Chapter 14 Route Window C12 Mile End Park and Eleanor Street shafts. Transport for London

Similar documents
Chapter 25 Route Window SE6 Plumstead portal. Transport for London

Chapter 6 Route Window NE5 Seven Kings station. Transport for London

Chapter 4 Route window W23 Taplow station. Transport for London

Chapter 4 Route Window NE3 Manor Park station. Transport for London

Chapter 7 Route Window C6 Farringdon station. Transport for London

Chapter 9 Route Window C8 Whitechapel station. Transport for London

Chapter 2 Route window W25 Maidenhead station. Transport for London

Chapter 21 Route window W6 West Ealing station. Transport for London

Chapter 8 Route Window NE7 Chadwell Heath station. Transport for London

Chapter 16 Route Window NE15 Brentwood station. Transport for London

Chapter 13 Route Window NE12 Harold Wood station. Transport for London

Chapter 12 Route window W15 Dog Kennel bridge. Transport for London

Chapter 26 Route Window SE6A Manor Wharf. Transport for London

A. CONCLUSIONS OF THE FGEIS

Sky Temporary Car Park Transport Statement

Major Scheme Business Case Summary Report for Programme Entry

Maidenhead Bridge. Proposed Work

Finchley and Golders Green Area Committee 27 April 2017

Route Windows Central route section

Gold Coast. Rapid Transit. Chapter content. Chapter four Route selection and staging

5.7 Local road upgrades

5.1 Traffic and Transportation

Concord Road Interchange. Standard hours of work

Jobcentre Plus advisers giving guidance to a job seeker at the Crossrail Visitor Information centre

Hospital Link Project Project Update Winter 2018

A63 Castle Street, Hull HullBID Network Lunch 24 August 2017

Open Report on behalf of Richard Wills, Executive Director for Environment and Economy

Construction Staging Adelaide Street West

Grade Crossings in High Speed Rail Corridors

Kent Pedestrian Guard Railing Assessment

Movement Strategy. November On behalf of Barton Oxford LLP

SHOREDITCH STATION TO CLOSE THIS JUNE by John Thomason

Boxley Parish Council Highway Issues Briefing Note M2 junction 3 A229 Local Traffic Infrastructure

Construction Staging Area Blue Jays Way (357 King Street West)

ACORNS PROJECTS LIMITED

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.

Date 24/10/2011. Date 04/11/2011. Date 25/10/2011. Date 10/11/2011. Date 25/10/2011. Date 25/10/2011. Date 10/11/2011.

A31 Ringwood improvement scheme

5.5 Material Assets - Transportation

Trigger Point Justification Note 30 th August 2013

PART VIII APPLICATION FOR REVISED SOUTH SIDE TRAFFIC MANAGEMENT WORKS TO FACILITATE LUAS BXD PLANNING REPORT ROADS & TRAFFIC DEPARTMENT

Appendix C Stage 1 Road Safety Audit

Commissioning Director - Environment. Officer Contact Details Jane Shipman;

Glasgow Street Traffic Review

Felixstowe Branch Line FAQ

Saighton Camp, Chester. Technical Note: Impact of Boughton Heath S278 Works upon the operation of the Local Highway Network

Proposals for the Harrogate Road / New Line Junction Improvement Scheme. August / September Supported by:

Planning Approval Consistency Assessment Form

BLACKWALL WAY SHAFT CROSSRAIL PROPOSALS. Blackwall Way Shaft

Road Closure & Traffic Mangement Information during the 2018 ASICS Windermere Marathon Race.

The Newcastle Central Motorway East and Other Plans

The Brief The Brief APS

E40. Temporary activities

Hospital Link Project Project Update September 2015

The Point Roundabout Improvement Scheme

Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April

Kent Pedestrian Guard Railing Assessment

4. Safety Concerns Potential Short and Medium-Term Improvements

FHWA P/N Guidelines. Corridor Relationship. Highway 22 Segment 1 - US 169 to CSAH 2 Relevance / Documentation of Need

Site Location and Setting

Capital & Counties. October 2007

LUDWIG RD. SUBDIVISION PROJECT TRAFFIC IMPACT ANALYSIS

Pedestrian Safety Review Spadina Avenue

EXISTING CONDITIONS A. INTRODUCTION. Route 107 Corridor Study Report

CITY OF EDINBURGH COUNCIL WRITTEN SUBMISSION

Pre-application submission for Committee: Phase 4 development at West Hendon

John Betts School Crossing Review

Appendix 9 Melbourn Greenway Review

WOKING INTEGRATED TRANSPORT PROJECT

Section 106 Update Memo #1 Attachment D. Traffic Diversion & APE Expansion Methodology & Maps

Lower Thames Crossing

WELCOME TO PROJECT EVERGREEN 3 CHILTERN S PROPOSED NEW OXFORD TO LONDON ROUTE

Scotchbarn Lane, Prescot Accessibility Statement

Queen s Circus Roundabout

Interstate 90 and Mercer Island Mobility Study APRIL Commissioned by. Prepared by

London Borough of Barnet Traffic & Development Design Team

H1: BIRMINGHAM CURZON STREET STATION

Treasure Island Supplemental Information Report Addendum

Frequently Asked Questions on the Route 29 Solutions Improvements Projects

STAR Bond Development

Transport Impact Assessment

Yonge Street / Highway 401 Improvements Update. Public Works and Infrastructure Committee. General Manager, Transportation Services

Spencer Environmental Appendix A: Alternative Analysis for Construction Access Route

Llandudno Junction. Regeneration Proposals for the Future. December 2009

Report to: Greater Cambridge Partnership Joint Assembly 18 January A10 Foxton level crossing bypass and travel hub

To: From: Plans showing the alignments of the routes discussed in this section are presented in Appendix A.

Submitted to: NYX CAPITAL CORP. 1131a Leslie Street, Suite 201 Toronto, Ontario M3C 3L8 Attention: Mr. Tim Jessop Development Manager

Network Safeworking Rules and Procedures

A63 Preferred Route Announcement

4.0 Context for the Crossing Project

Commissioning Director - Environment

Phase 1A North, Brent Cross Cricklewood Regeneration Area, London NW2

SUMMER VILLAGE OF SILVER SANDS. Municipal Development Plan

Board meeting

N4 Carrick-on-Shannon to Dromod Road Project. 2.1 Introduction

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization

Engagement Summary Report. Trans-Canada Highway 1 RW Bruhn Bridge Replacement Project. Community Engagement November 15, 2016 to January 15, 2017

Time to discover LIFE AT

PURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40

Prince Albert Road Towpath Ramp, Camden Feasibility Report

Transcription:

Chapter 14 Route Window C12 Mile End Park and Eleanor Street shafts

MILE END PARK AND ELEANOR STREET SHAFTS 14 Route Window C12 Mile End Park and Eleanor Street shafts Introduction 14.1 Crossrail s twin bored tunnels will broadly follow the existing railway corridor (the London to Southend line) in this route window. The permanent works in this route window will be the construction of: the running tunnels; the Mile End Park shaft; the Eleanor Street shaft. Both shafts are needed as escape and intervention points and to provide ventilation. 14.2 There will be two worksites in this route window. From west to east they are: Mile End Park Shaft worksite In the southeast corner of Mile End Park adjoining Burdett Road. Eleanor Street worksite Within the eastern extent of the current caravan park at the eastern end of Eleanor Street. 14.3 The maps provided at the end of this chapter present the main features of the route window and the assessed construction lorry routes. Baseline conditions 14.4 This route window is in the London Borough of Tower Hamlets. Although the main land uses are residential, being a mixture of Victorian terraces and post-war redevelopment, there are large areas of open green space, including Mile End Park and Tower Hamlets Cemetery Park. Mile End Park shaft 14.5 Mile End Park is a linear area of public open space, open to the public at all times, situated between the Regents Canal and Burdett Road. It also houses the Mile End Stadium Sports complex. 14.6 Bow Road Underground station and Bow Church DLR station are to the north, with the Royal London Hospital further to the west, all on the A11 Bow Road. There are also a number of schools in the area. 14.7 Access to east and west of this route window can be taken from the A11 Bow Road/Mile End Road and to the south from the A1205 Burdett Road. These roads form part of the for London Road Network. Waiting and loading on Tower Hamlets administered roads is controlled throughout the local area; CPZ waiting restrictions typically apply between 0830 and 1830 hours, Monday to Friday. 14.8 The area is well served with public transport; by Bow Road and Mile End Underground and Bow Church DLR stations. Bus routes serve the Mile End Road/Bow Road (A11) and the A1205 Burdett Road/Grove Road. 14.9 Moderate pedestrian flows occur in both the AM and PM peaks on Burdett Road and are generally associated with access to local public transport. Eleanor Street shaft 14.10 Eleanor Street is flanked to its east by a railway line and passes beneath a railway bridge immediately south of its junction with Tidworth Road. Frontages include the Bow Triangle Business Park, a traveller s caravan site and various small commercial/light industrial premises. Mornington Grove is a mainly residential street with privately owned terraced housing. The Thames Magistrates Court flanks the east side of Mornington Grove with its front entrance on the A11 Bow Road. 14.11 Red Route controls apply for approximately the first 10 m of Mornington Grove. The remainder of Mornington Grove and the entirety of Eleanor Street are incorporated within a CPZ (CPZ waiting restrictions typically apply between 0830 and 1830 hours, Monday to Friday). The daytime parking demand appears to be heaviest on Mornington Grove on its approach to the Bow Road (A11) junction, elsewhere there appears to be little daytime parking activity. Eleanor Street and Mornington Grove are partly traffic-calmed with speed cushions, although neither street is incorporated within a 20 m.p.h. zone. 14.12 Eleanor Street rail overbridge has a highway clearance of 4 m. This is the largest clearance of any potential local access route. 14.13 Moderate pedestrian flows occur in both the AM and PM peaks on Bow Road (A11), and are generally associated with access to local public transport. Pedestrian volumes are low on both Mornington Grove and Eleanor Street. A pedestrian footbridge over the railway links Eleanor Street and Arnold Road. C12 page 3

ROUTE WINDOW C12 Potential changes in baseline conditions Mile End Park shaft 14.14 A redevelopment of Mile End Stadium and the surrounding parkland areas has commenced and is due for completion by 2006. This includes reorientation to provide the main entrance to the complex off Burdett Road. A new access point and access road will be provided to the north of the Mile End Park Shaft Worksite. This is currently under construction. The permanent works Running tunnels 14.15 Two 6 m diameter running tunnels will be constructed that will descend from a depth of approximately 23 m at Mile End Park shaft to a depth of approximately 28 m below street level at Eleanor Street shaft. 14.20 The overall construction period including fit out and commissioning of Mile End Park shaft will be about three years and nine months. 14.21 The worksite will normally generate approximately five lorry loads (10 movements) per day and approximately 24 loads (48 movements) during the peak construction period, spanning about nine months. 14.22 have been consulted about potential traffic management arrangements and the detailed arrangements will be agreed prior to construction, in accordance with Crossrail s construction mitigation measures (refer Volume 8a and Appendix B1 of the Environment Statement). 14.23 Given the location of the site and the nature of the local highway network, the worksite arrangement and associated lorry access and entry points are not predicted to cause any significant adverse impact on local road users, pedestrians or cyclists. Mile End Park shaft 14.16 The Mile End Park shaft will be constructed in the southeast corner of Mile End Park, bounded by Burdett Road and Network Rail s viaduct that carries the line to and from Fenchurch Street. The shaft will provide escape, intervention and ventilation facilities with a surface structure located adjacent to Burdett Road. Once ground level works are completed, the site will be landscaped to integrate with the Mile End Park; hard standing will be constructed for use by emergency services. Eleanor Street shaft 14.17 The Eleanor Street shaft will be constructed within the eastern extent of the caravan park at the eastern end of Eleanor Street. The site is in an area of land bounded by LUL s District line and Network Rail s line to and from Fenchurch Street station. Ventilation and emergency intervention facilities will be provided. A surface structure will be constructed along with an area of hard standing. Beneath the surface, a concrete box will contain ventilation equipment. C12 page 4 Worksite assessment (group 1) Mile End Park Shaft Worksite 14.18 The proposed worksite arrangement will operate in close proximity to the redeveloped Mile End Stadium. Peaks of pedestrian and vehicular traffic activity may occur however these can be dealt with as part of the traffic management measures to be discussed with the operator and the local highways authority prior to construction. 14.19 Access to the site will be taken directly from the Road Network. In accordance with the advice of, the worksite access will be taken from the new Stadium access road rather than directly from Burdett Road to reduce the number of access points on this part of the TLRN. Figure 14.1 Burdett Road, looking south Lorry route assessment 14.24 Material, including excavated material will be delivered and removed by road only. 14.25 The worksite access will be from the new Mile End Stadium Access Road (currently under construction) off the A1205 Burdett Road, which is part of the TLRN. Egress is proposed directly onto the A1205 Burdett Road via an existing crossover. No specific lorry routes are therefore required. Lorry holding area assessment 14.26 It is anticipated that adequate lorry holding capacity is available on-site.

MILE END PARK AND ELEANOR STREET SHAFTS 14.27 A potential lorry holding area for sites in Route Window C8 (the Hanbury Street shaft in particular) has been identified on the north-westbound carriageway of the A1205 Burdett Road, approximately 50 m northwest from the proposed worksite access. This would require removal of the bus lane in this location. 14.28 The bus lane is operational for weekday morning and evening peak hours only. Recent site observations have taken place at these times and traffic queues were not observed and it is not anticipated that the use of the lorry holding area will cause a significant impact on general traffic and bus operations. Worksite assessment (group 2) 14.36 The worksite will normally generate approximately six lorry movements per day (ie three lorry loads) and approximately 34 (ie 17 lorry loads) during the peak construction period, spanning about seven weeks. 14.37 As noted above, light goods vehicles could potentially access the site via a new access to the rear on Rounton Road which links to the A11 Bow Road via Campbell Road. However, this is not a desirable route for heavy goods vehicles due to the restricted highway geometry and viaduct clearance constraints. 14.38 The daily flow of lorries generated by the worksite is too small to trigger any significant effect on the basis of the approved criteria. As a result, no significant traffic and transportation impacts are anticipated as a result of the proposed lorry routes. Eleanor Street worksite 14.29 Crossrail will construct a 15 m diameter shaft within the eastern extent of the current caravan park site at the eastern end of Eleanor Street. The site is in an area of land bounded by London Undergrounds District line and the LT&S line to Fenchurch Street. 14.30 The eastern section of Eleanor Street (approximately 70 m length) will be encompassed within the worksite. This section of highway is not a through road and currently allows only local access e.g. to the caravan park. Kerbside space is seldom used for waiting and loading activities and an adequate turning space will still be available for general traffic. Lorry access and egress will be from separate newly formed access and egress points on Eleanor Street. There is potential for light goods vehicles only to access and egress the worksite from Rounton Road (see lorry route assessment below), to reduce potential conflict with lorry traffic. 14.31 The overall construction period including fit out and commissioning of Eleanor Street shaft is about three years and three months. 14.32 The worksite arrangement and associated lorry access points are not predicted to cause any significant adverse impacts on local road users, pedestrians or cyclists. Lorry route assessment 14.33 Material, including excavated material will be delivered and removed by road. 14.34 Access to this worksite is proposed from Eleanor Street via Mornington Grove from the TLRN (at the A11 Bow Road). This route is restricted with a 4 m bridge clearance on Eleanor Street and this will be taken into account when planning deliveries. 14.35 Traffic movements at the Mornington Grove priority junction with the TLRN are restricted through a central reserve on Bow Road A11 so that there is no right turn permitted for vehicles entering or leaving Mornington Grove. This will mean that traffic exiting the site intending to travel eastbound will first have to travel west on the A11, then south via Burdett Road. As requested by the local authority, the potential to remove the central reserve and introduce signal control to reduce lorry mileage within the London Borough of Tower Hamlets was discussed with TfL. However, having regard to the traffic management implications and the low peak numbers of lorries anticipated, TfL did not support this proposal and hence no change to the junction arrangements is proposed. Figure 14.2 District line passing below bridge adjacent to Eleanor Street Lorry holding area assessment 14.39 An on-street lorry holding area is proposed on the northern section of the southbound carriageway of Eleanor Street adjacent to the railway. The location and operation of the lorry holding area is not anticipated to cause any significant impacts on road users, pedestrians or cyclists. Mitigation and temporary impacts 14.40 No significant temporary traffic and transport impacts are anticipated associated with this route window. C12 page 5

ROUTE WINDOW C12 Mitigation and permanent impacts 14.41 There are no significant permanent traffic impacts to note in this route window. 14.42 Both shafts are required for ventilation and emergency escape and intervention. Only occasional access for maintenance will normally be required. C12 page 6