ORV SAGAR KANYA CRUISE REPORT SK 324

Similar documents
The ship s keel has a diver-installed Multi-Beam Sonar mounting carriage located 1/3 length from the bow.

A project funded by the International Joint Ventures Fund of the Canada Foundation. for Innovation

replacement SONNE status report

R/V «Dr. Fridtjof Nansen» - Fishery and oceanographic research vessel

Mechanisms Controlling Hypoxia: Integrated Coastal Modeling Field Year 2010

Capable Accommodation work Barge with helideck. Large Work Deck with 400t deck crane. Accommodation for 165 pax. Mynx. Accommodation Work Barge

Cruise Report. FDS Submarine Channels RV Koca Piri Reis. 9 th -26 th May 2010

The field program has two main components: Underway Geophysics and On-site Sample collection and detailed mapping.

R/V Maurice Ewing Replacement

Vripack 21.5m Sportfisherman

L-DEO Office of Marine Operations: UNOLS Council and FIC Meetings June 5-7,2012 Boston, MA

Pre-Cruise Meeting 1400 Eastern Time (1100 Pacific), July 1, 2015

72' (21.95m) PERSHING

MAJOR REFIT OF R/V MARION DUFRESNE HÉLÈNE LEAU HEAD OF OCEANOGRAPHY DEPARTMENT INSTITUT POLAIRE FRANÇAIS, PAUL-EMILE VICTOR - IPEV

CANADOS 82 BROKERAGE CHARTER BERTHS FINANCE INSURANCE YACHT MANAGEMENT

68' (20.73m) FERRETTI

CORALFISH 2009 Cruise Report: CF0609. Eastern Ionian, Cephalonia and Zakynthos

74' Sunseeker Manhattan 74

Filippetti Navetta 30M

AZIMUT 88 BROKERAGE CHARTER BERTHS FINANCE INSURANCE YACHT MANAGEMENT

Hatteras Convertible

Make Model Length Price Year Condition. Amels Custom 178 ft EUR 14,950, Used

Nature of MATE Internships in 2011 thru May UNOLS/USCG Interns

M/Y SPIRIT OF THE C S

69' (21.20m) FERRETTI

Fleet Improvement Committee 7/12/2012

Benetti Vision 145 VICA Price: 13,500,000. Technical data. Monaco 27-29, Avenue des Papalins, MC Monaco

64' (19.60m) MONTE FINO

NOTIFICATION OF PROPOSED RESEARCH CRUISE

REPORT ON THE DEPLOYMENT OF RAPID-WAVE B. O. CORNIDE DE SAAVEDRA RADPROF0910 CRUISE 2010 VIGO-SANTANDER, 30 AUGUST-1 SEPTEMBER 2010

CRUISE REPORT. R/V Seward Johnson Cruise No. SJ RAPID/MOCHA Program September 25 October 12, 2006 Ft. Pierce to Ft. PIerce, Florida, USA

PRINCESS V PRICE: 349,950 EX VAT. Ref:PB RECENTLY SERVICED AND UPDATED

Coordination Center German Research Vessels

Riva Venere 75. Model: Venere 75 (GRP) 1,450,000

Hatteras 50 Convertible

Performance. Aircraft System

SERVICE BULLETIN SERIAL NUMBERS

DIMENSIONS LOA: (34.20m) Beam: (7.20m) Min Draft: (2.10m)

SPECIFICATION OF TUG VISION 6 (3300 HP)

PRINCESS ANNA PRINCESS YACHTS

Premier Portable Instruments

DF-99 ANTARCTIC PENINSULA SEDIMENT TRAP DEPLOYMENT AND WATER CHEMISTRY CRUISE R/V N.B. PALMER (MAR 28, 1999 to APR. 12, 1999) David A.

Installation & Commissioning Report

R. Weller December 10, 2014 Version 1.3

LOA 46, LWL 41, Beam 13.8, Draft 6.1, Displacement 28,500 lbs Designer: J Boats Built 2003 by Tillotson Pearson Inc.

Maxum 4600 SCB Captain Impatience

EGYPTIAN HYDROGRAPHIC DEPARTMENT ENHD. The ENHD following by the chain of command the Egyptian Naval HQ.

YACHT charter brokerage construction...

ANTARCTIC CROSSROAD OF SLOPE STREAMS expedition aboard B.O. HESPERIDES in the southwest Atlantic Ocean January-February, 2010

Carver 56 Voyager Flowergirl

Azimut EVOLUTION Flybridge Cruiser Quantum

SUNSEEKER MANHATTAN 74

Monte Fino 84 $2,950,000


Sub-Standard vessels in German ports 2016

Cruise Report YK10-E02

Princess 23 M. Prestige Yachts Investment (Yachts Invest) - Jean Lacombe. Prestige Yachts Investment, La Croisette, Port Canto, Cannes 06400, France

MAR Sanlorenzo. 20 November General Description:

LITA SEA RAY. Builder: SEA RAY. LOA: 40' 0" (12.19m) Year Built: Beam: 13' 2" (4.01m) Model: Cruiser. Max Draft: 3' 4" (1.

Baggage Reconciliation System

CARAVAN SALON DÜSSELDORF Page 1 of 5

Azimut 47 Seeker. Price: $ 749,000

CARAVAN SALON DÜSSELDORF Page 1 of 5

2007 Winston Marine Yachts 128' CUSTOM

R/V NEW HORIZON Scripps Institution of Oceanography CRUISE PLAN 1 (Draft = 29 August 2004)

Content. Price List Line Maintenance Services (German Stations only) 1/ Notes. 2/ Aircraft Handling. 3/ Ground Equipment. 4/ Fluids / Lubricants

Listing ID: DATE LAUNCHED:

Liberty Custom Silver Bullet

HOT 294: Chief Scientist Report Chief Scientist: Dan Sadler R/V Kilo Moana June 19-23, 2017

Short Cruise Report RV Maria S. Merian Cruise MSM 21/1A

FOR SALE m (94'2"ft) Overmarine Stella Bianca

FOR SALE m (116'1"ft) Feadship Utopia II

PRINCESS SOLD. Ref:PBS MODEL PRINCES 64 FLYBRIDGE MOTOR YACHT FOR SALE, FITTED WITH:

Access 2 Immunoassay System Supplies

PRINCESS 85 MOTOR YACHT 2010 PRICE: 2,490,000 EX VAT. Ref:PB PRINCESS 85 MOTOR YACHT FOR SALE FITTED WITH:

Hatteras V12-71TI M/Y BLUE HORIZONS

Capacity kw. Thermal turndown from specified maximum capacity 8:1 8:1

ISA Asking price: EUR ,-- VAT status: Not paid Marshall Islands South of France

SERVICE LETTER REVISION

Sabre Hardback Express Carina

Form 91 Application for Approval of an EFB System

Jonesport Shipyard Page 1 of 8 P.O. Box Main St. Jonesport, ME Ph Fax

PRINCESS PRICE: 279,000 INC VAT. Ref:PB MODEL PRINCESS 50 MKII FLYBRDGE MOTOR YACHT FOR SALE, FITTED WITH:

PRINCESS V SOLD. Ref:PB PRINCESS V58 SPORTS YACHT FOR SALE FITTED WITH:

C. Area of operation: Columbia River and Columbia River Estuary between mouth of estuary and Portland, Oregon.

CRAIG LOOMS WAVE PIERCER

Cruise Report R/V "ALKOR" Cruise- No. HE-365 ( 06AK1101 ) 01 February - 13 February This report is based on preliminary data!

Viking Convertible SANDBOB

Subject: Recurrent Training requirements for helicopter pilots

Captain Will Whatley RRS Sir David Attenborough A new ship for the British Antarctic Survey

HUDSON LEADER. Classification society: American Bureau of Shipping. Recognized Organization: American Bureau of Shipping

Revision of IATA RP1743e IATA Irregularity codes

SEDIMENT SAMP. SLUDGE & SEDIMENT SAMPLING. Drum & Tank Samplers Sludge/Sediment Core Profiler Sediment Dredge Sediment Sampler

Trader Windermere United Kingdom 64,995

La Dolce Vita ID#234771

(Parent Website)

Requirements for pilots for off shore operations

The Past, Present, and Future of Nortek and Glider Measurements

Viking Yachts Convertible

Dolphin Yachts S.L. Club de Mar Palma de Mallorca Spain Ferretti 68

Transcription:

- 1 - Norinco Private Limited ORV SAGAR KANYA CRUISE REPORT SK 324 Submitted to NATIONAL CENTRE FOR ANTARCTIC & OCEAN RESEARCH, HEAD LAND SADA, MORMUGAO, GOA, As per ORV Sagar Kanya Annual Maintenance Contract With Ministry of Earth Science, New Delhi By NORINCO PRIVATE LIMITED D3.19, Sancoale Industrial Estate Zuari Nagar Goa - 403 726 Phone: +91 832 2555 837 Fax: +91 832 2555 420 Email: goa@norinco.co.in Web: www.norinco.co.in

- 2 - Norinco Private Limited Vessel : ORV. Sagar Kanya. Cruise No : SK 324. Chief Scientist Objective Institution Embarkation Disembarkation : Dr. Sajid Ali : Geotraces : PRL, Ahmedabad. : Mormugao, Goa. : Port Luis, Mauritius. Period : 22.09.2015 to 21.10.2015. Participants : P Boopathy V C Sarathchandran. J Ragunath M Velkumar R. Ramesh

- 3 - Norinco Private Limited Acknowledgement. We, the Norinco engineers onboard, thank the Chief Scientist and the scientific team for their support and extending their knowledge during the course of our servicing activities onboard. We thank the Captain, ship staff and crew for their active support and care during the voyage. The co-ordination and support of Director, NCAOR and his colleagues are gratefully acknowledged. -Norinco Engineers Team

- 4 - Norinco Private Limited Introduction. This report forms part of the Annual Maintenance Contract awarded to Norinco Private Limited for maintenance of scientific equipment onboard ORV. Sagar Kanya. Regular servicing and Maintenance of equipment during cruise was carried out as per maintenance schedule. This report describes the breakdown service carried out on those equipments that were found defective during routine maintenance, equipment used and required breakdown maintenance and performance of those equipment used in the cruise. The report also includes a list of spares consumed, their source and requirement of spare for future use onboard.

- 5 - Norinco Private Limited A. Chemical / Analytical Instruments A 02. Oxygen Titration Units Date & Service: 14.10.2015: MS 14.10.2015: Monthly service carried out as per the schedule and all three Titration units are A 03. Quartz Distillation Unit Date & Service: 13.10.2015; QS 13.10.2015: Quarterly service carried out as per the schedule and the equipment is A 04. Water Purifying system Date & Service: 24.09.2015: MS Prior to the cruise all cartridges and filters of both units were changed, tested and confirmed the operational status. The system was used throughout the cruise by PRL and NIO Vizag scientists. 24.09.2015: Monthly service carried out as per the schedule and both units are A 06. ph Meter Date & Service:25.09.2015} 02.10.2015} 09.10.2015} 16.10.2015} : WS 25.09.2015} 02.10.2015} 09.10.2015} 16.10.2015}: Weekly service carried out on these days as per the schedule and the equipment is A 08. UV Chamber, UV Lamp Date & Service: 25.09.2015: QS Port side and STBD side fume hoods were used by PRL Scientists. 25.09.2015: Quarterly service carried out as per the schedule and all Chambers are

- 6 - Norinco Private Limited B. Geological / Geological Instruments B 01. Gravity Corer Date & Service: Operation Gravity Corer was operated 11 times at 08 stations and samples were collected. The collected sample was sub-sampled and kept in deep freezer. The equipment is B 02. Hydraulic Piston Corer Date & Service: 06.102015; MS 06.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 03. Rock Saw Date & Service: 04.10.2015: MS 04.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 04. Liner Saw Unit Date & Service: 04.10.2015: MS 04.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 05. Rock Mill Date & Service: 10.10.2015: MS 10.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 06. Bottom Grab {Small] Date & Service: 11.10.2015:MS. 11.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 07. Bottom Grab {Large} Date & Service: 11.10.2015:MS. 11.10.2015: Monthly maintenance carried out as per the schedule and the equipment is

- 7 - Norinco Private Limited B 10. Side Scan Sonar + Tow Fish Date & Service: 15.10.2015: MS. 15.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 12. Pingers Date & Service: 16.10.2015; QS 16.10.2015: Quarterly maintenance carried out as per the schedule and both units are B 13. Deep Sea Echo sounder + Repeaters Date & Service: Operation : 07.10.2015; MS Deep sea echosounder was used throughout this cruise and data was recorded. On completion of the cruise the recorded data was copied on CD. 07.10.2015: Monthly maintenance carried out as per the schedule and the equipment is Shallow Water Echo sounder + B 14. Repeaters Date & Service: 07.10.2015; MS 07.10.2015: Monthly maintenance carried out as per the schedule and the equipment is partially B 15. MBES Date & Service: Operation 16.10.2015: MS The system was used for surveying the Gravity coring station area and operational status of the equipment was satisfactory. 16.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 16. SBP Date & Service: Operation 09.10.2015: MS

- 8 - Norinco Private Limited On 22.09.2015, as soon as the vessel left harbour, the system was switched on and the system was ON throughout the cruise and data was recorded. On completion of the cruise data was copied on CD. 09.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 17. Spade Corer Date & Service: 17.10.2015: MS 17.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 18. Chain Bag Dredge Date & Service: 18.10.2015: MS 18.10.2015: Monthly maintenance carried out as per the schedule and the equipment is B 19. Core Sub-Sampling Station Date & Service: The Core sub-sampling station was used for sub-sampling the collected core and the unit is B 21. Tension Meter for Winch Date & Service: Operation 20.10.2015: MS The unit was used during Gravity coring operations along with Deep Sea Winch. 20.10.2015: Monthly maintenance carried out as per the schedule and the equipment is C. Oceanography / Meteorology / Biology Equipment C 01. MPN Date & Service: 22.09.2015: QS 22.09.2015: Quarterly maintenance carried out as per the schedule and the equipment is C 04. CTD Idronaut Date & Service: Operation 14.10.2015: QS

- 9 - Norinco Private Limited On 29.09.2015, the Geo Oceanic Carousel unit was charged with external battery charger. The CTD was operated 43 times at 12 stations and samples were collected. After every operation the system was washed with fresh water and secured 14.10.2015: Quarterly maintenance carried out as per the schedule and the equipment is C 05. Niskin Sampler 1.7Ltrs Date & Service: 23.09.2015: QS 23.09.2015: Quarterly maintenance carried out as per the schedule and the samplers are C 06. Niskin Sampler 5Ltrs Date & Service: Operation 24.09.2015: QS Eight numbers of samplers were used for water collection. Found rubber chords of five samplers were faulty these were replaced with new ones from Norinco s stock. 24.09.2015: Quarterly maintenance carried out as per the schedule and the samplers are Spare used:- Rubber Chords : 05 Nos C 07. Niskin Sampler 10Ltrs Date & Service: Operation 23.09.2015: QS Twelve numbers of samplers were used for water collection throughout the cruise. Found rubber chords of some samplers were faulty these were replaced with new ones from Norinco s stock. 23.09.2015: Quarterly maintenance carried out as per the schedule and the samplers are Spare used:- Rubber Chords : 05 Nos C 08. Niskin Sampler 30Ltrs Date & Service: 24.09.2015: QS 24.09.2015: Quarterly maintenance carried out as per the schedule and the samplers are

- 10 - Norinco Private Limited C 09. Go-Flo Sampler 30Ltrs Date & Service: 25.09.2015: QS 25.09.2015: Quarterly maintenance carried out as per the schedule and the units are C 11. Bucket Thermometers Date & Service: 18.10.2015: MS 18.10.2015: Monthly service carried out as per the maintenance schedule and both the units are C 13. Barometer Date & Service: 19.10.2015: MS 19.10.2015: Monthly service carried out as per the maintenance schedule and the unit is C 15. Radio Sonde Date & Service: 02.10.2015: QS 02.10.2015: Quarterly maintenance carried out as per the schedule and unit is C 17. Thermosalinograph Date& Service: Operation 18.10.2015: MS Thermosalinograph was used during entire period of the cruise and data was recorded. The recorded data was processed and copied on CD. At the end of the cruise the sensors were flushed with fresh water. 18.10.2015: Monthly service carried out as per the schedule and it is C 20. Rotary Shaker Date& Service: 22.09.2015: MS 22.09.2015: Monthly maintenance carried out as per the schedule and the equipment is D. Auxiliary / General Equipment D 01 GPS + Power Supply Date & Service: Operation. : 05.10.2015: QS

- 11 - Norinco Private Limited GPS was used throughout during the cruise and navigational data was made available to all under way equipments (DSES, TSG, and SBP). 05.10.2015: Quarterly maintenance carried out as per the schedule and the equipment is D 02 CCTV Date & Service: 06.10.2015: MS. CCTV was used throughout the cruise for monitor various activities onboard especially in DSW and CTD operations. The system was operational during this cruise period. 06.10.2015: Quarterly maintenance carried out as per the schedule and the equipment is D 03. Refrigerators Date & Service:25.09.2015} 02.10.2015} 09.10.2015} 16.10.2015: WS. Refrigerators in Chemistry Lab and Multipurpose Lab were used during this cruise and these are 25.09.2015} 02.10.2015} 09.10.2015} 16.10.2015: Weekly service carried out on the above dates as per the maintenance schedule and all refrigerators are operational except the one fitted in Wet Lab STBD. This defective fridge will be attended during the next Indian port. D 05. Deep Freezer Date & Service: One of the Deep Freezer (Aft side) was used throughout the cruise by PRL Scientists. Both units are D 06. Meter Wheel Units Date & Service: 17.10.2015: MS. Forward Pulley was used during CTD operation and the performance was satisfactory 17.10.2015: Monthly maintenance was carried out as per the schedule. Except cable payout unit, both pulleys are D 07 Personal Computer / Server & Peripherals (12 CPUs, 15 monitors) Date & Service: 28.09.2015: MS.

- 12 - Norinco Private Limited The following computers are included in AMC and their status are as follows: Sl. No 01 02 03 04 05 06 07 PC Computer: 01 Make: Lenovo Think Centre. M/N: 8811-FRA. S/N: L9AM500. Monitor: 01 Lenovo Think Vision Computer: 02 Make: Lenovo Think Centre P/N: MT-M 8811-FR8 S/N: L9AM507 Monitor: 02 Make: HPLE1851W. P/N: NK033A. S/N: CNC102QH7B Computer: 03 Make: HP Compaq 8100. P/N: XT767PA#ACJ. S/N: INA109VJRJ. Monitor: 03 Make: HP LE1851w. P/N: NK033A. S/N: CNC102QH85. Computer: 04 Make: HP Compaq 8100 P/N: XT767PA#ACJ S/N: INA109VJYS Monitor: 04 Make: HP LE1851w. P/N: NK033A. S/N: CNC102QHX1. Computer: 05 Make: HP Compaq 8100 P/N: XT767PA#ACJ S/N: INA109VJRR Monitor: 07 Make: HP LE1851w. P/N: NK033A. S/N: CNC102QHM3. Computer: 06 Make: Lenovo Think Centre. M/N: 8811-FRA. S/N: L9AM534. Monitor: 06 Make :AOC Model No. TFT185W80PS S/N: AOCWSM5NA1802098. Computer: 07 Make: HP Compaq 8100. P/N: XT 767PA#ACJ S/N: INA109VJWD. Monitor: 08 Loc: / Dedicated to Chief scientist Cabin Met Lab / AWS Met Lab / General Purpose Dry-Lab Port / Thermosalinograph Dry-Lab Port / CTD Dry-Lab Port/ ADCP Dry-Lab Port / Magnetometer Status / Remarks Used / Operational Operational Used / Operational Used / Operational Used / Operational. Operational Operational..

- 13 - Norinco Private Limited Make: HP LE1851w. P/N: NK033A. S/N: CNC102QH7K. Computer: 08 Make: Lenovo Think Centre. M/N: 8811-FRA. S/N: L9AM499. Monitor: 05 08 Make : Acer Model : V193HQL Version : V193HQL H6 P/N : VM.XV3SS.HO1 S/N : MMLKESS0063010C9938507 Computer: 09 Make: HP Compaq 8100. P/N: XT767PA#ACJ. S/N: INA109VJKN. 09 Monitor: 09 Make: HP LE1851w. P/N: NK033A. S/N: CNC102QFYF. Computer: 10 Make: HP Compaq 8100. P/N: XT767PA#ACJ. S/N: INA109VJYM. 10 Monitor: 10 AOC. 18.5 Wide LED P/N. e950sw Model No.185LM00013 S/N: AOCAR96C3052436 Computer: 11 Make: Lenovo Think Centre M/N: 8811-FRA. S/N: L9AM498 11 Monitor: 11 Make: Lenovo Model: 9227-AD1 Serial Number: VIA2955 Computer: 12 12 Make: Zebronics. Model: Elegance. Computer: 13 13 Make: XTECH. Monitors 14 Monitor:12 Make: Lenovo Think Vision Model: 9227 AD1. S/N: V1A2976. Dry Lab Stbd / Echo sounder Conference room Photo Lab Photo Lab Photo Lab Photo Lab Wheel House These defective CPU and monitor were offloaded to NPL Chennai office on 18.06.2015 and the repairs are in progress through OEM. Operational Operational Operational Operational Operational Operational. This is connected as deep sea echo sounder repeater in wheel house. 15 Monitor:13 Make : AOC S/N: AOCWSM5NA1801905 Dry Lab Stbd / SWES 28.09.2015: Monthly maintenance carried out as per the schedule. Except CPU #08 and Monitor #05 all other systems are Operational. This is connected with SWES.

- 14 - Norinco Private Limited D 08 LAN Date & Service: 30.06.2015: MS 29.09.2015: Monthly maintenance carried out as per the schedule and the LAN is D 09 Printers Date & Service: 30.06.2015: MS The following printers are included in AMC and their status are as follows: No Make of the printer Location Status / Remarks 1 HP LaserJet P2015dn CS Cabin Used, Operational 2 HP LaserJet P1007 Met Lab Used,Operational 3 HP LaserJet P1007 Photo Lab Operational 4 HP LaserJet P1007 Photo Lab Operational 5 HP LaserJet CP 1525n Conference Room Used,Operational 6 HP LaserJet P2015dn CTD Lab Used, Operational 7 HP LaserJet 1150 Photo Lab Operational 8 HP LaserJet 1150 Tape Store Operational, Cover broken 9 HP LaserJet 1150 Tape Store Operational 30.09.2015: Monthly service carried out to all printers as per the maintenance schedule and all of them are D 10. External CD Writer Date & Service: 01.10.2015: MS 01.10.2015: Monthly maintenance was carried out as per the schedule and the CD Writer is D 11. Scanner Date & Service: 01.10.2015: MS. 01.10.2015: Monthly maintenance was carried out as per the schedule and the Scanner is D 12. Plotter Date & Service:

- 15 - Norinco Private Limited This plotter is defective and offloaded from the vessel to Norinco office for repairs. Dynamic Positioning System & All D 18. sub - Units Date &Service: 27.09.2015: QS Service carried out and Remarks : The DP was used during the CTD and Gravity Coring operations. Though the system is operational, Portside Wind sensor is non-functional which needs replacement: 27.09.2015: Quarterly service carried out to DP system as per the maintenance schedule and it is D 19. HI-PAP Date & Service: 27.09.2015: QS Service carried out and Remarks : 27.0.2015: Quarterly maintenance carried out as per the schedule and the unit is D 20. Deck Crane Date & Service: Service carried out and Remarks : PRL Clean CTD operations were carried out though a pulley which is attached to the deck crane. Hence, the Crane was used during all CTD stations during this cruise and it was E 25. Deep sea Winch Date & Service: Service carried out and Remarks : The Deep Sea Winch was operated for Gravity Coring operations. On 23.09.2015 at 1845hrs, while retrieving Gravity corer and it reached at a depth of 903 meters, the deep sea winch stopped. This same was informed to ship officials, further inspection found that a driver transformer in the control panel was burnt out. As there was no accurate spare transformer available onboard they managed a temporary arrangement to retrieve the Corer and successfully retrieved the corer. After some modifications the winch was used for rest of the operations.

- 16 - Norinco Private Limited ADDITIONAL WORKS CARRIED OUT Clean CTD + Winch [PRL] Date & Service: operation Service carried out and Remarks : During the cruise Clean CTD was operated 43 times at 18 stations and data was collected. On completion of every operation, CTD underwater unit was washed with fresh water and secured. The recorded data was processed as per the requirement of the scientist s team and handed over to Chief scientist. In first two stations, it was observed that the DO Sensor was showing erratic reading and this was rectified by cleaning the bulkhead connector on the sensor. Tested and found operational thereafter. On 27.09.2015, at station #05, the CTD was lowered up to a depth of 3750 meters and noticed SBE32 carousel unit (SN:3264933-0864) stopped working. It was not responded with the triggering command and an error message unsupported modem message from SBE carousel was appeared on the computer display. Tried to close the bottles manually from deck unit, but no response from the carousel. Restarted Seasave, the acquisition software, observed that the water sampler was failed to initialize, a message data acquisition stopped, failed to initialize water sampler appeared on the screen. De-selected the water sampler from software and started. Brought back the CTD to deck and tested, without water sampler the system works fine. Removed the carousel from the frame and opened the pylon for any water ingress, but it was found intact. As there are no spare PCB s for repairing the carousel, SK CTD s pylon connector was modified and remaining stations were successfully carried out with this arrangement. On 15.10.2015 at station #17, the CTD was around 3500mtrs of water depth, the communication between underwater unit to deck unit was interrupted and this was rectified by restarting the acquisition software. During this cruise, the umbilical cable got damage three times and chopped off the damage

- 17 - Norinco Private Limited portion of cable and re-joined with the pig tail connector. Around 50m of cable were chopped off during these splicing. The equipment is SBE 9/11plus CTD. (Deck unit SN: 11P61163-0862 / Underwater unit SN: 09P61163-1019). Date & Service: operation Service carried out and Remarks : During the cruise CTD was operated 14times at 04 stations and data was collected. After every operation the underwater unit was washed with fresh water and secured. On 27.09.2015, at station No 05, the PRL Clean CTD s carousel became faulty, necessary changes made to SK SBE CTD s carousel and connected to PRL CTD for water sample collection. Hence the rest of the CTD operations carried with Idronaut CTD. The equipment is Autosal Date & Service: Operation Service carried out and Remarks : Prior to the cruise the system was calibrated with pure sea water ampule and used by scientists from PRL. The performance of the system was satisfactorily. CTD Winches (Aft& forward). Date & Service: Operation Service carried out and Remarks : Forward CTD winch was operated during the CTD operations and the performance was satisfactorily. For Norinco Private Limited, Chief Scientist

- 18 - Norinco Private Limited P.Boopathy Senior Manager Dr.Sajid Ali PRL, Ahmedabad.