One month after Typhoon Jebi October 3, 2018
Status of damage by Typhoon Jebi [RWY & apron] Almost entire area flooded Runway B [Aeroplaza] Glass in lobby on Level 2 broken. One pax hurt arm Terminal 2 [Pax handling systems] Partially unavailable due to power outage and flood (checkin, BHS, etc.) [T1] Electrical equipment, AC, pax/cargo handling facilities and disaster prevention facilities flooded Power down in the north and central areas of the main terminal building [Cargo warehouse] Roofs ripped apart. Shutters damaged Utilities like power and AC partially or all unavailable in almost all buildings due to flood Some goods in warehouse damaged Cargo warehouse Terminal 1 [Ground handling] 90% of 600 vehicles like towing cars and 2,200 pieces of equipment submerged *Information source: 2 airlines Runway A [Access bridge] Tanker smashed into the bridge Gas leak from the damaged part Road blocked Rail service halted Access bridge 1
Recovery status Runway B: Resumed on Sept 7 T2 : Resumed on Sept 7 Cargo warehouse: Gradually resuming service from Sept 14 T1 south: Resumed on Sept 14 T1 north: Resumed on Sept 21 Runway A: Resumed on Sept 14 Airport access by rail: Resumed on Sept 18 Access bridge: The damaged girders removed on Sept 14. Full-scale restoration targeted for around GW next year* 2 *Subject to the weather in the next spring: This is based on the assumption that the weather is stable, not causing a delay in the offshore work.
Recovery Time Steps towards early recovery (1) Emergency Sept 7, 2018 (3 days after the typhoon) Domestic flight operations at T2 Take-off and landing facilities on Phase II Island T2 Domestic T2 International (Partially resumed on Sept 8) (2) Partial Sept 14, 2018 (10 days after the typhoon) Int l/dom flights at T1 partially resumed T2 fully reopened Int l cargo area partially reopened Runway A reopened Taxiways and aprons partially reopened T1: Check-in function restored (Level 4, south) - South wing reopened - CIQ functions restored (3) Full Scale Sept 21, 2018 (17 days after the typhoon) T1 fully reopened Taxiways and aprons fully reopened T1: Check-in function restored (Level 4, north) - North wing reopened *T1: Terminal 1, T2: Terminal 2 *Recovery efforts ongoing towards full restoration of airport functions 3
Disaster Response Task Force - Aiming to redesign BCP - October 3, 2018
Seawall Task Force Responsibility Study Item Description Schedule CTOs Survey and analyze floodcausing seawall damages to identify necessary measures 1. Establish a third-party committee participated by experts named Committee on Assessing Overtopping Waves Caused by Typhoon Jebi to study oceanographic phenomena and wave overtopping which occurred around the island during the flood event (First meeting held on Oct. 3). 2. Plan for future recovery & disaster efforts based on the study result of the third-party committee Kick-off: Sept. 19 Interim report: Late Oct. 3. Work closely with the central government on the above efforts 1
Basement Facility Task Force Responsibility Study Item Description Schedule CTOs Examine key basement facilities such as power control panels and drainage pump systems to identify necessary measures Work on: 1. relocation of power facilities in Terminal 1 to a higher floor 2. anti-flooding measures for basement facilities in Terminal 1 3. identification of key basement facilities on the island to install anti-flooding measures Kick-off: Sept. 19 Interim report: Late Oct. 2
Crisis Management Task Force Responsibility Study Item Description Schedule COOs & CAOs Identify and address problems Desired crisis management & future vision Communications to customers/business operators 1. Proactive approach (better crisis management in daily operations) Enhanced operation center functions taking into account 3 airports backup system Reform of the group-wide crisis management system for KAP Group 2. Disaster mitigation & emergency responses (including customer assistance) Closer cooperation with business partners and government agencies Customer communications (including multilingual support) Kick-off: Sept. 20 Interim report: Late Oct. 3. Early recovery (restoration of airport functions) Incident-based recovery planning 3