. 42% $17,380.00
Mount Prospect March 22, 2017 Mount Prospect March 9, 2017 Mount Prospect March 9, 2017 Salt Creek February 15, 2017 Schaumburg March 8, 2017 Evergreen Park - remove exisiting asphalt surface and regrade subgrade so as to conform to less than the maximum running and cross slope. Re-pave surface with asphalt, 5/8 of the 8-foot wide path width. 42% $38,955.00 Westbury Park - remove existing asphalt surface that has settled and/or heaved over time. Re-grade subgrade so as to conform to less than the maximum running and cross slope. Re-pave surface with asphalt, 5/8 of the 8- foot wide path width. 42% $7,544.00 Friendship Park Conservatory - accessible routes of travle and entry to Conservatory 100% $2,000.00 Einstein Park - asphalt parking lot, asphalt pathways, concrete paving, surfacing and concrete curb and estimate of fees and asbuilt survey. 36% $115,927.02 Lions Memorial Park Bandshell - compliant paths of travel for public assemblies and entertainment events. 26% $19,298.00 South Park - concrete walkway, ramps, playground surface and asphalt parking area. 67% $68,425.00 Spring Valley Nature Center, Bison's Bluff - concrete paving of playground area, playground protective surfacing, boardwalk to main structure, foot bridges (A,B, & C) and concrete paving of parking lot area. 13% $298,170.00