Regular Board Meeting August 4, 2015

Similar documents
STUDY WORK GROUP MEETING No. 4. July 12, 2017

CHAPTER 1: INTRODUCTION

AIRPORT MASTER PLAN UPDATE

FORECASTING FUTURE ACTIVITY

Table of Contents. Overview Objectives Key Issues Process...1-3

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Finance and Implementation

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

Friedman Memorial Airport Authority. Regular Meeting September 4, 2012

Lake Tahoe Airport Master Plan

Addendum - Airport Development Alternatives (Chapter 6)

The CLE Master Plan Includes:

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

City of Monett, Missouri. Pride and Progress. Airport Master Plan Update. for the Monett Municipal Airport

CHAPTER 3 ALTERNATIVES CONSIDERED

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

PUBLIC NOTICE ***************************** New Castle Airport. Intention to File a Passenger Facility Charge (PFC) Application

Punta Gorda Airport Master Plan Update

Westover Metropolitan Airport Master Plan Update

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

AGENCY SCOPING MEETING

Planning, Development and Environment Committee

Regular Board Meeting December 1, 2015

Friedman Memorial Airport Authority. Regular Meeting April 09, 2013

BNA Master Plan Update Community Advisory Committee Meeting No. 5

Collier County Airport Authority. Joint Automated Capital Improvement Program

General Aviation Master Plan Update

HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

CHAPTER 1 EXECUTIVE SUMMARY

Chapter 1 Introduction and Project Overview

Preferred Alternative Summary

Chapter 2 FINDINGS & CONCLUSIONS

Merritt Island Airport

Raleigh Executive Jetport Master Plan Update MPAC MEETING #3 NOVEMBER 1, 2018

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

STUDY WORK GROUP MEETING No. 3. November 29, 2016

New PFC Application #13

Birmingham Airport 2033

Airlake Airport 2035 Long Term Comprehensive Plan (LTCP)

ACTION TRANSMITTAL

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis

Ted Stevens Anchorage International Airport

CHAPTER 4: ALTERNATIVES

THE CASE OF A SUCCESSFUL PFC APPLICATION

PREFERRED PLAN Kahului Airport Master Plan and Noise Compatibility Program Update

Ted Stevens Anchorage International Airport

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018

Chapter 4.0 Alternatives Analysis

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

Financial Feasibility Analysis

Chapter 8.0 Implementation Plan

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D

2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP)

INDEPENDENCE STATE AIRPORT (7S5)

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Dallas Love Field Update. Dallas City Council Briefing February 18, 2015

Beaver Island Airport Terminal Building Project Q & A Prepared by Mead & Hunt

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport

Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

Savannah / Hilton Head International Airport Master Plan Update

SAN FRANCISCO INTERNATIONAL AIRPORT

Airports and UAS: Integrating UAS into Airport Infrastructure and Planning

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016

Amended & Restated Lease of Terminal Building Premises (Airport Use & Lease Agreement)

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS

Appendix C AIRPORT LAYOUT PLANS

SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES

Chapter 1: Introduction Draft

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment


Planning Advisory Committee November 20, 2014

Chapter 9 Airport Financial Plan

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM. April 10 th 2017

Friedman Memorial Airport Authority. Regular Meeting June 5, 2012

TO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Meeting #4 Presentation Material DATE: July 18, 2017

Chapter 1 Introduction and Project Overview

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

BNA Master Plan Update Public Meeting No. 2

Las Vegas McCarran International Airport. Capacity Enhancement Plan

Chapter 1: Introduction

2015 PURDUE ROAD SCHOOL March 11, 2015

Sunshine Coast Airport Master Plan September 2007

Public Review Draft South County Airport Master Plan Report. County of Santa Clara San Martin, California

MASTER PLAN CONCEPT 1 DRAFT

Transcription:

Regular Board Meeting August 4, 2015 1616 Airport Circle Hailey, ID 83333 208.788.4956

PUBLIC COMMENT

FY 16 Rates & Charges FY 16 Budget Approval

Rates & Charges will provide the Board the ability to operate FMA and meet all of the coming year s needs. Adjustments being proposed are those associated with recovery of expenses resulting from lost keys and/or Airport Identification Badges Public Comment/Approve the proposed Friedman Memorial Airport FY 16 Rate and Charges

Proposed FY 16 Budget The Board reviewed and made revisions to the Draft Budget during June and July FMAA meetings. Since last month s public review, adjustments were made to include an approximate $60,000 acquisition of a wheeled Tool Cat utility vehicle Provides the Board the ability to operate FMA and meet all of the coming year s needs Provides the Board the ability to complete all Runway Safety Area Implementation projects Facilitates acquisition of a new Runway Broom/Plow Truck Facilitates the continued Master Planning process Proposes a maximum of 4% in merit pay adjustment, contingent on exceptional performance. Does not propose any CPI pay adjustment May begin the process of restoring FMAA operational reserves to Pre-Runway Safety Area Improvement Project capacity in FY 16 Budget

As stated in the Joint Powers Agreement, the Board is required to hold a public hearing on or before the first Tuesday in August and to approve the budget on or before August 15 th.

July 7, 2015 Regular Meeting Approval

Chairman Report Blaine County Report City of Hailey Report Airport Manager Report

AIRPORT STAFF BRIEF QUESTIONS

UNFINISHED BUSINESS

Plan to Meet 2015 Congressional Safety Area Requirement Presented by: - Mr. Dave Mitchell, T-O Engineers - Airport Manager

Project 1: Hangar Taxilane and Apron Improvements Project 2: Relocate/Extend Taxiway B and RSA Grading Project 3: Terminal Reconfiguration Project 4: Airport Operations Building Project 5: Terminal Apron/Site Preparation Project 6: Relocate Twy B/Remove Twy A/North Apron Project 7: Central Bypass Apron Other Projects

Ongoing/Remaining work: Punchlist Tenant finish out Rotating exit door

3/3/2015

3/3/2015

3/3/2015

3/3/2015

3/3/2015

3/3/2015

3/3/2015

On schedule Working on finishes/final steps Punchlist

Todd Combs Served projects at FMAA over a 15-year period Passed away on August 13, 2014 Recognition/tribute in the AOB for Todd Thoughts?

Two Bidders: Bidder Total Engineer s Estimate $872,120.00 Knife River Corp. Northwest $899,288.00 Western Construction, Inc. $738,921.00

Bids have been reviewed Both bids appear to be complete Recommend award to the apparent low bidder, Western Construction, Inc., in the amount of $738,921.00, subject to final review by Staff, Engineer, Legal Counsel and FAA.

Grant application requested approximately $9.4M in FAA funding Grant was issued for $8,249,000 Amendment was requested on July 23 to increase the grant to $9,486,350 (maximum amendment amount) Request approval to accept the grant amendment when the offer is made to finish implementing the Runway Safety Area Project.

Runway Rehabilitation/Parking Lot Improvements Landscaping Improvements Terminal Tenant Finish Out

Nearly complete Terminal areas complete Finishing AOB area Scheduled to be complete by August 14

Negotiations nearly complete Work to begin soon

Fly Sun Valley Alliance Update

Master Plan Process/Timeline Update Chapter D Existing Airport Site Alternatives Next Steps Comments & Discussion

INVENTORY (completed) Documents existing Airport conditions, facilities, and context. FACILITY REQUIREMENTS (completed) Identifies needs for key facilities (runways, taxiways, hangars, etc.) FINANCIAL ANALYSIS & IMPLEMENTATION PLAN Identifies phasing plan, required regulatory approvals, and capital funding sources. BACKGROUND INFORMATION PLAN FORMULATION FORECASTS (completed) Predicts future passenger enplanements, takeoffs and landings, and aircraft based at the airport. ALTERNATIVES ANALYSIS (in progress) Develops concepts for meeting facility requirements and recommends preferred solutions. AIRPORT LAYOUT PLAN UPDATE Depicts recommended future projects.

Incorporate FMAA Feedback into Draft Chapter D Draft Chapter E, Replacement Airport Sites Re- Evaluation, to be delivered in September Public Information Meeting o o Co-schedule for the week of the October FMAA Meeting? Preferred meeting format?

Assumptions Key Facilities Approach Concepts

Compliance Customer Service Economic Growth Planning Thresholds Design Aircraft Efficient Use of Existing Property Flexibility Land Acquisition Land Use Compatibility Runway Length Passenger Terminal Highway 75 Snow Storage & Stormwater Drainage

Air Traffic Control Tower Passenger Terminal Facilities Terminal Building Commercial Aircraft Parking Passenger Vehicle Parking General Aviation Facilities Aprons Hangars

No Action Alternatives Existing Site Footprint Alternatives Existing Site Expansion Alternatives Replacement Airport Alternatives (next step)

Three of nine sites identified by 2004 tower study still viable Two additional sites were identified for Master Plan These five sites were analyzed with reference to: o o o o o Visibility performance Orientation and glare Airspace Construction cost Site-specific factors Master Plan analysis provides starting point for required FAA siting process

Sites 3 and 4 not good candidates due to cost and operational challenges Sites 1 and 2 are good candidates but limit terminal area options Site 5 is a good candidate but is off Airport property and in Highway 75 right-of-way Sites 1, 2, and 5 recommended for formal FAA siting process

New design can accommodate 3 peak hour flights Will be congested at 4 peak hour flights in some functional areas Further building expansion would be beneficial for 5 peak hour flights or greater Secure Holdroom 200 425 Security Screening Checkpoint 150 300 Baggage Claim 145 300 Ticketing/Outbound Baggage 135 275 0 50 100 150 200 250 300 350 400 450 Peak Hour Enplanement Capacity Post-2015 Capacity Ultimate Expansion Capability

Existing apron has 3 aircraft parking positions o At capacity during peak seasons 20-year forecast estimates peak hour of 4 to 7 departing flights o Actual number of peak hour flights dependent on airline scheduling Two alternatives were developed o o Expand apron to 4 positions and provide 2 remote staging positions Expand apron to 7 positions

Parking availability currently strained at 360 spaces 20-year forecast estimates that parking needs will nearly double Sufficient space not available for parking expansion within existing terminal area property footprint

Two alternatives to regain lost capacity o o 150,000 square feet of apron 14,500 square feet of hangar space Two alternatives to accommodate projected demand o o Additional 225,000 square feet of apron Additional 78,700 square feet of hangar space

Instrument Approaches/Departures o Will incorporate findings of on-going independent study Compliance with Standards o Chapter D identifies previously-studied constraints within context of reasonable expense

Incorporate FMAA Feedback into Draft Chapter D Draft Chapter E, Replacement Airport Sites Re- Evaluation, to be delivered in September Public Information Meeting o o Co-schedule for the week of the October FMAA Meeting? Preferred meeting format?

Last month, the Board had a short discussion regarding the needed for a Communication Director Chairman Schoen developed a draft agreement for consideration Discuss/Direct/Public Comment/Action

NEW BUSINESS

Original AIP 40 grant offer was for $18,000,000. Grant was amended shortly after offer. Amended grant total became $20,700,000. AIP guidelines place Sponsor with grants that exceed $20,000,000 in a nominal risk category with regard to grant closeout. Nominal risk means the FAA requires the grant be substantially complete or closed out before the Sponsor can draw the last 10% of the federal share of the grant.

The reality of this FAA policy is that FMA will pay the last $2,070,000 of AIP 40 project costs before the federal share can be drawn down. This FAA policy will make cash flow in the next few months complex and may exhaust most of the Board s operational reserves for a short period of time Staff has applied for a $500,000 line of credit with Mountain West Bank to bridge the time period between expenditure of approximately $2,070,000 in project cost and reimbursement for federal share at substantial completion or project closeout.

The cost of the line of credit will be reimbursed by the grant as project cost If approved by the Board, the line of credit will only be used if absolutely necessary and use will be vetted by the Board s Finance Committee and Chairman Discuss/Direct/Public Comment/Action

PUBLIC COMMENT

1616 Airport Circle Hailey, ID 83333 208.788.4956