Update Presented by Siobhan O Donnell. 27 th July 2017

Similar documents
Dublin Airport Update Presented by Pat Molloy

Measuring, Managing and Mitigating Aircraft Related Noise

No. Item Responsible 1. Siobhan O Donnell went through the daa update.

Minutes. St. Margaret s Community Liaison Group

Dublin Airport Update Presented by Pat Molloy

Presentation to the British Irish Airport s EXPO John Heffernan Chief Development Officer, Dublin Airport

Completion of concrete runways. Passenger numbers reach 200,000 per year. Passenger numbers. Celebrates 50th birthday.

Dublin Airport - Noise Management Plan

Community Noise Consortium Meeting (CNC)

Perth and Kinross Council Development Control Committee 27 August 2008 Recommendation by Development Quality Manager

Portable Noise Monitor Report

Portable Noise Monitor Report

East Midlands Airport 2018 Aerodrome Manual

TAG Farnborough Airport

Community Noise Consortium Meeting (CNC)

Portable Noise Monitor Report

Portable Noise Monitor Report

COMMONWEALTH PORTS AUTHORITY

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited

Edinburgh Airport Corporate Responsibility Report 2008

MEETING MINUTES Page 1 of 5

TAG Farnborough Airport

TAG Farnborough Airport

Consultation by Luton BC on Planning Application for expansion of London Luton Airport (our ref: CB/13/00088/OAC)

Portable Noise Monitor Report

TABLE OF CONTENTS 1.0 INTRODUCTION...

Advisory Circular CT

Why build a third runway, when you can build a longer runway?

The Corporation of the City of Kawartha Lakes Council Report

Rushmoor Local Plan 6 July 2017 Louise Piper Planning Policy & Conservation Manager Richard Ward Environment & Airport Monitoring Officer

2009 Muskoka Airport Economic Impact Study

Memorandum. Federal Aviation Administration. Date: June 19, Richard Doucette, Environmental Protection Specialist. From: To:

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN

For Airport Environmental Services. Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018

Canberra Airport Aircraft Noise Information Report

Guidance material for land use at or near aerodromes

Skellig Michael Action Plan Appendix 2 Position as of January Objective: Action: Complete: In Progress: Not yet Commenced

IRELAND AERONAUTICAL INFORMATION SERVICE IRISH AVIATION AUTHORITY BALLYCASEY CROSS SHANNON CO. CLARE Tel Fax

Planning & Development Group

Airport Master Plan Update June 15, 2017

ACI Noise Rating Index and its applications

Framework Brief. Edinburgh SIDs

Section 32 TABLE OF CONTENTS Airfield and Aircraft Operations. 32.A General B Aircraft

Technical Report. Aircraft Overflight and Noise Analysis. Brisbane, California. December Prepared by:

EXHIBIT LIST. No Exhibit Name Page. 1 R391 HS2 Residents Charter.pdf (R391) R392 Response to Select Committee

PUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT

A63 Castle Street, Hull HullBID Network Lunch 24 August 2017

Perth Noise Abatement Procedures - Change to Preferred Runways

Portable Noise Monitor Report

BOARD OF AIRPORT COMMISSIONERS

Part 139, Amendment 11. Aerodromes Certification, Operation and Use. Docket 14/CAR/3

SECTION 106 ACTIVITIES ANNUAL REPORT

Community Noise Consortium Meeting (CNC)

Wellington International Airport Runway Overlay

SECTION 32. Airfield and Aircraft Operations

CHRISTCHURCH INTERNATIONAL AIRPORT NOISE MANAGEMENT PLAN. 28 March 2014 V10

Rodrigues Regional Assembly Chief Commissioner s Office

Preliminary Findings of Proposed Alternative

Runway Status Lights (RWSL) in Japan. July 2015

3,500 SMO RUNWAY. Issues and Questions. May 2, Airport Commission Member

Why are the underground fuel tanks being removed and replaced with above ground tanks?

The Point Roundabout Improvement Scheme

O Hare Noise Compatibility Commission Technical Committee April 19, Proposed Interim Fly Quiet Runway Rotation Plan

IAA Submission on the Commission for Aviation Regulation s Draft 2014 Determination of Maximum Level of Charges at Dublin Airport

REVALIDATION AND VALIDATION: PROCESSES AND PROCEDURES

Terms of Reference: Introduction

Arriving and departing aircraft at Edinburgh Airport

E40. Temporary activities

Government consultations : Airports National Policy Statement, UK Airspace Policy, Night Flights

Report of the Strategic Director, Regeneration to the meeting of Bradford South Area Committee to be held on 28 January U

REPORT IN-011/2012 DATA SUMMARY

Birmingham Airport Airspace Change Proposal

Community Meeting for the Planned Ground Run-Up Enclosure. June 28, 2016

REVIEW OF GOLD COAST AIRPORT Noise Abatement Procedures

Airport Master Plan Update June 15, 2017

DESIGN CONTROL GUIDELINES NORTHLAKE HOME LOTS

Gold Coast Airport Aircraft Noise Information Report

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS

Appendix F Cultural Resource Consultation

UNDERSTANDING NOISE COMPLAINTS

Ryanair RAAS Programme

Noise Action Plan Summary

EMA Noise Action Plan FOREWORD

Toron Notio s e Pe M a a r n s a o g n e U me p n d t a at t e Toronto Pearson CENAC June 21, 2017

The GMC protocol for making revalidation recommendations: Guidance for responsible officers and suitable persons Fifth edition (March 2018)

PUBLIC ATTENDEES: Steve Marriott, South Burlington Jeremy King, So. Burlington Energy Committee Jen Norz, Efficiency VT

PART VIII APPLICATION FOR REVISED SOUTH SIDE TRAFFIC MANAGEMENT WORKS TO FACILITATE LUAS BXD PLANNING REPORT ROADS & TRAFFIC DEPARTMENT

TAG Farnborough Airport

Portable Noise Monitor Report

Applewood Heights Community Open House

DTTAS Quarterly Aviation Statistics Snapshot Quarter Report

Dublin Route Support Scheme ( RSS ) Long-Haul Operations (the Scheme )

REPORT 2014/065 INTERNAL AUDIT DIVISION. Audit of air operations in the United. Nations Assistance Mission in Afghanistan

Gold Coast Airport Aircraft Noise Information Report

2. Sign Types Signing for Canadian TODS qualified tourism attractions, services and facilities has been divided into two categories:

PUBLIC INFORMATION WORKSHOP #4 / PUBLIC HEARING November 8 / 9, 2006

USE OF REMOTELY PILOTED AIRCRAFT AND MODEL AIRCRAFT IN AVIATION

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

Lake Tahoe Airport Master Plan

South Fremantle Solar Farm Agenda 1 March 2018

Transcription:

Update Presented by Siobhan O Donnell 27 th July 2017

daa Actions from Previous Meetings Action Item 1. SOD to investigate flight deviation on 25 th April 2017 Summary We have followed up on this request with the Noise Flight Track Monitoring team at Dublin Airport. At c. 8am on 25 th April 2017, there was a missed approach to Runway 28 by a Ryanair arrival flight. The aircraft had to carry out a go round procedure due to low visibility. The safety of passengers is paramount and the conditions required the necessary safety precautions to be taken 2

North Runway Construction Package 1 Update Construction Package 1 Road surfacing works are on going, as are fencing and landscaping The original 11 archaeological sites (on the Naul Road footprint) are resolved and work has commenced on other sites around the North Runway footprint Drainage & utility works to continue into September Road Works SI 238 Roads Act 1993 (Extinguishment of Public Right of Way) Order 2017 over the part of Naul Road (R108) for 663m between R07 and R08 has been processed by the Department of Transport, Tourism and Sport and will come into effect on 18 August 2017; the switch over to the new road will take place towards the end of August Local resident groups will continue to be informed of upcoming traffic management measures as soon as information becomes available Proposed upcoming works (tentative dates subject to FCC approval): TBA Forest Little Road East End Tie-In Lane Closure TBA Forest Little Road West End Tie-In Lane Closure 4 th Sep 15 th Sep Naul Road East Tie In R108 Boot Inn Side Lane Closure 2 nd Oct 13 th Oct Toberburr Road West Tie-In Lane Closure 3

Construction Package 1 - Update Waste Discovery of a soft spot of earth beside Forrest Road which contained bags of waste Specialist environmental consultants appointed to carry out a risk assessment of the site Consultants report, method statements and a remediation proposal was submitted to Fingal County Council Remediation works to commence on 8 th August 2017 FCC have granted approval for Forrest Road to remain closed until 29 th September Every effort is being made to complete the works as soon as possible 4

Construction Package 1 Statistics We want to minimise the impact of construction activities on our neighbours daa and Roadbridge have been closely monitoring construction activities over the past few months We have collated a number of statistics related to activities which have taken place to date We are complying with all controls and procedures as per the Environmental Protection Plan which has been approved by Fingal County Council, in order to minimise the impacts of construction Activity Q1 2017 Q2 2017 To Date Average number of staff (on site per working week) 49 69 59 Total number of staff inducted 184 129 313 Total hours worked 30,785 44,413 75,198 Night and out-of-hours works* 0 4 (days) 4 (days) Road sweeping (number of times sweepers cleaned roads) 106 51 157 Ornithologist's site inspections 6 6 12 Bat specialist's site inspections 5 1 6 Archaeologists average number on site per week 17 15 16 *Road works took place over the course of two weekends on the St. Margaret s Bypass and Forrest Little Road 5

Rwy 10/28 Overlay and Associated Taxiways Works completed on Taxiways B7, E6 and E3 Overlay of Runway 10/28 is 25% complete Project scheduled to be completed by end of April 2018 149 shifts worked on the project up to May, 29 shifts cut short and 8 shifts cancelled due to low visibility procedures/wind or other operational reasons Works took place on Sat 24 th June and Sat 8 th of July. Works will take place on Sat 12 th August Stats: 152,000 hours worked on the project 33,000 tonnes of asphalt laid to date 48,000 metres of ducting laid 400 no. electrical pits installed 16-34 Movements Since project started % Total 16-34 Movements 3,800 16 Movements 2,935 77% 34 Movements 865 23% 6

Forrest Tavern Monument A new Forrest Tavern Monument will be erected at a site opposite the Boot Inn at Pickardstown Works associated with the Forrest Tavern Monument are fully compliant with planning requirements The materials that formed part of the Monument were assessed by Conservation Architect, Bill Hastings and FCC s Conservation Officer, Helena Burgin; it was concluded that the replica concrete mile markers which date from the 1990s do not have a historical significance; the pump and rings will be reinstated It is anticipated that work on the new Monument will be completed by mid-august daa has received several requests from local residents for the salvaged materials namely, the mile markers In the interest of fairness it is proposed that the names of interested parties, residing in the vicinity of the monument, be placed in a draw and the mile markers distributed accordingly Interested parties should submit their names to daa Residents should be aware that these concrete markers weigh approximately half a ton each 7

Dublin Airport Home Sound Insulation Programme Eligibility for Dublin Airport s Home Sound Insulation Programme is based on the 2016 63dB LAeq 16-hour contour. 85 dwellings are eligible to participate in this new programme. 8

Dublin Airport Home Sound Insulation Programme In total, over 200 local dwellings are now eligible for insulation An earlier 1990s insulation scheme associated with southern runway operations was appropriate for that time and dwellings which were part of that initiative will be revisited under this new programme. 63dB LAeq is a daytime threshold for mitigation used at other airports and was the standard which was approved by Fingal County Council for North Runway s scheme following rigorous scrutiny by independent consultants and extensive consultation with local residents. By using the same standard, we are dealing with impacted communities in a fair and equitable manner. Dublin Airport is neither conditioned nor compelled to implement this programme but is doing so as a good neighbour to limit noise impact from our current operations. 9

Dublin Airport Home Sound Insulation Programme This programme will be reviewed to comply with any future IAA requirements. It is separate to mitigation measures which are being developed as part of our application for change to permitted operations associated with North Runway. The programme was launched on 23 rd June 2017. All eligible dwelling owners have been contacted. An information day for eligible owners is being held on 16 th August from 2pm - 7pm at The Maldron Hotel. The first phase of the procurement process is ongoing, and we expect this element to be complete by Q3 2017. This would be followed by the first phase of surveying which could commence towards the end of 2017. When all surveying is complete, installation works could commence Q3 2018. Eligible dwellings nearest the southern runway will be surveyed and insulated first. The project team is contactable via freephone 1800-804422 or by email at insulation@daa.ie. 10

Dublin Airport Community Fund Dublin Airport Community Fund officially launched 22 nd June 2017 400,000 will be invested each year for the next 25 years, totalling 10m The Fund will focus on a number of categories such as environment and sustainability, health and wellbeing, education and training etc. Areas within the Funds catchment area are: Cloghran Hollystown Rolestown Swords Forrest Little Malahide Santry The Ward Greater Baskin Portmarnock St. Margaret s Tyrrelstown Three types of grants available under the Fund: Minor Grant < 5,000 (one stage process) Major Grant > 5,000 (two stage process) Capital Grant (two stage process) The Fund will also support up to 10 students annually from economically disadvantaged backgrounds to enable them to attend Dublin City University (DCU) via its Access Programme 11

Dublin Airport Community Fund Funding decisions will be made by a Grant Making Panel independently chaired by Marian Burns, Director of Human Resources with DCU The Panel will review and assess applications taking into consideration various criteria such as: Governance Benefits of the project Quality of the proposal The Fund will be open to applications twice yearly, in February and September First applications will be accepted from 1 st September 2017 and the application window will remain open for a period of six weeks Further information is available on our website: www.dublinairport.com/community-fund 12

END