Trigger Point Justification Note 30 th August 2013

Similar documents
TEUE-OAR-008. Tiverton EUE Extension. Option Assessment Report Final Draft December 2013

Saighton Camp, Chester. Technical Note: Impact of Boughton Heath S278 Works upon the operation of the Local Highway Network

London Borough of Barnet Traffic & Development Design Team

Dyke Road Cycle and Pedestrian Improvements 14/02/2014 Reference number PEDESTRIAN CROSSING AND GUARDRAILING ASSESSMENT

Sky Temporary Car Park Transport Statement

Major Scheme Business Case Summary Report for Programme Entry

Commissioning Director - Environment

Queen s Circus Roundabout

Regulatory Committee

Capital & Counties. October 2007

Report on the Crafthole Traffic Light Project 3 rd July th September 2017

Traffic Calming and Road Safety Provision Options Woore Village

Finchley and Golders Green Area Committee 27 April 2017

A31 Ringwood improvement scheme

Treasure Island Supplemental Information Report Addendum

John Betts School Crossing Review

M621. Junctions 1 to 7 Improvement scheme. Share your views

Cuadrilla Elswick Ltd

Launceston City Council. Kings Meadows Traffic Management Report for Public Consultation

Transport Assessment Appendix M: Avonmouth Impacts

A. CONCLUSIONS OF THE FGEIS

Appendix E CIL Affordability Calculation

Traffic calming on major roads: a traffic calming scheme at Costessey, Norfolk

Chapter 14 Route Window C12 Mile End Park and Eleanor Street shafts. Transport for London

Lake Erie Commerce Center Traffic Analysis

A303. Sparkford to Ilchester Dualling Scheme. Public consultation. Welcome. Highways England -- creative MCR18_0016

Chapter 21 Route window W6 West Ealing station. Transport for London

"TOUCAN" - An unsegregated crossing for pedestrians and cyclists

Table 1 overleaf summarises the changes in planned growth between the 2016 and 2017 iterations of the plan.

Crash and Behavioral Characteristics, and Health Outcomes, Associated with Vehicular Crashes by Tourists in Wisconsin,

Appendix 9. Impacts on Great Western Main Line. Prepared by Christopher Stokes

Surveillance and Broadcast Services

NM Top 5 Safety Priorities. Tzvetomir BLAJEV

ACCIDENT RATES AT PEDESTRIAN CROSSINGS IN HERTFORDSHIRE

APPENDIX H MILESTONE 2 TRAFFIC OPERATIONS ANALYSIS OF THE AT-GRADE CROSSINGS

Sarawia Street Laxon Terrace Rail Level Crossing Removal

Chapter 25 Route Window SE6 Plumstead portal. Transport for London

The Point Roundabout Improvement Scheme

MEMORANDUM. Lynn Hayes LSA Associates, Inc.

Table of Contents. List of Tables

M2 Junction 5. improvements scheme. Preferred route announcement

Chapter 26 Route Window SE6A Manor Wharf. Transport for London

DRAFT. Airport Master Plan Update Sensitivity Analysis

JOINT CORE STRATEGY FOR BROADLAND, NORWICH AND SOUTH NORFOLK EXAMINATION MATTER 3C EASTON/COSTESSEY

Traffic Calming Measures

For a 1309 System Approach of the Conflict Management

HERNE BAY AREA MEMBER PANEL 16 TH JANUARY This report is open to the public.

AECOM Metro Wolverhampton City Centre Extension (WCCE) Transport Assessment 55

THE ECONOMIC IMPACT OF NEW CONNECTIONS TO CHINA

Member-led Review of Cycling Infrastructure

Chapter 4 Route window W23 Taplow station. Transport for London

USING SCOOT MULTI-NODES TO REDUCE PEDESTRIAN DELAY AT DUAL CROSSINGS IN BRISTOL

Scheme Evidence Update Planning & Sustainable Development. Adran yr Economi a r Seilwaith Department for Economy and Infrastructure

Welcome. Great Yarmouth Third River Crossing. Norfolk County Council

CBD Rail Link Business Case

WRITTEN STATEMENT ON HIGHWAYS / TRANSPORT ISSUES PREPARED BY M BAKER BSc CEng MICE FCIT FILT Eur Ing ON BEHALF OF LOVE BRAUNTON

5.1 Traffic and Transportation

HOW TO IMPROVE HIGH-FREQUENCY BUS SERVICE RELIABILITY THROUGH SCHEDULING

Measuring Productivity for Car Booking Solutions

Proposals for the Harrogate Road / New Line Junction Improvement Scheme. August / September Supported by:

Movement Strategy. November On behalf of Barton Oxford LLP

Chapter 13 Route Window NE12 Harold Wood station. Transport for London

1. Case Study Area and Character Sections

Uniclass L534+L212. August home zones. paving PRECAST CONCRETE PAVING SOLUTIONS FOR TODAY S RESIDENTIAL STREET ENVIRONMENTS.

Chapter 8 Route Window NE7 Chadwell Heath station. Transport for London

Summary Proof of Evidence Traffic

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Darwen East Development Corridor

Transport Focus Train punctuality the passenger perspective. 2 March 2017 Anthony Smith, Chief Executive

Review of Highcliffe Shopping Centre

November 11, 2009 BY . Planning and Growth Management Department 110 Laurier Avenue West, 4 th Floor Ottawa, Ontario K1P 1J1. Dear Mr.

Open Report on behalf of Richard Wills, Executive Director for Environment and Economy

Project Deliverable 4.1.3d Individual City Report - City of La Verne

Interstate 90 and Mercer Island Mobility Study APRIL Commissioned by. Prepared by

ACAS on VLJs and LJs Assessment of safety Level (AVAL) Outcomes of the AVAL study (presented by Thierry Arino, Egis Avia)

Arcadis LLP Proposed Secondary School (Bolder Academy) Macfarlane Lane, Isleworth Access Management Strategy. June 2017

CONGESTION MONITORING THE NEW ZEALAND EXPERIENCE. By Mike Curran, Manager Strategic Policy, Transit New Zealand

2016 Development Cost Charges (DCC) UPDATE

2009 Muskoka Airport Economic Impact Study

Transport Assessment Appendix L: Match Day Impacts

Puffins at Junctions Design & Modelling Implications. JCT Symposium Paper 18 September 2003

Laxon Terrace - Sarawia. Click to add title. Street Rail Level Crossing. Public Forum. December

INNOVATIVE TECHNIQUES USED IN TRAFFIC IMPACT ASSESSMENTS OF DEVELOPMENTS IN CONGESTED NETWORKS

Chapter 6 Route Window NE5 Seven Kings station. Transport for London

Transport Impact Assessment

Chapter 16 Route Window NE15 Brentwood station. Transport for London

Non-technical summary

Planning. Proposed Development at the Southeast Corner of Lakeshore Road West and Brookfield Road Intersection FINAL.

Boxley Parish Council Highway Issues Briefing Note M2 junction 3 A229 Local Traffic Infrastructure

Initial Road Link Capacity Assessment Land East of Elsenham, Essex The Fairfield Partnership. 31 st July 2006

Perth and Kinross Council Development Control Committee 27 August 2008 Recommendation by Development Quality Manager

IRISH PARKING ASSOCIATION. The use of Pay and Display in Traffic Management in Kilkenny City

Display of 1 no. internally illuminated advertisement hoarding

Project No Brent Cross, Cricklewood London, UK Phase 1A North RMA

Sensitivity Analysis for the Integrated Safety Assessment Model (ISAM) John Shortle George Mason University May 28, 2015

WOKING INTEGRATED TRANSPORT PROJECT

M621 Junctions 1 to 7 Improvement Scheme Public Consultation Report

Welsh Assembly Government Transport Wales New M4 Project - Magor to Castleton Contents Page 1 INTRODUCTION 1 2 OPTIONS CONSIDERED Intermediate J

Woodford Community Council

Table : M-2 Highway International Roughness Index Table : Baseline Link Capacity Assessment

Transcription:

1. Introduction Trigger Point Justification Note 30 th August 2013 DCC constructed a highway assignment model of Tiverton and the surrounding area and this suggested that in pure capacity terms, up to 1,000 dwellings could be accommodated on the current network. However, other aspects have to be considered such as the safety of vulnerable road users. The particular issue associated with the Tiverton EUE development is the impact of increased traffic levels of pedestrians crossing Blundell s Road outside Blundell s School. 2. Conflict Study DCC commissioned Parsons Brinckerhoff to carry out a Conflict Study on Blundell s Road outside Blundell s School. After studying video analysis of this section of road carried out on 19 th June 2013, a total of 12 near misses / almost near misses were identified in a 12 Hour period. These were any incidents that required some action by the driver to avoid a collision with pedestrians crossing the road. The number of pedestrians crossing the road was recorded by location and a map showing these zones is located in Appendix 1. The results of this pedestrian survey showed that although the majority of pedestrians crossing Blundell s Road within the vicinity of Blundell s School cross at the pedestrian crossing facility at Zone C (70%), a significant proportion cross within Zone E (20%). The remaining10% cross along the length of the road in Zones A, B and D. This indicates that 30% of pedestrians are crossing in an uncontrolled location on a relatively busy road, the same location as the conflicts were seen to occur. 3. PV² Calculations To assess the level of conflict between vehicles and pedestrians, PV² calculations were carried out with reference to DMRB Advice Note TA 68/96 The Assessment and Design of Pedestrian Crossings. The PV² values have been determined for Zones A to E using the pedestrian flow data mentioned above and a traffic count carried out on the same day at the Blundell s Road / Tidcombe Lane junction. For robustness this does not include an additional factor to be applied to the pedestrian flows to take into account the large proportion of children crossing the road although there is some evidence that this could be as high as 4. These results are summarised in Table 1 below.

Hour Starting PV² x 10-8 Zone A Zone B Zone C Zone D Zone E 7 0.01 0.01 0.11 0.02 0.04 8 0.11 0.02 4.44 0.21 0.96 9 0.04 0.00 0.22 0.02 0.14 10 0.05 0.01 1.26 0.03 0.28 11 0.05 0.01 1.25 0.02 0.33 12 0.10 0.00 1.25 0.08 0.18 13 0.06 0.00 1.28 0.09 0.32 14 0.02 0.00 0.19 0.03 0.17 15 0.04 0.01 0.95 0.03 0.18 16 0.08 0.03 0.32 0.04 0.32 17 0.03 0.01 0.24 0.01 0.17 18 0.00 0.00 0.27 0.07 0.13 Average Max 4 Hours 0.09 0.02 2.06 0.11 0.48 Table 1: Current PV² Values TA 68/96 specifies that the assessment criteria for determining whether or not a pedestrian crossing is required is based upon the highest four hourly values of PV² and that where the average of these values is greater than 10 8 for an undivided road, then this would meet the criteria. Based upon the pedestrian and traffic flow data provided, the results indicate that at present, only Zone C meets the criteria of the requirement for a pedestrian crossing facility and this already exists at this location. To assess the impact of the EUE development traffic on this section of road, future traffic flows were taken from the DCC traffic model and factored to replicate the flows from the traffic count identified above. For a robust approach, it was assumed that the number of pedestrians would remain constant in the future. After a meeting with developers and Mid Devon District Council on 15 th August 2013, the stages of the highway improvements were suggested. These are outlined below along with the network code applied to each stage. Net0 Current Network Net101 Current Network + Improvements to J27 Net102 Net100 + Left-In, Left-Out junction onto A361 Net103 Net102 + Blundell s Road Traffic Calming outside School and improvements to Lowman Way and Blundell s Road roundabouts Net104 Net103 + Full Cloverleaf Junction onto A361. To assess the impact of this, each of the scenario s was modelled and with different development levels to assess the impact of the changing traffic levels on Blundell s Road. The PV² values for each of these scenarios are summarised in the table below.

Housing Employment A361 Junction Zone A Zone B Zone C Zone D Zone E Existing Current 0.09 0.02 2.06 0.11 0.48 0 0 Net101 0.10 0.02 2.24 0.12 0.52 0 0 Net102 0.08 0.01 1.85 0.10 0.43 200 4,000 Net102 0.10 0.02 2.25 0.12 0.52 200 4,000 Net103 0.08 0.02 1.82 0.10 0.43 300 4,000 Net101 0.13 0.02 3.03 0.16 0.70 600 10,000 Net103 0.10 0.02 2.44 0.13 0.57 600 10,000 Net104 0.06 0.01 1.53 0.08 0.37 1000 10,000 Net101 0.23 0.04 5.41 0.29 1.27 1000 10,000 Net103 0.14 0.03 3.43 0.18 0.79 1500 40,000 Net103 0.20 0.04 4.76 0.25 1.09 1500 40,000 Net104 0.11 0.02 2.59 0.14 0.62 Table 2: Future PV2 Values This analysis shows that if the first phase of the junction is built before 300 dwellings and 4,000m² of employment then the PV² values remain relatively low and the only location that requires a signalised pedestrian crossing facility is zone C which already has one. The PV² value for zone E reaches 0.7 which is still below 0.8x10-8 which is the level recommended for a zebra crossing but should be considered in the traffic calming measures. If 1,000 Dwellings were allowed to come forward before phase 1 (LILO) of the junction was implemented, or the full development was operated off just the first phase of the junction, an additional signalised crossing would be required in Zone E to accommodate the 20% that cross at this location. This then leads to the consideration of the residual 10% that cross at uncontrolled locations. 4. Ability to Cross the Road for Residual 10% In the Existing Situation a significant proportion of pedestrians cross at uncontrolled locations, the gap between vehicles on the road was analysed for the AM peak (08:00 09:00) as this was the hour with the most vehicles and pedestrians. This gave a mean gap of 3.5 seconds but there were a number of gaps greater than 10 seconds, with a maximum of 27 seconds. Assuming a gap of 5 seconds is required for a pedestrian to safely cross the road, the probability of a gap being large enough for pedestrians to cross is currently 20%, (i.e. 20% of the time the recorded gap was bigger than 5 seconds). The EUE development would add additional vehicles along this road which would result in smaller gaps between vehicles; as a consequence there would be less opportunity for pedestrians to cross outside of the designated crossing. To assess the impact of this, the length and number of gaps between vehicles was factored by the percentage increase in traffic. The results of this are summarised in Table 3 below.

Housing Employment A361 Junction Probability of Crossing Existing Situation Current 20% 0 0 Net101 19% 0 0 Net102 21% 200 4,000 Net102 18% 200 4,000 Net103 20% 300 4,000 Net101 14% 600 10,000 Net103 16% 600 10,000 Net104 23% 1000 10,000 Net101 8% 1000 10,000 Net103 11% 1500 40,000 Net103 8% 1500 40,000 Net104 14% Table 3: Probability of Crossing Road Outside of Crossing This analysis shows that for the majority of the scenarios the probability of crossing the road is above 14% which DCC believes is acceptable and only decreases if 1000 dwellings are allowed on the current network or the full development comes forward before the full junction is constructed. This is likely to result in pedestrians taking more risks in crossing the road which increases the chance of collisions. The only way of preventing this from happening is to add guardrails along the whole section of road funnelling the pedestrians to the designated crossing(s). Guardrails are not an attractive option and according to Manual for Streets 2, It disadvantages pedestrian movement by making people walk further, away from their desire lines, and creates an unpleasant feeling or restraint. It also narrows the usable footway which can lead to congestion. It is unsightly and detracts from local character and visual amenity, and there is evidence that it can increase traffic speeds and present an increased risk to cyclists, who can be crushed against it by vehicles. 5. Conclusion The DCC highway SATURN model outlined that in capacity terms, up to 1,000 dwellings could be accommodated on the current network. However, this technical note has outlined the impacts the development traffic would have on the pedestrians crossing Blundell s Road outside Blundell s School. This analysis shows that if 1,000 dwellings were allowed without phase 1 (LILO) of the A361 junction then an additional signalised pedestrian crossing would be required at zone E to allow pedestrians to cross the road safely at this location. This would also require guardrails along the whole length of road outside the school on both sides to funnel the pedestrians to the signalised crossing points. This mitigation measure is considered unacceptable because it has various safety implications and would not fit in with the image of the school. Taking all this information into account, DCC proposed the following trigger points: Before construction Blundell s Road traffic calming 100 Dwellings Improvements to Lowman Way Roundabout and Blundell s Road Roundabout 300 Dwellings, 4,000m² Employment Left-in, left-out junction onto A361 600 Dwellings, 10,000m² Employment Full movements junction onto A361 2000 Dwellings Secondary access onto Heathcoat Way (beyond EUE Development)

After the meeting on 15 th August, the impact of construction traffic was considered and to mitigate this, it was proposed to bring forward the highway improvements and the following trigger points were proposed: Before construction south slips for construction traffic Before occupation Left-In, Left-Out junction and connection to Blundell s Road 200 Dwellings, 4,000m² Employment Blundell s Road traffic calming phase 1 (outside Blundell s School) and improvements to Blundell s Road roundabout and Lowman Way roundabout 600 Dwellings, 10,000m² Employment Full A361 Junction and phase 2 of Blundell s Road traffic calming 2,000 Dwellings, 40,000m² Employment Secondary access onto Heathcoat Way

6. Appendix 1: Zonal Map