An insider s look at the world s best infrastructure project: An interview with Mr. Dono Boestami, President Director of PT MRT Jakarta

Similar documents
IMPROVEMENT OF URBAN TRANSPORT SYSTEM IN GREATER JAKARTA (LRT and MRT Progress)

Comparison of Bangkok & Kuala Lumpur

JAKARTA TRANSPORTATION

Jakarta Investment Project Digest

Khon Kaen Light Rail Transit

Network Size and Growth

Profile of Phoenix Tours INT L Inc. Security code:5706

METRO HOLDINGS REGISTERS REVENUE OF S$46.3 MILLION AND PROFIT AFTER TAX OF S$13.0 MILLION FOR 2QFY2019

Ministry of Transportation Republic of Indonesia

Sustainable Urban Transport Development in Indonesia

Infrastructure Projects in Mumbai Metropolitan Region & Maharashtra

Safe, Timely & Comfortable Move for Better Future ~Japan-India Cooperation on Railway Sector ~

Brogent Technologies Inc. 智崴資訊股份有限公司數位內容跨界新世代

METRO HOLDINGS GROWS ITS PRESENCE IN CHINA BY ACQUIRING A MIXED-USED DEVELOPMENT IN SHANGHAI

PLAN MAESTRO DE TRANSPORTE SOSTENIBLE EN GUATEMALA

JOB REFERENCE. The following are projects that we have engaged in Hong Kong, China, Macau and Overseas during the past years:-

BROAD SPECTRUM SURVEY OF METRO RAIL SERVICE

Welcome. Green Line in Your Community

BBR wins S$ $153.1 m contract to design and constructt a mixed-use development at Fusionopolis Place

Transport and Climate Change Week: SUSTAINABLE URBAN TRANSPORT DEVELOPMENT IN INDONESIA

METRO HOLDINGS REGISTERS PROFIT AFTER TAX OF S$11.9 MILLION FOR 1HFY2018

Japan India Cooperation on Railway Sector

Public transport strategy


Notice regarding expected tender

OKP HOLDINGS LIMITED JOINTLY ACQUIRES A FREEHOLD OFFICE COMPLEX IN PERTH, AUSTRALIA, FOR AUD43.5 MILLION

METRO GROUP GROWS ITS PRESENCE FURTHER IN SHANGHAI 35% EQUITY INTEREST IN A JV TO ACQUIRE SHANGHAI PLAZA, THE PRC

Honorable Minister for Industries inspection at CMRL Metro Stations from AG-DMS to Washermanpet

Railway Master Plan in Tokyo (2016)

Austrade Supporting Australian Rail Industry s Global Focus. Rail Sector Lead and Trade Manager, Infrastructure

TORONTO TRANSIT COMMISSION REPORT NO.

FAQ RAPID KL AIRPORT SHUTTLE (updated as of 31th Jan 2019)

TORONTO TRANSIT COMMISSION REPORT NO.

The Upcoming Opportunities of Rail Transportation Development in Southeast Asia MANAGING DIRECTOR OF PROFREIGHT GROUP

Nusajaya s High-Speed Rail Station Just Minutes Away from Puteri Cove Residences

TORONTO TRANSIT COMMISSION REPORT NO.

JOIN s Investment for Urban Development Projects in Indonesia

Taoyuan International Airport Terminal 3 RFI presentation

Update on the Thameslink programme

Singapore, 12 July 2016 MAINBOARD-LISTED infrastructure and civil engineering company, OKP Holdings Limited ( 胡金标控股有限公司 ) ( OKP or the Group ),

Now Available. Urban Rail Transport. in India Urban Bus Transport. in India India Infrastructure Research.

LEVERAGE VIABILITY TO SECURE THE INVESTMENT RETURN FOR PALEMBANG MONORAIL PROJECT USING PUBLIC PRIVATE PARTNERSHIP FINANCIAL SCHEME

2 nd Quarter 2011 Results Presentation 12 th August 2011

Australian International Education Conference

ROXY-PACIFIC & TONG ENG GROUP SUCCESSFULLY DIVESTS PRIME COMMERCIAL BUILDING 117 CLARENCE STREET, SYDNEY, FOR A$153 MILLION

ITA AITES WORLD TUNNEL CONGRESS 2009

Convenience Retail Asia maintains growth momentum in turnover and profit for first half

LIGHT RAIL TRANSIT DRIVES TRANSFORMATION

Mitsubishi Estate and Landmark Project in a nutshell. Jo Kato Deputy President

STUDY ON SOEKARNO HATTA INTERNATIONAL AIRPORT EXPANSION AND UPGRADING PROJECT IN JAKARTA IN THE REPUBLIC OF INDONESIA

Mitsui Fudosan Decides to Participate in the Zhongshan Zhongxiao Hotel (Tentative Name) Business, Very Close to Taipei Main Station

國泰航空有限公司 (Incorporated in Hong Kong with limited liability) (Stock Code: 293)

West Midlands Sustainable Urban

Corporate Presentation

$550 BILLION WORTH OF GOVERNMENT

CATHAY PACIFIC AIRWAYS LIMITED 國泰航空有限公司 (Incorporated in Hong Kong with limited liability) (Stock Code: 293)

Subway Productivity, Performance, and Profitability: Tale of Five Cities

JR East: Domestic and International Perspectives

BBR Holdings First Half 2014 Net Profit Surges 110% to S$10.2 million

臺灣桃園國際機場第三航站區新建工程委託設計暨監造技術服務案資訊徵求 (RFI) 說明會

Rapid Transit From Arbutus Street to UBC. Policy and Strategic Priorities Council Meeting January 30, 2019

Middle East Rail Market Report

Aerotel soon to open in Guangzhou Baiyun International Airport New Terminal

Calderdale MBC. Wards Affected: Town. Economy and Investment Panel: 20 October Halifax Station Gateway Masterplan

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

Building Connections to PROVIDE A TOTAL CUSTOMER EXPERIENCE

Sound Transit. Tunnels and Underground Structures Committee January 24, 2011

CONNECTED TRANSACTION REORGANISATION OF A NON-WHOLLY OWNED SUBSIDIARY

For personal use only

Update for members of the SYDNEY HARBOUR HIGHLINE ASSOCIATION (SHHL)

BHP Billiton Iron Ore Western Australia. Iron Ore. Presentation to Analysts June Ian Ashby, President and COO BHP Billiton Iron Ore

1270 km of new Urban Rail infrastructure put in revenue service in 2017

Extending TRACKS. Design and engineering effort nears completion. Animation shows how light rail will operate in Hopkins

4 th Annual Civil Aviation Training Forum. December 5 th - 6 th, 2018 Guanghan, China. Supported by: Organized by: Hosted by:

Commercial Aviation Ground Training

GOVERNMENT PARTNERSHIP CELEBRATES LAUNCH OF ZÜM BUS RAPID TRANSIT SERVICE IN BRAMPTON

BBR Holdings reports significant increase in both revenue and net profit for nine months ended 30 September 2013

WEST JAVA- SHIZUOKA REPUBLIK INDONESIA THE PROVINCE OF WEST JAVA

THE WORLD BANK Washington, DC

Adelaide Shores. Presentation to Recreation and Parks Conference 8 April How to become a world class Tourism, Recreation and Sport precinct

Efforts and Inter-City Partnership of FutureCity Yokohama

DAMASCUS PROVIDING SAFE AND EASY ACCESS TO THE MEDINA. Key words: Planning; Public-transport projects; City-centre regeneration

SHS secures modular construction contracts worth S$28 million in New Zealand

Feature: Priority Initiative 01 Railway Network Expansion

Opportunity and Function of Airport in Lowcost Aviation Development

Welcome Delegates of the ASPE Chapters in the Northwest & Southwest Regions

Yongnam Holdings Limited. FY2009 Results Presentation

Japanese Construction Industry and Overseas Activities

N4 Carrick-on-Shannon to Dromod Road Project. 2.1 Introduction

Building the transportation network we need for the future in Niagara Region

Planning for RAV: Lon LaClaire, Transportation Engineer Anita Molaro, Development Planner CITY OF VANCOUVER

Yongnam Holdings Limited. 1HFY2010 Results Presentation

CUSTOMER SATISFACTION INDEX OF SINGAPORE 2018 Q2 RESULTS OVERVIEW AIR TRANSPORT AND LAND TRANSPORT

Hyderabad Metro Rail in PPP Mode

Ex-Ante Evaluation (for Japanese ODA Loan)

Gold Coast. Rapid Transit. Chapter twelve Social impact. Chapter content

Brisbane Metro Infrastructure Association of Queensland 14 February 2018

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JANUARY 25, 2011

History of Japan Exhibition Association(JEXA)

New World Group Structure

Transcription:

專題報導SPECIAL REPORT An insider s look at the world s best infrastructure project: An interview with Mr. Dono Boestami, President Director of PT MRT Jakarta Keywords: RAPID transit system, MRT Jakarta 台灣世曦工程顧問股份有限公司 / 海外中心 / 工程師 /Gabrie Gleatemia 台灣世曦工程顧問股份有限公司 / 捷運部 / 計畫副理 / 馬富強 台灣世曦工程顧問股份有限公司 / 捷運部 / 副理 / 諶家瑞 台灣世曦工程顧問股份有限公司 / 捷運部 / 資深協理 / 陳幼華 114 No.110 April, 016

專 Jakarta's traffi c congestion is the biggest pain for the capital's 10 million residents and a major liability to economic growth. In order to solve the traffi c gridlock before it overwhelms the city, the fi rst rail-based mass rapid transit (MRT) project in Indonesia is in progress. This megaproject comprises of urban excavation and tunnel construction. However, the challenge is not only in engineering, but also a fi nancial and political one. The MRT Jakarta is currently selected as one of the world s best infrastructure projects, and listed on the 16th position of the top 0 megaprojects by the World Finance (February,014). CECI is honored to meet the director of MRTJ, the organization that oversees MRT Jakarta, to understand the challenges and the future of this project. Construction of MRT Jakarta in Indonesia stations and surrounding area. PT MRTJ is a has been discussed since 1985 and started to limited liability (Perseroan Terbatas) company become a national project on 005. Moreover, founded by the Jakarta Provincial Government. together with state budget and regional budget, The shares are made up from 99% Jakarta Japan Bank for International Cooperation Provincial Government and 1% PT Pasar Jaya (JBIC) was the funder for the Jakarta s MRT (another Jakarta Regional-Government-Owned project. The agreement between JBIC and Company). PT MRTJ is classed as a Regional- Governor has been signed on November Government-Owned-Company (Badan Usaha 8 th, 006. JBIC then has merged with Japan Milik Daerah-BUMD). MRT Jakarta is the first International Cooperation Agency (JICA) which project in Indonesia that implement three sublevel agreement among JICA (Lender) and acts as assessment team from JBIC. There is also agreement between JBIC and Governor of Central Government, Regional Government Indonesia to appoint one body as organization and state-owned company (PT. MRT Jakarta). to implement the MRT project. With this in mind then PT Mass Rapid Transit Jakarta (PT The Governor has elected Mr. Dono MRTJ) has established since June 17 th, 008 Boestami as president Director of the company to be responsible for engineering service, to lead the implementation of Jakarta s MRT construction, operation and maintenance, as project. Mr. Dono fi nished his Bachelor in Civil well as the business development at the MRT Engineering and Master Degree in Project No.110 April, 016 115 ABSTRACT 題報導

Source: http://www.jakartamrt.com/informasi-mrt/pendanaan-proyek/ Information Model) technology to him and did brief interview at PT. MRT Jakarta. Excerpts from the interview: 1.Vision of Jakarta Metro Operation 專題報導116 No.110 April, 016 and Construction Management at United States. He has a notable financial background in his career from banking to state-owned enterprises. There is no wonder if he can understands the complexity of problems from beginning of MRTJ project, traffic congestion, utilities, as well as technical issues during the construction, operation and maintenance, even financial matter. Fortunately, at Friday, January 9 th, 016, CECI has a chance to present BIM (Building Jakarta MRT will stretch over ±110.8 km Jakarta roads, consists of South-North Corridor (Lebak Bulus Kampung Bandan) and East- West Corridor with about 3.8 km and 87 km length, respectively. The construction of South- North Corridor will be carried out in stages. Stage 1 will be carried out to connect Lebak Bulus with Bundaran HI over 15.7 km railway with 13 stations (7 elevated stations and 6 underground stations). This stage is targeted to be completed on 018 and will be operated on 019. Stage will expand South-North Corridor

Source: http://www.jakartamrt.com/informasi-mrt/rencana-rute-mrt-jakarta/ from Bundaran HI to Kampung Bandan over 8.1 km railway. The construction will have been initiated before Stage I operates and is targeted to be completed on 00. A feasibility study is on progress for East-West Corridor, which is targeted to operate at the latest on 04-07. Besides the MRT, Mr. Dono expressed the LRT project which is under construction to connect Jakarta city centre with sub-urbans in Greater Jakarta such as Bekasi and Bogor. The current development of Jakarta's LRT has its root in the cancelled monorail project. LRT was launched as the substitute to.previously abandoned Jakarta Monorail project. This LRT system will integrate Jakarta MRT, existing commuterline and planned airport monorail This LRT system has 6 lines which divided in phase of construction. The first construction phase will connect Cibubur in East Jakarta with Dukuh Atas in downtown of Jakarta with 4.1 km length and include 18 stations. The construction began on September 9 th, 015 and predicted will be finished in late 017. The other phase will be extension of planned route. The all construction is conducted by PT. Adhi Karya based on Presidential Decree No. 98 on 015. It is also stated there that Transportation Minister has to conduct procurement to select a body to responsible for operation and maintenance of LRT system. Since traffic conditions within Jakarta is MRTJ responsibility, MRTJ intends No.110 April, 016 117 based on Precedential Decree No. 54 on 013. 專題報導

Source: Precedential Decree No. 54 on 013 專題報導118 No.110 April, 016 to involved on such procurement. Mr. Dono believe that Jakarta has very huge population in upcoming years later as well as massive growth in road traffic volume. He thought that this is the time to do improvement and setting a benchmark for infrastructure with the MRT project, development a new law and government regulations that support the project and fi nally MRT Jakarta project can be a good case study for Indonesia infrastructure project management..observation of Jakarta MRT Stage 1 works Jakarta MRT Stage 1 works are on progress now to connect Lebak Bulus-Bunderan HI consist of 7 elevated stations with about 8.78 km length and 6 underground stations with about 6.81 km length. Stage 1 of Jakarta MRT project is a turnkey project which involved Japanese and Indonesia construction local company in join operation or join venture. There are 6 packages for this project which can be divided as: (1) CP101 and CP10 are elevated station packages from Lebak Bulus to Cipete Raya Station with about 5.95 km length done by Tokyu Wika JO. () CP103 is elevated station package from Haji Nawi to Sisingamaraja with about 3.84 km length done by OSJV JV (Obayashi Shimizu Jaya Konstruksi). (3) CP104 and CP105 are underground station packages from Bunderan Senayan to Setiabudi 3.9 km length done by SOWJ JV (Shimizu Obayashi Wijaya Karya Jaya Konstruksi)

(4) CP106 is underground station packages for Bunderan HI and Dukuh Atas with.0 km length done by SMCC HK JO (Sumitomo Mitsui Hutama Karya). This stage is targeted to be completed on 018 and will be operated on 019. This is caused by MRTJ still need to prepare the Term of Reference (TOR), regulation and CBCT certification related to operational of MRT in Jakarta. The regulation will be developed by referring to another country that has been started MRT operation first like Singapore, Kuala Lumpur, Taiwan, etc. 3.The outlook for Jakarta Metro Stage Second stage will expand South-North Corridor from Bunderan HI to Kampung Bandan over 8.1 km railway and will pass study has been done and MRTJ now together with Directorate General Railway and National Planning Board (BAPPENAS) are starting to prepare project funding and construction tender process. The process is targeted to be fi nished by 017. The construction tender will be open bid and usually announced in The Jakarta Post, Shimbun, also MRTJ website. The tender scheme will follow Stage 1 which is turnkey project with completely underground stations. On this stage, MRTJ intended to implement BIM technology and require the bidder to provide such service. Mr. Dono believes that this technology will be benefi t for future development of MRT and also whole plan of Jakarta transportation. some heritage area in Jakarta. The engineering 專題報導No.110 April, 016 119