Report to the Strategic Development Committee. Ronald Reagan Washington National Airport Project Journey. June 2018

Similar documents
January 2018 Air Traffic Activity Summary

SIOUX FALLS REGIONAL AIRPORT - SIOUX FALLS, SOUTH DAKOTA PFC Quarterly Report - Project Activity Page 1

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway

Charles H. Ada II Executive Manager A.B. Won Pat International Airport Guam

RECOMMENDED 2013 BUDGET

SAN LUIS OBISPO COUNTY REGIONAL AIRPORT ANNUAL AIRLINE PASSENGER SUMMARY SUMMARY BY YEAR AND MONTH 4/11/2018

INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE

Public Information Center August 12, 2010

ANNEX A Resolution No Monterey Peninsula Airport District - Schedule of Rates & Charges - FY 2018

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport

Planned Procurement Opportunities Report. June 2017

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation

AIRPORTS DIVISION. The Hawaii Airports System Is Self-Supporting

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

Exhibit 2. Preconstruction Jan Jun-19

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019

Domestic Visitation to the Northern Territory

Planning & Development Group

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

Brisbane Airport Ground Transport Operators Forum Tuesday 25 July, 2pm Brisbane Airport Meeting Room Ground Transport Operators

FORECASTING FUTURE ACTIVITY

RONALD REAGAN WASHINGTON NATIONAL AIRPORT NOVEMBER 2016

msp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010

2017 Appropriation Budget Table of Contents Board Approved August 19, 2016

PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM

CHAPTER 4: ALTERNATIVES

Public Meeting: Metropolitan Washington Airports Authority (MWAA) Transportation Network Company (TNC) Lot on S. Eads Street

Noise Oversight Committee

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan

U.S. DOMESTIC INDUSTRY OVERVIEW FOR MAY 2009

TAIT FY 2019 BUDGET Summary

Implications of Construction Cost Escalation

Reno-Tahoe Airport Authority U.S. DOMESTIC INDUSTRY OVERVIEW FOR FEBRUARY

Fort Lauderdale Hollywood International Airport

2018 Appropriation Budget Table of Contents Board Approved August 18, 2017

Brief Recap of Project to Date

Passenger and Cargo Statistics Report

State of Hawaii Dept. of Transportation Airports Division Capital Improvement Program Update

Dallas Love Field Update. Dallas City Council Briefing February 18, 2015

CONSTRUCTION COMMITTEE MEETING AGENDA

Passenger and Cargo Statistics Report

TERMINAL 3. tour guide booklet. April 2012

Kentucky Lock Project Update Inland Waterways Users Board Meeting No. 84

EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE

The CLE Master Plan Includes:

Technical Advisory Committee Briefing #3

Passenger and Cargo Statistics Report

Passenger and Cargo Statistics Report

Administration and Projects Committee Meeting STAFF REPORT July 3, 2014 Page 2 of 2 Agreement Consultant Project General Scope CT 107 URS Corporation

Master Plan Phase 2 Workshop

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

Passenger and Cargo Statistics Report

State of the Airport Robert S. Bowen, Executive Director October 18, 2018

MONTROSE REGIONAL AIRPORT

CIVIL AVIATION AUTHORITY

AIRPORT MASTER PLAN UPDATE

O Hare Noise Compatibility Commission Technical Committee April 19, Proposed Interim Fly Quiet Runway Rotation Plan

Los Angeles International Airport (LAX) Airside $907M

DTTAS Quarterly Aviation Statistics Snapshot Quarter Report

LOUIS ARMSTRONG NEW ORLEANS INTERNATIONAL AIRPORT For the Period Ending September 30, Enplaned Passengers by Airline

REPORT TO THE DULLES CORRIDOR COMMITTEE

RAPID CITY REGIONAL AIRPORT

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment

RONALD REAGAN WASHINGTON NATIONAL AIRPORT JUNE 2016

Management Presentation. November 2011

Regular Board Meeting August 4, 2015

Stakeholders Meeting

RENO-TAHOE INTERNATIONAL AIRPORT APRIL 2008 PASSENGER STATISTICS

Advertising Opportunities. Southwest Florida International Airport

SEPTEMBER 2015 BOARD INFORMATION PACKAGE

APRIL 2016 BOARD INFORMATION PACKAGE

Passenger and Cargo Statistics Report

Kansas City Aviation Department. Update to Airport Committee Customer Service

2017/ Q1 Performance Measures Report

August 2014 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport

Passenger and Cargo Statistics Report

14 C.F.R. Part 158. Passenger Facility Charge Program Logan International Airport. Public Notice

JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS

GREATER ORLANDO AVIATION AUTHORITY

Passenger and Cargo Statistics Report

Management Presentation. September 2011

air traffic statistics

Passenger and Cargo Statistics Report

May 2011 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport

MAXIMIZING INVESTMENT AND UTILIZATION

Birmingham Airport 2033

RESIDENT ENGINEERING, CONSTRUCTION MANAGEMENT & QA/QC SERVICES (CONTINUOUS CONTRACTS FROM

RECOMMENDED 2013 BUDGET AS SUBMITTED TO THE FINANCE COMMITTEE

May Air Traffic Statistics. Prepared by the Office of Corporate Risk and Strategy

Passenger and Cargo Statistics Report

July 2012 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport

8.0 AIRPORT LAYOUT PLANS

JANUARY 2017 BOARD INFORMATION PACKAGE

September 2013 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport

BOARD ITO Aide REPORT TO THE AIRPORT COMMISSIONERS

March 2014 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport

RESOLUTION No APPROVAL OF WAYNE COUNTY AIRPORT AUTHORITY FISCAL YEAR 2018 BUDGET. By Board Member Mark Ouimet

FREEING UP MELBOURNE'S BIGGEST BOTTLENECK

Tampa International Airport Master Plan Update. December 12, 2012

Transcription:

Report to the Strategic Development Committee Ronald Reagan Washington National Airport Project Journey June 2018

Secure National Hall

Secure National Hall Project Cost Summary Prior Month Expenditures $ 2,205,118 Total Expenditures (as of May 2018) Total Budget (includes 2018 Budget Escalation) $ 29,432,826 $ 255,333,197 Total Forecast $ 255,333,197

Secure National Hall Schedule of Activities Construction Lane Widening on Arrivals Level North Relocation of Communication Rooms to Ticket Level Entrances 2 and 5 Test Pile Program Install Auger Piles (Roadway Partial-Lane Closures on Arrival Level) Interior work Entrances to National Hall Selective Mechanical, Electrical, & Plumbing Demolition and Reroutes In Progress Completion: Jun 2018 In Progress Completion: Feb 2019 COMPLETED Starts: Jun 2018 In Progress Completion: Nov 2018

Construction Secure National Hall Schedule of Activities (Continued) Maintenance of Traffic (MOT) Phase 2 Outer Roadway June 2018 Nov 2018 Install SIDA Wall Mockup In Progress Completion: Jul 2018 Completion (Opening to the Public) 1 st Quarter 2021

Secure National Hall Progress Maintenance of Traffic (Phase 2) Day Time

Secure National Hall Progress Maintenance of Traffic (Phase 2) Night Time

Secure National Hall Progress Roadway Construction

Secure National Hall Progress Interior Work Former Alaska Airlines Ticket Counter Previous Capital One Tenant Space

Secure National Hall Progress Interior Work South Portal Demolition Future South Checkpoint Entrance Baggage Claim 12 Ceiling

Secure National Hall Progress Secure Identification Display Area (SIDA) Wall Markup & Staging

Secure National Hall Progress SIDA Wall Mockup Overnight Walkway Closure

New Concourse

Enabling Projects Cost Summary Prior Month Expenditures $ 1,173,893 Total Expenditures (as of May 2018) Total Budget (includes 2018 Budget Escalation) $ 36,763,824 $ 168,439,584 Total Forecast $ 168,439,584

Enabling Projects Schedule of Activities Central Utility Plant Modification Electrical Rough-in & Conduit Motor Control Centers COMPLETED Install Variable Frequency Drive Valves COMPLETED Selective Demolition Existing Electrical System COMPLETED Initial Startup Program Starts: Jun 2018 Commissioning / Training / Closeout Jun 2018 Dec 2018 Completion Jan 2019

New Concourse Project Cost Summary Prior Month Expenditures $ 4,955,301 Total Expenditures (as of May 2018) Total Budget (includes 2018 Budget Escalation) $ 51,146,622 $ 374,419,000 Total Forecast $ 374,419,000

New Concourse Schedule of Activities - Apron Construction Surcharge Settlement Period Phase 1 April 2018 October 2018 Blast Wall Foundation Installation Electrical and Communications Phase 1 Hydrant Fueling Phase 1 COMPLETED In Progress Completion: July 2018 In Progress Completion: December 2018

New Concourse Schedule of Activities New Concourse Construction Pavement Demolition and Grading In Progress Completion: Aug 2018 Test Pile Program Starts: Jun 2018 Foundations and Underslab Starts: Jul 2018 Temporary Chiller Installation Starts: Jun 2018 North Substation Enabling Work Starts: Jul 2018 New Concourse - Completion Summer 2021

New Concourse Progress Hydrant Fueling Piping Fabrication

New Concourse Progress Jet Blast Wall Foundation Installation

New Concourse Progress Concourse Footprint Pavement Demolition and Grading

FlyReagan.com/ProjectJourney

Report to the Strategic Development Committee Ronald Reagan Washington National Airport Project Journey Customer Impacts June 2018

Recent Customer Changes Mock-up of security barrier on ticketing level Roadway changes Establish new concourse work area Signage improvements

Mock-up of Security Barrier on Ticketing Level

Roadway Changes

Roadway Changes Construction reduces available lanes on the Outer Roadway from 9 AM 12 Midnight. Personal vehicles exiting the Airport may be diverted to the Inner Lanes at the north end [Pink Arrow]. North Pier Gates 35-45 Bag Claim 7-12 Bag Claim 1-6 Center Pier Gates 23-34 South Pier Gates 10-22 12 11 10 9 8 7 6 5 4 3 2 1 Door # FORMER TAXI CURRENT TAXI TNC Doors 6 & 7 CURRENT TAXI FORMER TAXI Construction Area Taxi Shift DAY Construction Area Taxi Shift

Roadway Changes Nightly road closures from 12 Midnight 9 AM will divert all Outer Roadway traffic to the Inner Lanes. North Pier Gates 35-45 Bag Claim 7-12 Bag Claim 1-6 Center Pier Gates 23-34 South Pier Gates 10-22 12 11 10 9 8 7 6 5 4 3 2 1 Door # FORMER TAXI CURRENT TAXI TNC Doors 6 & 7 CURRENT TAXI FORMER TAXI Closed Nightly for Construction Taxi Shift NIGHT Taxi Shift

Establish New Concourse Work Area North Access South Access Construction

Signage Improvements

Upcoming Customer Changes Ceiling removal on baggage level Additional utility work at north end of Airport

Ceiling Removal on Baggage Level

Additional Utility Work on North End of Airport

FlyReagan.com/ProjectJourney