A DIALOGUE WITH THE NORTHERN VIRGINIA DISTRICT Nicholas J. Roper, P.E. Northern Virginia District Project Development Engineer
Agenda Dashboard 2019 Project Advertisements for Construction 2019 New Projects for Design Project Development Engineer Topics o o Cost Estimates Alternative Intersections and Interchanges
Dashboard Statewide and NOVA District Statewide All Projects NOVA District All Projects
Dashboard NOVA District NOVA District VDOT Admin NOVA District Local Admin
2019 Project Advertisements for Construction Locally Administered Projects 27 Projects scheduled for advertisement; total estimate = $165.6M for construction 14 projects are bike/pedestrian or multi-modal improvements Min CN estimate = $500k; median CN estimate = $939k; max CN estimate = $64.6M Significant projects: UPC Description Location Admin Ad Date Delivery 110038 77378 S. Washington Street Multi-Modal Improvements Eisenhower Avenue Widening and Remove Traffic Circle Construction Estimate Falls Church Locally 29-Mar-19 D-B-B $3,540,647 Alexandria Locally 17-May-19 D-B-B $4,668,894 96721 Route 28 Widening -Manassas Manassas Locally 30-May-19 D-B-B $17,145,217 108720 106274 #HB2.FY17 Widen Route 28 from 4 to 6 Lanes Divided Springfield CBC Commuter Parking Garage Fairfax Co Locally 30-Sep-19 D-B $64,600,000 Fairfax Co Locally 2-Dec-19 D-B-B $55,200,000
2019 Project Advertisements for Construction VDOT Administered Projects 9 projects scheduled for advertisement; total estimate = $91.9M for construction Min CN estimate = $500k; median CN estimate = $1.9M; max CN estimate = $54.6M Significant projects: UPC Description Location Admin Ad Date Delivery 111318 109473 111725 104406 #SGR Centreville Rd over Bull Run - FED ID 6269 Belmont Ridge Road Interim Widening at Dulles Greenway #SMART18 - VA 286 Popes Head Road Interchange #SGR Major Bridge Rehab at Rte 7/King St over I-395 Construction Estimate Fairfax Co VDOT 12-Nov-19 D-B-B $4,599,995 Loudoun VDOT 10-Dec-19 D-B-B $6,200,000 Fairfax Co VDOT RFP Summer/Fall 2019 D-B $54,600,000 Fairfax Co VDOT Late 2019 D-B-B $11,350,000 Maintenance & Operations Bridge: $5M Joint Closures & Repairs at 3 bridges on I-495 over the Dulles Toll Road, date TBD Operations: $3.5M for pavement marking and roadway departure March 2019 Paving: $101.7M in spring/fall 2019
SMART 18 Rte 286 & Popes Head Road Interchange Currently being designed with Fairfax County Parkway widening Interchange at Rte 286 & Popes Head Road approved separately as a SMART SCALE project Provide interchange at Popes Head Rd, access to future development of Patriot Park and accommodate the future extension of Shirley Gate Road Interchange configuration still in development RFP summer/fall of 2019 Phase Estimate PE --- RW CN Total $9.7M $54.6M $64.3M
Route 28 Widening from Prince William County line to Old Centreville Road Widen Route 28 from four to six lanes for a distance of 2.3 miles Provide intersection, pedestrian and bicycle improvements Design-Build project delivery, administered by Fairfax County Dept. of Transportation RFP in late 2019 Phase PE RW CN Total Estimate $4.6M $7.4M $64.6M $76.6M Existing four lane section Conceptual Typical Section in Bifurcated Areas
Springfield CBC Commuter Garage Multi-modal and multi-functional facility Advertise in Dec 2019 Phase PE RW CN Total Estimate $5.5M $3.1M $55.2M $63.8M
2019 New Projects for Design Transportation Improvements at National Landing Includes Metro improvements, pedestrian bridge to DCA, Route 1 Urban Boulevard Exact details for delivery are still unknown Anticipate starting a project on Route 1 in 2019
2019 New Projects for Design Braddock Road Multi-modal Improvements Study completed by FCDOT in 2018; see https://www.fairfaxcounty.gov/transportati on/study/braddock-multimodal o Shared use paths, bike/pedestrian bridges, intersection Improvements, I-495 interchange modification VDOT will administer the project and anticipates starting design in 2019 Estimate Phase I II PE $7.6M $6.3M RW $14.0M $13.4M CN $66.0M $54.7M Total $87.6M $74.4M II I
SMART SCALE ROUND 3 47 applications submitted by NOVA localities for $3.1B Funds (@ $800M statewide) available in FY23-24 Project administration o All Projects: 16 VDOT (33%) & 31 Locally (66%) o 39 New Projects: 8 VDOT (20%) & 31 Locally (80%)
Cost Estimate Reviews Draft IIM-259 District and Central Office Estimate Review and Verification All new projects in the construction program to be reviewed by subject matter experts in the District and approved by the District Project Development Engineer For Hampton Roads, Richmond, and NOVA Districts: all new projects in the construction program with estimates > $10M require review by the Assistant L&D Engineer All projects with estimates > $50M will have an independent estimate prepared by Central Office and approved by the State L&D Engineer VDOT wants to institute multiple layers of estimate reviews to guard against project overruns Demonstrates the importance VDOT is attributing to the accuracy of cost estimates
Alternative Intersections and Interchanges Consider and encourage alternative intersections and interchanges whenever possible http://www.virginiadot.org/innovativeintersections/