SAN FRANCISCO INTERNATIONAL AIRPORT

Similar documents
PUBLIC NOTICE Passenger Facility Charge Application #8 San Francisco International Airport. December 28, 2017

Winona Runway Shift Project

CHAPTER 2.0 ALTERNATIVES

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

Dallas Executive Airport

Chapter One PROJECT DESCRIPTION

Appendix D Airfield Ongoing Projects Alternatives

Preliminary Findings of Proposed Alternative

Regular Board Meeting August 4, 2015

D.1 Introduction. Ronald Reagan Washington National Airport

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

CHAPTER 3 ALTERNATIVES CONSIDERED

II. Purpose and Need. 2.1 Background

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Appendix F Cultural Resource Consultation

MASTER PLAN CONCEPT 1 DRAFT

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

2015 PURDUE ROAD SCHOOL March 11, 2015

Master Plan Update Technical Advisory Committee Meeting

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016

MEETING MINUTES Page 1 of 5

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Friedman Memorial Airport Authority. Regular Meeting September 4, 2012

BNA Master Plan Update Community Advisory Committee Meeting No. 5

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

Lake Tahoe Airport Master Plan

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

REPORT TO THE BOARD OF DIRECTORS

Table of Contents. Overview Objectives Key Issues Process...1-3

10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM

BNA Master Plan Update Public Meeting No. 2

The San Diego Region s Air Transportation Future

CHAPTER FOUR AIRPORT ALTERNATIVES

FAA RECAT Phase I Operational Experience

Public Information Meeting. September 2015

CatExes vs. EAs When and How to Prepare

FORECASTING FUTURE ACTIVITY

Westover Metropolitan Airport Master Plan Update

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION

CHAPTER 9 RUNWAYS AND AIRFIELD DEVELOPMENTS

LOS ANGELES INTERNATIONAL AIRPORT MAY 2014

Morristown Municipal Airport Runway 5-23 Rehabilitation Environmental Assessment

FAA Office of Airport Safety and Standards

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Buchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

CHAPTER 2 ALTERNATIVES

Study Committee Meeting. September 2015

INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE

Morristown Municipal Airport Runway 5-23 Rehabilitation Environmental Assessment

KSFO RNAV TO GLS DEMONSTRATION

Preferred Alternative Summary

STUDY WORK GROUP MEETING No. 4. July 12, 2017

AGENCY SCOPING MEETING

Environmental Assessment Las Vegas Area Airspace Optimization Project

Update on the Aspen/Pitkin County Airport Improvements

3.9 AIRPORT SUPPORT FACILITIES

Merritt Island Airport

CHAPTER 4: ALTERNATIVES

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

Dallas Executive Airport Town Hall Meeting April 3, 2014

Wake Turbulence Standards

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

Chapter 4. Development Alternatives

Addendum - Airport Development Alternatives (Chapter 6)

Public Notice July 14, 2017

Special Modification To Standards Process for Airplane Design Group VI. The Boeing Federal Aviation Administration

Airlake Airport 2035 Long Term Comprehensive Plan (LTCP)

CHICAGO DEPARTMENT OF AVIATION. Current Construction Projects AND THE O HARE MODERNIZATION PROGRAM. May 2, 2014

New Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together

Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, Shannon Eibert, C&S Companies

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN

A Love Note from Me to You

Airports and UAS: Integrating UAS into Airport Infrastructure and Planning

Hartford-Brainard Airport Potential Runway Closure White Paper

Chapter 4.0 Alternatives Analysis

Elevating the Upstate

Chapter Seven Implementation Plan. Tacoma Narrows Airport. Master Plan Update

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

IDENTIFICATION AND EVALUATION OF ALTERNATIVES ST. PETERSBURG-CLEARWATER INTERNATIONAL AIRPORT

AIRPORT MASTER PLAN ADVISORY COMMITTEE MEETING #2 AGENDA

NorCal Metroplex Update: Review of the FAA Initiative Interim Response

Wake Vortex R&D. Status Briefing. NBAA Convention. Federal Aviation Administration. By: Steve Lang Date: September 2007

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

SAN FRANCISCO AIRPORT COMMISSION MINUTES

Technical Advisory Committee Meeting February 29, 2016

CHAPTER 1: INTRODUCTION

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor June 11, :30 a.m.

EXECUTIVE SUMMARY. Master Plan Update Phase 2/3 FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT 1. INTRODUCTION 2.

AIRPORT WITH NO RUNWAYS IS A MALL

CHAPTER 1 EXECUTIVE SUMMARY

Community Noise Consortium Meeting (CNC)

msp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010

DRAFT GENERAL IMPLEMENTATION PLAN AND SPECIFIC IMPLEMENTATION PLAN MIDDLETON MUNICIPAL AIRPORT MOREY FIELD. Revised 12/12/03

STAFF REPORT. Airport Land Use Plan Consistency Review: Old Town Village Mixed Use Project City of Goleta. MEETING DATE: June 18, 2015 AGENDA ITEM: 5M

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

Transcription:

1 SAN FRANCISCO INTERNATIONAL AIRPORT Runway Safety Area Program ACI-NA Operations and Technical Affairs Conference April 7, 2011

RSA Status Completed RSA Studies Environmental Assessment ongoing and on track. EA Draft submittal in June. FAA Environmental determination expected in November. Construction phasing analysis complete. Operational impacts analysis complete. Proposed RSA schedule has been agreed to by FAA. Facilities has begun design work. 2

Existing Conditions Key: Non-standard Safety Areas Standard Safety Areas San Francisco Bay Runway 10L-28R Runway 10R-28L Runway 1L-19R Runway 1R-19L 3 3

Arrival and Departure Flows Departures West Plan Heavy Departures Arrivals 4 4

Arrival and Departure Flows Arrivals Southeast Plan Departures 5 5

RSA Study Convened Pier Working Group Conference Calls and Presentations to Airlines Cost Estimates Construction Environmental Mitigation SF Bay Fill Environmental Screening EMAS Analysis Risk Assessment ACRP Report Applied Research Associates (ARA) Created two separate RSA studies 6

RSA Study SFO RSA Working Group: FAA ATCT, Region, ADO; SFO Planning, Facilities, Operations, Finance, Legal, Governmental Affairs, Communications, COO Conducted according to FAA Order 5200.8, Runway Safety Area Program, which describes the basic concept alternatives that airport sponsors need to consider. Wide range of alternatives identified and analyzed in order to meet Public Law 109-115. Alternatives considered include filling SF Bay or relocation of U.S.101. to improve existing RSAs. Working Group considered operational and environmental impacts, along with determining feasibility of meeting the 12/31/2015 deadline. 7

Runways 10-28 Five basic concepts considered: Construct standard safety areas Relocate/shift runway Reduce runway length Implement declared distances Install EMAS One preferred alternative declared distances. One enhanced preferred alternative: Includes runway extension to 10R to maintain existing takeoff and landing distances. Analyzed runways as a pair, rather than individually. 8

Runways 10-28 Preferred Alternative Proposed project components include: Displace arrival thresholds by 300 ft to accommodate 600-ft long arrival RSA. Relocate Approach Light Systems. Shifting RW in 100 increments limits ALS pier work. Relocate co-located Glideslopes. 9

Runways 10-28 Proposed project components include: Runway 10R threshold relocated 771 feet west: Maintains takeoff and landing distances for 10R Reduces bad WX delays with 499-foot threshold stagger. Relocate RW 28L Localizer. Realign taxiways to relocated Runway 10R threshold. 10

Runways 10-28 Declared Distances 11

Runways 1-19 Summary Site constraints: SF Bay and Highway 101. Critical to evaluate as a pair of runways, rather than individually. Five basic concepts considered none deemed practicable. 37 Alternatives developed that combined the five basic concepts Narrowed to 15 by combining/deleting alternatives that were similar In order to narrow 15 alternatives to shortlist, evaluation matrix was developed Five alternatives shortlisted One preferred alternative Non-standard EMAS. 12 12

Short List Selection Tool In order to narrow down the Refinement Alternatives to a Short List, a Decision Tree was developed. It is comprised of three main questions: 1. Close Taxiway A? 2. Reduce the effective runway length? 3. Add bay fill or construct a platform? 13 13

Runways 1-19 Evaluation Matrix Close Taxiway A? Yes No Reduce Runway? Reduce Runway? Yes No Yes No Bay fill Platform? Bay fill Platform? Bay fill Platform? Bay fill Platform? Yes No Yes No Yes No Yes No N/A N/A R9 R7 N/A IV-11 IV-15 R3, R4, R5, R8, R10, R11, R12 R1, R2, R6 14

Runways 1-19 Short List Alternatives 15 15

Runways 1-19 Short List Alternatives 16 16

Runways 1-19 Short List Alternatives 17

Runways 1-19 Short List Alternatives 18 18

Runways 1-19 Short List Alternatives 19 19

Runways 1-19 Preferred Alternative Proposed project components include: Install nonstandard EMAS on Runways 19L & 19R. Shift Runways south. Realign taxiways. Demolish existing runway ends and taxiways. Relocate RW 19L Glideslope. Relocate a light station/trestle with side bars by existing increment of 200 ft. 20

Runways 1-19 Preferred Alternative Proposed project components include: Shift both Runways south. Install nonstandard EMAS on ends of Runways 1L and 1R. Realign Taxiway A. Fill open surface water detention basins; replace with underground water drainage pipes, new stormwater detention basin, pump station, and outfall pipes. Relocate electrical substation outside of taxiway object free area. Realign airport security fence and vehicle service road. 21 21

RSA Construction RSA Construction expected to begin in April 2012 Airport has completed a schedule that meets the December 31, 2015 deadline (completion in October 2014) Construction phasing analysis complete for Runways 1/19. Looked at limited runway closings, closing runways individually, and closing both together. Operational impacts analysis complete. Shows closing Runways 1/19 simultaneously is preferable to closing individually. Airline briefing in May Construction will be done in three (3) phases 22

RSA Construction Phase 1, 2012 Work expected to begin in Spring of 2012 Construction activities include: Relocate RW 28L localizer; Pave RW 10R threshold relocation (Sept. completion); Begin pier work; Begin utility work for RWs 28L/R threshold displacement. RW 28L limited to landing only during paving. Southfield work also to begin during this phase. 23

RSA Construction Phase 2, 2013 Construction activities include: Relocate glide slopes for RWs 28L/R; Install new RW 28L approach lights; Relocate RW 28R approach lights; Displace RWs 28 L/R landing thresholds. Southfield work continues during this phase. Runway closures expected for two (2) days on each runway. 24

RSA Construction Phase 3, 2014 Full closure of both RWs 1/19 for approximately 4 months (June Sept.) Construction activities include: Relocate Taxiway A; Shift RWs 1/19 south; Construct new RW entrance taxiways; Relocate glideslope and approach lights for RW 19L; Install EMAS. Expected RW openings by second week of October, prior to Fleet Week. Substantial completion of RSA program 1 year ahead of Congressional mandate. 25

Next Steps Perform aerial survey in summer months. Complete NEPA and CEQA environmental review process. Obtain environmental permits. Complete design documents for Runways 10/28. Continue quarterly meetings with FAA and OAK Contract with ESCO for design services. This also reserves SFO s dates for installation. Contact: Michael Lawrance michael.lawrance@flysfo.com 650-821-0162 26