COMMONWEALTH OF THE BAHAMAS MINISTRY OF PUBLIC WORKS & TRANSPORT NASSAU HARBOUR PORT IMPROVEMENT PROJECT. Nassau Harbour Port Improvement Project

Similar documents
NEW TECHNOLOGIES AND THEIR IMPACT ON PORT DEVELOPMENT IN JAMAICA. Christopher Hamilton May

PORT DEVELOPMENT STRATEGIES & SUCCESS STORIES. PORTMIAMI AN EVOLVING GATEWAY Juan M. Kuryla, PPM PortMiami Director and CEO

VERSION DATE OF ISSUE DESCRIPTION PREPARED CHECKED APPROVED Technical note HHP DKA OYBE

The Americas. Port of the Americas. Rhonda M. Castillo Gammill, Esq., P.E. Executive Director, Port of the Americas Authority

PRESENTATION ON CAIRNS SHIPPING DEVELOPMENT PROJECT

COMMUNICATION THE RT. HON. PERRY G. CHRISTIE PRIME MINISTER AND MEMBER OF PARLIAMENT FOR CENTREVILLE

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #1 September 24, Peter O. Knight Airport

Public Information Center August 12, 2010

Port Everglades Master/Vision Plan Update

APPENDIX 20 EFFECTS ON NAVIGATIONAL SAFETY

Appendix N MAINTENANCE DREDGING STATEMENT OF NEED & PERMIT COMPLIANCE. North Thousand Islands Management Plan Appendices

Marine Notice No. 19 of 2014 This Marine Notice supersedes Marine Notice No. 12 of 2013.

Roberts Bank Terminal 2 Project

Ports. Water and Environment Solutions

Serving the Tampa Bay Maritime Community Since Celebrating over 125 Years of Service

Port of Durban. Entrance Channel Widening & Deepening Project Completion Function. 31 March 2010

Dredging in Fowey Chapter 3 Post departure of the Lantic Bay

Beyond Gateway Ports Navigating New Destinations

Virgin Islands Port Authority Hurricane. Recovery Update. March 2018

FORECASTING FUTURE ACTIVITY

FUTENMA REPLACEMENT FACILITY BILATERAL EXPERTS STUDY GROUP REPORT. August 31, 2010

North Cruise Berth Projects PortMiami

DOVER WESTERN DOCKS REVIVAL (DWDR) NEWSLETTER. The single biggest investment ever undertaken in Dover

Preparing for Larger Cruise Vessels. Gary Ledford AAPA Facilities Engineering Seminar November 17, 2009

HYDRAULIC DESIGN OF THE TOURISTIC BERTHING IN ASWAN CITY

U.S. Army Corps of Engineers Wilmington District

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

PortMiami Director and CEO Juan M. Kuryla PUBLIC-PRIVATE PARTNERSHIPS (P3)

Credit No IN. National Project Director 9,Institutional Area, Lodhi Road, New Delhi Tel:

Policy, Practice and Procedures for Lay Up and recommissioning of a Netherlands Registered and certificated seagoing commercial Vessel.

Santa Cruz Wharf Improvement Project. Briefing Paper. Prepared by City of Santa Cruz. for

TNPA 2 nd Strategic Customer Forum Update on Infrastructure Projects. 13 August

SEA DUBAI. By Rasiena

Amended Maintenance Dredge Spoil Management Plan. Shute Harbour Marina Resort

Port Everglades 2014 Master/Vision Plan Update

Cv-c; Re: Hotel Development Charges in York Region. March 24, 2016

Panama Canal Stakeholder Working Group Meeting

Mr. David Peng, General Manager, Kings Aviation. Set Up an AOC and Operating Helicopters in China

MESO-AMERICAN AND CARIBBEAN HYDROGRAPHIC COMMISSION. National Report (October 2006) - Jamaica

Section II. Planning & Public Process Planning for the Baker/Carver Regional Trail began in 2010 as a City of Minnetrista initiative.

MANAGING COASTAL HAZARDS THROUGH BENEFICIAL REUSE OF DREDGED SAND AND AN ADAPTIVE WORKS STRATEGY

Port Everglades: Making The Last Mile Count. AAPA Annual Convention November 3, 2015

SUMMARY OF THE MEETING OF THE WOODS HOLE, MARTHA S VINEYARD AND NANTUCKET STEAMSHIP AUTHORITY. September 25, 2018

Port Everglades Master/Vision Plan Update

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

Annual Port Review. June 22, 2016

Project Update 3. Carpentaria Rail. Port Carpentaria Railway Project. Carpentaria Rail. 21 Second Ave, Mount Isa, Queensland, Australia, 4825

Mr. Jeff Keever Deputy Executive Director Virginia Port Authority May 2, 2012

Port Everglades Master Plan Update Tenant Workshop. July 12, Port Everglades Master Plan Update 2006

Roberts Bank Terminal 2 Project

L1584-D1 North Service Area Improvements Program

5.7 Other Air Navigation Matters THE BAHAMAS FLIGHT INFORMATION REGION (FIR) (Presented by Bahamas EXECUTIVE SUMMARY

Port of Los Angeles CIP Shaun Shahrestani Chief Harbor Engineer Director of Construction September 27, 2018

Port MacKenzie Rail Extension

Port MacKenzie Rail Extension

Waterways Management Program

City of Fort Lauderdale. Frequently Asked Questions. Proposed Sea Wall Ordinance

Project Data Sheet BASIC PROJECT DATA

Stage 2 ION: Light Rail Transit (LRT) from Kitchener to Cambridge

Port Everglades Receives Federal Authorization to Deepen and Widen Channels

New Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together

Decision Strategic Plan Commission Paper 5/ th May 2017

HOW TO OPERATE A PRODUCT DEVELOPMENT FAMILIARIZATION TOUR MANUAL FINAL REPORT FOR DEPARTMENT OF TOURISM & CULTURE

2. Project Need and Alternatives

Mercer Island should continue to press Renton for public input on noise and other environmental effects of the options then under consideration.

Rodrigues Regional Assembly Chief Commissioner s Office

Maximising Beneficial Reuse through the use of a Novel Dredging Contract

TSAKOS INDUSTRIAS NAVALES S.A.

ANTIGUA ST. MA ARTEN ST. KITTS

Our world. the Gladstone region. What will it do for industry?

California Department of Transportation. UAS Operations

KINGSTON HARBOUR IN THE YEAR SEMINAR SPONSORED BY NEPA 2003 November 06

Ohio Freight Conference Great Lakes Commercial Navigation

CAIRNS A STRATEGIC PORT

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

Sam Imperati Facilitator

Site Formation Works of the Kai Tak Cruise Terminal Project

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Potomac River Commuter Ferry Feasibility Study & RPE Results

Canaveral Port Authority Department of Infrastructure, Construction, Engineering & Environmental Port Projects Status Update. Updated 2 Weeks Ago

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET

Port Everglades 2014 Master/Vision Plan Update

Work Programme 01/ /2012

CAIRNS A STRATEGIC PORT

INNOVATIVE MARINE DESIGNS PND ENGINEERS, INC. January 14, 2016

AAPA CRUISE SEMINAR CRUISE FACILITY DESIGN, PROCESSING, SAFETY & SECURITY Jim Rowe, AIA Bermello Ajamil & Partners APRIL 25, 2013

Manson Construction Co.

Update on STX France. October, 2017

FULL SHIP CHARTER FAQ S

Bluewater Coastal Cruiser Kristannalee

STUDY TO DETERMINE CAPACITY & SAFETY IN MARINE RECREATIONAL AREAS INCEPTION REPORT. Table of Contents

Yorkshire s Offshore, Renewable Energy and Operations and Maintenance Centre. 7 th October 2014

Jason J. Hull, P.E. Director of Engineering. Port Freeport 1100 Cherry Street Freeport, Texas

PORT OF CORPUS CHRISTI BUILDING FOR THE FUTURE

October 7, Mr. Geoffrey Wilson Chief Executive Officer PortsToronto 60 Harbour Street Toronto, Ontario M5J 1B7. Dear Geoff,

SAMOA PORTS AUTHORITY

TENTATIVE SCHEDULE

RFP No B013 Travel Agency Services for the Metropolitan Washington Airports Authority

Water Space. A development opportunity at the Canting Basin, Pacific Quay, Glasgow

CAA MINDED TO REJECT EDINBURGH AIRSPACE CHANGE PROPOSAL

Transcription:

COMMONWEALTH OF THE BAHAMAS MINISTRY OF PUBLIC WORKS & TRANSPORT NASSAU HARBOUR PORT IMPROVEMENT PROJECT AUGUST 2009

OVERALL VIEW OF NASSAU HARBOUR

AERIAL VIEW OF NASSAU HARBOUR

PROJECT HISTORY 1960 s s initial dredging of Nassau Harbour and formation of Kelly Island. 1980 s s dredging completed to accommodate cruise lines vessels as presently calling to port. 2007 cruise industry to improve efficiency by increase in vessel size, and reduction in overall fleet size. Evaluation of present manouvering,, and berthing areas to accommodate future ship traffic. Ministry of Works and Transport tender consultancy services for specialized activity.

PROJECT HISTORY Cont d. Royal Caribbean Cruise Lines' "Oasis of the Seas will arrive 11 December 2009. Ship characteristics: Length: 1,180 ft; Beam: 140 ft; Draft: 35 ft. Passengers: 6,400 Crew: 3,000 This is the first of a number of similar sized ships replacing smaller ships.

PROJECT HISTORY Cont d.

PROJECT COMPONENTS Dredging 1.9 million cubic yards of material. Widening of the Approach Channel. Lengthening of the Turning Basin. Installation of 3 Mooring Dolphins. Westward Extension of Arawak Cay. Stockpiling of 1.0 million cubic yards of dredge material for future development.

PROJECT COMPONENTS Cont d AERIAL VIEW DREDGE AREAS

PROJECT COMPONENTS Cont d DREDGE AREAS 1, 2, 3, 4, 5 ARAWAK CAY EXTENSION

PROJECT COMPONENTS Cont d 3 NEW MOORING DOLPHINS

PROJECT COMPONENTS Cont d ARAWAK CAY EXTENSION AND STOCKPILE AREA

PROJECT EXECUTION Ministry of Public Works & Transport Input From: Cox & SHAL Consultants & their Sub-consultants Ministry of Environment Port Department BEST Commission Ministry of Tourism Ministry of Finance Royal Bahamas Defense Force

PROJECT EXECUTION Cont d Site Investigations & Studies: Ship Simulation Study Harbour Geometry Geotechnical - Harbour & Arawak Cay Hydrographic Surveys - Water Depths Coastal Engineering Beach Effects Environmental EIA Harbour & Arawak Cay Preliminary Engineering Report Final Design, Drawings Specifications Tender Contract Documents Review During Construction

PROJECT EXECUTION Cont d Prequalification of Contractors: August 2008 Issue for Tender: December 23, 2008 Pre-Tender Meeting: January 21, 2009 Tender Receipt: February 24, 2009 Contract Award: March 27, 2009 Mobilized to site: May 2009

PROJECT DETAILS Contract Value: US $ 44.2 million Contractor: Boskalis International b.v. Subcontractors: American Bridge Bahamas Bahamas Marine Construction Project Timing: July 1, 2009 Start fieldwork Aug 13, 2009 Start Dredging Nov 30, 2009 Complete Dredging Dec 11, 2009 Arrival, Oasis of the Seas March 2010 Total Project Completion

PROJECT IMPACTS No change to Western Esplanade Beach. No change to Saunders Beach. No storage of fish and conch within the Project Area (Arawak Cay to Potter s s Cay) Turbidity Controls: Florida EPA Standard. There will be a visible Turbidity Plume within the mixing zone.

PUBLIC AWARENESS Meetings held with Government Stakeholders January 2009. Meetings held with private stakeholders directly affected January 2009: Mail Boat Association Tourism Operators Shipping Agents Arawak Cay Vendors Association Potter s s Cay Dock Vendors Association Jet-ski Operators Association Downtown Development Committee

CONTACT INFORMATION MINISTRY OF PUBLIC WORKS & TRANSPORT CIVIL ENGINEERING SECTION TEL: (242) 302-9772 FAX: (242) 302-9770 EMAIL: publicworks@bahamas.gov.bs

NASSAU HARBOUR PORT IMPROVEMENT PROJECT SPEAKING NOTES Slide 1 The cruise line industry has a significant impact on tourism providing up to 70% of visitors experiencing the Bahamas, and in particular Nassau. To this end the Government of the Bahamas has seen fit to maintain or improve facilities required to support this vital segment. This has given rise to what is called the. The 2004 aerial view is indicative of Nassau Harbour today. (Explain map pointing out Silver Cay, Arawak Cay, PGW, Potter s Cay, Western Esplanade) Slide 2 and 3 History provides insight to ascertain answers to the questions why, when and how? A harbour requires to provide among other things adequate protection and ease of access by sea and land. Nassau Harbour fulfills these requirements with natural protection from Paradise Island, a natural channel for sea access, and located in the center of commerce. The continuous development of New Providence and Nassau specifically, has created challenges for expansion to facilitate today s operations. (Switch to slide 3) The original designer s intent in the 1960 s accounts for some elements of future development with the formation of Kelly Island, also known as Arawak Cay. This island provided and efficient solution for the use of the dredge material. My colleuges from the Project Execution Unit and Arawak Cay Port Development Company will address the other independent elements involved with access and operations. Again in the 1980 s when work was required in the harbour, Arawak Cay was used to stockpile the relatively small quantity of dredge material. In 2007, due to changing cruise line industry forces, the Government of the Bahamas was faced with the challenges of providing a reasonable solution to future development, accommodating a new cruise line vessel size. Slide 4 and 5 The maiden voyage of this new vessel type will be Royal Caribbean Cruise Lines Oasis of the Seas which is significantly larger than the ships calling today in terms of size and passenger capacity. Other cruise lines will follow, and Ministry of Tourism and Aviation will provide details. (Pictures of the vessel on sea trials at the bottom of the screen). (Switch to slide 5) (Artist rendition of the Oasis of the Seas ) TOWN HALL MEETING AUGUST 2009 PAGE 1

NASSAU HARBOUR PORT IMPROVEMENT PROJECT SPEAKING NOTES Slide 6 In order to accommodate the arrival of the new ships, improvements to the harbour include; widening of the channel, lengthening of the turning basin, increase in the depth of the harbour to 40-ft, installation of 3 mooring dolphins at Prince George Wharf on Pier 1 west and east ends, and Pier 2 west end. Slide 7 and 8 This is an aerial view of the proposed dredge limits, with the doted circle representing the existing turning basin. (Emphasize dredge limits and independence from Arawak Cay). (Switch to Slide 8) This is a depiction of the pre-dredge survey where the dark blue shades represent areas with minimum dredging required; light green shaded areas represent new areas to be dredged (Area 1 is southside of Paradise Island, Area 2 is north of Western Esplanade, Area 3 is the approach Channel, Area 4 is at the southwest end of Prince George Wharf, Area 5 is the northeast corner of PGW) Slide 9 This depicts a typical mooring dolphin arrangement to be installed for securing bow and stern lines where the pier is physically not long enough. The Mooring Dolphin consists of pipe piles, concrete pile cap, and suspended walkway for access (This schematic along with others from the presentation are posted throughout the room for viewing). Slide 10 The minimum required daily production for dredging is 8,000 to 10,000 cubic yards to achieve the completion time. The most cost effective choice for storage is Arawak Cay. Arawak Cay stockpile capacity is only 600,000 cubic yards, a short fall of 1.3 million cubic yards. Therefore, alternatives were discussed during the design phase, and the most appropriate solution was the extension of Arawak Cay, with size determined by the amount of material to be stockpiled and possible future use of land area. The Extension is approximately the same width as existing, and 1,000-ft in length from the most extreme point from existing Arawak Cay. A total of 44 acres will be created, consuming approximately 0.7 million cubic yards of material. Approximately 0.2 million cubic yards of material will be used for reinstatement of the existing Arawak Cay, and 1.0 million cubic yards of material to be stockpiled on the extension. This stockpiled material potential use, as previously indicated by the Government will include downtown revitalization (to be addressed by my colleague of the Downtown Development Committee), use by Department of TOWN HALL MEETING AUGUST 2009 PAGE 2

NASSAU HARBOUR PORT IMPROVEMENT PROJECT SPEAKING NOTES Environmental Health Services for landfill maintenance, and support private sector demand for suitable fill material. Slide 11 The Ministry of Public Works and Transport is responsible for the execution of the project, and as such known as the Client, with support from Cox and SHAL Joint Venture Consultants, acting as the Engineer. All the relevant agencies have been providing input to the Ministry of Public Works and Transport for necessary permitting of the Project. This is a continuous and coordinated effort for the project duration to ensure a successful completion. Slide 12 To date listed is the information collected and evaluated, by the project execution team, so informed decisions could be presented for consideration. The environmental impact assessment posted on the Ministry of Environment s website, is the collaboration of all the studies you see listed, which will be explained in more detail by the BEST Commission. The consultant then produced the necessary documentation for design prequalification of contractors, and Tender Documents. Slide 13 and 14 Timelines for the project to date show actions completed. A total of nine contractors requested pre-qualification, including one Bahamian firm. Seven contractors pre-qualified, with 5 submitting Tenders. These five were considered to be some of the leaders in the industry. (Switch to Slide 14) The Government of the Bahamas ultimately selected Boskalis International from the Netherlands to complete the works, with their named sub-contractors American Bridge Bahamas, and Bahamas Marine Construction. Luck has it that the third largest dredge in the world became available to be used on the project, the Ursa (depicted, a cutter suction dredge), capable of removing up to 20,000 cubic yards per day, and pumping material up to 1 mile from the dredge area. This has the potential advantage of reducing the time the construction period is affecting the environment. Preparatory works (which you might have seen on your travels to the Town Meeting tonight) are presently on-going for the anticipated dredging start date of 13 August 2009. TOWN HALL MEETING AUGUST 2009 PAGE 3

NASSAU HARBOUR PORT IMPROVEMENT PROJECT SPEAKING NOTES Slide 15 The EIA s identified several sensitive receptors which included the Beaches of the Hilton Hotel, Western Esplanade, and Saunders Beach; and storage of fish and conch within the potential turbidity limits. There will be a visible turbidity plume. Turbidity is the milkyness in the water seen after inclement weather or ship manevouers, but to a greater extent. The project has adopted the Florida Environmental Protection Agency Standards which are considered to be the most stringent in the industry, and application of the Environmental Management Plan will minimize impacts. The EIA s for the project will be explained in more detail by BEST Commission later in the presentation Slide 16 During the tender period, various meetings were conducted with Government and directly affected private stakeholders which include (read list on slide), to inform and obtain reasonable feedback on the project, so that appropriate amendments to the Tender Documents could be provided if required, or other programs put in place to minimize any potential inconveniences during the project. Slide 17 The completion of this major improvement to the Port of Nassau, will not only facilitate the expansion of Tourism in the Bahamas, but ultimately impact the level of employment and indeed the sustainability of the standard of living. THANK YOU!!!!! TOWN HALL MEETING AUGUST 2009 PAGE 4