Correction to Quarterly Report for quarter ending June 2016

Similar documents
QUARTERLY ACTIVITIES REPORT 31 OCTOBER 2018

Atlas Lifts Production Guidance and Lowers Cost Forecast After Record September Quarter

For personal use only

HK GAAP RESULTS RELEASE 18 November 2005

CROWN ANNOUNCES 2018 HALF YEAR RESULTS

Uniquely positioned to be Australia s next coal producer

QUARTERLY ACTIVITIES REPORT 31 JANUARY 2019

Whitehaven Coal Limited

PORT WARATAH COAL SERVICES

FIRST QUARTER OPERATING PROFIT IMPROVES TO $274 MILLION

QUARTERLY ACTIVITIES REPORT. For three months ended 31 March Highlights. 2. Operating Summary

For personal use only

PROFIT OF $1.24b ON STRONG REVENUE GAINS BUT FUEL COSTS REMAIN GREATEST CHALLENGE

ASX Announcement. Company Update

SECOND QUARTER OPERATING PROFIT IMPROVES TO $87 MILLION

Aer Lingus Group plc. Interim Management Statement

NEWS RELEASE ON FINANCIAL RESULTS FOR THE THREE MONTHS ENDED 31 DECEMBER 2003 CONTINUED RECOVERY IN THIRD FINANCIAL QUARTER

ASX Announcement. Appointment of Preferred Contractor for CHPP Construction at Colton Mine

Matilda Zircon Limited (ASX: MZI) (formerly Olympia Resources Ltd) Quarterly Activities Report for Period Ended. 30 June 2009

THIRD QUARTER NET PROFIT OF $397 MILLION ON RECORD REVENUE

PARENT AIRLINE OPERATIONS LIFT GROUP PROFIT

QANTAS DELIVERS STRONG FIRST HALF RESULT DESPITE HIGHER FUEL BILL

HK GAAP RESULTS RELEASE 12 August 2008 STAR CRUISES GROUP ANNOUNCES FIRST HALF RESULTS FOR 2008

SWISS posts CHF 187 million EBIT for the third-quarter period

The Changing Face of Australian Export Coal Industry

For personal use only

CROWN ANNOUNCES 2017 FULL YEAR RESULTS

December 2018 Quarterly Production Report

27 December Companies Announcement Office Australian Securities Exchange Limited 20 Bridge Street Sydney NSW Dear Sir

For personal use only

$131 MILLION OPERATING PROFIT IN THIRD QUARTER AMID CHALLENGING ENVIRONMENT

Aer Lingus Group plc. Interim Management Statement

NEWS RELEASE 8 NOVEMBER Gladstone LNG Project Arrow-AGL Joint Venture Acquires Enertrade s Gas and Pipeline Business

HK GAAP RESULTS RELEASE 25 February 2008 STAR CRUISES GROUP ANNOUNCES FOURTH QUARTER AND FULL YEAR RESULTS FOR 2007

FIRST QUARTER OPERATING PROFIT IMPROVES 69% TO $463 MILLION

For personal use only

Land area 1.73 million km 2 Queensland population (as at December 2016) Brisbane population* (preliminary estimate as at 30 June 2016)

Highlights. Quarterly Activities Report: September Kurnalpi Project. Lindsays project

For personal use only

For personal use only

Air China Limited Interim Results. August Under IFRS

Media Release QANTAS RESULTS FOR THE HALF YEAR ENDED 31 DECEMBER 2004 HIGHLIGHTS. Fully franked interim dividend of 10 cents per share

THIRD QUARTER OPERATING PROFIT UP 51% TO $675 MILLION

FIRST QUARTER OPERATING PROFIT RISES TO $281 MILLION

December 2017 Quarterly Activities Report

Australian Securities Exchange Notice

Gruyere Gold Project Development Update

20 November Company Announcements Australian Securities Exchange Limited Level 4, 20 Bridge Street SYDNEY NSW 2000 AUSTRALIA.

Outlook: FY13 EBITDA guidance $28M - $29M. Pursuing contracted 300MW in 2013 growth strategy. FY13 maiden franked dividend payment expected

QUARTERLY ACTIVITIES REPORT 31 JULY 2017

Market Announcement ASX:NTL, NZX:NTL For Immediate Release

STRONG OPERATING RESULTS LIFT NET PROFIT 7.3% TO $932 MILLION

For personal use only

WEAK FOURTH QUARTER CAPS FULL-YEAR PROFIT AT $1.06 BILLION

RECORD REVENUE AND EFFICIENCY DRIVE SOFTEN IMPACT OF HIGH FUEL COST, ENABLE HALF YEAR PROFIT OF $578 MILLION

Altera Resources Ltd

Department of Employment, Economic Development and Innovation. Current Queensland coal infrastructure developments

Land area 1.73 million km 2 Queensland population (December 2015) Brisbane population* (June 2015)

ASX RELEASE. Erdenet to Ovoot Concession Agreement Executed

For personal use only

BHP BILLITON PRODUCTION REPORT FOR THE QUARTER ENDED 31 MARCH 2004

THIRD QUARTER OPERATING PROFIT UP 96%

For personal use only

Copa Holdings Reports Net Income of $49.9 million and EPS of $1.18 for the Second Quarter of 2018

Gruyere Gold Project Update

For personal use only

CROWN ANNOUNCES 2010 FULL YEAR RESULTS

For personal use only

First Thunderbox gold now anticipated in June Quarter 2016

QUARTERLY REPORT 1 JULY 2017 to 30 SEPTEMBER 2017

Japan Post Media Release

BHP Billiton Limited Annual General Meeting 2016

An Update on Coal for the Bowen Basin

Haoma Mining NL A.B.N

The Manager Company Announcements Australian Stock Exchange Limited Sydney NSW Dear Sir. Demerger of BHP Steel

FULL YEAR OPERATING PROFIT RISES TO $259 MILLION 25 CENTS SPECIAL DIVIDEND PROPOSED OUTLOOK REMAINS CHALLENGING

QANTAS RESULTS FOR THE YEAR ENDED 30 JUNE 2000 HIGHLIGHTS. Net profit before tax of AUD$762.8 million, up AUD$100.3 million, 15 percent on last year

This transaction is at the securityholder level and will not impact the day-to-day operations, management or employees of SP AusNet.

Air China Limited Announces 2009 Annual Results

Media Release. Qantas Group Full Year 2017 Financial Result 1. Sydney, 25 August 2017

SKYWEST, INC. ANNOUNCES THIRD QUARTER 2014 RESULTS

BHP BILLITON PRODUCTION REPORT FOR THE QUARTER ENDED 31 MARCH 2003

HIGH FUEL PRICES DRIVE HALF YEAR PROFIT DOWN 62% AMIDST CHALLENGING ENVIRONMENT

Overview. Mining projects map

CROWN ANNOUNCES 2014 FULL YEAR RESULTS. MELBOURNE: Crown Resorts Limited (ASX: CWN) today announced its results for the full year ended 30 June 2014:

Yoma Strategic s 3Q2017 Revenue grew by 16.6% with improved Gross Profit margins

RESTRUCTURING OF AUSTRALIAN EXPORT COAL INDUSTRY IMPACT OF CHINA AND INDIA. Bede Boyle and George Edwards. Coal Ventures Limited

For personal use only

HALF YEAR REPORT February Leighton Holdings Limited

THIRD QUARTER PROFIT DOWN 43% TO $337 MILLION

For personal use only

23 February The Manager Market Announcements Australian Securities Exchange Limited 20 Bridge Street SYDNEY NSW 2000.

JUNE 2017 QUARTERLY ACTIVITIES REPORT

2008 INTERIM ANNOUNCEMENT

Mungana Signs Agreement with Newcrest to unlock Porphyry Gold-Copper Potential at Chillagoe

Tat Hong Reports 13% Decline in FY2017 Revenue

MATRIX METALS LIMITED

MOUNT GIBSON IRON LIMITED QUARTERLY REPORT FOR THE PERIOD ENDED 31 MARCH April 2018

WHITEHAVEN COAL LIMITED (ASX:WHC) AMENDED INVESTOR PRESENTATION

For personal use only

Transcription:

YANCOAL AUSTRALIA LTD ADDRESS: Level 26, 363 George Street Sydney NSW 2000 PHONE: 61 2 8583 5300 FAX: 61 2 8583 5399 WEBSITE: www.yancoal.com.au 26 July 2016 Correction to Quarterly Report for quarter ending June 2016 Sales volumes (equity share) published 20 July 2016 in Yancoal Australia Ltd s Quarterly Production Report for quarter ending June 2016, were incorrectly reported on page four, paragraphs one and two. The correct sales volumes (equity share) are: Metallurgical Coal sales volumes (equity share) of 1.96 million tonnes, up 8 percent on the year prior. Thermal coal sales volumes (equity share) of 2.78 million tonnes, down 7 percent year-on-year. The revised Quarterly Production Report for quarter ending June 2016 follows. Ends Media and Investor Relations contact: James Rickards General Manager Investor Relations and Corporate Affairs Yancoal Australia Limited Phone: +61 2 8583 5922 Mobile: +61 419 731 371 Email: james.rickards@yancoal.com.au YANCOAL AUSTRALIA LTD ASX RELEASE, 2015 1

Quarterly Report HIGHLIGHTS Quarterly production (equity share) of 3.88 million tonnes saleable coal, down eight percent on the year prior. Quarterly sales volumes (equity share) of 4.74 million tonnes, down two percent on the year prior. Effective from 2 May 2016, the Donaldson coal operation moved to care and maintenance, following the cessation of mining activities at the Abel underground mine and the commencement of new feasibility studies. First development coal extracted from the new Moolarben underground in April. Commenced installation and manning required to facilitate the proposed recommencement of longwall production at Austar in July 2016. YANCOAL AUSTRALIA LTD

OUTLOOK Recent thermal coal price improvements are anticipated to continue, buoyed by the reduction of China production and Indonesian exports. Gains are expected to be offset slightly by the challenges facing the coal industry, specifically driven by Europe and the US as those markets move towards a reliance upon gas and alternative energy sources. Coal demand in Asia is still expected to be strong and continued growth in coal demand is expected in the future. Yancoal continues to implement operational efficiencies and cost saving strategies across all operated and managed mine sites. OPERATIONS Effective 31 March, Yancoal ceased to control the New South Wales underground assets of Austar, Ashton and Donaldson. 1 Yancoal was appointed as the exclusive provider of mine management, marketing, infrastructure and other corporate support services under 10-year contracts. The Ashton, Austar and Donaldson mines are managed by Yancoal Mining Services Pty Ltd, a 100 percent owned Yancoal subsidiary and employing entity for all eastern region underground operations staff. As announced 2 May 2016, the Donaldson coal operation moved to care and maintenance, following the cessation of mining activities at the Abel underground mine and the commencement of new feasibility studies. The move to care and maintenance is in response to ongoing global market challenges as the operation considers the future development of new underground working areas. The majority of Donaldson employees were redeployed to the neighbouring Austar and Ashton underground operations. PRODUCTION In accordance with expectations, operations produced a total 3.88 million tonnes saleable coal (equity share) for the reporting period, down eight percent on the year prior. The reduction in production was mostly attributable to the cessation of production of the Abel underground mine; continued challenges experienced within the geology of the Stratford Duralie pit; poor weather conditions at Moolarben; and scheduled longwall moves at the Ashton and Austar mines. Sales volumes (equity share) for the reporting period were 4.74 million tonnes, down two percent on the year prior. In New South Wales, the Moolarben complex achieved strong production results, up 46 percent on the year prior, with production gains and fleet efficiencies established earlier in the year overcoming significant wet weather impacts during the reporting period. 1 On 17 February 2016, Yancoal announced a new financing arrangement to secure up to US$950 million in debt-funding via the issuing of nine-year secured debt bonds by a newly established Yancoal subsidiary, Watagan Mining Company Pty Ltd ( Watagan ), to Industrial Bank Co. Ltd, BOCI Financial Products Limited and United NSW Energy Limited. Under the arrangement, Yancoal s interests in the assets of Ashton, Austar and Donaldson were transferred to and held by Watagan. YANCOAL AUSTRALIA LTD PAGE 2 OF 4

The Moolarben Stage Two project continues on schedule, with first development coal from the new Stage Two underground achieved in April and the new open cut box cut completed on schedule, with first coal to be extracted in July. Ongoing geotechnical issues within the current operating area of the Stratford Duralie open cut continued to negatively affect extraction rates for the period, with production down 37 percent on the year prior. Geotechnical modelling and pit redesign work is currently underway, with overburden extraction and production rates scheduled to increase in the second half of the year, once through the current mining area. Ashton underground production was down 47 percent on the year prior, resulting from the completion of a longwall move in April to finish the block and a second longwall move in June into a new mining area. Three development units moved into the ULLD seam during the reporting period to prepare the area for the recommencement of full production and longwall cutting in July. Austar production was down 89 percent year-on-year, as the site completed the development of the Bellbird South mining area and subsequent longwall installation. Longwall production at Bellbird South is set to commence in the second half of the year. Donaldson production was in accordance with expectations, down 81 percent on the year prior, following the operation s move to care and maintenance on June 6 and cessation of production at the Abel underground mine. The majority of the Abel underground workforce were redeployed to the Ashton and Austar operations, with crews engaged to help prepare the Austar underground for the resumption of cutting in July. In Queensland, the Yarrabee open cut operation returned to strong production for the majority of the reporting period, experiencing minor interruptions to extraction rates due to wet weather conditions. Production gains continue to be achieved following a change in shift arrangements, with Yarrabee production up three percent on the year prior. Steady production for the Middlemount joint venture was affected by wet weather interruptions during the reporting period, with production down four percent on the year prior. PRODUCTION (100% Basis) June Qtr June YTD 2016 2015 Change 2016 2015 Change ASHTON 208 395-47% 532 624-15% AUSTAR 34 328-89% 111 545-80% MOOLARBEN 2,435 1,665 46% 4,280 3,367 27% YARRABEE 761 741 3% 1,305 1,234 6% GLOUCESTER 258 409-37% 462 718-36% DONALDSON 78 412-81% 193 846-77% MIDDLEMOUNT 1,133 1,181-4% 1,972 2,098-6% TOTAL (100% Basis) 4,908 5,130-4% 8,856 9,432-6% Total Production - Equity Basis 3,879 4,223-8% 7,056 7,726-9% YANCOAL AUSTRALIA LTD PAGE 3 OF 4

SALES VOLUMES (Equity Share) June Qtr 2016 2015 Change 2016 2015 Metallurgical 1,964 1,826 8% 3,432 3,299 4% Thermal 2,775 2,992-7% 4,534 5,165-12% TOTAL EQUITY SHARE 4,738 4,818-2% 7,966 8,464-6% Metallurgical Coal sales volumes (equity share) of 1.96 million tonnes, up eight percent on the year prior. Thermal coal sales volumes (equity share) were 2.78 million tonnes, down seven percent year-on-year. June quarter operating review Safety no significant events were recorded for the reporting period. June YTD Change Permitting The New South Wales Planning and Assessment Commission ( NSWPAC ) granted approval for the Moolarben Mod 12 (Underground 1 optimisation) on 29 April 2016. Permitting - The NSWPAC granted approval for the Ashton Mod 5 (integration modification) on 20 June 2016. CORPORATE INFORMATION Shareholder Enquiries Computershare Investor Services Pty Limited Level 4, 60 Carrington Street, Sydney, NSW, 2000 Phone: 1300 850 505 Website: www.computershare.com.au Directors CEO Xiyong Li Chairman Reinhold Schmidt Baocai Zhang Cunliang Lai Yuxiang Wu Co-Vice Chairman Co-Vice Chairman Director CFO Lei Zhang Fuqi Wang Director Company Secretary Boyun Xu Director Laura Ling Zhang William Randall Director Vincent O Rourke Director Registered Office Dr Geoff Raby Director Level 26, 363 George Street, Sydney NSW 2000 Gregory Fletcher Director Phone: (02) 8583 5300 Huaqiao Zhang Director Fax: (02) 8583 5399 Email: info@yancoal.com.au Website: www.yancoal.com.au Mailing Address: Level 26, 363 George Street, Sydney, NSW, 2000 Contact: James Rickards Investor Relations (02) 8583 5922 0419 731 371 Substantial Shareholders as at 30 June 2016 Name Percentage of issued shares Yanzhou Coal 78.0% Noble 13.2% Number of ordinary shares on issue: 994,216,659 YANCOAL AUSTRALIA LTD PAGE 4 OF 4