A pilot flood retention area in La Bassée

Similar documents
The Lower Prut Floodplain Natural Park (Romania)

SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN DRAFT ROOF REPORT INTRODUCTION AND GENERAL APPROACH

ANALYSIS OF INADEAUTE WATER QUALITY OD THE RESERVOIR VONARJE/SUTLA LAKE AND POSSIBILITY OF RESTORATION AND UTILIZATION

Réseau électrique métropolitain (REM)

The Ramsar Convention

Field excursion 2: ERRC2014 SEE River Project Final Event

Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: Northing: River / Catchment / Sub-catchment Type of Flooding / Flood Risk

BEFORE PROJECT THE BEGINNING

The Rhône, a river shaped by man

The Problem.. SuDS: Controlling the Flow. LANDF RM Technical delivery of SuDS 15/10/2013. Bridget Woods Ballard HR Wallingford 1.

Case Study: 1. The Clarence River Catchment

Satoquo SEINO (Graduate School of Engineering, Kyushu University, Japan)

Nature Conservation Agency (NCA) Salacgrīva 05/07/2018

WALKER SWAMP INFORMATION DAY Saturday 23 rd June 2018

SAN ANTONIO RIVER IMPROVEMENTS PROJECT. August 6, 2008

Field excursion 4: ERRC2014 SEE River Final Project Event

An experimental habitat enhancement effort for a sandy river: San Rafael River restoration project

Submission on the Tukituki Catchment Proposal: EPA reference numbers; NSP 13/ , NSP 13/ , NSP 13/ , NSP 13/02.

Prosjekt Lesina Mediteranean sea Coastal lagoon


GOOSENECK SWAMP INFORMATION DAY - Saturday 14 th December 2013

SAN ANTONIO RIVER IMPROVEMENTS PROJECT. April 27, 2009

The Vjosa River in Albania

SMALL WETLAND OF BRĂILA MANAGEMENT PLAN

MPA French Agency and Natura 2000 at sea. Biogeographical marine seminary for the management of Natura2000 sites, 2015, May 5th

Phoenix Habitat Restoration Projects

MEXICO CITY S NEW INTERNATIONAL AIRPORT 2017 ACI-LAC Conference. November 2017

Introduction. The System. Model Limitations, Assumptions, and Parameters. Optional Services Tech Memo

Europe s wild jewel - The Vjosa River in Albania

Groundwater Recharge/Discharge Y 1, 2, 3, 4, 5, 16 X Wetland appears to be a contiguous hydraulic system, draining towards Goff Mill Brook.

Long Term Ecological Research in the Upper Paraná River Floodplain, Brazil: main patterns and variations:

SECTION 3 GENERAL DESCRIPTION OF THE RIVER BASIN

Investigation of River Stage Simulation Before and After Bengoh Dam Construction: Case Study of Sarawak River Basin Malaysia

Damn those dams their effects on stream ecosystems

HELLENIC REPUBLIC Voluntary National Review on the Implementation of the 2030 Agenda for Sustainable Development. 16 July 2018

INTRODUCTION Background: Definitions Wetlands in Egypt Threats to Wetlands Wetland Services

PORTISHEAD BRANCH LINE PRELIMINARY ENVIRONMENTAL INFORMATION REPORT VOLUME 4 APPENDIX Water Receptors

4/28/17. Clicker Question. Clicker Question. #37 Floods IV (Case Histories-Mississippi River Flood, 1993; Red River of North Flood, 1997)

WATER MANAGEMENT IN ROMANIA. Elisabeta CSERWID National Institute of Hydrology and Water Management ROMANIA

Introduction on the Taedong River Basin.

ETOBICOKE CREEK NORTH TRAIL PROJECT. May 18, 2017 at Michael Power High School 105 Eringate Drive, Etobicoke ON M9C 3Z7

2.1 Physical and Biological Description Matabitchuan River Watershed

The Danube Experience

Conservation Partners for the National Reserve System Program: a Western NSW focus

Tourism and Wetlands

Workshop on WATER-FOOD-ENERGY-ECOSYSTEMS NEXUS ASSESSMENT IN THE SAVA RIVER BASIN. Sectoral goals in the Sava River Basin

EAST DON TRAIL ENVIRONMENTAL ASSESSMENT. Community Liaison Committee Meeting #3 July 15, :30 to 8:30 pm Flemingdon Park Library

Order of the Minister of Environment #39, August 22, 2011 Tbilisi

Congo names four large Ramsar sites

Public Lands in Alaska. 200 million acres of federal land - Over 57 Million acres of Wilderness more than half the Wilderness in the entire nation

Ceremonies for Albania's Butrint

I Natura 2000 in action! I

Large Scale Irrigation Modernization Project Procurement Plan

DRAFT. Dorabelle Campground Rehabilitation

The Loire-Anjou-Touraine regional nature Park. Last update : September, 2010.

TRINITY RIVER CORRIDOR

PRESPA BIOSPHERE RESERVE MANAGEMENT MACEDONIAN PERSPECTIVE

Riverine Sand Mining/Scofield Island Restoration (BA-40)

"ST. KLIMENT OHRIDSKI FACULTY OF GEOLOGY AND GEOGRAPHY

AN OUTLINE OF THE NILE BASIN

The Isonzo/Soca river basin

Paris fight(s) for a better air quality. Dominique Alba Atelier parisien d urbanisme (APUR) CEO London 01/20/2017

An NPS Wetland of International Significance!

IMPACT conference 2018 «Affordability of Public Transport» Enforcing attractiveness & relevance Of Public Transport Services

A Brief Overview of the Rio Grande Compact 04/26/06

Boatswain bay biodiversity reserve

Hungary and Slovak Republic cooperate on transboundary Ramsar site

Intervention of a task force composed of professional water technicians in Sri Lanka, after the dec.2004 tsunami

THE ICs INTERNATIONAL BRISBANE AREA AQUA PARK PROPOSAL

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE March 2009 Report No.: AB4607 Project Name

DETECTION OF WATER LEAKS IN FOUM EL-GHERZA DAM (ALGERIA)

Wilts & Berks Canal. Appendix E: Hydrology and Hydraulics CONTENTS 1. INTRODUCTION 2 2. HYDROLOGY 2 3. HYDRAULIC MODEL 2 4.

Draft LAW. ON SOME AMENDAMENTS IN THE LAW No.9587, DATED ON THE PROTECTION OF BIODIVERSITY AS AMENDED. Draft 2. Version 1.

Final Drainage Letter Pikes Peak Community College Downtown Parking Lot Colorado Springs, Colorado

Conservation Results In An Urban Environment Through Public-Private Partnerships

Amended Maintenance Dredge Spoil Management Plan. Shute Harbour Marina Resort

Park-specific management and policies Wainuiomata Recreation Area

Management of nature and protected areas in Greenland - Efforts in conservation, research and development

MANAGING FRESHWATER INFLOWS TO ESTUARIES

Terrestrial Protected Area Nomination: Central Mangrove Wetland South-West, Grand Cayman

Geoscape Toronto The Oak Ridges Moraine Activity 2 - Page 1 of 10 Information Bulletin

Creation of a Community-managed Biodiversity Park in the Saloum Delta of Senegal. Voré Gana Seck Director GREEN Senegal for People, Land, Ocean

Draft Resolution on wetlands in polar and subpolar regions

The Living Danube Partnership

Protection of Ulcinj Saline

Catchment and Lake Research

Kurobegawa No.4 Power Plant Toyama Prefecture, Japan (Asia)

Hydro-Electric Schemes Compliance Report June June 2013

Prosjekt Amvrakikos Gulf, Greece

Population and habitat conservation of Danube salmon (Hucho hucho) in The Sava River (Danube catchment) - Slovenian case -

FLOW REDUCTION IMPACTS ALONG RIVER NILE IN EGYPT

ICPDR FP-EG project overview

Remeandring of river Lemme where crossing a fen, Jura Plateau

Croatia completes inventory of wetlands

Whitemouth Falls Provincial Park. Draft Management Plan

SHARE Toolkit: Case Studies. Integrated management of the Senegal River. IUCN Water Programme. By Madiodio Niasse. 1. Origin and Background

The Sand Ridge - Tulare Lake Conservation Report proposes the following recommendations:

TOWARDS SUSTAINABLE MANAGEMENT OF MARINE AND COASTAL HABITATS ASIA- PACIFIC DAY FOR THE OCEAN

Nemos - NEMOS project - improvement of ALpine wetland areas LIFE00 NAT/IT/007281

University of Rouen-Normandy, UMR CNRS 6014 COBRA, 55 rue Saint Germain, Evreux, France. 2

Transcription:

A pilot flood retention area in La Bassée Institution interdépartementale des barrages-réservoirs du bassin de la Seine 8, rue Villiot - 75012 Paris - Tél. : 01 44 75 29 29 - Télécopie : 01 44 75 29 30

Flood risk in the Paris region

The 1910 flood in Paris

Flood risk in the Paris Region Flooded area for the 1910 flood 140 km of metro lines would be interrupted 850 000 people flooded 2 M without electricity 2,7 M without water supply 170 000 businesses would be affected A 1910 flood would cost more or less 30 to 40 billions

The 2016 june flood in Paris

The necessity of a new storage reservoir The existing storage reservoirs control only 17% of the river Seine catchement The river Yonne, one of the tributaries of the river Seine, gives quick and high flow peaks leading to high flood risks in Paris The dam located on the river Yonne controls only 2% of the Yonne catchment Need to mitigate the impact of the river Yonne on the flood risks downstream The only area available for an efficient mitigation of the Yonne flow peaks is the Bassée area, located at the confluence between the Seine and the Yonne rivers

La Bassée project

The downstream Bassée area o The downstream Bassée area is located at the confluence between the Seine and the Yonne Rivers in the Ile de France region La Bassée o The Bassée area used to be a flood plain for the river Seine before the 1960 s (flooded every 1-2 years)

The downstream Bassée area The Bassée area used to be a floodplain for the Seine river before the 1980 s (flooded every 1-2 years) but two major projects deeply altered its structure and hydrodynamics on its downstream part: 1-The local transformation of the river Seine into a shipping canal: o local decrease of the river level with no more sollicitation of the area as a floodplain o increase of the flood risks downstream o drainage of the area leading to a poorer ecosystem 2- Sand and gravel excavation: o random-located extraction sites o resulting holes filled with rain and groundwater

Two Objectives - hydraulic aspects : flood alleviation - ecologic s aspects 1

Concept: retaining part of the Seine river flow during Yonne flood peaks Pumping from the Seine river into the retention areas Flow decrease downstream from the confluence High flood event on the Yonne river

Features and layout of the global project o 10 retention areas built by the means of shallow dykes (up to 4,70 m high) o a potential retention capacity of 55 Mm 3 ranged over 23 km 2 and 12 districts o 50 pumps with an overall capacity of 230 cumecs (7 pumping stations) o gravitary emptying into the river once the level has decreased (13 sluice gates) Estimated decrease in the water level of the river Seine: between 20 and 50 cm according to the cities location and the type of floods

A second goal: wetland restoration o The downstream Bassée area used to be a frequently flooded wetland. The area is Natura 2000 and Ramsar classified o The second goal of the project is to restore its dynamics of alluvial wetland o In particular the ecological project aims to restore the former flora and fauna biodiversity by : creation of spawning grounds, combat invasive species transform poplar plantations in wetlands monitoring of the species living in the area: evolution, number other actions of biodiversity improvement

La Bassée: a multi-functional area Flood alleviation 55 Mm3 Wetland classified Ramsar, Natura 2000... Mineral extraction Archeology and cultural heritage Water resources Agriculture and recreation green-blue

A first step : a pilot project

Global project How choose the pilot area - 10 retention area - 58 km of dikes - 2 300 ha of surface area - pumping capacity of 230 m 3 /s - capacity of 55 Millions m3 - Global cost : 600 Millions The choice d based on multi-factory analysis (technical, environnemental and uses approach), have been discused with stakehloder during a progressing process during 18 month Pilot project - 7,8 km of dikes - Capacity of 8,8 M. de m3-372 ha of surface area - pumping capacity of 34 m 3 /s - Global cost : 100 Millions

Principe de fonctionnement Management principle Pumping : 3 days Storage : 5 d approx. Draining : 15 d-1,5 month Water level : 2,5 m Frequency : 7 to 10 year in average

Why filling in the storage compartments by pumping? La Bassée floodplain used to be floodable every 1-2 years before the 80 s (Q>150 cumecs) In the 80 s the river Seine was transformed into a great template channel (Q>400 cumecs corresponding to the 1910 flood) Pumping station Storage compartment Pumping station Up to max. level

Modèle amont : filaire 2D - casiers 35 000 mailles couvrant le lit majeur gravières modélisées par des casiers de stockage Lit mineur : modélisation 1D

4. Construction du modèle casier pilote Taille moyenne d une maille : 20 m

Réseau de mesures Le réseau de mesures en 2016 3

Suivi continu: 27 piézomètres Suivi de manière ponctuelle: 69 piézomètres Suivi des niveaux d eau des rivières : 3 dans l Auxence, 1 dans la Seine, 1 canal de Bray-la- Tombe Suivi des niveaux des gravières : 6 Suivi de la qualité des eaux : Seine, Auxence, gravière, eau de nappe alluviale et nappe de la craie

06/12/2016 25/01/2017 16/03/2017 05/05/2017 24/06/2017 13/08/2017 Premières observations Cote d'eau (m NGF) Suivi hydrogéologique 51,00 Comparaison des niveaux piézométriques et de l'auxence 50,50 50,00 49,50 26-EPTB-AA AUXINT 9-EPTB-CR 49,00 48,50

/2017 > Carte piézométrique d Octobre 2016 (piézométrie de calage en régime permanent) :

/2017 >dratec Modèle conceptuel : structure géologique Seine Auxence

Further steps The pilot storage area would be operated once every 7 to 10 years on average Water level decreased by 5 to 10 cm in Montereau and Paris 1 invested 2,3 avoided damages the project enables to save 171 M in 50 years time Design studies Environnemental impact studies Public enquiry Construction works 2019 2020 2024

Thank you for your attention